Plant-SBD-YB-1stage-postQ-20240715 Final
Plant-SBD-YB-1stage-postQ-20240715 Final
Plant-SBD-YB-1stage-postQ-20240715 Final
BIDDING DOCUMENT
FOR
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
2
Preface
This Standard Bidding Document (“SBD”) for Procurement of Plant Design, Supply
and Installation has been prepared by KfW Development Bank (“KfW”) and is
based on the Master Procurement Document “Standard Bidding Documents for
Procurement of Works and User’s Guide” developed by the Multilateral
Development Banks and International Financing Institutions, which represents the
best practices of these institutions.
Project Executing Agencies (referred to hereafter as “Employers”) shall use this
SBD in the procurement of plant design, supply and installation, financed in whole
or in part by KfW in International Competitive Bidding (ICB) procedures for plant
design, supply and installation contracts. The works requirements included herein
have been extended to include environmental and social and health and safety
requirements (ESHS). These requirements were adopted to reflect the ESHS
impacts and risks of the implementation of the particular works contract.
This document has been adopted to include post-qualification criteria. All
documentation will be requested in one stage. A qualification evaluation will be run
before technical and financial evaluation. Those bidders who pass the qualification
criteria will be evaluated further.
Technical and Financial Bids are to be placed in two separate envelopes. The
opening of the bids takes place in two public sessions. In the first public session,
only the Post-Qualification and Technical Bids will be opened and examined for
completeness. The Technical Bid will be evaluated on non-responsive (fail) or
substantial-responsive (pass) criteria. In the second public session, only the
Financial Bids of those Bidders who have fulfilled the defined criteria for the Post-
Qualification and Technical Bids will be opened.
The Bidder with the most economically advantageous Bid will then be awarded the
Contract.
Feedback to or questions about this document should be in writing to the following address:
[email protected]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
3
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
4
Bids must be delivered to the address indicated in the clause ITB 22.1 of the
bidding documents on or before 6th September 2024. Late Bids will be rejected.
In the first public session, only the Technical Bids will be opened in the presence
of the Bidders’ designated representatives. In the second public session only the
Financial Bids of those Bidders who have fulfilled the technical requirements as
per the tender document will be opened.
The bid validity period shall be 120 days. All Bids must be accompanied by a Bid
Security (The amount and currency of the Bid Security shall be: 200,000 EUR or
equivalent USD or NPR in the form of bank guarantee. The bid security issued from
a foreign bank shall be duly counter guaranteed by any reputed commercial bank
of Nepal. The Bid Security shall be valid for thirty (30) days beyond the original
validity period of the Bid, including beyond any period of extension if requested).
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
5
Regions II Project
Bidding Documents
for
photovoltaic systems
July, 2024
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
6
Table of Contents
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
7
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 8
Table of Clauses
A. General ................................................................................................10
1. Scope of Bid ......................................................................................... 10
2. Source of Funds ................................................................................... 10
3. Corrupt and Fraudulent Practices ........................................................ 10
4. Eligible Bidders .................................................................................... 11
5. Eligible Materials, Equipment, and Services ........................................ 12
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
9 Section I. Instructions to Bidders
31. Invitation to 2nd Public Session for Opening of Financial Bids ........... 33
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 10
A. GENERAL
1. Scope of Bid 1.1 In connection with the Invitation for Bids specified in
the Bid Data Sheet (BDS), the Employer, as
specified in the BDS, issues these Bidding
Documents (“Bidding Documents”) to Bidders
(“Bidders”) interested in submitting bids (“Bids”) for
the procurement of Plant and Installation Services
as specified in Section VII, Employer’s
Requirements. The International Competitive
Bidding (“ICB”) number corresponding to this bidding
process is also provided in the BDS.
1.2 Throughout these Bidding Documents:
(a) The term “in writing” means communicated in
written form and delivered against receipt;
2. Source of Funds 2.1 The Employer as indicated in the BDS has applied
for or received financing (hereinafter called “funds”)
from KfW Development Bank (hereinafter called
“KfW”) towards the cost of the project named in the
BDS. The Employer intends to apply a portion of the
funds to eligible payments under the contract(s)
resulting from this bidding process.
3. Corrupt and 3.1 KfW requires compliance with its policy in regard to
Fraudulent Practices corrupt and fraudulent practices as set forth in
Section VI.
3.2 In further pursuance of this policy, Bidders shall
permit and shall cause its agents to provide
information and permit KfW or an agent appointed
by KfW to inspect on site all accounts, records and
other documents relating to bid submission and
contract performance (in the case of award), and to
have them audited by auditors or agents appointed
by KfW.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
11 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 12
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
13 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 14
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
15 Section I. Instructions to Bidders
C. PREPARATION OF BIDS
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the
preparation and submission of its Bid, and the
Employer shall not be responsible or liable for those
costs, regardless of the conduct or outcome of the
bidding process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and
documents relating to the bid exchanged by the
Bidder and the Employer, shall be written in the
language specified in the BDS. Supporting
documents and printed literature that are part of the
Bid may be in another language provided they are
accompanied by an accurate translation of the
relevant passages in the language specified in the
BDS, in which case, for purposes of interpretation of
the Bid, such translation shall govern.
11. Documents 11.1 The Bid shall comprise the following:
Comprising the Bid
(a) TECHNICAL BID
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 16
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
17 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 18
13. Alternative Bids 13.1 The BDS indicates whether alternative bids are
allowed. If they are allowed, the BDS will also
indicate whether they are permitted in accordance
with ITB 13.3, or invited in accordance with
ITB13.2 and/or ITB 13.4.
13.2 When alternative times for completion are explicitly
invited, a statement to that effect will be included in
the BDS, and the method of evaluation shall be
included in Section III, Evaluation and Qualification
Criteria.
13.3 Except as provided under ITB 13.4 below, Bidders
wishing to offer technical alternatives to the
Employer’s requirements as described in the bidding
document must also provide: (i) a price at which they
are prepared to offer a plant meeting the Employer’s
requirements; and (ii) all information necessary for a
complete evaluation of the alternatives by the
Employer, including drawings, design calculations,
technical specifications, breakdown of prices, and
proposed installation methodology and other
relevant details. Only the technical alternatives, if
any, of the lowest evaluated Bidder conforming to
the basic technical requirements shall be considered
by the Employer.
13.4 When bidders are invited in the BDS to submit
alternative technical solutions for specified parts of
the facilities, such parts shall be described in Section
VII, Employer’s Requirements. Technical
alternatives that comply with the performance and
technical criteria specified for the Plant and
Installation Services shall be considered by the
Employer on their own merits, pursuant to ITB 35.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
19 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 20
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
21 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 22
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
23 Section I. Instructions to Bidders
19. Period of Validity 19.1 Bids shall remain valid for the period specified in the
of Bids BDS after the Bid submission deadline date
prescribed by the Employer in accordance with ITB
22.1. A Bid valid for a shorter period shall be rejected
by the Employer as non-responsive.
19.2 In exceptional circumstances, prior to the expiration
of the Bid validity period, the Employer may request
Bidders to extend the period of validity of their Bids.
The request and the responses shall be made in
writing. If a Bid Security is requested in accordance
with ITB 20, it shall also be extended for forty-two
(42) days beyond the deadline of the extended
validity period. A Bidder may refuse the request
without forfeiting its Bid Security. A Bidder granting
the request shall not be required or permitted to
modify its Bid, except as provided in ITB 19.3.
19.3 In the case of fixed price contracts, if the award is
delayed by a period exceeding fifty-six (56) days
beyond the expiry of the initial bid validity, the
Contract price shall be adjusted by a factor or factors
specified in the request for extension. Bid evaluation
shall be based on the Bid Price without taking into
consideration the above correction.
20. Bid Security 20.1 The Bidder shall furnish as part of its Bid, either a
Bid-Securing Declaration or a Bid Security as
specified in the BDS, in original form and, in the case
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 24
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
25 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 26
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
27 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 28
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
29 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 30
27. Determination of 27.1 The Employer will examine the Technical Bids to
Responsiveness of determine whether they are complete, whether the
Technical Bids documents have been properly signed and whether
the bids are generally in order. Any bids found to be
non-responsive or not meeting the minimum levels
of the performance or other criteria specified in the
bidding document will be rejected by the Employer
and not included for further consideration. The
Employer will also carry out a preliminary
examination of any alternative bids submitted by
bidders.
27.2 The Employer may request that the Bidder submit
the necessary information or documentation, within
a reasonable period of time, to rectify nonmaterial
omissions in the Technical Bid related to
documentation requirements. Failure of the Bidder
to comply with the request may result in the
rejection of its Technical Bid.
27.3 Notwithstanding ITB 27.2, from the time of bid
opening to the time of Contract award, if any Bidder
wishes to contact the Employer on any matter
related to the bidding process, it should do so in
writing.
28. Evaluation of 28.1 The Employer will carry out a detailed evaluation of
Technical Bids the Technical Bids not previously rejected in order
to determine whether the technical aspects are in
compliance with the Bidding Document. The bid
that does not meet minimum acceptable standards
of completeness, consistency and detail, and the
specified minimum (or maximum, as the case may
be) requirements for specified functional
guarantees, will be rejected for non-
responsiveness. In order to reach such a
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
31 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 32
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
33 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 34
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
35 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 36
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
37 Section I. Instructions to Bidders
G. AWARD OF CONTRACT
43. Award Criteria 43.1 Subject to ITB 42.1, the Employer shall award the
Contract to the Bidder whose combined Technical
and Financial Bid has the highest score and is
substantially responsive to the Bidding Documents,
provided further that the Bidder is determined to be
eligible and qualified to perform the Contract
satisfactorily.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section I. Instructions to Bidders 38
44. Notification of 44.1 Prior to the expiration of the period of Bid validity, the
Award Employer shall notify the successful Bidder, in
writing, that its Bid has been accepted. The
notification letter (hereinafter and in the Conditions
of Contract and Contract Forms called the “Letter of
Acceptance”) shall specify the sum that the
Employer will pay the Contractor in consideration of
the execution and completion of the Plant and
Installation Services (hereinafter and in the
Conditions of Contract and Contract Forms called
“the Contract Price”). Subsequently, the Employer
shall also notify all other Bidders of the results of the
bidding.
44.2 Until a formal contract is prepared and executed, the
Letter of Acceptance shall constitute a binding
Contract.
44.3 The Employer shall promptly respond in writing to
any unsuccessful Bidder who, after notification of
award in accordance with ITB 44.1, requests in
writing the grounds on which its Bid was not
selected.
44.4 In exceptional circumstances, the Employer may
need to communicate with the successful Bidder,
established in terms of ITB 39.1, certain aspects of
Contract performance prior to sending the Letter of
Acceptance. Should such a need arise, this
communication shall be limited to the following
topics, as identified in the evaluation report,
(a) coordination of mobilization timing;
45. Signing of 45.1 Promptly upon notification, the Employer shall send
Contract the successful Bidder the Contract Agreement.
45.2 Within twenty-eight (28) days of receipt of the
Contract Agreement, the successful Bidder shall
sign, date, and return it to the Employer.
45.3 Notwithstanding ITB 45.2 above, in case signing of
the Contract Agreement is prevented by any export
restrictions attributable to the Employer, to the
country of the Employer, or to the use of the Plant
and Installation Services to be supplied, where such
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
39 Section I. Instructions to Bidders
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 40
ITB 1.1 The list of contracts (lots) comprising the ICB is: “Procurement of
utility-scale ground-mounted photovoltaic systems”
ICB name and number are: ICB-SEPP-EPC-SOLAR-01/2024-KfW-
BMZ-PN511010
ITB 2.1 The name of the Project is: Promotion of Solar Energy in Rural and
Semi-urban Regions II Project
Maximum number of members in the JV shall be: 3 (three), including
ITB 4.1 (b) Lead Member
Delete the sentence: “This bidding is open only to prequalified
ITB 4.5 Bidders.”
B. Bidding Document
ITB 6.1 The contents of Parts 1, 2 and 3 are revised as follows:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
41 Section II. Bid Data Sheet
ITB 7.1 For clarification purposes only, the Employer’s address is:
Attention: Mr. Prakash Raut, Project Manager
Project: Promotion of Solar Energy in Rural and Semi-Urban
Regions II Project
Nepal Electricity Authority
Distribution and Consumer Services Directorate
Planning and Technical Services Department
Ratnapark, Kathmandu, Nepal
E-mail address: [email protected], [email protected]
Email:
[email protected]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 42
C. Preparation of Bids
The language of the Bid is English.
ITB 10.1
All correspondence exchange shall be in the English language.
Language for translation of supporting documents and printed
literature is English.
ITB 11.1 (a) The Technical Bid shall include an environmental, social, health and
safety (ESHS) Methodology meeting the requirements of the ESHS
Specifications.
The Bidder shall use the ESHS Methodology Form provided for this
purpose in Section IV – Technical Bid.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
43 Section II. Bid Data Sheet
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 44
ITB 11.1 (b) (v) Bid Security in accordance with ITB 20.1 shall be provided in
Technical Bid, only
The Bidder shall submit with its Financial Bid the following additional
documents:
No additional documents
Alternative Bids shall not be permitted under ITB 13.2 / ITB 13.3 /
ITB 13.1 ITB 13.4
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
45 Section II. Bid Data Sheet
ITB 17.5(d) Taxes, duties and fees exemptions, to which payments under the
Contract are entitled, are specified in clause 14.16 of the Particular
Conditions of Contract.
ITB 17.7 The prices quoted by the Bidder shall be: fixed
ITB 17.12 With regard to Taxes and Duties, the conditions mentioned in Part
III, Sub-Clause 14.16 shall be duly considered by the Bidders.
ITB 18.1 The currency(ies) of the Bid and the payment currency(ies) shall be
in accordance with Option B as described below:
(i) for those inputs to the Plant and Installation Services that
the Bidder expects to supply from within the Employer’s
country, in Nepalese Rupees (NPR), and further referred
to as “the local currency”; and
(ii) for those inputs to the Plant and Installation Services that
the Bidder expects to supply from outside the Employer’s
country (referred to as “the foreign currency
requirements”), in Euro (EUR).
(iii) for the services of design and the assembly, the prices
will be quoted in foreign currency (limited to Euros (EUR)
or US Dollars (USD)) and/or in the currency of the country
of the Employer according to the currency in which the
costs are incurred.
ITB 21.1 In addition to the originals of the Technical and Financial Bids, the
number of copies is: Two (2) paper copies, each including one (1)
digital copy (USB). In the digital copy of the Bid, the length of the file
path shall be limited to 120 characters.
The USB stick in the Technical Bid must not contain the Financial
Bid.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 46
Ratnapark, Kathmandu
ZIP Code: 44600
Nepal
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
47 Section II. Bid Data Sheet
ITB 26.1 In the first public session, only the Bidders’ Qualification Documents
and Technical Bids will be opened.
The Bid opening (first public session) shall take place at:
Nepal Electricity Authority
Distribution and Consumer Services Directorate
Planning and Technical Services Department
Kathmandu
ZIP Code: 44600
Nepal
ITB 26.5 Delete paragraph and replace by “The Employer shall notify all
Bidders in writing of the names of those Bidders whose Technical
Bids have passed the technical evaluation. In addition, those
Bidders who have been disqualified will be informed separately.”
ITB 26.6 Delete paragraph and replace by “Bidders whose technical bids
have passed the technical evaluation will be informed by the
Employer of the date, time and place of the second public session
for the opening of Financial Bids.”
ITB 26.7 Delete first sentence and replace by “Only the Financial Bids of
those Bidders whose Technical Bids have passed the technical
evaluation will be opened in the second public session.”
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 48
ITB 28.2 Delete paragraph and replace by “The Technical Bids will be subject
to evaluation in accordance with Section III, Evaluation and
Qualification Criteria, 1.2 Technical Bid Evaluation System,”
ITB 29.2 At the end of ITB 29.2, add the following paragraph:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
49 Section II. Bid Data Sheet
ITB 43.1 Delete paragraph and replace with “Subject to ITB 42.1, the Employer
shall award the Contract to the Bidder whose Technical Bid is
substantially responsive to the Bidding Documents and has the
lowest evaluated Financial Bid, provided further that the Bidder is
determined to be eligible and qualified to perform the Contract
satisfactorily.”
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
50 Section III. Qualification and Evaluation
In accordance with ITB 28 and ITB 40, no other factors, methods or criteria shall be used. The
Bidder shall provide all the information requested in the forms included in Section IV, Bidding
Forms.
Wherever an Applicant is required to state a monetary amount, Applicants should indicate the
EUR equivalent using the rate of exchange determined as follows:
• For construction turnover or financial data required for each year - Exchange rate prevailing on the
last day of the respective calendar year.
• Value of single contract - Exchange rate prevailing on the date of the contract.
Exchange rates shall be taken from the publicly available rate published by the Central Bank of
the Employer’s country. Any error in determining the exchange rates in the Application may be
corrected by the Employer.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section III. Qualification and Evaluation 51
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
1. Eligibility
1.1 Nationality Nationality in accordance with ITB Must meet Must meet Must meet N/A Forms ELI-1.1,
4.3 requirement requirement requirement 1.2(a) and 1.2(b),
with attachments
1.2 Conflict of No conflicts of interest in accordance Must meet Must meet Must meet N/A Letter of Technical
Interest with ITB 4.2 requirement requirement requirement Bid
1.3 KfW Eligibility Not being ineligible for KfW Must meet Must meet Must meet N/A Declaration of
financing, as described in ITB 4.3 requirement requirement requirement Undertaking
1.4 Government- Meet conditions of ITB 4.3 Must meet Must meet Must meet N/A Forms ELI-1.1,
Owned Entity requirement requirement requirement 1.2(a) and 1.2(b),
with attachments
2. Historical Contract Non-Performance
2.1 History of Non- Termination of a contract did not Must meet Must meet Must meet N/A Form CON-2
Performing occur as a result of contractor’s requirement requirement requirement
Contracts default in the past five (5) years
2.2 Suspension Not under suspension based on Must meet Must meet Must meet N/A Letter of Technical
Based on execution of a Bid Securing requirement requirement requirement Bid
Execution of Bid Declaration pursuant to ITB 4.4
Securing
Declaration by
the Employer
2.3 Pending All pending litigation shall in total not Must meet Must meet Must meet N/A Form CON-2
Litigation represent more than fifty percent requirement requirement requirement
(50%) of the Applicant’s net worth
and shall be treated as resolved
against the Applicant
3. Financial Situation and Performance
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 52
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
3.1 Financial (i) The Applicant shall demonstrate Must meet Must meet N/A N/A Form FIN–3.1 with
Capabilities: that it has access to, or has requirement requirement attachments and
Liquidity available, liquid assets, FIN-3.3
unencumbered real assets, lines of
credit, and other financial means
(independent of any contractual
advance payment) sufficient to meet
the construction cash flow
requirements estimated as EUR 1.66
million for the subject contract(s) net
of the Applicants other commitments
3.2 Financial (ii) The Applicant shall also Must meet Must meet N/A N/A Forms FIN–3.1
Capabilities: demonstrate, to the satisfaction of requirement requirement and FIN-3.4
Other Sources the Employer, that it has adequate
of Finance sources of finance to meet the cash
flow requirements on works currently
in progress and for future contract
commitments.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section III. Qualification and Evaluation 53
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
3.3 Financial (iii) The audited balance sheets or, if Must meet Must meet Must meet N/A Form FIN–3.1 with
Capabilities: not required by the laws of the requirement requirement requirement attachments
Financial Applicant’s country, other financial
Position statements acceptable to the
Employer, for each of the last 3 years
shall be submitted and each
statement must demonstrate the
current soundness of the Applicant’s
financial position based on the
following criteria:
a) Liquidity ratio ≥ 1.1
𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝐴𝑠𝑠𝑒𝑡𝑠
≥ 1.1
𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑖𝑒𝑠
3.4 Average Annual Minimum annual construction Must meet Must meet Must meet Must meet Form FIN–3.2
Construction turnover of 10.00 million EUR (ten requirement requirement minimum minimum forty
Turnover million five hundred sixty thousand twenty five percent (40 %)
Euros), for the last 3 years, percent (25 of the
calculated as total certified annual %) of the requirement
payments received for contracts in requirement
progress and/or completed
4. Construction Experience
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 54
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
4.1 General Experience under construction Must meet N/A Must meet N/A Form EXP–4.1
Construction contracts in the role of prime requirement requirement
Experience contractor, JV member,
subcontractor, or management
contractor for at least the last 5
years, starting on the bid submission
deadline.
4.2 Specific Similar1 contracts, satisfactorily and Must meet Must meet N/A Must meet Form EXP-4.2 (a)
(a) Construction & substantially2 completed as a prime requirement requirements minimum
Contract contractor, joint venture member3, twenty five
Management management contractor or percent (25 %)
Experience subcontractor 4 for the last 5 years, of the
starting on submission deadline of requirement
minimum TOTAL value of 4.0 million
EUR (Four Million Euro)
1 The similarity shall be based on the physical size, complexity, methods/technology and/or other characteristics described in Section VII, Scope of Works. Summation of number
of small value contracts (less than the value specified under requirement) to meet the overall requirement will not be accepted.
2 Substantial completion shall be based on 80% or more works completed under the contract.
3
For contracts under which the Applicant participated as a joint venture member or sub-contractor, only the Applicant’s share, by value, shall be considered to meet this
requirement.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section III. Qualification and Evaluation 55
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
4.2 Construction For the above or any other contracts Must meet Must meet N/A N/A Form EXP–4.2 (b)
(b) Experience in completed and under implementation requirements requirements
key activities as prime contractor, joint venture
member, management contractor or
subcontractor4 on or after the first
day of the calendar year during the
period stipulated in 4.2(a) above, a
minimum construction experience in
the following key activities
successfully completed4:
one (1) or more PV plant
installations with minimum total
capacity of 12 MWp
5. Environmental and Social and Health and Safety (ESHS) Experience and Capacity
5.1 Certificates Availability of a valid ISO certification Must meet N/A Must meet N/A
as below requirement requirement
- Quality Management
certificate ISO 9001
Form CER-5.1
- Environmental management
certificate ISO 14001:2014
Form CER-5.1
- Health and Safety certificate
ISO 45001:2018
Form CER–5.1
4 Volume, number or rate of production of any key activity can be demonstrated in one or more contracts combined if executed during same time period. The rate of production
shall be the annual production rate for the key construction activity (or activities).
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 56
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
5.2 Experience in For the above and any other Must meet Must meet N/A Must have Form EXP–5.2
Projects with contracts completed and under requirement requirement executed at
significant implementation as prime contractor, least 1 (one)
ESHS Impact joint venture member, management contract(s)
contractor or subcontractor5 on or demonstrating
after the first day of the calendar year experience
during the period stipulated in 4.2(a) with the key
above, experience relating to the ESHS
either one of the following ESHS requirements
requirements6: as listed in the
Requirements
• Relevant Nepal National laws and column.
regulations or
• World Bank Environmental and
Social Standards, ILO Core
Labour Standards, World Bank
Environmental, Health and Safety
Guidelines or
• Sustainability Guideline of KfW
Development Bank or
• International financing institution
standards (e.g. ADB)
5.3 Environmental The Applicant must demonstrate that Must meet Must meet N/A N/A Form ENV-5.3
Capacity its business setup and operations requirement requirement
meet the minimum requirements
towards an effective environmental
management system
5 For contracts under which the Applicant participated as a joint venture member or sub-contractor, only the Applicant’s share, by value, shall be considered to meet this
requirement.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section III. Qualification and Evaluation 57
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
5.4 Occupational The Applicant must demonstrate that Must meet Must meet N/A N/A Form ISO
Health and its business setup and operations requirement requirement 45001:2018-5.4
Safety Capacity meet the minimum requirements
towards an effective health and
safety management system
5.5 Socially The Applicant must demonstrate a Must meet Must meet Must meet N/A Form LOC-5.5
Responsible comprehensive understanding of the requirement requirement requirement
Work requirements regarding work site
Implementation implementation and operation
5.6 ILO Core Labor Undertaking to fully respect the ILO Must meet Must meet Must meet N/A Application
a) Standards Core Labor Standards in the requirement requirement requirement Submission Form
Applicant’s business practice (f) and form COC-
5.6
5.6 Ethical business The Applicant must demonstrate that Must meet Must meet N/A N/A Form COC-5.6
b) principles its business setup and operations requirement requirement
meet the minimum requirements
towards ethical Business principles.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section II. Bid Data Sheet 58
Criteria Requirements
Documentation
Joint Venture (existing or intended) Requirements /
No. Subject Requirement Single Entity All Parties Each Forms
One Member
Combined Member
5.7 ESHS and The Applicant must demonstrate that Must meet Must meet N/A N/A PER-5.7
Construction it has access to adequate candidates requirement requirement
Personnel for the ESHS personnel profiles,
listed in Section VII, Scope of Works.
The candidates must fulfill the
minimum specific profile
requirements and the general
requirements (if any). Combining
several candidates to fulfill one
candidate profile is not allowed.
Providing multiple candidates for a
single profile is allowed.
The substantial responsiveness of the documents will be determined as per Section I, Clause 27.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
59 Section IV. Bidding Forms
This Section contains all the criteria that the Employer shall use to evaluate Technical
and Financial Bids and verify that the qualifications of the Bidders have not changed
since the post-qualification stage. In accordance with ITB 28 and ITB 40, no other
factors, methods or criteria shall be used. The Bidder shall provide all the information
requested in the forms included in Section IV, Bidding Forms.
Wherever a Bidder is required to state a monetary amount, Bidders should indicate
the EUR equivalent using the rate of exchange determined as follows:
(a) For construction turnover or financial data required for each year - Exchange
rate prevailing on the last day of the respective calendar year;
(b) Value of single contract - Exchange rate prevailing on the date of the contract.
Exchange rates shall be taken from the publicly available source identified in the ITB
38.1. Any error in determining the exchange rates in the Financial Bid may be
corrected by the Employer.
The substantial responsiveness of the documents will be determined as per Section I,
Clause 27.
1. Technical Bid
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 60
All the documents referred to form part of the bid and must fulfil the requirements in order for
technical compliance to be achieved.
Bids offering a completion date beyond the maximum designated period shall be rejected.
The minimum (or maximum) requirements are stated in the Employer’s Requirements.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
61 Section IV. Bidding Forms
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 62
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
63 Section IV. Bidding Forms
(b) Subcontractors/manufacturers
Subcontractors for the following additional major items of supply or
services must meet the following minimum criteria, herein listed for that
item:
Item
Description of Item Minimum Criteria to be met
No.
1 PV Modules Manufacturers shall be listed tier 1 suppliers
list of Bloomberg New Energy Finance
(BNEF)6, reference is the last published
version at the time of Proposal submission
6
Tier 1 module manufacturers are those which have provided own-brand, own-manufacture products to five
different projects, which have been financed non-recourse by five different (non-development) banks, in the
past two years. 1.5 MW+ deals must be tracked by BNEF database. One exception is manufacturers which
have filed for bankruptcy or a form of insolvency protection, or experienced a major default on bond
payments; these are removed from the tier 1 list until further notice.
http://about.bnef.com/content/uploads/sites/4/2012/12/bnef_2012-12-03_PVModuleTiering.pdf
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 64
Failure to comply with this requirement will result in the rejection of the
subcontractor.
In the case of a Bidder who offers to supply and install major items of
supply under the contract that the Bidder did not manufacture or otherwise
produce, the Bidder shall provide the Manufacturer’s Authorization, using
the form provided in Section IV, showing that the Bidder has been duly
authorized by the manufacturer or producer of the related plant and
equipment or component to supply and/or install that item in the
Employer’s country. The Bidder is responsible for ensuring that the
manufacturer or producer complies with the requirements of ITB 4 and 5
and meets the minimum criteria listed above for that item.
2. Financial Bid
2.1 Evaluation
In addition to the criteria listed in ITB 40.2 (a) – (e) the following additional
evaluation factors and methods will apply:
(a) Time Schedule
No credit will be given for earlier completion.
Bids offering a completion date beyond the maximum designated period
shall be rejected.
(b) Operating and Maintenance Costs
Operating and maintenance costs of the facilities, including the cost of
spare parts, will be evaluated in the financial evaluation
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
65 Section IV. Bidding Forms
𝑃𝑅𝐴𝑣𝑟 = ∑ 𝑃𝑅𝑖 /5
𝑖=1
𝑃𝑟𝑜𝑑𝑡𝑜𝑡𝑎𝑙 = ∑ 𝑃𝑟𝑜𝑑𝑖
𝑖=1
For the purposes of evaluation, for each percentage point below the
maximum offered value (by the best Bidder) an adjustment of
400,000 EUR/% will be added to the proposal price. If the drop is less than
one percent (%), the adjustment will be prorated accordingly
System Production: For the purposes of evaluation, total Guaranteed
Minimum PV System Production for the first five years (the sum of
guaranteed production for year 1 - 5) will be calculated. For each MWh
below the maximum offered values (by the best Bidder) an adjustment of
150 EUR/MWh will be added to the proposal price.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 66
The Bidder shall furnish guaranteed no load and full load loss data at
rated load with the bid for all ratings of transformers.
When evaluating the individual bid received from Bidders, the bid price
shall be evaluated for the cost of transformer loss values (no-load
losses and load losses) based on the following loss capitalization
formula:
PE = Pb + KL * LL + KNL* LNL
where,
PE = Evaluated Price
Pb = Bid Price
KL = Value of Load Loss
LL = Guaranteed load losses at rated current (Maximum MVA
base)
KNL = Value of no load Loss
LNL = Guaranteed no load losses
Any adjustments in price that result from the above procedures shall be added, for
purposes of comparative evaluation only, to arrive at an “Evaluated Bid Price.” Bid
prices quoted by bidders shall remain unaltered.
The Purchaser shall use the criteria and methodologies listed in this Section to evaluate Bids.
By applying the criteria and methodologies the Purchaser shall determine the Most
Advantageous Bid. This is the Bid that meets the Qualification Criteria and has been
determined to be:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
67 Section IV. Bidding Forms
TECHNICAL BID
Technical Bid.........................................................................................100
Plant .....................................................................................................106
Personnel ..............................................................................................107
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 68
FINANCIAL BID
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
69 Section IV. Bidding Forms
FORM ELI-1.1
APPLICANT INFORMATION FORM
Date: _________________
ICB No. and title: ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Page __________of _______________pages
Applicant's name
[insert full name]
In case of Joint Venture (JV), name of each member:
[insert full name of each member in JV]
Applicant's actual or intended country of registration:
[indicate country of Constitution]
Applicant's actual or intended year of constitution:
[indicate year of Constitution]
Applicant's legal address [in country of registration]:
[insert street/ number/ town or city/ country]
Applicant's legal structure and ownership structure
Legal structure: [provide details]
Ownership structure: [provide details of direct and indirect ownership]
Applicant's authorized representative information
Name: [insert full name]
Address: [insert street/ number/ town or city/ country]
Telephone/Fax numbers: [insert telephone/fax numbers, including country and city codes]
E-mail address: [indicate e-mail address]
1. General Presentation of the Applicant (name, legal structure, business areas, subsidiaries and
shareholdings, number of staff, etc.)
2. Attached are copies of original documents of
Articles of Incorporation (or equivalent documents of constitution or association), and/or
documents of registration of the legal entity named above, in accordance with ITA 4.1.
In case of JV, JV agreement, in accordance with ITA 4.1 or Declaration of Association as per
ELI 1.2(b).
In case of Government-owned enterprise or institution, in accordance with ITA 4.3 documents
establishing:
- Legal and financial autonomy
- Operation under commercial law
- Establishing that the Applicant is not a dependent agency of the Employer.
3. Included are the organizational chart, a list of Board of Directors, and the beneficial ownership.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 70
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
71 Section IV. Bidding Forms
[The following form shall be provided by each member of a Joint Venture and, if applicable, by
any specialized subcontractor, nominated in accordance with ITA 24]
Date: _______________
ICB No. and title: ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Page _______________ of ____________ pages
We hereby declare our intent to associate with the following firms for the purpose of
forming a [insert here “joint venture”]:
[Insert the name of the Lead Member] shall be the Lead Member.
We hereby confirm that we have not associated with any other firms for the purposes of
this assignment and that we will not submit an Application separately from the firms listed
above. Further, we understand that if one of the above JV Members appears as a member
in more than one Application, all Applications in which the Member appears shall be
disqualified.
In the event that this JV is awarded a Contract, we shall perform the works in the
composition and in the form of cooperation described above.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 72
FORM CON-2
HISTORICAL CONTRACT NON-PERFORMANCE, PENDING
LITIGATION AND
LITIGATION HISTORY
[The following table shall be filled in for the Applicant and for each member of a Joint Venture]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
73 Section IV. Bidding Forms
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 74
FORM FIN-3.1
FINANCIAL SITUATION AND PERFORMANCE
[The following table shall be filled in for the Applicant and for each JV Member]
1. Financial data
Type of Financial information Historic information for previous _[insert number] years,
in [insert in words]
(currency) (amount in currency, currency, exchange rate, EUR
equivalent)
2. Financial documents
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
75 Section IV. Bidding Forms
The Applicant and its parties shall provide copies of financial statements for [number] years
pursuant Section III, Qualification and Evaluation, Sub-factor 3.1. The financial statements shall:
(a) reflect the financial situation of the Applicant or JV member , and not an affiliated
entity (such as parent company or subsidiary).
Attached are copies of financial statements7 for the [number] years required above; and
complying with the requirements
7 If the most recent set of financial statements is for a period earlier than 12 months from the date of application,
the reason for this should be justified.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 76
FORM FIN-3.2
AVERAGE ANNUAL CONSTRUCTION TURNOVER
[The following table shall be filled in for the Applicant and for each member of a Joint
Venture]
Average Annual
Construction
Turnover *
* Total EUR equivalent for all years divided by the total number of years. See Section III,
Qualification and Evaluation, Clause 3.2.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
77 Section IV. Bidding Forms
FORM FIN–3.3
SOURCES OF FINANCE
[The following table shall be filled in for the Applicant and all members combined in case of a
Joint Venture]
Specify proposed sources of financing, such as liquid assets, unencumbered real assets,
lines of credit, and other financial means, net of current commitments, available to meet
the total construction cash flow demands of the subject contract or contracts as specified
in Section III, Qualification and Evaluation.
Financial Resources
No. Source of financing Amount (EUR equivalent)
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 78
FORM FIN–3.4
CURRENT CONTRACT COMMITMENTS / WORKS IN
PROGRESS
[The following table shall be filled in for the Applicant and all members combined in case of a
Joint Venture]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
79 Section IV. Bidding Forms
FORM EXP-4.1
GENERAL CONSTRUCTION EXPERIENCE
[The following table shall be filled in for the Applicant and in the case of a JV Applicant,
each Member]
[Identify contracts that demonstrate continuous construction work over the past [number]
years pursuant to Section III, Qualification and Evaluation, Sub-Factor 4.1. List contracts
chronologically, according to their commencement (starting) dates.]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 80
Information
Similar Contract No.
[insert number] of [insert
number of similar contracts
required]
Contract Identification [insert contract name and number, if applicable]
Award date [insert day, month, year, i.e., 15 June, 2015]
Completion date [insert day, month, year, i.e., 03 October, 2017]
Role in Contract Prime Member in Management Sub-
[check the appropriate box] Contractor JV Contractor contractor
Total Contract Amount [insert total contract amount in EUR [insert Exchange rate and
local currency] total contract amount in EUR
equivalent]
If member in a JV or [insert a [insert total [insert exchange rate and total
subcontractor, specify percentage contract contract amount in EUR
participation in total Contract amount] amount in equivalent]
amount local currency]
Employer's Name: [insert full name]
Address: [indicate street / number / town or city / country]
Telephone/fax number [insert telephone/fax numbers, incl. country/city area codes]
E-mail: [insert e-mail address, if available]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
81 Section IV. Bidding Forms
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 82
1. Key Activity No. One: [insert brief description of the Activity, emphasizing its
specificity]
Information
Contract Identification [insert contract name and number, if applicable]
Award date [insert day, month, year, i.e., 15 June, 2015]
Completion date [insert day, month, year, i.e., 03 October, 2017]
Member
Role in Contract Prime Management Sub-
[check the appropriate box] in
Contractor Contractor contractor
JV
Total Contract Amount EUR [insert exchange rate
[insert total contract amount in
and total contract amount
contract currency(ies)]
in EUR equivalent]
Quantity (Volume, number or rate Total quantity in Percentage Actual
of production, as applicable) the contract participation Quantity
performed under the contract per (i) (ii) Performed
year or part of the year (i) x (ii)
[Insert extent of participation
indicating actual quantity of key
activity successfully completed in
the role performed]
Year 1
Year 2
Year 3
Year 4
Employer’s Name: [insert full name]
8 If applicable
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
83 Section IV. Bidding Forms
Information
Address: [indicate street / number / town or city / country]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 84
[The following table is optional and depending on the nature of the project, it shall be
filled in for contracts performed by the Applicant or each member of a Joint Venture, and
if so nominated in accordance with ITA 24, nominated sub-contractor]
Description Information
List of utilized specific construction __[based on the specific construction experience in Forms 4.2
equipment (a or b) the Applicant shall provide a list of specific construction
equipment, utilized for the execution of the works. The list shall
not specify commonly used equipment (ordinary cement mixers
or cranes, etc.) but specific equipment related to the specific
characteristics of the project as per the form below. For each
item one form.]_
Purpose: __[describe the use of the item in relation to the specific work
requirements of the project]___
Capacity / power rating / quantities, __[give details of the capacity / power rating / quantities in
etc. relation to the work description]__
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
85 Section IV. Bidding Forms
FORM CER–5.1
CERTIFICATION
ESHS level = (2) The following table shall be provided by the Applicant for each
certificate:
- Quality Management certificate ISO 9001:2015
- Environmental management certificate ISO 14001:2015
- Health and Safety certificate ISO 45001:2018
Description Information
Identification of the certificate __________ [insert full name of the certificate]
If no, proof of conformity with the The Applicant shall demonstrate the equivalency
international standard by the of their management systems with the
Applicant international standards.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 86
Information
ESHS Contract No.
[insert number] of [insert
number of S&E contracts
required as per Section III, 5.]
Contract Identification [insert contract name and number, if applicable]
Award date [insert day, month, year, i.e., 15 June, 2015]
Completion date [insert day, month, year, i.e., 03 October, 2017]
Role in Contract Prime Member in Management Sub-
[check the appropriate box] Contractor JV Contractor contractor
Total Contract Amount [insert total contract amount in EUR [insert Exchange rate and
local currency] total contract amount in EUR
equivalent]
If member in a JV or [insert a [insert total [insert exchange rate and total
subcontractor, specify percentage contract contract amount in EUR
participation in total Contract amount] amount in equivalent]
amount local currency]
Employer's Name: [insert full name]
Address: [indicate street / number / town or city / country]
Telephone/fax number [insert telephone/fax numbers, incl. country/city area codes]
E-mail: [insert e-mail address, if available]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
87 Section IV. Bidding Forms
3. ESHS knowhow transfer to[description of know how transfer and capacity building
local staff, local partners andmeasures implemented, incl. supporting documentation,
subcontractors if available]
[insert brief description or, if applicable, short abstract of the documentation annexed ]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 88
FORM ENV–5.3
ENVIRONMENTAL MANAGEMENT CAPACITY
[The following table shall be filled by the Applicant or each member of a Joint Venture]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
89 Section IV. Bidding Forms
[The following table shall be filled by the Applicant or each member of a Joint Venture]
[insert brief description or, if applicable, short abstract of the documentation annexed]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 90
FORM LOC–5.5
SOCIALLY RESPONSIBLE WORKS IMPLEMENTATION
[The following table shall be filled by the Applicant or each member of a Joint Venture]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
91 Section IV. Bidding Forms
FORM COC–5.6
ETHICAL BUSINESS PRINCIPLES
[The following table shall be filled by the Applicant or each member of a Joint Venture]
1 - that ILO core labor standards9 Our business operations respect the core Pass/
are fully respected in business labor standards on: fail
operations by explicitly ticking Freedom of Association
the boxes. Elimination of Forced Labour
Non-Discrimination
Abolishment of Child Labour
[insert brief description or, if applicable, short abstract of the documentation annexed ]
9 See relevant ILO conventions C087, C098, C029, C105, C100, C111, C138, C182. In case ILO conventions
have not been fully ratified or implemented in the Employer’s country the Applicant / Bidder / Contractor
shall, to the satisfaction of the Employer and KfW, propose and implement appropriate measures in the
spirit of the said ILO conventions.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 92
Complete the list below to demonstrate the extent to which you have access (internally /
externally) to ESHS and Construction expertise required for personnel profiles described
in Section VII; Scope of Works.
(Description of project-related
Country/Regional Experience
Education/ Degree
experience)
Languages
Applicant10
Name
10 For freelance experts (e.g. with retainer contracts or formal agreements) indicate “FE” and how long the
expert has been associated with the Applicant. For sub-consultant staff indicate “Sub”. Staff from affiliated
firms of the Applicant shall be considered as sub-consultant staff.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
93 Section IV. Bidding Forms
TECHNICAL BID
Letter of Technical Bid
[The Bidder shall prepare his Letter of Bid on a Letterhead paper specifying his name and
address]
Date:
ICB No.: ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
To:
______________________________________________________________________
(a) We have examined and have no reservations to the Bidding Documents, including
Addenda issued in accordance with Instructions to Bidders (ITB 8) ;
(c) We have not been suspended nor declared ineligible by the Employer based on
execution of a Bid Securing Declaration in the Employer’s country in accordance
with ITB 4.4;
(e) Our Bid shall be valid for a period of _________________ days from the date fixed
for the bid submission deadline in accordance with the Bidding Documents, and it shall
remain binding upon us and may be accepted at any time before the expiration of that
period;
(f) We are not participating, as a Bidder, in more than one Bid in this bidding process in
accordance with ITB 4.2(e), other than alternative Bids submitted in accordance with
ITB 13;
(g) We understand that this Technical Bid, together with your written acceptance thereof
included in your notification of award, shall constitute a binding contract between us,
until a formal contract is prepared and executed; and
(h) We acknowledge and agree that the Employer reserves the right to annul the bidding
process and reject all Bids at any time prior to contract award without thereby incurring
any liability to us;
(i) We hereby certify that we have taken steps to ensure that no person acting for us or
on our behalf will engage in any type of fraud and corruption.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 94
*: In the case of the Bid submitted by a JV specify the name of the JV as Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be
attached with the Bid
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
95 Section IV. Bidding Forms
Declaration of Undertaking
11 Capitalised terms used, but not otherwise defined in this Declaration of Undertaking have the meaning given
to such term in KfW’s “Guidelines for the Procurement of Consulting Services, Works, Goods, Plant and Non-
Consulting Services in Financial Cooperation with Partner Countries”.
12 The PEA means the purchaser, the employer, the client, as the case may be, for the procurement of
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 96
2.6) being subject to an exclusion decision of the World Bank or any other
multilateral development bank and being listed on the website
http://www.worldbank.org/debarr or respectively on the relevant list of any other
multilateral development bank (in the event of such exclusion, the Applicant or
Bidder shall attach to this Declaration of Undertaking supporting information
showing that this exclusion is not relevant in the context of this Contract and that
adequate compliance measures have been taken in reaction); or
2.7) being guilty of misrepresentation in supplying the information required as
condition to participation in this Tender Procedure.
3. We hereby certify that neither we, nor any of the members of our Joint Venture or any
of our Subcontractors under the Contract are in any of the following situations of conflict
of interest:
3.1) being an affiliate controlled by the PEA or a shareholder controlling the PEA,
unless the stemming conflict of interest has been brought to the attention of KfW
and resolved to its satisfaction;
3.2) having a business or family relationship with a PEA's staff involved in the
Tender Process or the supervision of the resulting Contract, unless the stemming
conflict of interest has been brought to the attention of KfW and resolved to its
satisfaction;
3.3) being controlled by or controlling another Applicant or Bidder, or being under
common control with another Applicant or Bidder, or receiving from or granting
subsidies directly or indirectly to another Applicant or Bidder, having the same legal
representative as another Applicant or Bidder, maintaining direct or indirect
contacts with another Applicant or Bidder which allows us to have or give access
to information contained in the respective Applications or Offers, influencing them
or influencing decisions of the PEA;
3.4) being engaged in a Consulting Services activity, which, by its nature, may be
in conflict with the assignments that we would carry out for the PEA;
3.5) in the case of procurement of Works, Plant or Goods:
i. having prepared or having been associated with a Person who prepared
specifications, drawings, calculations and other documentation to be used
in the Tender Process of this Contract;
ii. having been recruited (or being proposed to be recruited) ourselves or any
of our affiliates, to carry out works supervision or inspection for this
Contract;
4. If we are a state-owned entity, and compete in a Tender Process, we certify that we
have legal and financial autonomy and that we operate under commercial laws and
regulations.
5. We undertake to bring to the attention of the PEA, which will inform KfW, any change
in situation with regard to points 2 to 4 here above.
6. In the context of the Tender Process and performance of the corresponding Contract:
6.1) neither we nor any of the members of our Joint Venture nor any of our
Subcontractors under the Contract have engaged or will engage in any
Sanctionable Practice during the Tender Process and in the case of being awarded
a Contract will engage in any Sanctionable Practice during the performance of the
Contract;
6.2) neither we nor any of the members of our Joint Venture or any of our
Subcontractors under the Contract shall acquire or supply any equipment nor
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
97 Section IV. Bidding Forms
operate in any sectors under an embargo of the United Nations, the European
Union or Germany; and
6.3) we commit ourselves to complying with and ensuring that our Subcontractors
and major suppliers under the Contract comply with international environmental
and labour standards, consistent with laws and regulations applicable in the
country of implementation of the Contract and the fundamental conventions of the
International Labour Organisation13 (ILO) and international environmental treaties.
Moreover, we shall implement environmental and social risks mitigation measures
when specified in the relevant environmental and social management plans or
other similar documents provided by the PEA and, in any case, implement
measures to prevent sexual exploitation and abuse and gender based violence.
7. In the case of being awarded a Contract, we, as well as all members of our Joint
Venture partners and Subcontractors under the Contract will, (i) upon request, provide
information relating to the Tender Process and the performance of the Contract and (ii)
permit the PEA and KfW or an auditor appointed by either of them, and in the case of
financing by the European Union also to European institutions having competence
under European Union law, to inspect the respective accounts, records and
documents, to permit on the spot checks and to ensure access to sites and the
respective project.
8. In the case of being awarded a Contract, we, as well as all our Joint Venture partners
and Subcontractors under the Contract undertake to preserve above mentioned
records and documents in accordance with applicable law, but in any case for at least
six years from the date of fulfillment or termination of the Contract. Our financial
transactions and financial statements shall be subject to auditing procedures in
accordance with applicable law. Furthermore, we accept that our data (including
personal data) generated in connection with the preparation and implementation of the
Tender Process and the performance of the Contract are stored and processed
according to the applicable law by the PEA and KfW.
Signature: …………..
Dated: ……………….
13 In case ILO conventions have not been fully ratified or implemented in the Employer’s country the
Applicant/Bidder/Contractor shall, to the satisfaction of the Employer and KfW, propose and implement
appropriate measures in the spirit of the said ILO conventions with respect to a) workers grievances on working
conditions and terms of employment, b) child labour, c) forced labour, d) worker’s organisations and e) non-
discrimination.
14 In the case of a JV, insert the name of the JV. The person who will sign the application, bid or proposal on
behalf of the Applicant/Bidder shall attach a power of attorney from the Applicant/Bidder.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 98
Appendix 1
Declaration of tax conformity – binding confirmation for legal
persons
Name of company
..............................................
(Signature(s))
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
99 Section IV. Bidding Forms
Appendix 1
Declaration of tax conformity – binding confirmation for natural
persons
......................................................
(Signature)
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 100
Technical Bid
- Site Organization
- Method Statement
- Mobilization Schedule
- Construction Schedule
- Plant
- Contractor’s Equipment
- Personnel
- Manufacturer's Authorization
- Others
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
101 Section IV. Bidding Forms
Site Organization
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 102
The ESHS Methodology submitted shall be in the form of a preliminary draft of the
Construction Environmental and Social Management Plan (C-ESMP), the content of which
is detailed in Appendix 1 to ESHS Specifications.
The selected Bidder will prepare a Construction Environmental and Social Management
Plan, C-ESMP, demonstrating the manner in which they will comply with the
requirements of Site-Specific Management Plans, and the mitigation measures proposed in
the ESMP according to ESIA study. The C-ESMP will be submitted within 90 days of
Contractor’s mobilization, and will be approved by NEA. The C-ESMP will form the part
of the contract documents and will be used as monitoring tool for compliance. Violation
of the compliance requirements will be treated as non-compliance leading to the
corrections or otherwise imposing penalty on the contractor.
Information should be provided on all items of the above mentioned table of contents.
In order to address the highly sensitive ESHS issues highlighted during the project’s
constructions, the ESHS Methodology shall provide detailed information on the
management of the following items:
A Bid for which the ESHS Methodology is evaluated as nonsubstantially responsive (i.e.
with title and material deviation, reservation or omission) to the ESHS Specifications may
be be rejected.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
103 Section IV. Bidding Forms
Method Statement
Each Bidder shall set out details of the Method Statement for the Works to
demonstrate how it will meet the Employer’s objective and requirements. As a
minimum, the Method Statement shall address the following:
(a) Details of the arrangements and methods which the Bidder proposes to
implement for the construction of the Works, in sufficient detail to
demonstrate their adequacy to achieve the requirements of the Contract
including completion within the Time for Completion stated in the
Particular Conditions of Contract.
(g) Outline of the arrangements of the Bidder to carry out testing upon
completion as specified in the Works Requirements.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 104
Mobilization Schedule
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
105 Section IV. Bidding Forms
Construction Schedule
Each Bidder shall set out a detailed Program and Schedule for mobilisation and
construction of the Works to be performed, including estimated starting and
finishing dates for individual components and identification of major milestones and
critical path. The proposed Program and Schedule shall be developed according
to Works Requirements and shall address the following:
(a) Details of the proposed schedule for obtaining permits that may be
necessary in order to commence the Works, including the preparation of
required studies, supporting information, and applications.
(b) Details of the proposed timeline for carrying out the Works within the Time
for Completion, in the form of a bar chart showing notably the critical path.
(c) Details of the proposed timeline for the testing, commissioning and handing
over of the completed Works.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 106
Plant
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
107 Section IV. Bidding Forms
Personnel
Form PER-1
Proposed Personnel
Bidders should provide the names of suitably qualified personnel to meet the specified requirements
stated in Section III. The data on their experience should be supplied using the Form below for each
candidate.
1. Title of position*
Name
2. Title of position*
Name
3. Title of position*
Name
4. Title of position*
Name
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 108
Form PER-2
Name of Bidder
Position
Professional qualifications
Address of employer
Fax E-mail
Summarize professional experience over the last 20 years, in reverse chronological order. Indicate
particular technical and managerial experience relevant to the project.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
109 Section IV. Bidding Forms
The following Subcontractors and/or manufacturers are proposed for carrying out the item of the
facilities indicated. Bidders are free to propose more than one for each item
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 110
Manufacturer's Authorization
[to be prepared in official letterhead of the manufacturer and duly signed and stamped by
a person competent and having the authorization to bid the manufacturer, including
complete address – name, contact number, email address, mailing address]
Date: [insert date (as day, month and year) of bid submission]
ICB No.: [insert number of bidding process)
We [insert complete name of the manufacturer], who are official manufacturer of [insert
type of goods manufactured], having factories at [insert full address of manufacturer's
factories], do hereby authorize [insert complete name of the bidder] to submit a bid, the
purpose of which is to provide the following goods, manufactured by us [insert name and/or
brief description of the goods], and to subsequently negotiate and sign the contract.
We hereby extend our full guarantee and warranty in accordance with Sub-clause 1.1.3.7
Defects Notification Period, with respect to the goods offered by the above firm.
Official Seal:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
111 Section IV. Bidding Forms
(to be used by Bidder when alternative Time for Completion is invited in ITB 13.2)
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 112
FINANCIAL BID
Date:
ICB No.: ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
To:
________________________________________________________________
(e) The price of our Bid, excluding any discounts offered in item (d) below is the
sum of: _________________________, (_____________), and __________________,
(___________)
(f) The discounts offered and the methodology for their application are:
(i) We are not participating, as a Bidder or a subcontractor, in more than one bid
in this bidding process in accordance with ITB 4.2, other than alternative bids
submitted in accordance with ITB 13;
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
113 Section IV. Bidding Forms
(j) We have paid, or will pay the following commissions, gratuities, or fees with
respect to the bidding process or execution of the Contract:
(k) We understand that this bid, together with your written acceptance thereof
included in your notification of award, shall constitute a binding contract
between us, until a formal contract is prepared and executed; and
(l) We understand that you are not bound to accept the lowest evaluated bid or
any other bid that you may receive.
(m) We hereby certify that we have taken steps to ensure that no person acting for
us or on our behalf will engage in any type of fraud and corruption.
*: In the case of the Bid submitted by joint venture specify the name of the Joint
Venture as Bidder
**: Person signing the Bid shall
have the power of attorney given by the
Bidder to be attached with the Bid
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 114
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
115 Section IV. Bidding Forms
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IV. Bidding Forms 116
Summary of currencies of the Bid for ___________ [insert name of Section of the Works]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
117 Section IV. Bidding Forms
We have been informed that [Insert name and address of the bidder, which in the
case of a joint venture shall be the name and address of the joint venture]
(hereinafter called “the Applicant”) has submitted or will submit to the Beneficiary
its bid (hereinafter called “the Bid”) for the execution of [Insert project, object of the
contract/brief description of the works] under International Competitive Bidding No.
[Insert ICB number].
Waiving all objections and defences, we, as Guarantor, hereby irrevocably and
independently undertake to pay the Beneficiary any sum or sums not exceeding in
total an amount of [Insert guarantee amount and currency in words and figures]
upon receipt by us of the Beneficiary’s first demand, supported by the Beneficiary’s
statement, whether in the demand itself or a separate signed document
accompanying or identifying the demand, stating that either the Applicant:
(a) Has withdrawn its Bid during the period of bid validity set forth in the Applicant’s
Bid Submission Form (the Bid Validity Period”); or
(b) Having been notified of the acceptance of its Bid by the Beneficiary during the
Bid Validity Period, (i) has failed to sign the contract agreement, or (ii) has
failed to furnish the performance security, in accordance with the Instructions
to Bidders (“ITB”) of the Beneficiary’s bidding document.
This guarantee shall expire not later than [Insert expiry date]15.
By this date we must have received any claims for payment by letter or encoded
telecommunication.
It is understood that you will return this guarantee to us on expiry or after payment
of the total amount to be claimed hereunder.
[As preferred option regarding guarantee rules insert16: This guarantee is subject
to the Uniform Rule for Demand Guarantees (URDG) 2010 Revision, ICC
Publication No. 758.]
15
Pursuant to ITB Clause 19.3 the guarantee must be valid for at least 42 days beyond the bid
validity.
16 In the case the issuing bank will not add the preferred option, the following must be added
instead: This guarantee is governed by the laws of [Insert country of jurisdiction]. Note: the country
of jurisdiction shall be the country where the bank’s branch issuing the guarantee is physically
located.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
119 Section V. Eligibility Criteria
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section V. Eligibility Criteria 120
3. State-owned entities may compete only if they can establish that they (i) are
legally and financially autonomous, and (ii) operate under commercial law. To
be eligible, a state-owned entity shall establish to KfW’s satisfaction, through all
relevant documents, including its charter and other information KfW may
request, that it: (i) is a legal entity separate from their state (ii) does not currently
receive substantial subsidies or budget support; (iii) operates like any
commercial enterprise, and, inter alia, is not obliged to pass on its surplus to
their state, can acquire rights and liabilities, borrow funds and be liable for
repayment of its debts, and can be declared bankrupt.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
121 Section VI. KfW Policy – Sanctionable Practice - Social & Environmental Responsibility
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VI. KfW Policy – Sanctionable Practice – Social & Environmental Responsibility 122
KfW defines, for the purposes of this provision, the terms set forth below as follows:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
123 Section VI. KfW Policy – Sanctionable Practice - Social & Environmental Responsibility
17 In case ILO conventions have not been fully ratified or implemented in the Employer’s country the
Applicant/Bidder/Contractor shall, to the satisfaction of the Employer and KfW, propose and implement
appropriate measures in the spirit of the said ILO conventions with respect to a) workers grievances on working
conditions and terms of employment, b) child labour, c) forced labour, d) worker’s organisations and e) non-
discrimination.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
124
PART 2 – EMPLOYER’S
REQUIREMENTS
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
125 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 126
(a) Read first the Clause or Sub-Clause text from the General Conditions of
Contract;
(b) Then check whether this text has been amended by the Particular Conditions of
Contract, and if so, to which extent.
As per CC Sub-Clause 1.5, when interpreting the Contract, the terms of the Particular
Conditions of Contract prevail over those found in the General Conditions of Contract.
Any term in these ESHS Specifications which is identical to a term in the Conditions of
Contract shall have the same meaning as the one defined in the Conditions of Contract.
Any term in capital letters in these ESHS Specifications is defined in CC Sub-Clause 1.1
– Definitions.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
127 Section VII. ESHS Requirements
Table of Contents
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 128
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
129 Section VII. ESHS Requirements
1. Responsibilities and 1.1. In conjunction with his obligations defined under the
liabilities Contract, the Contractor will plan, execute and document
construction works pursuant to the present Environment,
Social, Health and Safety specifications (ESHS).
1.2. The Contractor is liable for all damages to the
environment and people caused by the execution of the
works or the methods used for execution, unless it is
established that the execution or methods were
necessary, according to the provisions of the Contract or
an Engineer’s instruction.
1.3. Under the Contract and as introduced by the present
ESHS requirements , the project area means:
a) The land where work will be carried out; or
b) The land necessary for the implantation of
construction facilities (work camp, workshops,
offices, storage areas, concrete production plants)
and including special access roads; or
c) Quarries for aggregates, rock material and riprap;
or
d) Borrow areas for sand and other selected material;
or
e) Stockpiling areas for backfill material or other
demolition rubble; or
f) Any other location, specifically designated in the
Contract as a Project Area.
The project area” encompasses any individual project
area or all project areas.
For the sake of clarity, Project area is a different concept
than Construction site under CC Sub-Clause 1.1.6.7.
Project area defines an area within which the Contractor
is to comply with environmental, social, health and safety
obligations defined in the ESIA and ESMP
Construction site is the places where the Permanent
Works are to be executed and to which Plant and
Materials are to be delivered, and where right of access
to, and possession of, is to be given by the Employer to
the Contractor. The Employer is under no similar
obligation for any area located outside the construction
site, even if within the project area, where access is at
Contractor’s risk.
In term of physical footprint, the CC Sub-Clause 1.1.6.7
Site is included in the project area. The project area is
then of greater geographical extent than the construction
site.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 130
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
131 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 132
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
133 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 134
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
135 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 136
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
137 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 138
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
139 Section VII. ESHS Requirements
10. Protection of 10.1. The Contractor shall be responsible for any foreseeable
adjacent areas adverse environmental and social impacts arising from its
activities and operations and for putting in place any
necessary measures to avoid or if not possible mitigate
them.
10.2. Pursuant to Sub-Clause 4.18 of the CC, and unless
instructed otherwise by the Engineer, the Contractor uses
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 140
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
141 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 142
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
143 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 144
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
145 Section VII. ESHS Requirements
15.2. The Contractor will plan high noise generating works (e.g.
pile driving, blasting, rock clearing, drilling, percussion
drilling) in line with national regulations and respect
maximum ambient noise-levels and night time rest hours
at the nearest receptor area. A receptor is defined as an
area used for nocturnal socioeconomic activities (e.g.
accommodation camps, residential areas, hotels, health
centres).
15.3. The Contractor shall locate stationary equipment (such as
power generators and compressors) as far as possible
from nearby receptors (e.g. worker resting areas,
populated areas and environmentally sensitive areas).
Equipment known to emit noise strongly in one direction,
whenever possible, will be orientated so that the noise is
directed away from sensitive receptors
15.4. The use of heavy vehicles at night is specified in ESHS
Specifications Sub-Clause 50.9.
15.5. Standard noise abatement equipment shall be fitted to
equipment by the Contractor, used and maintained in
accordance with manufacturers’ instructions.
16. Waste 16.1. The Contractor is responsible for identifying, collecting,
transporting and treating all waste produced on the
Project Areas.
16.2. The Contractor shall minimize the generation of waste
and reuse, recycle and recover waste in a manner that is
safe for human health and the environment.
16.3. The Contractor shall establish a Waste Management Plan
which details a concept to manage non-hazardous and
hazardous waste in line with the local legislations and
adapted to the level of danger for human health or the
natural environment. In absence of adequate legislation,
waste shall be managed according to the guidance
provided in the respective sections of the General World
Bank Group EHS Guidelines with the objective of
protecting soil and water resources. The Waste
Management Plan shall include provisions for the training
of workers.
16.4. Waste register and categorization:
16.4.1. The Contractor establishes and maintains a waste
register, which is at the disposal of the Engineer.
This register will record all waste management
operations: production, collection, transport,
treatment. It will be available as of the Contractors
mobilisation to any Project Area. Waste shall be
categorized according to the following definitions:
a) Non-hazardous solid waste generated at
construction and decommissioning sites
includes excess fill materials from grading and
excavation activities, scrap wood and metals,
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 146
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
147 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 148
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
149 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 150
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
151 Section VII. ESHS Requirements
18. Biodiversity 18.1. The Contractor shall ensure that all personnel are informed
and aware of the importance to protect species, habitats,
fauna and flora and are informed about wildlife encounter
procedures. Information and awareness training is
documented.
18.2. If applicable, the Employer will provide to the Contractor a
range of ecological surveys prior to the start of construction,
conducted by the Employer. These will include but not be
limited to the type and location of identified species and
habitats of conservation interest within the Project Area,
and any resulting measures that are required by
Contractor.
18.3. The Employer will provide to the Contractor a constraints
map, showing the areas where sensitive, endangered or
breeding species are known to occur, including protected
areas, sites of importance for nature conservation, wildlife
refuges, nature and national parks, important bird areas.
18.4. The Employer will inform the Contractor about seasons for
the protection of birds and wildlife. If applicable, the
Employer will inform the Contractor if, as a result of
protecting birds and wildlife, construction is restricted
during a certain period and/or the Contractor must take
precautionary measures in compliance with respective
national laws and/or as stipulated by the respective local
authorities.
18.5. The Employer may update information on the presence of
wildlife or sensitive or endangered species’ in the Project
Area following any additional wildlife/endangered species´
survey. If any are identified, the Employer will notify the
Contractor who will ensure that all personnel are informed
and aware of the required mitigation procedures as
communicated by the Employer.
18.6. The Contractor shall apply the Contracting Authority’s
procedures with regards to fauna and flora management
prior to clearing activities.
18.7. The Employer will communicate to Contractor his specific
responsibilities related to protecting endangered species,
biodiversity and wildlife, present within the Project Area.
Responsibilities may include but not be limited to the
following measures:
a) The Contractor´s personnel shall not approach,
injure, hunt, capture, possess, feed, transport, rear or
trade wild animals and/or collect birds’ eggs on the
Project Areas
b) The Contractor´s personnel shall avoid where
possible breeding, feeding and nesting sites of
endangered species, as identified by the Employer´s
environmental experts and as communicated to the
Contractor by the Employer.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 152
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
153 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 154
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
155 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 156
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
157 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 158
22. Health and Safety 22.1. In application of Clauses 4 and 6 of the CC, the
Plan Contractor shall develop a Health and Safety Plan
(HS Plan) section of the C-ESMP, its organization for
managing health and safety, pursuant to its Health
and Safety Management system (HSMS).
22.2. Pursuant to Clause 6 of the CC, the HS plan
identifies and specifies:
a) That Contractor understands and manages all
health and safety risks relating to the execution
of the works, including gender-specific risks;
b) Prevention and protection measures to control
risks related to the execution of the works, by
differentiating, where necessary, measures
concerning the protection of women and men;
c) Human and material resources involved;
d) Works requiring a permit (e.g. blasting, butting
of trees);
e) Emergency plans to be implemented in the
case of an accident.
22.3. The Contractor implements prevention, protection
and monitoring measures, as described in the health
and safety plan.
22.4. The Contractor shall have in place a Behavioural
Safety Based Programme and actively train and
encourage Personnel to intervene on unsafe
behaviours and situations and report on deviations.
23. Health and Safety 23.1. The Contractor shall document in a structured
Reporting system (e.g. a Site Accident record sheet) all
accidents, dangerous occurrences and
investigations, which shall be available at all, times
for inspection by the Engineer.
23.2. The Contractor shall investigate any incident and
record and report systematic follow-up of relevant
findings and recommendations. Problem areas
related to HS shall be recorded with information
about status, responsible person(s) and alternative
solutions.
23.3. As specified in Sub-Clause 4.21 of the CC, the
Contractor includes in the Progress Report to the
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
159 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 160
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
161 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 162
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
163 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 164
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
165 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 166
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
167 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 168
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
169 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 170
42. Labour conditions 42.1. The Contractor shall ensure decent labour conditions for
workers and notably compliance with applicable law and
regulations in the country of implementation of the
contract, and with the fundamental conventions of the
International Labour Organisation (ILO). This includes
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
171 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 172
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
173 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 174
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
175 Section VII. ESHS Requirements
46.2. The Contractor provides for at least two meals per shift
to local Contractor’s Personnel pursuant to the hygiene
conditions specified in Clause 40 of the present ESHS
Specifications, at reasonable price for the Contractor’s
Personnel. If no canteen is available, the Contractor at
least pays for a minimum of 2 meals per day per shift.
46.3. The Contractor shall avoid any local disputes through
respecting local culture and values. The Contractor shall
ensure that workers are aware of local issues and
sensitivities, and respect local culture and values in order
to avoid any local disputes and crime.
47. Community 47.1. Commensurate with the size of Construction activities
Interaction and unsolved potential disturbances of the community
and risks to public health and safety, the Contractor shall
produce an Implementation Plan related to Community
Interaction and submit it to the Engineer for review and
acceptance prior the commencement of any works or
traffic related to works.
47.2. The plan shall include a schedule of planned work
activities which may impact a neighboring community
and describe (i) the activities per task and phase which
may impact the neighboring communities (ii) the
approach to engage and communicate with stakeholders
related to the works defined in (i); (iii) responsibilities for
community interaction per task and phase.
47.3. When meeting stakeholders in neighboring
communities, minutes of meetings shall be produced
and recorded as by Employer’s guidelines;
47.4. The Contractor shall disclose relevant information
related to the involved impacts and risks to communities
(e.g. related to Traffic Management or e.g. to entering of
private property for surveys) in local language and at a
level of complexity that is commensurate with local
realities to ensure that stakeholders fully understand the
content.
47.5. The Contractor shall include information about the
Employer´s grievance mechanism and the contact
details in all community communication materials.
48. Damage to people 48.1. The Contractor shall implement a worker´s Code of
and property Conduct and not disturb or interfere with the inhabitants
of local communities close to or in the Project Area, and
shall respect their houses, cultures, animals, properties,
customs and practices.
48.2. The Contractor`s personnel shall be trained to
understand the requirements about use of unapproved
land and the need to stay strictly within site boundaries
and within the working areas, using only approved
access and service roads.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 176
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
177 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 178
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
179 Section VII. ESHS Requirements
Appendix 1
Example for the Contents of a C-ESMP
− ESHS vehicles
− IT stations
− In situ noise, air and water measuring equipment
− Analysis laboratory used
➢ Reporting:
− Weekly inspections
− Monthly
− Accident/ Incident
4. ESHS ➢ Definition of standards for the applicable national ESHS regulations and the
regulations ESHS recommendations of institutions affiliated to the United Nations
(WHO, ILO, IMO, IFC), applicable to the execution of works:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 180
− Distribution of information
− Notification depending on the level of importance allocated to
non-conformities
− Archiving
− Use as a performance indicator
6. Project Areas ➢ Description of Project Areas (as per definition in ESHS Specifications Sub-
Clause 1.3:
− Number
− Location on a topographical map
− Activities
− Opening & closing schedule
− Access
➢ Reference to the Appendix: a Site-ESMP for each Project Area.
7. Health and ➢ Identification and characterisation of health and safety risks, including the
safety plan exposure of personnel to chemicals, biological hazards and radiation.
➢ Description of working methods to minimise hazards and control risks.
➢ List of the types of work for which a work permit is required
➢ Personal protection equipment
➢ Presentation of the medical facilities at Project Areas:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
181 Section VII. ESHS Requirements
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 182
21. Appendices ➢ Site-ESMPs (number and location specified in Section 6 “Project Areas”
above):
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
183 Section VII. ESHS Requirements
− Description of facilities
− Characterisation of hazards
− Emergency situations
− Organisation structure - roles and responsibilities
− Emergency procedures
− Human and material resources
− Triggering of the plan
− Reporting
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 184
1. Explosive substances and preparations which could explode in the presence of a flame or
which are more sensitive to impacts and friction than dinitrobenzene.
2. Combustive substances and preparations which, when in contact with other substances,
particularly inflammable substances, undergo strongly exothermic reactions.
3. Easily substances and preparations (i) in liquid phase (including extremely inflammable
inflammable liquids), with a flash point below 21°C, or which can heat up to the extent of
spontaneous combustion in ambient air; or (ii) in solid phase, which can burst into
flames easily in the brief presence of a source of inflammation and which will
continue to burn after the removal of the source of inflammation or (iii) in gaseous
phase, which are inflammable in air at normal pressure; or (iv) – which, when in
contact with moist air or water, produce dangerous quantities of gases which are
easily inflammable.
4. Inflammable liquid substances and preparations, with a flash point equal to or above 21°C and
less than or equal to 55°C.
5. Irritant non-corrosive substances and preparations which, when in immediate, extended or
repeated contact with the skin and mucosa, can cause inflammation.
6. Harmful substances and preparations which, in case of inhaling, swallowing or cutaneous
penetration, can lead to risks of limited severity.
7. Toxic substances and preparations (including highly toxic substances and preparations),
which, in case of inhaling, swallowing or cutaneous penetration, can lead to serious,
acute or chronic risks, and even death.
8. Carcino- substances and preparations which, in case of inhaling, swallowing or cutaneous
genic penetration, can lead to or increase the frequency of cancer.
9. Corrosive substances and preparations which, in case of contact with living tissues, can
destroy the latter.
10. Infectious substances containing viable micro-organisms or their toxins, for which it is known
or we have good reasons to believe that they cause disease in humans or other
living organisms.
11. Harmful to substances and preparations which, in case of inhaling, swallowing or cutaneous
reproductio penetration, can induce or increase the frequency of undesirable non-hereditary
n function effects in offspring or have a negative effect on reproductive functions and abilities.
12. Mutagenic substances and preparations which, in case of inhaling, swallowing or cutaneous
penetration, can lead to hereditary genetic disorders or increase the frequency of
these disorders.
13. React with substances and preparations which, in case of contact with water, air or an acid,
water release a toxic or highly toxic gas.
14. Sensitivis- substances and preparations which, in case of inhaling or cutaneous penetration,
ing can lead to a hypersensitation, so that renewed exposure to the substance or
preparation will cause characteristic harmful effects. This property can only be
considered if test methods are available.
15. Ecotoxic substances and preparations with inherent or potential immediate or deferred risks
for one or several environmental components.
16. Dangerous substances and preparations which are likely, after elimination, to lead to another
for the substance, by any means, e.g. a lixiviation product, with one of the above
environment characteristics.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
185 Section VII. ESHS Requirements
d) Personnel Requirements
The Bidder must demonstrate that it has the personnel for the key positions that meet the
following requirements: [Specify requirements for each lot as applicable]
The Bidder shall provide details of the proposed personnel and their experience records
using Forms PER-1 and PER-2 included in Section IV, Bidding Forms.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 186
e) Equipment Requirements
Currently not applicable, but the Contractor’s EHS management plan will give more
equipment description and requirements.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
187 Section VII. ESHS Requirements
2. Drawings
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VII. ESHS Requirements 188
3. Supplementary Information
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
189
PART 3 – CONDITIONS OF
CONTRACT (CC) AND CONTRACT
FORMS
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section VIII. General Conditions 190
These Standard Bidding Documents have been designed for use with the
Fédération Internationale des Ingénieurs-Conseils (FIDIC) General Conditions of
Contract for Plant and Design Build 1st edition, 1999. Due to the FIDIC copyrights,
these FIDIC General Conditions are not included in these Tender Documents
which contain instructions on how these conditions can be acquired.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
191 Section VIII. General Conditions
The conditions of Contract are the “General Conditions” which form part of the
Conditions of Contract for Plant and Design Build First edition 1999 published by
the Fédération Internationale des Ingénieurs-Conseils (FIDIC) and the following
“Particular Conditions” which are the Employer created amendments and additions
to such General Conditions.
Copies of the FIDIC Contract for Plant and Design Build can be obtained from:
International Federation of Consulting Engineers
World Trade Centre II
P.O. Box 311
CH-1215 Geneva 15
Switzerland
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 192
The following Particular Conditions shall supplement the GC. Whenever there is a
conflict, the provisions herein shall prevail over those in the GC.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
193 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 194
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
195 Section IX. Particular Conditions
Percentage of 14.3(c) 5%
Retention
Limit of Retention 14.3(c) 5% of the Accepted Contract Amount
Money
Minimum Amount of 14.6 Not less than 200,000 USD or equivalent.
Interim Payment
Certificates
Contractor’s Bank 14.7 To be defined.
Account
Payment of Retention 14.9 Payment of first half Retention money after
Money issuance of all (MMHEP, Surkhet and Gandak)
Taking Over Certificates.
To the Engineer:
To the Engineer:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 196
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
197 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 198
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
199 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 200
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
201 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 202
The Employer's 2.5 Replace the first sentence of the second paragraph
Claims as follows: “Notice shall be given as soon as
practicable but not later than 42 days after the
Employer became aware of the event or
circumstances giving rise to the claim.”
Replacement of 3.4 Not applicable
the Engineer
Contractor’s 4.1 Insert the following at the end of the 2nd
General paragraph:
Obligations “Goods and services from countries under embargo
from Germany, the European Union or the United
Nations are not eligible and shall not be used by the
Contractor.”
Add under the first paragraph:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
203 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 204
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
205 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 206
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
207 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 208
Facilities for Staff 6.6 Except as otherwise stated in the Specification, the
and Labour Contractor shall provide and maintain all necessary
accommodation and welfare facilities for the
Contractor’s Personnel. The Contractor shall also
provide facilities for the Employer’s Personnel as
stated in the Specification.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
209 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 210
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
211 Section IX. Particular Conditions
Remedial Work 7.6 Add new paragraph at the end of the Sub-Clause:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 212
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
213 Section IX. Particular Conditions
Delay Damages 8.7 Add new paragraph at the end of the Sub-Clause:
The resulting amount shall be paid according to the
Employer's instructions.
Suspension of 8.8 Add the following after the last sentence of the Sub-
Work Clause:
“As an example, and without limitation to other
possible causes, any suspension of work caused by
any failure from the Contractor to comply with the
obligations stated :
(a) Under the ESHS Specifications (if any), in the
event of a level 3 non-compliance;
(b) Under Sub-Clause 4.8 as to safety
procedures;
(c) Under Sub-Clause 4.9 as to the quality
assurance;
(d) Under Sub-Clause 4.18 as to the protection of
the environment; or
(e) Under Sub-Clause 6.7 as to health and safety;
shall be considered as cause of suspension which is
the responsibility of the Contractor”.
Taking Over of 10.1 The complete last paragraph of the Sub-Clause is
deleted and replaced as follows:
the Works and
Sections The date on which the Works or Sections were
completed in accordance with the Contract (including
the Tests on completion as per Clause 9) will be the
date applied for by the Contractor in accordance with
this Sub-Clause.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 214
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
215 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 216
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
217 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 218
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
219 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 220
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
221 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 222
Payment Procedures:
b. Local Currency
The Employer shall make/arrange payments
promptly within fifty six (56) days of
submission of an invoice/claim by the
Contractor, complete in all respects and
supported by the requisite documents and
fulfillment of stipulated conditions, if any. All
the payment shall be released to the
Contractor directly by KfW on Direct
Disbursement basis based on the certification
of the Employer. Necessary details to this
effect shall be tied-up with the successful
bidder.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
223 Section IX. Particular Conditions
c. Invoices
The Contractor shall submit the invoices
(original) in triplicate to the Project Office
whenever an invoice is required to be
submitted as per provision of the Contract.
Invoices should be duly certified by Project
Manager.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 224
Disbursement Schedule:
The Contractor shall submit, together with each
application for payment/invoice, a disbursement
schedule showing invoice number, type of invoice,
invoicing date, invoiced amount, amount received,
and date received. An updated version shall be added
to the Progress Reports.
Reimbursement Clause
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
225 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 226
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
227 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 228
In Nepal
General:
(a) Unless otherwise specifically declared in the
contract documents, the prices quoted by the bidder
in their bid and its suppliers and subcontractors shall
include business taxes and other taxes that may be
levied in accordance with the laws and regulations in
force or in effect in Nepal as of 28 days prior to the
closing date for submission of tenders in the
Employer's country on the Equipment, Plant,
Materials and Supplies (permanent, temporary and
consumables) acquired for the purpose of the
Contract and on the services performed under the
Contract. Whatsoever provisions made in the
Contract document shall not relieve the Contractor, its
suppliers and subcontractors from their responsibility
to pay income tax that may be levied in the Employer's
country on profits made by the Contractor, its
suppliers and subcontractors in respect of the
Contract.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
229 Section IX. Particular Conditions
Import License:
The Contractor shall inform the Employer and the
Engineer in writing the details of the equipment and
materials to be imported into Nepal for use on the
Works at least 56 days prior to arrival of shipment at
disembarkation port and shall submit a formal written
request for assistance from the Employer for
importation processing. The Employer will assist the
Contractor to obtain necessary permits for import of
such equipment and materials into Nepal. Import
license fees or any other charges shall be at the cost
of the Contractor. The Contractor shall be responsible
for transport from the Port of disembarkation to the
Site or location of the Works. The Contractor shall be
fully responsible to determine these rates and the
amount payable at the time of preparing tender
document and include such costs in its bids. In failing
to do so, the Employer shall not be liable to pay such
costs and the Contractor shall pay such charges as
local or any customs authorities en-route may impose,
which will not be an eligible item for refund from the
Employer.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 230
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
231 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 232
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
233 Section IX. Particular Conditions
By:
“Within the period stated in the Contract Data
(calculated from the Commencement Date), the
Contractor shall submit to the Employer:”
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 234
Cargo insurance:
The contracted insurance shall be in accordance with
the Institute Cargo Clauses (A) or (AIR) or (All Risks)
and if necessary, the Institute War Clauses (Cargo) or
(AIR CARGO) and the Institute Strikes Clauses
(Cargo) or (AIR CARGO) of the Institute of London
Underwriters, 1982 edition, or any similar set of
clauses.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
235 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 236
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
237 Section IX. Particular Conditions
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 238
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
239 Section IX. Particular Conditions
18 In case ILO conventions have not been fully ratified or implemented in the Employer’s country the
Applicant/Bidder/Contractor shall, to the satisfaction of the Employer and KfW, propose and implement
appropriate measures in the spirit of the said ILO conventions with respect to a) workers grievances on working
conditions and terms of employment, b) child labour, c) forced labour, d) worker’s organisations and e) non-
discrimination.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section IX. Particular Conditions 240
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
241 Section X. Contract Forms
Table of Forms
Notification of Award............................................................................................242
Performance Security...........................................................................................255
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 242
Notification of Award
Letter of Acceptance
[Letterhead paper of the Employer]
[Date]
This is to notify you that your Bid dated [date] for execution of the [name of the Contract
and identification number, as given in the Contract Data] for the Contract Price [amount
in numbers and words] [name of currency], as corrected and modified in accordance
with the Instructions to Bidders, is hereby accepted by our institution.
You are requested to furnish the Performance Security within 28 days in accordance
with the Conditions of Contract, using for that purpose the Performance Security Form
included in Section X, Contract Forms, of the Bidding Documents.
Authorized Signature:
Name and Title of Signatory:
Name of institution:
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
243 Section X. Contract Forms
Contract Agreement
3. The Appendixes listed in the attached List of Appendixes shall be deemed to form an
integral part of this Contract Agreement:
Appendix 1 - Price Adjustment
Appendix 2 - Insurance Requirements
Appendix 3 - Time Schedule
Appendix 4 - List of Major Items of Plant and Services and List of Approved
Subcontractors
Appendix 5 - Scope of Works and Supply by the Employer
Appendix 6 - List of Documents for Approval or Review
Appendix 7 - Functional Guarantees
Reference in the Contract to any Appendix shall mean the Appendixes attached hereto,
and the Contract shall be read and construed accordingly.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 244
5. The Employer hereby covenants to pay the Contractor in consideration of the execution
and completion of the Works and the remedying of defects therein, the Contract Price or
such other sum as may become payable under the provisions of the Contract at the times
and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of _____________________________ on the day, month and year
specified above.
Signed by ________________________________________________ (for the Employer)
Signed by __________________________________________________ (for the Contractor)
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
245 Section X. Contract Forms
Not Applicable
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 246
In accordance with the provisions of GCC Clause 34, the Contractor shall at its expense
take out and maintain in effect, or cause to be taken out and maintained in effect, during
the performance of the Contract, the types of insurance set forth below in the sums and
with the deductibles and other conditions specified. The identity of the insurers and the
form of the policies shall be subject to the approval of the Employer, such approval not
to be unreasonably withheld.
Deductible Parties
Amount From To
limits insured
[in [in
[names] [place] [place]
currency(ies)] currency(ies)]
110% of total price
Dispatch Site
for plant and (*) Contractor
Certificate Delivery
equipment
(*) Excess 5% of claimed amount subject to minimum of NRs. 20,000 for Normal and
NRs. 80,000 for act of God perils and collapse.
Deductible Parties
Amount From To
limits insured
[in [in
[names] [place] [place]
currency(ies)] currency(ies)]
110% of total price
Site Final
for plant and (*) Contractor
Delivery Acceptance
equipment
(*) Excess 5% of claimed amount subject to minimum of NPRs. 500,000 for Normal and
NPRs. 15,000,000 for testing period
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
247 Section X. Contract Forms
Covering bodily injury or death suffered by third parties (including the Employer’s
personnel) and loss of or damage to property (including the Employer’s property and
any parts of the Facilities that have been accepted by the Employer) occurring in
connection with the supply and installation of the Facilities.
Deductible Parties
Amount From To
limits insured
[in [in
currency(ies) currency(ies) [names] [place] [place]
] ]
NRs. Contractor’ Final
Commenceme
1,000,000 as s Acceptanc
nt of work
in (b) above Employee e
NRs. Final
Third Party Commenceme
1,000,000 as Acceptanc
Personnel nt of work
in (b) above e
NRs. Final
Third Party
1,000,000 as Site Delivery Acceptanc
Personnel
in (b) above e
Details:
Deductible
Amount Parties insured From To
limits
[in [in
[names] [place] [place]
currency(ies)] currency(ies)]
The Employer shall be named as co-insured under all insurance policies taken out by
the Contractor pursuant to GCC Subclause 34.1, except for the Third Party Liability,
Workers’ Compensation, and Employer’s Liability Insurance, and the Contractor’s
Subcontractors shall be named as co-insureds under all insurance policies taken out by
the Contractor pursuant to GCC Subclause 34.1, except for the Cargo, Workers’
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 248
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
249 Section X. Contract Forms
The Employer shall at its expense take out and maintain in effect during the performance
of the Contract the following insurance policies. NONE
Details:
Deductible
Amount Parties insured From To
limits
[in [in
[names] [place] [place]
currency(ies)] currency(ies)]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 250
1.1 The activity(ies) under the Contractor’s program for Project Completion shall be in the
form of a master network (MNW) and shall identify the various activities like design,
engineering, manufacturing, supply, installation, factory testing, transportation to site,
site testing and commissioning, trial operation and Taking Over etc. of the Facilities or
specific part thereof (where specific parts are specified in SCC). The network shall
conform to the above Project Completion Schedule.
This master network will be discussed and agreed before Award in line with above,
engineering drawing and data submission schedule shall also be discussed and finalized
before Award. Liquidated damages for delay in successful completion of the Facilities or
specific part thereof (where specific parts are specified in SCC) and Operational
Acceptance at rates specified in relevant SCC clause shall be applicable beyond the
date specified above.
1.2 The Employer reserves the right to request minor changes in the work schedule at the
time of Award of Contract to the successful Bidder.
1.3 The successful Bidder shall be required to prepare detailed Network(s) and project
implementation plans & program and finalize the same with the Employer as per the
requirement specified in Technical Specifications, which shall from a part of the
Contract.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
251 Section X. Contract Forms
APPENDIX 4 - LIST OF MAJOR ITEMS OF PLANT AND SERVICES AND LIST OF APPROVED
SUBCONTRACTORS
The following Subcontractors and Manufacturers are approved for carrying out the item
of the facilities indicated. Where more than one Subcontractor is listed, the Contractor
is free to choose between them, but it must notify the Employer of its choice in good
time prior to appointing any selected Subcontractor. In accordance with GCC
Subclause 19.1, the Contractor is free to submit proposals for Subcontractors for
additional items from time to time. No Subcontracts shall be placed with any such
Subcontractors for additional items until the Subcontractors have been approved in
writing by the Employer and their names have been added to this list of Approved
Subcontractors.
Major Items of
Approved Subcontractors and
Plant and Nationality
Manufacturers
Services
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 252
Personnel, facilities, works, and supplies will NOT be provided or supplied by the
Employer.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
253 Section X. Contract Forms
Pursuant to GCC Clause 5 Design, the Contractor shall prepare, or cause its
Subcontractor to prepare, and present to the Project Manager the following documents
for
(A) Approval
1. Work Program
2. Work Procedure
(B) Review
None
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 254
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
255 Section X. Contract Forms
Performance Security
We have been informed that [Insert name and address of contractor, which in the case
of a joint venture shall be the name and address of the joint venture] (hereinafter called
“the Applicant”) has entered into Contract No. [Insert reference number of the contract]
dated [Insert contract date] with the Beneficiary, for the execution of [Insert object of
the contract and brief description of Works] (hereinafter called “the Contract”).
Furthermore we understand that, according to the conditions of the Contract, a
performance guarantee is required for [Insert percentage in words and figures] % of
the contract price.
Waiving all objections and defences, we, as Guarantor, hereby irrevocably and
independently undertake to pay the Beneficiary any sum or sums not exceeding in total
an amount of [Insert guarantee amount and currency in words and figures]19 upon
receipt by us of the Beneficiary’s first demand, supported by the Beneficiary’s
statement, whether in the demand itself or a separate signed document accompanying
or identifying the demand, stating that the Applicant is in breach of its obligation(s)
under the Contract, without the Beneficiary needing to prove or to show grounds for
the demand or the sum specified therein.
In the event of any claim under this guarantee, payment shall be effected to account
No.: 9900001460000955 maintained at NMB Bank Limited, Babarmahal, Kathmandu
(Account holder: NEA-Promotion of Solar Energy Project)
This guarantee shall expire not later than [Insert expiry date]20.
By this date we must have received any claims for payment by letter or encoded
telecommunication.
It is understood that you will return this guarantee to us on expiry or after payment of
the total amount to be claimed hereunder.
[As preferred option regarding guarantee rules insert21: This guarantee is subject to
the Uniform Rules for Demand Guarantees (URDG) 2010 Revision, ICC Publication
No. 758, except that the supporting statement under Article 15(a) is hereby excluded.]
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 256
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
257 Section X. Contract Forms
We have been informed that [Insert name and address of contractor, which in the case
of a joint venture shall be the name and address of the joint venture] (hereinafter called
“the Applicant”) has entered into Contract No. [Insert reference number of the contract]
dated [Insert contract date] with the Beneficiary, for the execution of [Insert object of
the contract and brief description of Works] (hereinafter called “the Contract”).
Furthermore we understand that, according to the conditions of the Contract, an
advance payment in the sum of [Insert amount and currency in words and figures]22,
representing [Insert percentage in words and figures] % of the contract price, is to be
made against an advance payment guarantee.
Waiving all objections and defences, we, as Guarantor, hereby irrevocably and
independently undertake to pay the Beneficiary, any sum or sums not exceeding in
total an amount of [Insert guarantee amount and currency in words and figures] upon
receipt by us of the Beneficiary’s first demand, supported by the Beneficiary’s
statement, whether in the demand itself or a separate signed document accompanying
or identifying the demand, stating that the Applicant is in breach of its obligation(s)
under the Contract, without the Beneficiary needing to prove or to show grounds for
the demand or the sum specified therein.
The advance payment guarantee shall come into force and effect as soon as the
advance payment has been credited to the Applicant on its account. Minor deductions
of the above mentioned amount notably due to bank fees shall have no effect on the
entry into force.
[For guarantees issued in foreign currency insert the following:
In the event of any claim under this guarantee, payment shall be effected to [Either
insert the account on which payments are to be made with prior approval from KfW or,
if no particular account is provided, insert instead:] KfW, Frankfurt am Main (BIC:
KFWIDEFF, BLZ 500 204 00), account no. 38 000 000 00 (IBAN: DE53 5002 0400
3800 0000 00), for the account of [Insert name of the Purchaser and the Purchaser’s
country].
[For guarantees issued in local currency insert the following:
In the event of any claim under this guarantee, payment shall be effected to [Insert the
account on which payments are to be made], for the account of [Insert name of the
Purchaser and the Purchaser’s country].
The maximum amount of this guarantee shall be progressively reduced by the amount
of the advance payment repaid by the Applicant as specified in copies of interim
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 258
statements or payment certificates which shall be presented to us. This guarantee shall
expire, at the latest, upon our receipt of a copy of the interim payment certificate
indicating that ninety (90) per cent of the Accepted Contract Amount, less provisional
sums, has been certified for payment, or on the [Insert date], whichever is earlier.
Consequently, any demand for payment under this guarantee must be received by us
at this office on or before that date, by letter or encoded telecommunication.
It is understood that you will return this guarantee to us on expiry or after payment of
the total amount to be claimed hereunder.
[As preferred option regarding guarantee rules insert23: This guarantee is subject to
the Uniform Rules for Demand Guarantees (URDG) 2010 Revision, ICC Publication
No. 758, except that the supporting statement under Article 15(a) is hereby excluded.]
23 In the case the issuing bank will not add the preferred option, the following must be added instead:
This guarantee is governed by the laws of [Insert country of jurisdiction]. Note: the country of
jurisdiction shall be the country where the bank’s branch issuing the guarantee is physically
located.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
259 Section X. Contract Forms
We have been informed that [Insert name and address of contractor, which in the case
of a joint venture shall be the name and address of the joint venture] (hereinafter called
“the Applicant”) has entered into Contract No. [Insert reference number of the contract]
dated [Insert contract date] with the Beneficiary, for the execution of [Insert object of
the contract and brief description of Works] (hereinafter called “the Contract”).
Furthermore we understand that, according to the conditions of the Contract, the
Beneficiary retains moneys up to the limit set forth in the Contract (“the Retention
Money”), and that when the Taking-Over Certificate has been issued under the
Contract and the first half of the Retention Money has been certified for payment,
payment of [insert the second half of the Retention Money or if the amount guaranteed
under the Performance Guarantee when the Taking-Over Certificate is issued is less
than half of the Retention Money, the difference between half of the Retention Money
and the amount guaranteed under the Performance Security] is to be made against a
Retention Money guarantee.
Waiving all objections and defences, we, as Guarantor, hereby irrevocably and
independently undertake to pay the Beneficiary any sum or sums not exceeding in total
an amount of [insert guarantee amount and currency in words and figures] 24 upon
receipt by us of the Beneficiary’s first demand supported by the Beneficiary’s
statement, whether in the demand itself or in a separate signed document
accompanying or identifying the demand, stating that the Applicant is in breach of its
obligation(s) under the Contract, without the Beneficiary needing to prove or show
grounds for the demand or the sum specified therein.
The retention money guarantee shall come into force and effect as soon as the second
half of the Retention Money has been credited to the Applicant on its account. Minor
deductions of the above mentioned amount notably due to bank fees shall have no
effect on the entry into force.
[For guarantees issued in foreign currency insert the following:
In the event of any claim under this guarantee, payment shall be effected to [either
insert the account on which payments are to be made with prior approval from KfW or,
if no particular account is provided, insert instead:] KfW, Frankfurt am Main (BIC:
KFWIDEFF, BLZ 500 204 00), account no. 38 000 000 00 (IBAN: DE53 5002 0400
24
The Guarantor shall insert an amount representing the amount of the second half of the Retention
Money or if the amount guaranteed under the Performance Guarantee when the Taking-Over
Certificate is issued is less than half of the Retention Money, the difference between half of the
Retention Money and the amount guaranteed under the Performance Security and denominated in
the contract currency(ies) only.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010
Section X. Contract Forms 260
3800 0000 00), for the account of [Insert name of the Purchaser and the Purchaser’s
country].
[For guarantees issued in local currency insert the following:
In the event of any claim under this guarantee, payment shall be effected to [Insert the
account on which payments are to be made], for the account of [Insert name of the
Purchaser and the Purchaser’s country].
This guarantee shall expire not later than [Insert expiry date]25.
By this date we must have received any claims for payment by letter or encoded
telecommunication.
It is understood that you will return this guarantee to us on expiry or after payment of
the total amount to be claimed hereunder.
[As preferred option regarding guarantee rules insert26: This guarantee is subject to
the Uniform Rules for Demand Guarantees (URDG) 2010 Revision, ICC Publication
No. 758, except that the supporting statement under Article 15(a) is hereby excluded.]
25Insert the same expiry date as set forth in the performance security, representing the date twenty-
eight days after the completion date described in the Appendix to Bid. The Employer should note that
in the event of an extension of this date for completion of the Contract, the Employer would need to
request an extension of this guarantee from the Guarantor. Such request must be in writing and must
be made prior to the expiration date established in the guarantee. In preparing this guarantee, the
Employer might consider adding the following text to the form, at the end of the penultimate
paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to
exceed [six months][one year], in response to the Beneficiary’s written request for such extension,
such request to be presented to the Guarantor before the expiry of the guarantee.”
26In the case the issuing bank will not add the preferred option, the following must be added instead:
This guarantee is governed by the laws of [Insert country of jurisdiction]. Note: the country of
jurisdiction shall be the country where the bank’s branch issuing the guarantee is physically located.
ICB-SEPP-EPC-SOLAR-01/2024-KfW-BMZ-PN511010