Attachment # 6B BOQ For Habshan Station Executed Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Attachment # 6B

Habshan Station Executed Works


Reference for Unit
Specification / Unit Unit Rate Total Cost
S.No Description Quantity rate (13528001‐A.04 ‐ Remarks
Standard (Quantity) (USD) (USD)
EPC SOW)

Following Items completed by EPC CONTRACTOR at HABSHAN Area


Civil Items
2
1 Site clearance Extra 2 m all around m 92.00 15.00 1,380.00 A.4.4.5.1 Item 1.1
2 Valve Pit m3 21.25 2000.00 42,508.80 A.4.4.5.2 Item 4.2.c
3 Pipe support m3 2.16 748.00 1,615.68 A.4.4.5.2 Item 4.1.a
4 Access Gate 1.0 m Wide Nos 1.00 2700.00 2,700.00 A.4.4.5.1 Item 6.3
5 Block Work 200 Thick m2 45.60 55.00 2,508.00 A.4.4.5.2 Item 6.1.e
6 Fencing m 30.40 240.00 7,296.00 A.4.4.5.1 Item 6.1
7 Paving Heavy Duty Tiles m2 47.04 100.00 4,704.00 A.4.4.5.1 Item 8.1
Total 62,712.48
Piping /PipeLine Items (4" Line)
Valve
1 Hot tapping 4" x4 " Nos 1 36000 36,000.00 A.4.4.5.4.7 Procurement
EXCLUDED
Pipe work 12 m ‐ standard
2 Nos/inch 33.33 40 1,333.33 A.4.4.5.4.1 S.No 1
Welding pipeline length
Pipe Work laying
3 m/inch 100.00 50 5,000.00 A.4.4.5.4.2
and installation
Excavation for
4 90.00 27 2,430.00 A.4.4.5.1 Item No 3.1
Pipeline
Placement and
Backfilling for
5 89.22 7.2 642.35 A.4.4.5.1 Item No 4.3 compaction cost
pipeline
considered

Placement and
6 Berm Sand 100.00 7.2 720.00 A.4.4.5.1 Item No 4.3 compaction cost
considered
7 Berm Gatch 100.00 22 2,200.00 A.4.4.5.1 Item No 4.6
Total 48,325.68

Total Construction Cost based on actual work executed by Contractor based on unit rates
111,038.16
for Variation (Addition or deletion of SOW)=

Total Construction and Pre‐Commissioning Cost as per Agreement (13528001‐A.04) Clause


701,940.00
A4.1.3=

Total Construction Cost to be recovered from CONTRACTOR based on balance amount as Amount to be gained from
590,901.84
per Agreement (13528001‐A.04) Clause A4.1.3= CONTRACTOR

You might also like