Sap Apo SNP CTM
Sap Apo SNP CTM
Special Sorting
1) Demand Prioritization
SPRO – IMG - Advanced Planning and Optimization - Supply Chain Planning - Multilevel Supply &
Demand Matching (SDM) - Capable-to-Match (CTM) - Demand Prioritization - Define Special Sorting
SAVE
SPRO – IMG - Advanced Planning and Optimization - Supply Chain Planning - Multilevel Supply &
Demand Matching (SDM) - Capable-to-Match (CTM) - Define Supply Categories
In its search for a feasible solution, Capable to Match (CTM) considers constraints and priorities. CTM
prioritizes demand and categorizes supplies to come up with the first feasible solution, which is not
necessarily the optimum solution. This is the reason why it is recommended to use CTM in conjunction
with the other SNP planning runs.
Powertastic’s top management has decided that priorities will not be set for the location-specific
products or for locations. Therefore, prioritization will occur on a first-come, first-serve basis by due
dates. Powertastic’s policy is to satisfy all customer orders, before the forecasted demand.
Procedure:
SPRO – IMG - Advanced Planning and Optimization - Supply Chain Planning - Multilevel Supply &
Demand Matching (SDM) - Capable-to-Match (CTM) - Demand Prioritization - Define Sort Profile
4. Enter TD_SORT_XX
5. Select the new profile created by clicking the small rectangular box to the left of the profile name
6. Double click on the criteria folder on the left side section of the screen.
8. Select the ATPCAT field from the drop down list under the field name column
10. Select the delivery date (LFTMS) field from the drop down list under the field name column
12. Save
The CTM time stream will enable Powertastic to create a planning period based on more flexible time
bucketing than it is possible with an APO time stream.
1 365
Document Type Configuration
APO Module SNP – Supply Network Planning
Activity Sort Profile
Transaction /nspro
SPRO – IMG - Advanced Planning and Optimization - Supply Chain Planning - Multilevel Supply &
Demand Matching (SDM) - Capable-to-Match (CTM) - Define CTM Time Stream
Note: You may also reach the same transaction through the CTM menu.
Procedure:
2. Click on to create
6. Save.
5. Change Planning Strategy in the Product Master
In order to consider both the sales orders and forecast requirements in the total demand, include
planning strategy 20 (Planning with Final Assembly) in the demand tab of TD_FSD_XX product master at
location TD_DLO_XX.
Procedure:
2. Enter Product : TD_FSD_XX, Location: TD_DLO_XX. Ensure both check buttons are also selected.
4. Demand Tab
The CTM profile allows Powertastic to access the CTM control panel, which contains all the
necessary settings, needed for a CTM planning run. In this step, you will create a work area and new
profile for your Powertastic subset.
SAP menu - Advanced Planning and Optimization - Multilevel Supply & Demand Matching –
Environment - Master Data Selection
T.Code - /SAPAPO/CTMMSEL
2. Click on
5. You will only plan for the products- location relationships that you have created. Therefore,
include Your Model : 000 in Model Name
9. Press Generate button, system generates the product location combinations for the model
and other master data as well
10. Go To external Procurement Tab and check the transportation lanes (TD_PCH_XX to
TD_DLO_XX and TD_VPO_XX to TD_PCH_XX) have been correctly generated (green light)
11. In The In-house Production , check that the Plan TD_FSD_CHICAGO_XX have been correctly
generated (green light)
12. Save
SAP menu - Advanced Planning and Optimization - Multilevel Supply & Demand Matching –
Environment - Order Selection
T.Code - /SAPAPO/CTMORDSEL
5. You will only plan for the products- location relationships that you have created. Therefore, include
Master Data Selection TD_SEL_XX.
SAP menu - Advanced Planning and Optimization - Multilevel Supply & Demand Matching –
Planning - Capable-to-Match (CTM) Planning
T.Code - /SAPAPO/CTM
2. Click on
5. Click on at the following information screen (Status of CTM Planning Profile PRF_PP was reset)
8. Click on All Master Data in Model in the master data selection section.
9. Save
13. In Master data Selection-> Choose Radio button Master Data Selection
The CTM planning method determines which orders will be included in the CTM planning run based on
the pegging relationships in an order net. The planning method configured in the strategies tab of the
CTM profile.
In this exercise you will be required to configure a planning method, create a search strategy and
complete the strategies tab for your Powertastic CTM profile.
1. Create search strategy SXX for you Powertastic CTM profile. The strategy is the sequence in which
the system will search the supply categories so it can fill the order. The search strategy should
followed the sequence below:
To create your search strategy from the CTM Profile screen go to: Edit -> Search Strategy
Click on
Click on New Entry and enter data based on guidelines provided for search strategy per table 1
Table 1
Sequence Category
1 W3
2 W2
Save
Click on to go to the CTM profile screen.
Discussion:
In the area of supply categorization, Powertastic will use the CTM run to achieve three main objectives:
Supply items will be assigned to categories such as normal or excess stock. When an order for an item
comes in, the system searches for the best way to meet the demand based on the strategy that you
would assign (SXX). The strategy is the sequence in which the system will search the supply categories
so it can fill the order.
Procedure:
Go to “Strategies” Tab
Save.
3. Assign sort profile to the CTM Profile
Go to “ Demands tab”
Hit enter when you get a message to enter the sort profile
Save
4. Check Data
To check data from the CTM profile screen, go to - Edit -> Check Your Data
Make sure that all the planning objects are checked in the “CTM: Select Master Data to be
Checked” screen
Click
Make sure that there are no error messages (no red lights)
Click on the green back arrow twice to come back to main menu.
Due to the fact that the demand planning team is absent today, you will be required to load the
demand manually for Powertastic distribution center in Los Angeles, CA. Note that in this exercise you
are required to create two types of demand (Forecast and Sales orders)
Procedure:
1. To create demand manually for version TD_VER3_XX, go to: Tools ABAP/4 workbench
Development ABAP editor (Transaction Code SE38)
In this field Enter
Program /SAPAPO/SJKTST04
Version 000
Location TD_DLO_XX
Category BM
Product TD_FSD_XX
Horizon 5
Quantity 2000
4. Press the execute button (green clock check mark) on the upper left hand side of your screen.
5. Press green check mark to acknowledge that sales orders will be copied to liveCache.
Version 000
Location TD_DLO_XX
Category FA
Product TD_FSD_XX
In this field Enter
Horizon 5
Quantity 2000
7. Press the execute button (green clock check mark) on the upper left hand side of your screen.
8. Press green check mark to acknowledge that sales orders will be copied to liveCache.
CTM takes current demand data stored in liveCache (e.g., sales orders and Demand Planning forecasts)
and prioritizes them based on type of demand, defined priorities and due dates.
Prioritizing determines the order in which Powertastic demands are processed in the CTM run.
2. All customer orders will be satisfied based on a first come – first serve basis.
Procedure:
To access the CTM profile from the APO main menu, go to:
Click on Demand at the bottom of the screen and fill results in the table below
Product Pr. : Priority Cat : Demand Date
Category (Order type)
Result: The demand is listed based on the priority set in the sort profile
7. CTM Profile – Supply Tab
In the CTM supply tab, Powertastic will define the sequence, in which the system searches the supply
categories (configured in exercise 15). During supply categorization, the supply objects are assigned to
In this exercise, you will be required to configure the supply limits for each of the Powertastic supply
categories as well as complete the CTM supply tab of your CTM profile.
From the APO main menu, Multilevel Supply & Demand Matching Planning Capable-to-Match
(CTM) Planning
3. Click Yes on the CTM - Supply Limits ID window (Message: The entered ID does not exist. Do you
want to create ID)
4. Enter a description for this set of supply limits (Supply Limits for XX)
Product TD_FSD_XX
In this field... Do this
Location TD_DLO_XX
Limit 1 1000
Limit 2 2000
6. Save
12. Double Click on the folder for Profile CAT_XX in the Left Window
15. Double click on the Supply Limits under the profile folder
13. Save
From the APO main menu, Multilevel Supply & Demand Matching Planning Capable-to-Match
(CTM) Planning
Assign the CTM time stream created for Powertastic to the Transportation lanes corresponding to Plant
to DC and Vendor to Plant in the transportation calendar field
Procedure
3. Press Change
4. In the Central table (means of Transport) , Assign CTM_XX Time stream to Transport Calendar
5. Save
The CTM planning run matches the categorized supplies to the prioritized demands. Run the CTM
planning for your Powertastic model.
Procedure:
Access the CTM profile from the APO main menu, go to:
3. Look at Planning results in interactive planning /N/SAPAPO/SDP94 or (You can also navigate from
CTM profile using button.