NS130
NS130
NS130
Document No : NW000-S0088
Amendment No : 5
NETWORK Approved By : Head of AR&P
Approval Date : 01/10/2020
Review Date : 01/10/2023
Minor amendments approved 08/09/2021
ISSUE
For issue to all Ausgrid and Accredited Service Providers’ staff involved with the design and installation of underground cables and
conduits, and is for reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments on www.ausgrid.com.au.
Where this Standard is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document.
DISCLAIMER
As Ausgrid’s Standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at
any time. It is possible that conflict may exist between Standard documents. In this event, the most recent Standard shall prevail.
This document has been developed using information available from field and other sources and is suitable for most situations
encountered in Ausgrid. Particular conditions, projects or localities may require special or different practices. It is the responsibility of
the local manager, supervisor, assured quality contractor, accredited service provider and the individuals involved to make sure that
a safe system of work is employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for anything done or not done, as a result of this Standard.
All design work, and the associated supply of materials and equipment, must be undertaken in accordance with and consideration of
relevant legislative and regulatory requirements, latest revision of Ausgrid’s Network Standards and specifications and Australian
Standards. Designs submitted shall be declared as fit for purpose. Where the designer wishes to include a variation to a Network
Standard or an alternative material or equipment to that currently approved the designer must obtain authorisation from the Network
Standard owner before incorporating the variation to a Network Standard or alternative material into a design. All designers including
external designers authorised as Accredited Service Providers will seek approval through the approved process as outlined in NS181
Approval of Materials and Equipment and Network Standard Variations. Seeking approval will ensure Network Standards are
appropriately updated and that a consistent interpretation of the legislative framework is employed.
Notes: 1. Compliance with this Network Standard does not automatically satisfy the requirements of a Designer Safety Report. The
designer must comply with the provisions of the Work Health and Safety Regulation 2017 (NSW - Part 6.2 Duties of designer of
structure and person who commissions construction work) which requires the designer to provide a written safety report to the person
who commissioned the design. This report must be provided to Ausgrid in all instances, including where the design was commissioned
by or on behalf of a person who proposes to connect premises to Ausgrid’s network, and will form part of the Designer Safety Report
which must also be presented to Ausgrid. Further information is provided in Network Standard (NS) 212 Integrated Support
Requirements for Ausgrid Network Assets.
2. Where the procedural requirements of this document conflict with contestable project procedures, the contestable project
procedures shall take precedent for the whole project or part thereof which is classified as contestable. Any external contact with
Ausgrid for contestable works projects is to be made via the Ausgrid officer responsible for facilitating the contestable project. The
Contestable Ausgrid officer will liaise with Ausgrid internal departments and specialists as necessary to fulfil the requirements of this
Standard. All other technical aspects of this document which are not procedural in nature shall apply to contestable works projects.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain, ambiguous or otherwise in need of
interpretation, the user should request Ausgrid to clarify the provision. Ausgrid’s interpretation shall then apply as though it was
included in the Standard, and is final and binding. No correspondence will be entered into with any person disputing the meaning of
the provision published in the Standard or the accuracy of Ausgrid’s interpretation.
KEYPOINTS
This Standard has a summary of content labelled “KEYPOINTS FOR THIS STANDARD”. The inclusion or omission of items in this
summary does not signify any specific importance or criticality to the items described. It is meant to simply provide the reader with a
quick assessment of some of the major issues addressed by the Standard. To fully appreciate the content and the requirements of
the Standard it must be read in its entirety.
Where there are changes to this Standard from the previously approved version, any previous shading is removed and the newly
affected paragraphs are shaded with a grey background. Where the document changes exceed 25% of the document content, any
grey background in the document is to be removed and the following words should be shown below the title block on the right hand
side of the page in bold and italic, for example, Supersedes – document details (for example, “Supersedes Document Type (Category)
Document No. Amendment No.”).
This network standard NS130 provides the This standard includes the following topics in Construction requirements may include Where there are post construction requirements
requirements for trenching, laying and relation to project planning and design and the references to safety and construction that need to be considered they should be
reinstatement of underground conduits and excavation works required: management processes: summarised here.
cables, for distribution circuits up to and
including a nominal 11kV in Ausgrid’s The client is responsible for obtaining all Describes details of Joint pits, bays, vaults Describes the requirements of backfilling of
supply area. The standard is limited to development consents (refer NS104 and concrete construction work. excavations and reinstatement of
scope identified below and provides Specification for Electrical Network Project Describes installation requirements of pavements and pathways.
controls for associated risks as listed below: Design Plans). conduits, power and control cables,
General design requirements outlined for thermally stable bedding material.
The needs of Ausgrid, developers, new residential subdivisions, CBD projects, Specifies Standard depth of cover and
customers, Roads and Maritime roadway, driveway and rail track crossings. reduced depth of cover requirements
Services, local councils and other Also outlined is the requirement for cable
service utilities have been addressed easements on private property, provision
in this standard. of detailed designs, Ausgrid site
This standard frequently references inspections, and provision of field book
NATSPEC 1152 – Road Openings and recordings.
restorations (Utilities) document.
Where to for more information? Where to for more information? Where to for more information?
Section 4, 5, 6 & 7 Section 8, 9, 10, 11, 12 & 13 Section 14 & 15
Network Standard
NS130
Laying Underground Cables up to and including 11kV
Contents
PURPOSE ............................................................................................................................................. 8
SCOPE .................................................................................................................................................. 8
NATSPEC 1152 ..................................................................................................................................... 8
PROJECT PLANNING AND DESIGN ................................................................................................... 8
General ....................................................................................................................................... 8
New residential subdivisions ...................................................................................................... 8
Central business district (CBD) projects ..................................................................................... 8
Roadway crossings .................................................................................................................... 9
Driveway crossings ..................................................................................................................... 9
Railway track crossings .............................................................................................................. 9
Trenchless technology ................................................................................................................ 9
Ausgrid’s cables in easements on private property .................................................................... 9
Provision of detailed design by the client ................................................................................. 10
Inspection by Ausgrid ............................................................................................................... 10
Provision of field book recordings and survey plans ................................................................ 10
Field recording of network assets ............................................................................. 10
Survey plan (red line plan) ........................................................................................ 10
Registration of easement.......................................................................................................... 10
Installation of cables under waterways ..................................................................................... 10
SETTING OUT OF EXCAVATIONS .................................................................................................... 11
General ..................................................................................................................................... 11
Additional work ......................................................................................................................... 11
Shared trenching agreements .................................................................................................. 11
Dimensions of trenches ............................................................................................................ 12
Pegging of easements .............................................................................................................. 12
Set out for excavations in new subdivisions ............................................................................. 12
Set out for excavations in established areas ............................................................................ 13
EXCAVATION OF TRENCHES AND OTHER SITES ......................................................................... 14
General ..................................................................................................................................... 14
Removal of pavement layers in established areas ................................................................... 14
Locating existing services......................................................................................................... 14
Precautions ............................................................................................................................... 14
Excavation of trenches ............................................................................................................. 14
Excavation of joint holes ........................................................................................................... 15
Excavation of substation sites .................................................................................................. 15
BREAKING INTO AND REMOVAL OF CONCRETE ENCASED CONDUITS.................................... 15
JOINTING PITS ................................................................................................................................... 16
Removal and/or reconstruction of existing jointing pits containing cables/conduits................. 16
Construction of jointing pits ...................................................................................................... 16
General...................................................................................................................... 16
Additional penetrations in cable pits ......................................................................... 16
CONCRETE CONSTRUCTION WORK .............................................................................................. 17
General ..................................................................................................................................... 17
Site mixed concrete .................................................................................................................. 17
Ready mixed concrete .............................................................................................................. 18
Concrete construction ............................................................................................................... 18
INSTALLATION OF CONDUITS ......................................................................................................... 20
General conduit requirements .................................................................................................. 20
Approved conduits .................................................................................................................... 20
Storage of conduits ................................................................................................................... 21
Coupling of conduits ................................................................................................................. 22
Conduit bends........................................................................................................................... 22
Installation of telecommunication conduits ............................................................................... 22
Sealing of conduits ................................................................................................................... 23
Laying of conduits ..................................................................................................................... 23
Banks of conduits ..................................................................................................................... 23
Standard conduit and cable spacings ...................................................................................... 23
Standard depth of cover ........................................................................................................... 24
Reduced depth of cover ........................................................................................................... 28
Bedding types ........................................................................................................................... 31
Concrete encased conduits ...................................................................................................... 32
General...................................................................................................................... 32
Conduit spacers ........................................................................................................ 34
Sand/cement bedding of banks of conduits ............................................................................. 34
Sand/cement bedding ............................................................................................... 34
Construction procedure ............................................................................................. 34
Standard bedding of banks of conduits .................................................................................... 34
Standard bedding material ........................................................................................ 34
Construction procedure ............................................................................................. 34
Procedure for dry bedded banks of conduits............................................................................ 35
Protection of conduits ............................................................................................................... 35
Use of warning tape .................................................................................................................. 36
Inspections by Ausgrid ............................................................................................................. 36
Kerb marking ............................................................................................................................ 36
Bridge crossings ....................................................................................................................... 37
THERMALLY STABLE BEDDING MATERIAL .................................................................................... 37
General ..................................................................................................................................... 37
Approved materials and mix design ......................................................................................... 38
Default slurry mix ...................................................................................................................... 39
General...................................................................................................................... 39
Installation of thermally stable slurry mixes .............................................................. 39
Dry mix...................................................................................................................................... 40
Alternative TSB materials ......................................................................................................... 41
Minimum coverage of thermally stable bedding ....................................................................... 41
Testing ...................................................................................................................................... 41
INSTALLATION OF PILLARS AND RAG-BOLT ASSEMBLIES FOR STEEL LIGHTING POLES ..... 42
Installation of pillar bases ......................................................................................................... 42
Installation of rag bolt assemblies for steel lighting poles ........................................................ 42
PURPOSE
This Network Standard provides the requirements for trenching, laying and reinstatement of
underground conduits and cables, for distribution cables up to and including 11kV in Ausgrid’s
network.
SCOPE
This Network Standard specifies the requirements for Trenching, Laying Conduits and
Reinstatement that have been established to meet the particular needs of Ausgrid, developers,
customers, Roads & Maritime Services (RMS), local councils and other service utilities.
Refer to NS168 for underground sub-transmission cables above 11kV.
NATSPEC 1152
This Network Standard frequently refers to the 1152 document which is an industry specification
dealing with road openings and restoration. It is managed by NATSPEC, and supersedes AUS-
SPEC#2, 306U, which was previously used in this regard.
The method used in this Network Standard to call up a specified Clause in the NATSPEC 1152
document is as follows, 1152.1.10 Subheading where 1.10 is the section number and Subheading
is the title of the relevant paragraph (generally a bold heading in 1152) if necessary.
A copy of the NATSPEC 1152 - Road Openings and Restorations (Utilities) document is available
from NATSPEC via their website.
Roadway crossings
All distribution cables shall be laid in approved conduits across or along roadways to allow for
future system alterations/augmentations with minimal civil works. Refer to Section 10 for
construction requirements. Additional spare conduits in roadway crossings may also be required by
Ausgrid. This will be specified on the Design Information.
Due to the requirements of certain Roads Authorities (eg RMS and Local Councils), open trenching
across certain roadways and other public thoroughfares may not be permitted without specific
approval. Refer to Clause 4.7 Trenchless Technology.
Once an installation is completed, all conduits shall be tested in accordance with Clause 13.2
Testing of Conduits.
Driveway crossings
Where a cable route crosses concrete formed or paved driveways, special precautions shall be
taken to ensure minimal damage to such driveways. Trenchless methods of crossing these
driveways shall be considered to minimise the impact of cable laying on the local community, and
to reduce the overall cost of cable laying.
Once an installation is completed, all conduits shall be tested in accordance with Clause 13.2
Testing of Conduits.
Trenchless technology
For information on using trenchless technologies refer to NS159 Installation of Cables and
Conduits using Trenchless Techniques.
The cables should be installed in conduit for the full length of the easement unless the cable
route dictates otherwise; eg excessive conduit bends and/or jointing requirements.
One spare conduit for each cable shall be installed at depth of cover appropriate for the cable
voltage.
The cable route along the easement shall be marked in accordance with the requirements of
NS143.
The installed conduits/cables must be surveyed to capture the correct installed location over
the entire length of the easement. For contestable projects, this survey shall occur prior to
electrification.
Inspection by Ausgrid
Ausgrid will carry out an appropriate level of site inspection during the construction phase to ensure
that the network assets, including cables and conduits, are being constructed in accordance with
the certified design, Ausgrid’s Network Standards, Policies and Safety requirements.
Unforeseen site conditions requiring a variation or design change must be documented and
referred to the designer for amendments to the design approval and re-certification as required.
Registration of easement
Refer to the following documents,
Policy for ASP/1 Premises Connections - Clause 2.3, Leases and Easements as well as
Section 10, The Connection Process, Stage 16.
Model Standing Offer – Standard Connections Services for Contestable ASP/1 Premises
Connections no greater than 11kV – Clause 4 & Clause 5
All waterway crossings must be risk assessed in accordance with a methodology approved by
Ausgrid. Ausgrid employees should refer to NEG OH14 – Guide to the Assessment of Waterway
Crossing Risk.
Additional work
Local Council may request additional removal and restoration works beyond the scope of works
approved by Ausgrid (see 1152.3.3):
If the additional work is deemed non-contestable, such work will be identified and defined by
Ausgrid in negotiation with the Local Council's Restoration Officer.
If the additional work is contestable work, the Client shall consult with the Local Council's
Restoration Officer concerning Council's requirements and shall make these details available
to Ausgrid's Representative.
No utility service shall be within 100mm of a low voltage cable or 300mm of a high
voltage cable.
Recording details of the project shall clearly define the start and finish points of the
shared trench, its dimensions and the service utilities involved (sectionalised if necessary
to indicate the presence or absence of certain utilities).
Dimensions of trenches
The trench size depends on the following factors:
Pegging of easements
The location of the easement shall be pegged by a Registered Surveyor prior to commencement of
excavation work. If the pegs or marks made by the Surveyor have been disturbed or removed,
excavation shall not commence until the pegs or marks have been re-established. The only time re-
establishment of the pegs may not be required is if the easement boundaries have been thoroughly
marked subsequent to the Surveyor pegging them, and those boundary markings are sufficient to
permit the trench to be excavated and recorded relative to the easement boundaries. If it is
necessary to locate any part of the trench outside the planned easement boundaries due to other
obstructions, then the extent of the diversion must be clearly marked and the markings preserved
until the Surveyor can return to adjust the plan.
Final ground level shall be marked on all pegs.
Bitumen and Concrete Paving - In accordance with the reinstatement provisions and
sketches of the NSW Streets Opening Coordination Council (SOCC) Guide to Codes
and Practices for Streets Opening.
Segmental Paving Units - The set out line shall be at least one whole unit clear of
both sides of the minimal alignment of the trench.
Textured or Patterned Concrete - The set out line shall enable an aesthetically
acceptable restoration of the pavement as approved by Ausgrid.
(ii) Where Ausgrid directs that certain driveways are not to be disturbed, services under
these driveways shall be installed by trenchless technology where suitable and no other
services are present. A risk assessment must be completed by the Constructor to ensure
no damage can occur to other services if trenchless technology is to be utilised.
(b) Carriageways
(i) In asphalt pavements, the trench set out shall be at minimum width, and wherever
possible, shall be at right angles to the street alignment.
(ii) In concrete pavements, the advice of the appropriate road authority and/or professional
engineering advice shall be sought regarding the location of trench set-out lines.
(iii) Any trench or surface work proposed in the vicinity of Permanent or State Survey Marks
shall be referred to the Land Information Centre of the Department of Lands, prior to
commencement of Work, to obtain protection or relocation requirements.
Refer to 1152.3.6 for further information.
Precautions
All cables and conduits detailed in underground plans in the vicinity of the proposed works must be
exposed. Excavations must be cleared of spoil to a minimum of 200mm around any cable covers,
joints, cables or conduits.
The persons carry out the works shall also observe the requirements of Network Standard NS156
Working Near or Around Underground Cables with regards to the safety aspects of working in
close proximity to underground cables.
When cutting cable covers or conduits, appropriate controls must be put in place to avoid creating
a hazardous condition through the contact with live cable.
Where existing cables have been exposed and found to be non-compliant with the standard depth
of cover in Table 3 and the reduced cover and backfill requirements in Table 4, Ausgrid’s
Representative shall be notified. The protection requirements of Table 4 should be retrospectively
implemented. Where these protection requirements are impractical to implement, as a minimum,
steel plates shall be installed across the full width and length of the exposed trench, above the
existing cables’ bedding. Details of reduced cover and backfill on existing cables shall be provided
to Ausgrid as part of field book recording to enable updating asset records in Ausgrid’s Geographic
Information System (GIS) see Clause 4.11.
Where it is found in URD areas where driveways have been lowered so that the initial standard
cover (Clause 10.11) has been reduced, the owner of the property serviced by the driveway shall
be asked to meet reduced cover requirements or restore the cover to the original level.
Excavation of trenches
Trenches shall be kept as straight as possible and the bottom of an open trench shall be firm and
smooth, free of rocks, pebbles, foreign matter and sharp projections. Where trenches pass from
footway to roadway and a change of level is necessary, the rise and fall shall be gradual.
If the excavated material is considered by Ausgrid to be unsuitable for re-use as backfill, the
material shall be removed and disposed of as specified in 1152.3.6 Unsuitable material /
Contaminated or hazardous material. Unsuitable backfill materials include building materials (eg
concrete, bricks, pavers, rocks, roofing tiles, rubble), contaminated substances (including
Hazardous Materials) and other materials that cannot achieve the required compaction (eg heavy
clays).
If the excavated material meets the requirements of Section 0 and additionally is considered
suitable by Ausgrid, the excavated material shall be reused in backfilling operations. Stockpiling of
suitable excavated material shall be in accordance with NS174 and 1152.3.6 Excavated material
stockpiles.
Safe and direct access to substations must not be impeded by excavation works.
NS141, Site Selection and Site Preparation Standards for Kiosk Type Substations
NS165, Safety Requirements for Non-Electrical Work in and Around Live Substations.
carried out by competent persons having regard to the nature of the work, the nature of the
risks associated with the work, and the control measures implemented.
The procedure shall also safeguard Ausgrid’s assets against any mechanical damage. The
persons carrying out the works shall be responsible for the costs associated with working to an
approved procedure and for any damage caused.
Some of the existing conduits and troughing are made of asbestos cement and appropriate
asbestos handling methods shall be used.
JOINTING PITS
Removal and/or reconstruction of existing jointing pits containing
cables/conduits
Prior to commencing any demolition or reconstruction of existing jointing pit which contains cables
or conduits, special precautions must be taken to protect the cables and any joints involved against
mechanical damage.
It is critical that existing cables/conduits and associated joints are not disturbed unless
specific written approval has been obtained from Ausgrid to the contrary.
All cables and associated joints in a pit that is undergoing demolition and/or reconstruction work
shall be supported and protected using non-conductive structures. These structures shall be
mechanically capable of supporting the cables and associated joints.
Cables shall be secured to the horizontal member of the supporting structures with non-metallic
fixings at no more than 1500mm intervals. Joints shall be supported at both ends of the joint. The
supported cables and joints are to be enclosed in fibre reinforced non-conductive troughings.
Protective Mats (Refrasil mats) shall then be draped over the enclosed cables and supports and
secured to prevent dislodgment.
Prior to removing the roof/lid of a jointing pit the Constructor shall place timber sheeting to fully
cover all cables and joints to prevent damage by falling materials.
corrosion protection
Concrete construction
(a) Formwork
Formwork shall comply with AS3610. Forms shall conform to the shapes, lines and dimensions
shown on the drawings. All forms and supports shall be of sound timber or steel, masonite,
plywood or similar material of sufficient strength and be adequately tight to prevent leakage of
mortar.
Formwork ties shall be used to maintain correct separation of vertical surfaces.
Timber formwork for exposed surfaces shall be dressed. All forming surfaces shall be coated with
an approved form release agent before pouring commences. Coating shall be done before any
reinforcement is fixed in position.
(b) Fixing of reinforcement
Reinforcement shall be accurately placed and tied at alternate intersections with 1.2mm soft iron
wire so as to form a rigid cage or mat which will maintain its shape and position both before and
during placing of concrete. Sufficient supporting devices shall be used to ensure the correct
concrete cover as shown on the drawings or as required by the provisions of AS3600, if not shown
on the drawings.
(c) Cast-in fixtures
All holding down bolts and other fixtures to be incorporated in the concrete shall be accurately fixed
in position before pouring.
(d) Inspection
Before any concrete pour, the reinforcement and fixtures for that pour may be inspected by a
Representative of Ausgrid. At the time of inspection, the work shall be in every respect, ready for
concrete placing. This requirement includes fixing and tying of all reinforcement and cleaning out of
formwork.
(e) Transporting of concrete
Concrete shall be transported to its final location as rapidly as practicable by methods which will
prevent segregation or loss of ingredients. Under no circumstances shall concrete which has
partially hardened, be used.
The containers used for transporting concrete shall be thoroughly cleaned before use.
Pumping of concrete will be acceptable provided the methods and equipment used are approved
by Ausgrid. Pumped concrete shall comply with this Specification in all other respects.
(f) Testing of concrete
Testing of concrete shall comply with the provisions of AS3600 and the constituent parts with
AS1012. Test results must be supplied to Ausgrid on request.
Test cylinders and slump tests may be taken on site as required by Ausgrid. The minimum
sampling frequency shall be that specified in AS3600.
Plant-control testing will be accepted at the discretion of Ausgrid’s Representative, provided that
the testing is by characteristic strength and that all relevant provisions of AS3600 are met.
INSTALLATION OF CONDUITS
General conduit requirements
Where required, the number of conduits and spare conduits shall be specified on the Certified
Design/Design Plan, and HV Connection diagram (HV Connection diagram applies only to High
Voltage designs). Conduits shall be of the approved type and shall be installed in accordance with
the requirements of the Certified Design/Design Plan, and this Network Standard.
Obstructions and other site constraints may make alterations to the Certified Design/Design Plan
necessary during installation. Any proposed departures from the Certified Design/Design Plan shall
first be submitted to Ausgrid for assessment prior to starting the proposed works.
Approved conduits
Ausgrid has approved a rationalised range of Unplasticised Poly Vinyl Chloride (UPVC) orange
conduits for underground cabling as a minimum standard. The stockcode numbers for these
conduits are listed in Annexure G. The application of the various sizes is as follows:
Table 1: Approved conduit size and application
125mm Distribution cables (high voltage including 11kV, low voltage, some street
lighting and services).
Low voltage cables where high voltage cables have been direct buried
150mm 11kV 500mm2 three core cables where 125mm conduits are not considered
adequate, eg complex cable routes with multiple bends.
Sub-transmission cables, and at other locations as required by Ausgrid
The requirements for the various installation conditions are provided in Table 2. These
requirements constitute a minimum standard. The use of heavier class conduits of the same
nominal diameter as specified below will be at the cost of the Accredited Service
Provider/Contractor and subject to the written approval of Ausgrid. Heavier duty polyethylene
conduits are normally required for trenchless installation. Details are to be agreed with the
trenchless contractor.
Heavier class conduits can be considered for roadways etc where the ASP has elected to use
heavier compaction exceeding the minimum requirements of this Network Standard. In all cases,
heavier class conduits and bends shall comply with Clause 14.7 for Testing of Conduits including
the use of an approved solid mandrel. Under no circumstances shall a heavier class conduit be
joined to a continuous installed length of light duty conduit as this may create issues with the
testing of conduits using an approved mandrel ie the diameter of the standard mandrel used for the
light duty conduit will be too large for the heavier class conduit.
Complex cable routes with multiple bends 150mm Light Duty (LD) UPVC (orange) conduit to
when 500mm2 three core cables are used AS/NZS 2053.2
and at other locations approved by
Ausgrid.
Concrete encased and sand/cement 125mm Light Duty (LD) UPVC (orange) conduit to
encased conduits, regardless of location AS/NZS 2053.2
(eg CBD conduits, major roadway
crossings).
All sand/cement/TSB grouted bore holes 180mm HDPE pipes to AS/NZS 4130. 125mm ID
HDPE pipe is used where space constraints do not
allow installation of larger pipes.
All State Roadway crossings. All CBD 125mm Light Duty (LD) UPVC (orange) conduit to
roadway and laneway crossings. All AS/NZS 2053.2
commercial/industrial driveway crossings.
All local and regional roadway crossings, 125mm Light Duty (LD) UPVC (orange) conduit to
(eg URD subdivisions), for high voltage, AS/NZS 2053.2
low voltage and service cables.
All light traffic driveway crossings
Conduits in footways and non-roadway 125mm Light Duty (LD) UPVC (orange) conduit to
easements for high voltage and low AS/NZS 2053.2
voltage network cables
Conduits for low voltage services supplied 100mm Light Duty (LD) UPVC (orange) conduit to
from low voltage pits AS/NZS 2053.2
Optical fibre pilot cables 63mm Heavy Duty (HD) UPVC (orange) conduit to
AS/NZS 2053.2
Conduits for low voltage domestic 50mm Heavy Duty (HD) UPVC (orange) conduit to
services and street lighting cables in AS/NZS 2053.2
footpaths or non-roadway easements
Conduits in substation chambers and for Sizes, types and quantities are as specified in
high voltage and low voltage cables to Network Standard NS113, as amended
and from substation chambers
Note: Profile wall smooth conduit type conduits shall not be used.
Ausgrid does not presently have a standard range of approved polyethylene pipes for use in
trenchless technology (bores). The PE pipes to be used in bores shall generally comply with the
requirements of AS4130, with the internal diameter determined in accordance with NS159
Installation of Cables and Conduits using Trenchless Techniques, and wall thickness determined in
accordance with the requirements of the bore design (grouting pressure and temperatures).
Storage of conduits
Orange PVC pipe or conduit does not contain any temporary UV stabilisers. If it is exposed to UV
over time, it will whiten on the surface and although it will not lose tensile strength it will become
brittle and can become subject to damage from impact loads. Protection from prolonged exposure
to direct sunlight can be achieved by under-cover storage, or by covering pipe stacks with an
appropriate material such as Hessian. Heat entrapment should be avoided and ventilation
provided. Black plastic sheeting should not be used.
Coupling of conduits
Conduits are to be coupled using spigot and socket arrangements. A suitable primer must be used
first on both mating surfaces. PVC solvent cement shall then be applied to bond the primed
surfaces.
All joints must be properly made to eliminate the entry of water and foreign matter into the installed
conduits.
Conduit bends
Conduit bends shall be selected giving consideration to the ‘during installation’ minimum internal
cable bending radius as detailed in Tables 7, 8 & 9 of Section 13. Excessive bending of conduits to
avoid using conduit bends is not acceptable. Where obstructions require conduits to be diverted,
only gradual large radius bends (minimum 2.3 metres) shall be used so as not to limit the size of
cables that can be pulled through. Approved bends are listed in the Annexure G.
Sealing of conduits
Refer to NS171, Fire Stopping in Substations for details on Ausgrid’s specification and
requirements for the installation of fire stopping materials in openings in substation walls, floors and
ceilings.
Conduits which are direct buried shall be sealed against the ingress of water and any foreign
material which may hinder the removal and/or pulling through of cables. For conduits that form part
of a pit and duct system and the pits are located in a tidal area or below the water table, the
conduits need to be sealed against the ingress of water. Apart from being susceptible to blockage,
unsealed conduits may cause flooding of cable pits and basement type substations and
switchrooms.
Unused conduits shall be sealed using the appropriately sized conduit end cap or plug.
Used conduits (ie conduits with cables in them) shall be sealed using approved conduit sealing
foam/putty.
Laying of conduits
The roadway conduits at street intersections and other locations should be laid as nearly
perpendicular to the street as practicable, terminating at the road-side edge of Ausgrid’s cable
allocation. Refer to Annexure D for the cable allocation that applies in the relevant area. Minor
deviations to align with offset lot boundaries on opposite sides of the road are permitted.
All conduits shall be installed so that they are true to line. The ends of conduits shall be smooth
and cleanly cut, with sharp edges removed. Where conduits enter pits, bell mouths shall be
installed flush with the inside of the wall.
Once installed, the manufacturer’s markings on the conduits must be visible for inspection.
Banks of conduits
In busy shopping centres, pedestrian malls and the Central Business District of Sydney (‘the CBD’),
conduits are generally installed in multiple rows linking vaults and pits. These are usually referred
to as banks of conduits. Conduit requirements and layouts are usually specified on the Certified
design/ Design plan.
Banks of conduits shall be built so that their cross section is rectangular. The exit points at each
end of the conduits bank shall correspond exactly without any cross-overs along the conduit
lengths.
Conduit banks containing six or more power cable conduits must be installed in thermally stable
bedding (TSB) in accordance with Section 11. Conduit bedding material shall be specified on the
Certified design/ Design plan.
Conduit banks containing six or more power cable conduits which are short in length (eg for local
road crossings) may not need to be installed in TSB provided the cables at both ends of the conduit
bank are direct laid. In each case, the deletion of TSB shall require a rating assessment completed
by the Designer as per NS272 and the rating assessment shall be submitted to Ausgrid for review
and written approval.
The requirements above apply also to suburban and other areas where the design calls for conduit
banks containing six or more power cable conduits. For details regarding the installation of banks
of conduits on Private Property, see Clause 4.8.
The carriageway of Classified State Roads – Low 1000 Concrete or TSB to achieve 3 to
Voltage and High Voltage Conduits 5MPa
(Note: excluding footways) See Figure 3
The carriageway of Classified Regional & 750 Standard bedding material as per
Unclassified Roads and heavy commercial / Clause 10.16.1
industrial car parks – Low Voltage and High See Figure 1
Voltage Conduits
(Note: excluding City of Sydney Roadway or
Laneway)
Footways and driveways of Classified and 600 Standard bedding material as per
Unclassified Roads, light commercial / residential Clause 10.16.1
car parks - High Voltage Conduits See Figure 5
Footways and driveways of Classified and 500 Standard bedding material as per
Unclassified Roads, light commercial / residential Clause 10.16.1
car parks – Low Voltage Conduits See Figure 6
Note 1: Refer to the following RMS website link for the Schedule of Classified Roads and Unclassified
Regional Roads. Local Roads are unclassified roads and therefore are not included in the
Schedule.
https://www.rms.nsw.gov.au/business-industry/partners-suppliers/lgr/documents/classified-
roads-schedule.pdf
If the standard depth of cover requirements cannot be met, reduced cover in accordance with the
requirements of Clause 0 may be allowed by Ausgrid if prior approval is sought.
LV and/or HV conduits in the Less than 1 Shall be negotiated with the RMS on a case-
carriageway of Classified State metre and by-case basis. In addition, polymeric cable
Roads greater than covers are to be used (refer to note 2)
(Note: excluding footways) 750mm
LV and/or HV conduits in City of 500* 20:1 sand/cement dry mix or TSB (refer to
Sydney Roadway or Laneway. Figure 8 and Note 1)
Steel plates and polymeric cable covers are to
be used (refer to Note 2)
LV and/or HV conduits in other public 450 Standard bedding material - see Clause
access areas, eg light commercial / 10.16.1 (refer to Figure 9)
residential car parks, recreation Steel plates and polymeric cable covers are to
areas. be used (refer to Note 2)
Bedding types
Conduit bedding material shall be specified on the Certified design/ Design plan. The type of
bedding material used for banks of conduits (including single conduit installations) shall be in
accordance with Table 3 or Table 4.
Additionally, when conduits are installed either below or beside or above other cables or conduits,
the conduits shall be encased in the same bedding material as the adjacent cables or conduits
unless otherwise directed in the Design Information.
Conduit bedding material shall comprise of one of the following;
Concrete
The specific concrete specifications required for the concrete encasement of the HV conduit
line is to be indicated on the drawings. Ausgrid's requirements, including those indicated below,
shall be referenced.
Admixtures in the concrete mix shall be subject to the approval of Ausgrid following the
submission of a product specific data sheet. The use of accelerators to speed concrete curing
or admixtures that entrain air will not be approved.
The total fly ash in the concrete mix (by weight) shall not exceed 5% unless separately
approved by Ausgrid. Fly ash reduces the thermal performance of the installed conduit bank.
Where reinforcement is required, detailing shall be arranged to reduce the potential for induced
currents. Transverse reinforcement around the conduit bank shall not form a closed loop at any
location.
ASPs or contractors wishing to vary concrete mix from approved requirements shall provide
documentation demonstrating that their proposal achieves the specified thermal resistivity (TR)
value without increasing the in-situ concrete curing temperature such that conduits are likely to
be damaged.
The standard thickness of the concrete encasement on the top, bottom and each side of the
conduits in a conduit bank shall be as specified in Table 5 below. Where the depth of cover
over the conduits has to be reduced, the requirements for encasement shall be as specified in
Clause 0.
Table 5: Concrete encasement dimensions
125mm 100 50 50
150mm 100 70 70
200mm 100 70 70
Encased conduits shall be installed with suitable spacers between the conduits prior to placing the
encasement material. Refer to Annexure I for further information on suitable spacers.
Where construction joints in the encasing material occur, each joint shall be provided with at least
four 16mm diameter steel dowels, extending into the encasement material for 450mm on either
side. Two additional dowels shall be provided for every additional row of four conduits above four
installed.
Conduits should be secured to avoid flotation during the pouring of concrete. This may be achieved
by tying the conduits with rope at three metre intervals and anchoring the conduits using timber
stakes driven into the cable trench, or by other approved methods.
Concrete encasement should be designed to ensure the heat of hydration does not result in
overheating and deformation of the conduits. Ausgrid specifies that conduits shall not be damaged
by operation at 80°C.
The conduits shall be fixed in place so that the top concrete cover remains at no less than 100mm.
Special attention shall be paid to recording the depth of cover (refer to NS100, Field Recording of
Network Assets). The Constructor for the work shall be responsible for ensuring that the concrete
cover over the top conduits is uniform, or if this is not possible, that the actual cover is accurately
recorded, in accordance with NS100. Depth gauges may be used if required to measure the actual
cover at critical locations.
Figure 11 shows the typical layout of a nine-way bank of conduits where 125mm conduits are
installed as three layers of three. The conduit spacer shown in the illustration has stockcode which
appears in Annexure G.
Figure 12 shows a nine-way bank of 150mm conduits.
Conduit spacers
Foam spacers
The foam conduit spacers are for dry mix TSB or for bedding material that need to be compacted.
The purpose of the conduit spacers is to keep the conduits in their correct position relative to each
other and the surrounding soil. The foam conduit spacer must be installed where bedding needs to
be compacted or dry mix TSB is to be installed. Foam spacers shall not be installed where TSB
slurry mix or concrete slurry is to be applied.
The conduit spacers must be designed:
Construction procedure
Sand/cement bedded conduit banks shall be constructed using the procedure for dry bedding of
conduits in Clause 10.17.
Construction procedure
The conduit banks shall be constructed using the procedure for dry bedded banks of conduits in
Clause 10.17.
Protection of conduits
Conduits are considered to be inherently protected from mechanical damage, provided they are
installed with a standard depth of cover (refer to Clause 10.110) and are either:
concrete encased, or
TSB encased, or
All other conduit installations, including those installed with standard or reduced depth of cover with
standard bedding material or 20:1 sand/cement dry mix bedding, shall be protected against
mechanical damage using Ausgrid approved cable protection covers laid directly above the
bedding material.
For reduced cover installations, additional protection against mechanical damage shall also be
provided in accordance with Clause 0.
Currently approved cable protection covers are of the polymeric type complying with Ausgrid's
performance requirements. The standard sizes used and the corresponding stockcode numbers
are listed in Annexure G.
Where there is a single conduit in the trench, a single 150mm or 300mm wide strip of polymeric
cable cover shall be used. The single cable cover shall completely cover and be centred over that
conduit.
Where 2 or more conduits are laid side-by-side, the wider 300mm size of polymeric cable cover
shall be used.
If more than one strip of 150mm wide polymeric cable covers is required side by side, 300mm wide
strips shall be used.
Polymeric cable cover strips laid side-by-side shall butt up against each other. Polymeric cable
cover strips laid end-to-end shall overlap by approximately 20mm.
Cable covers must be immediately secured in position by covering with a 150mm thick (minimum)
layer of backfill material.
Inspections by Ausgrid
Ausgrid has the right to inspect all works regarding the installation of its assets. If access to our
assets is unavailable, then the constructor must provide Ausgrid access at the constructor’s
expense.
Kerb marking
Permanent kerb marking must be provided (except where there is no kerb or gutter) at all roadway
conduit crossings and under road borings, using the letter E (for Electricity). The markings shall be
done by engraving or other approved means, and shall be positioned on the face of the kerb
directly above the installed conduits at both sides of the roadway crossing.
Note: Permanent markings shall not be installed in heritage situations unless approved.
For example, permanent kerb marking may consist of an approved stainless steel ‘E’ plate
anchored onto the kerb as shown in Figure 13. The supplier is Hi-Tech Horizontal Drilling.
http://www.kerbmarkers.com.au
Bridge crossings
Where bridge crossings are required, specific structural designs must be provided. Before any work
occurs, the design must be certified, and authorisation must be obtained from the relevant bridge
Authority/Owner and from Ausgrid.
The cable and cable/conduit support design shall allow for the expected bridge movements
(vertical and longitudinal).
Cable design shall meet the distribution network rating requirements.
For exposed HV and LV cables and conduits, suitable measures shall be used to provide adequate
mechanical protection and to restrict public access. These measures shall be subject to review and
approval by Ausgrid.
For all bridge crossings, clearly visible permanent surface marking at 3m intervals along the cable
route shall be provided, in accordance with Clause 0.
All bridge crossings shall have a rating assessment completed by the Designer as per NS272, and
the rating assessment shall be submitted to Ausgrid for review and written approval.
Any design requiring the use of TSB shall comply with the performance requirements of the above
table. The Designer shall clearly specify the site location of the TSB mix in the design in the
following way:
Admixtures for Pumping etc - subject to Ausgrid approval (product specific data sheet
required).
Cement
Flyash
Crushed gravel
Coarse sand
Water.
Ausgrid’s Approved Material List (AML) provides a list of suppliers of TSB mixes and their product
codes.
TSB mixes from other suppliers not listed in the AML can also be submitted to the Ausgrid
Representative for consideration using the NS181 approval process. In this case, the Constructor
shall provide the Ausgrid Representative a TR test report, Compressive Strength test report and
mix design / recipe for review.
The Constructor shall provide a copy of the TSB delivery docket to the Ausgrid Representative for
every batch of TSB mix supplied and shall demonstrate compliance with the AML for the approved
TSB mix and site location specified in the design. If the TSB mix is not listed on the AML, the
Constructor shall demonstrate compliance of this TSB mix to a design approved by Ausgrid for the
site location.
Once approved, the TSB mix design shall not be modified without the further approval of Ausgrid.
All materials used in the approved mix design shall continue to be sourced from the original
locations to ensure consistent strength and TR values. Any change to the source of material supply
will require a revised mix design, re-testing of strength and TR values, and the subsequent
approval of Ausgrid.
11.3.2.3 Flotation
Since thermally stable bedding mixes are a hydraulic fill, conduits may tend to float, and therefore
they must be secured to the bottom of the trench. The TSB shall be placed from a minimum height
that does not exceed 1.8 metres.
Where further compaction of the TSB is deemed to be required, the preferred method is by the use
of immersion vibrators. Vibration of TSB shall only be undertaken by trained and experienced
operators using equipment that is suitably sized for the installation. The use of vibrators shall be
constantly monitored to ensure proper technique, suitable immersion times and complete coverage
of the TSB installation.
In this regard, it should be noted that compaction is a two stage process that involves:
(a) Initial Consolidation – aggregate particles are set in motion and slump to fill the formed
space giving a level top surface.
(b) Entrapped Air is expelled – air bubbles rise to the surface over a period of time after the
surface has levelled.
Both stages need to be effectively completed to produce a dense, compacted material with minimal
entrapped air voids.
Poorly monitored or excessive vibration may cause segregation of the mix aggregates and thereby
reduce the thermal performance of the TSB.
Dry mix
Application: Difficult site locations where default slurry mix is not practical (steep slopes, road
crossings requiring immediate backfill). This mix must not be used unless written approval is
obtained from Ausgrid.
This dry mix gives a fully dry nominal thermal resistivity value of 0.9K.m/W when compacted to
98% Standard Proctor. Refer to Clause 10.17 for suitable installation methods applicable to dry
bedded banks of conduits.
Special care must be observed with thorough mixing of the ingredients, installed moisture content,
and proper compaction measures.
For a typical example of a dry mix design that may satisfy the performance requirements, refer to
Annexure M.
Testing
For effective TSB performance, periodic tests are required to ensure that:
the specified mix ingredients continue to be used, and “similar” ingredients are not substituted
without approval, and
the TSB mixes achieve their designated function, including thermal and mechanical
characteristics.
TSB mixes shall be tested according to the following guidelines:
prior to delivery of the first batch of a new mix (ie from a new batch plant or source of supply),
and
whenever one or more ingredients are to be sourced from a different location or supplier, and
Trenches >50m long - one sample per 50m length of trench or part thereof, with sample
locations being equally spaced along the trench length.
The location/s of the sampling must be accurately recorded and provided with the TSB test results
to Ausgrid no later than six (6) weeks after the sampling, who will submit them to:
[email protected] for incorporation into Ausgrid's Geographic Information System (GIS), and
Position the base so that the top is level and 50mm above the footpath level at street alignment as
shown in the above figure. Allow for grass when determining the final footpath level.
Cable terminations shall be installed in accordance with NS127 Low Voltage Joints and
Terminations.
Once the distributor and service cables have been installed and terminated, the trench around the
base and supporting structure must be backfilled with well-compacted granular soil.
Installation of the pile footing, rag-bolt assembly and plinth shall be in accordance with Ausgrid
drawing 514087, using plinth steel mould to Ausgrid drawing 514020.
The rag-bolt assembly must be installed in a 600mm diameter hole. Where unstable ground exists
or shared trenching is used, a 600mm diameter former tube must be fitted to the hole.
The hole or former tube must be filled with 32MPa concrete. Any gaps around the concrete core
must be filled with well compacted granular soil, and any sharp edges must be removed after the
concrete has set.
Once in its final position, the rag-bolt assembly must:
have its centre line 400mm from the street alignment (unless specified otherwise)
have the top of the threaded rods 100mm above the top of the plinth steel mould in accordance
with Ausgrid drawing 514087.
Once the street lighting cables have been installed and terminated in accordance with NS119
Public Lighting Design and Construction, the trench around the rag-bolt assembly must be
backfilled with well compacted granular soil.
Pilot Cables
13.1.1.1 Sydney CBD
The Sydney CBD 11kV Triplex network uses a "coloured" pilot cable system with:
Cables that are direct buried and surrounded or partially surrounded in a sand/cement mix are
known as solid laid cables. When excavating around such cables extreme care must be taken to
avoid creating a hazardous condition to personnel, or damage to the cables.
When solid laid cables are encountered, the constructor shall consult with Ausgrid to arrange for all
solid laid cables at the work site to be de-energised before work continues. This will eliminate the
possibility of hand held tools penetrating the energised cables. Alternatively, a hydro vacuum
excavator can be used to expose all solid laid cables without the need for de-energisation, provided
the precautions detailed in NS156 are followed.
Where the solid laid cables are de-energised, the constructor shall prepare a work procedure
designed to safeguard Ausgrid's assets against any mechanical damage whilst exposing the
cables.
Sealing of cables
General
All power and control cables shall be protected against moisture ingress, including while being laid,
regardless of site and/or weather conditions.
Cable ends which are not intended to be worked on immediately after laying must be electrically
shorted and sealed against moisture ingress as soon as they are cut. This requirement applies to
all cable ends, including cables in pillars and pillar-standards, cables intended to be abandoned or
temporarily decommissioned, and cables still on cable drums.
The seals and electrical shorts must not be removed until the cables are ready to be connected.
Stripping of the outer sheathing of LV service cables and connection of any of the cores must not
be carried out until connection of supply is required.
Where a laid cable is found to have high moisture content due to inadequate sealing, the
Constructor carrying out the works must remedy this at their own cost.
Method of sealing
Where LV cables/service cables enter a customer’s premises, the cable shall be at least single
sealed to avoid the risk of water entering the premises via the cable.
A triple end seal arrangement is required for all HV cables. A triple end seal arrangement is
required for all exposed LV Distributor cables. Only a single seal cap is required for LV Distributor
cables which are enclosed (eg cables left in a LV pillar or inside a kiosk for future connection). A list
of approved triple end seal kits is given in Annexure G. The triple end seals shall be constructed in
accordance with the installation instruction (ESD-3410-AU-5/03 for high voltage single core cables,
ESD-3408-AU-5/03 for multicore cables and ESD-5891-AU-07/12 for low voltage single core
polymeric cables) supplied in the triple end seal kit.
Completed permanent sealed ends must be laid in either suitable troughing or 1000mm lengths of
UPVC conduit, and filled with sand. The sealed ends must then be buried and protected with
approved polymeric cable covers. Sealed cable ends which are awaiting jointing shall be elevated
clear of any free standing water in the excavation.
For polymeric insulated/polymeric sheathed service cables of cross sectional area 50 mm2 or less,
which are intended to be buried, a single heatshrink cap over the mastic tape may be used instead
of the triple seal arrangement. The end caps used shall be selected from the approved range
specified in Annexure G.
Note that cable surfaces which will come into contact with adhesive lined heatshrink components
must be thoroughly cleaned, then degreased and abraded before applying the heatshrink
components. Some older cables may have graphite coatings on the outer sheaths, which must be
removed before the cable surfaces are cleaned. Refer to NS177 for the graphite removal
procedure.
Swallowed - Keep individual calm, do not induce vomiting, seek medical attention.
Eye - Flush eyes with water for 15 minutes, seek medical attention if irritation persists.
Skin - Wash with soap and water, remove contaminated clothing and launder before reuse.
Inhaled - If affected, remove individual to fresh air, seek medical attention if breathing
difficulties occur.
Single core low voltage polymeric cables 185 mm2 and 300 mm2
Refer to Installation Instruction ESD-5891-AU-11/11 and stockcode 182467 for the kit.
Proposed joint locations subjected to high traffic volumes, and which have cables installed in
conduits, shall require the cable joints to be installed within a pit to the requirements of NS172.
Examples of high traffic locations include CBD areas and RMS roads.
Proposed joint locations not subjected to high traffic volumes are permitted to have cable joints
direct buried under the carriageway, at a location which takes into consideration Ausgrid’s
future maintenance activities as determined by the Ausgrid Representative.
If the above conditions cannot be met regarding the positioning of cable joints, then the matter shall
be referred to the suitable Ausgrid Representative (ie for contestable projects, the Contestable
Project Co-ordinator, or for all other cases, the applicable Field Manager) to make a decision based
on a careful study of the local site specific conditions.
Cables are to be installed with a 1.2 metre overlap at all joint positions. Where two or more cables
are installed and the joints occur in the same vicinity, joints are to be staggered by a minimum of 1
metre if space is available.
Constructors shall employ sufficient controls to ensure that no damage is caused to newly laid
cables, or to existing cables and infrastructure. Particular attention shall be paid during cable
pulling to sections of the new cable route where there is a significant change in direction, and
where the cable enters a conduit.
Figure 18
Joint bays
Joint bays are the most likely section of a project to be re-excavated, and these locations shall be
filled with compacted, well graded standard bedding material as per Clause 10.16.1.
Coarse aggregates must not be used in joint bays due to risk of damage to the cable during
compaction.
Concrete or TSB shall not be used as a bedding material around direct buried cables in joint bays.
Refer to Clause 13.3.
Note: “D” is the overall diameter of the cable in mm or the circumscribing overall diameter of a
bundled cable.
The minimum internal bending radius of each core of a three core polymeric cable after it has been
trifurcated is 15D, where D is the diameter of the rejacketed individual core. Refer to Table 9 for
more details.
Table 8: Nominal Minimum Internal Bending Radii for Specified Cables (Guide Only)
Table 9: Nominal Minimum Internal Bending Radii for the Individual Cores of the Three Core
Polymeric Cable (After Trifurcation) - Guide Only
The plant used to pull cables shall be firmly anchored before a pull commences to prevent uneven
tension on the cable due to winch movement. Prior to securing any floor mounted pulling
equipment to the substation floor in accordance with the manufacturer’s instructions, written advice
shall be obtained from a competent person (ie a Civil / Structural Engineer) regarding the structural
integrity and load capacity of the substation floor, and the suitability of the anchoring method
proposed. The cable shall be drawn smoothly into position with a minimum of stops and at a
maximum speed of 12-15 metres per minute. The cable drum shall be placed so that the cable is
pulled from the top of the drum.
On completion of a cable pulling operation, all cable ends shall be inspected for damage. The
length of cable laid shall be extended to compensate for damaged cable ends.
Where existing conduits have cables installed and are not fitted with bellmouths at the cable pit
entry, a “split type” bellmouth should be installed where it is safe to do so. This may require cables
to be de-energised and/or isolated.
Cables for which the existing supporting structure is to be removed in order to allow the new cables
to be installed, shall be temporarily supported so that no movement occurs to the cable and
associated cable joints while the existing support is removed. All temporary supports are to be of
non-metallic materials. Refer to Clause 8.1 for further information regarding cable supporting
requirements.
On completion of the cable installation, the existing supporting system is to be restored.
Consideration must be given to cable management in pits to ensure the safe and efficient access
and emergency egress for personnel and equipment. This is achieved through the use of thorough
job planning, and use of cable stands, tray, cleats, etc. Cable pits shall be kept clean by removing
all scrap joints, cable and materials, debris, and general rubbish from the pit at the conclusion of
works.
Cable labelling
Multiple cable installations shall have the cables identified as “cable 1”, “cable 2”, “cable 3” etc to
assist identification. Labels must be removed upon commissioning of cables or modified at the new
cable ends in the case of in-line joints carried out before commissioning.
During cable installation, the cables shall be labelled as shown in the design drawings. The cable
identification labels must to be placed on the cable ends at the termination points and in joint bays.
For example, a design drawing will show the cable labels at termination points as follows:
Figure 19a
Whilst the design drawing does not show the joint bay locations as they are determined at
construction stage, cables must be labelled in the joint bays with respective cable labels as shown
below:
Figure 19b
The Certified design/Design drawing will include the following in the Important Note section:
“For identification and jointing purposes, all cable ends shall be labelled at the termination locations
and in joint bays during cable installation. The cables must be labelled as per certified
design/design drawing.”
All High Voltage cables shall be laid so that they enter perpendicular to the High Voltage infill
panels and vertically up inside the HV cable entry area of the kiosk. All Low Voltage cables
shall be laid as per the range of acceptance entry angles as per the diagram given below.
The internal bending radius of the cable being laid shall not be less than the cable
manufacturer’s specification. The cable manufacturer’s specifications are based on Tables 8 &
9.
Ausgrid will not accept excessive bending of cables.
Figure 20
the clamps carry the weight of the cable(s) if the latter are not supported on trays;
the cables are sufficiently restrained to stop them from whipping around under fault conditions;
the clamps are not over-tightened to the extent that they damage the cable, particularly under
cyclic loading.
Polymeric cables have a relatively high thermal coefficient of expansion and will soften when
operating at high temperatures. If a polymeric cable is clamped too tightly when it is installed, the
polymeric insulation may permanently deform when the cable heats up resulting in a reduction in
the insulation thickness.
Another possible cable damage that could occur as a result of over-clamping is that the screen
wires could be forced through the insulation screen and into the polymeric insulation. Therefore,
clamps shall be tightened only to the extent necessary to ensure that the cables are held firmly in
place.
Where single core cables are used, the cables shall be laid and clamped in a trefoil configuration
unless specified otherwise. The following also applies:
Where single core cables are clamped in a trefoil configuration, the clamps used must be
sufficiently robust to withstand the potential repulsive forces acting on individual phase cables
under fault conditions. Clamps utilising magnetic material can be used for clamping single core
cables in a trefoil configuration, as magnetic fields generated by the three currents cancel each
other out.
Where single core cables are required to be clamped individually in a flat formation, the clamps
shall be of a non-magnetic material to prevent localised heating of the cores due to the closed
magnetic circuit of the clamp.
Clamps approved by Ausgrid are listed in Table 10. All cable clamps shall be used with a nitrile or
neoprene rubber-cushioning strip of minimum thickness 3mm, wrapped around the cable
assembly.
Other clamps may be acceptable subject to Ausgrid’s Representative’s approval. Examples of the
approved clamps are shown in Figure 21 below.
* Note: EA-UKRB200 is supplied with one bracket. Use an additional bracket (ABB part number
EA-B200) on trefoils of large cables such as 630 mm2 polymeric cable.
BACKFILLING OF EXCAVATIONS
Backfill material
General
Ideally, the backfill material should restore the sub-grade to its original condition, which may be
achieved by replacing the excavated materials in the same position from which they were
excavated, and in the same state with regard to moisture content and compaction. This is usually
difficult with "moisture unstable" soils. Where these exist under heavy traffic pavements, it will
generally be required to import granular material that is capable of spreading the traffic load over a
larger area of sub-soil.
Testing of conduits
After installation and backfilling of a bank of conduits, Ausgrid’s Representative is to be notified to
witness conduit testing.
All new conduits shall be thoroughly cleaned and an approved solid mandrel of diameter 12mm
less than the internal diameter of the conduit and minimum 230mm in total length and minimum
130mm in flat length, shall be pulled by hand or with winch/machine (with suitable sized fuse)
through every conduit in both directions to ensure their integrity.
Figure 23
After passage through each conduit, the mandrel shall be thoroughly inspected for cuts or damage.
If in the opinion of Ausgrid’s Representative, there is any doubt as to the freedom from foreign
material or any object or defect that may cause damage to the cable in the conduit, the Constructor
shall repeat pass the mandrel through the conduit(s) until the Ausgrid Representative is satisfied.
Ausgrid reserves the right to request that a waste length of the cable to be installed be passed
through the conduits, or video cameras be used to inspect the conduits where reasonable concern
exists as to the condition of the conduits or if they have been backfilled without Ausgrid's
Representative being present.
Conduits found to have defects which, in the opinion of Ausgrid’s Representative, may cause
damage to cables shall be repaired by the Client / Constructor at no cost to Ausgrid and at a time
nominated by Ausgrid’s Representative. Several commercial conduit repair systems are available.
Road furniture
The Contractor is responsible for installation of road furniture that is damaged or removed by the
cable laying project. Road furniture that is required for the safety of vehicles and the public must be
installed temporarily as a minimum before the opening of the road for the carriage of traffic. All road
furniture must be replaced like for like using current industry practice and approved materials and
techniques and in accordance with the manufacturer’s instructions. The Contractor must ensure
that temporary road furniture is maintained and is suitable for its purpose until replaced by
permanent road furniture.
Final reinstatement
Other than for State Roads, the Client shall arrange for permanent reinstatement which complies
with 1152.3.12 – 3.14.
For State Roads, the Client shall arrange for permanent reinstatement which complies with RMS
Specification M209.
Activity to be Tested Key Quality Maximum Lot Minimum Test Test Method
Verification Size Frequency
Requirements (see note 5)
Materials supplied for trench Material properties 1 contract 1 per contract or source As specified
backfill under carriageways, as specified of supply for each type
footpaths, and all joint holes of material used or
suppliers test
certificates
Materials supplied for sub- Material properties 1 contract 1 per contract or source As specified
base and base layers as specified of supply for each type
of material used or
suppliers test
certificates
Trench and joint bay backfill Compaction 1 continuous 1 per layer, per 30 AS 1289.5.1.1
and sub-base and base under trench or 1 metre length per trench AS 1289.5.2.1
carriageways, heavy duty joint bay or (see note 6) AS 1289.5.6.1
vehicular crossings and car one road
parks crossing
Trench backfill and sub-base Compaction 1 project (see 1 per layer, per 100 AS 1289.5.1.1
and base under footpaths, note 1) metre length of trench AS 1289.5.2.1
light/medium duty driveways or part thereof (see AS 1289.5.6.1
and turfed areas notes 2 and 3)
Backfilling of individual joint Compaction 1joint bay (see 1 per layer AS 1289.5.1.1
bays in footways (see note 3) note 4) AS 1289.5.2.1
AS 1289.5.6.1
Activity to be Tested Key Quality Maximum Lot Minimum Test Test Method
Verification Size Frequency
Requirements (see note 5)
Materials supplied for Material properties 1 contract Supplier test certificates As specified
temporary road surface (or as specified
sealing material
Notes:
1. ‘Project’ refers to the works executed within a reasonable timeframe by the same contractor
as part of a single Certified design/Design plan. Where a Certified design/Design plan
involves two or more well-defined stages, and each stage is executed separately, each stage
shall be regarded as a separate project for the purpose of testing frequency.
2. The length of trench backfilled shall be taken to be the total of all discrete excavations
backfilled together by the same Constructor.
3. Joint bays and trial holes backfilled and compacted concurrently with cable trenches shall be
regarded as cable trenches for the purpose of testing frequency.
4. Individual joint bays shall be taken as those which were part of a cable trench but were
backfilled separately from this trench, or any discrete joint bays which were not associated
with any other cable trenches.
5. A layer is defined in 1152 or RMS Specification M209 depending on the location.
6. Every separate trench in a roadway or carriageway must have at least one compaction test.
For example; if there is a requirement for two road crossings of 10m each, a compaction test
is required for each road crossing.
CABLE JOINTING
Jointing work on the electrical distribution system and details of the joints and terminations
required, are referenced in NS127 LV Cable Joints and Terminations, NS129 11kV Joints and
Terminations - Paper Insulated Lead Covered Cables and NS177 11kV Joints (including Transition
Joints) and Terminations - Polymeric Insulated Cables.
All other excavations are safely barricaded and protected, and arrangements are put in place
for regular checking to ensure that they remain safely barricaded and protected.
(*Ausgrid's Electrical Safety Rules cover access permit procedures and requirements).
CABLE TUNNELS
For dedicated Ausgrid cable tunnels, specific fire engineering solutions shall be provided that deal
with cable type, cable joints, fire detection, fire suppression, ventilation, emergency response and
other aspects. Installed cables within dedicated Ausgrid cable tunnels will generally include an
additional layer of low smoke zero halogen (LSOH) material over the normal HDPE over-sheath, to
retard the spread of fire and smoke.
The design of cable installations in cable tunnels shall be approved by Ausgrid prior to proceeding
with construction works.
Fire retardant (low smoke, zero halogen or LSOH), HDPE sheaths shall be used on all
power cables in tunnels. Where this is not feasible, a fire retardant cable wrap or cable
coating shall be used to protect a conventional power cable.
The LSOH cable shall extend into the next underground joint bay, or into the
substation, up to the terminations, as applicable.
2. Cable Support, Protection and Signage:
Ausgrid’s HV and LV cables shall be carried on dedicated cables trays (or equivalent),
in an elevated location if possible, and separated as much as possible from any
existing LV cables, communications cables, services etc that are owned by others.
Clear signage shall be provided indicating that the cables are HV and are owned by
Ausgrid.
3. Cable Joints:
Where joints are essential, encapsulation and/or local protective shields shall be used
in consultation with Ausgrid to minimise the risk of a joint failure damaging adjacent
cables or initiating a fire in the tunnel.
Consideration shall be given to modified joint kits for any cables using LSOH sheaths,
as the standard joint kits may not be suitable.
Localised fire retardant cable blankets or "wraps" shall be used around Ausgrid HV
cables at locations that are exposed (1m -1.5m) to joints in major LV cables. Any
derating of Ausgrid cables will need to be assessed and submitted to Ausgrid for
approval.
Other issues that are to be considered in the design of shared services tunnels include, but are not
limited to, the following:
Fire rating of any spray-on fire protective coating used (eg Fendolite)
COMPLIANCE FRAMEWORK
The requirements of this standard should always be adhered to.
As specified in NS261 Compliance Framework for Network Standards, designers shall develop and
maintain a compliance framework, related to the compliance with Ausgrid Network Standards and
other technical documents in accordance with AS ISO 19600:2015.
Where variations to this Network Standard are proposed or non-compliance is the result of specific
site conditions or design decisions this needs to be identified and approval sought as per NS181
prior to their implementation.
RELATED DOCUMENTS
All work covered in this document shall conform to all relevant Legislation, Standards, Codes of
Practice and Network Standards. Current Network Standards are available on Ausgrid’s Internet
site at www.ausgrid.com.au.
ASPs and other persons external to Ausgrid are responsible for sourcing the manufacturer’s
instructions and manuals.
Ausgrid documents
ASP Level 1 Authorisation Agreement
Connection Policy
Model Standing Offer (MSO) – Standard Connection Services for Contestable ASP/1 Premises
Connection no greater than 11kV
NS113 Site Selection and Construction Design Requirements for Chamber Substations
NS129 11kV Joints and Terminations - Paper Insulated Lead Covered Cables
NS141 Site Selection and Site Preparation Standards for Kiosk Type Substations
NS165 Safety Requirements for Non-Electrical Work in and Around Live Substations
NS177 11kV Joints (including Transition Joints) and Terminations – Polymeric Insulated
Cables
NS224 Low Voltage Suburban Commercial and Industrial Underground Distribution Utilising
Pillars
AS1289.5.1.1 Method of testing soils for engineering purposes - Soil compaction and density
tests - Determination of the dry density/moisture content relation of a soil using standard
compactive effort
AS1289.5.2.1 Method of testing soils for engineering purposes - Soil compaction and density
tests - Determination of the dry density/moisture content relation of a soil using modified
compactive effort
AS1289.5.6.1 Method of testing soils for engineering purposes - Soil compaction and density
tests - Compaction control test - Density Index method for a cohesionless material.
AS2053.2 Conduits and fittings for electrical installations - Rigid Plain Conduits and Fittings of
Insulating Material
Memorandum of Understanding Between Ausgrid & Roads And Maritime Services & Transport
For NSW
New South Wales Specification (AUS-SPEC#2, 306U) – Road Openings and Restorations
NSW Streets Opening Coordination Council (SOCC) Guide to Codes and Practices for Streets
Opening
Specification 3051 – Granular Base and Subbase Materials for Surfaced Road Pavements
DEFINITIONS
Accredited Service An individual or entity accredited by the NSW Department of Planning,
Provider (ASP) Industry and Environment, in accordance with the Electricity Supply
(Safety and Network Management) Regulation 2014 (NSW).
Authorised Person An authorised person can be either the ASP, as a sole trader or company
and an ASP’s employee or sub-contractor, who has personally been
granted permission in writing by Ausgrid to carry out contestable work in
Ausgrid’s network area.
Authorised Work Work requiring specific permission in writing from Ausgrid to undertake
contestable design or work on or near its network. Refer to ES4 for further
information.
Backfill Material placed to refill an excavated area above the conduits or cables
Base course The layer of the pavement immediately below the wearing surface.
(Base)
Bedding Material placed around conduits carrying cables to obtain good thermal
ratings and mechanical strength.
Carriageway That portion of a road or bridge devoted particularly to the use of vehicles,
inclusive of shoulders and auxiliary lanes and heavy duty vehicular
crossings.
Certified A CAD drawing in either hardcopy or electronic format prepared by an
Design/Design authorised designer working for a Level 3 Accredited Service Provider
Plan (ASP/3) and certified by Ausgrid, detailing proposed alterations to
Ausgrid’s Network. The proposed alterations may be components of
contestable services or of Ausgrid approved asset augmentation or
relocation works.
Classified road All classified roads under the Roads Act are designated as either State
Road or Regional Road under agreements with councils.
Clearing The removal of vegetation or other obstacles at or above ground.
Client A Client is an individual or an entity who has responsibility for the design
and construction of the network addition, and who enters into an
agreement/contractual arrangement with accredited parties, who may be
internal or external to Ausgrid, for developing the installation. A Client
could be a developer, an accredited service provider, Ausgrid or a
customer. Accredited parties include designers and service providers.
Contestable Work Contestable work is work such as the design, construction and installation
of electricity works which are required to connect a Client’s installation to
an electricity distributor’s network. Customers are required to fund the cost
of contestable work and they have the choice of selecting the ASP to carry
out the work.
Constructor The company or persons responsible for carrying out the construction
work.
Customer A Customer is an individual or an entity that is an end-user of electricity.
Depth of cover Vertical distance from the top of conduit/direct buried cable to the ground
surface level.
Document control Ausgrid employees who work with printed copies of document must check
the document repository regularly to monitor version control. Documents
are considered “UNCONTROLLED IF PRINTED”, as indicated in the
footer.
Duct/ductline Has the same meaning as “conduit”.
Electricity Electricity Distributor means an electricity distributor constituted as a body
Distributor corporate under the Electricity Act 1945 (as amended). It is the party
setting conditions under which assets shall be constructed, and will
eventually take over title and maintenance responsibility for these assets.
Footpath The paved section of a pathway.
Joint bay An enlarged section of excavated trench in which cable joints are installed
and which is backfilled on completion of jointing works
Joint pit Underground enclosure constructed of brick or concrete in which cable
joints are installed. Typically used in heavily congested areas such as a
Central Business District.
Local Council The Local Government Authority responsible for the area where the work
is being performed.
Local Roads Those roads controlled by Local Council.
Lot Boundary The dividing boundary line between adjoining lots and road reserve.
Network Addition The network addition (the installation) shall mean the electricity cables,
wires, substations and associated equipment involved in a project. The
project could be Client driven (eg to extend or augment the existing
electricity network to supply the Client's premises or development) or
Ausgrid driven (eg to augment or refurbish the existing electricity network).
Network Standard A document, including Network Planning Standards, that describes the
Company's minimum requirements for planning, design, construction,
maintenance, technical specification, environmental, property and
metering activities on the distribution and transmission network. These
documents are stored in the Network Category of the document repository
and available externally on Ausgrid’s website.
Pathway That portion of a road or bridge reserved for the movement of pedestrians
and manually propelled vehicles.
Pavement That portion of a carriageway placed above the sub-grade for the support
of, and to form a running surface for, vehicular traffic including the sub-
base and base course.
Property (See definition for 'Street Alignment').
Alignment
Regional Roads The roads owned by the Roads and Maritime Services (RMS), but under
the management of the local council.
Representative of Contestable Project Coordinator (CPC) – Responsible for ensuring the
Ausgrid Ausgrid component of each contestable project is delivered in a
satisfactory manner ie contractually & provision of services such as design
RECORDKEEPING
The table below identifies the types of records relating to the process, their storage location and
retention period.
Table 12 – Recordkeeping
Draft Copies of the Network Standard Work Folder for Network Standards Unlimited
during amendment/creation (HPRM ref. 2014/21250/292)
* The following retention periods are subject to change eg if the records are required for legal
matters or legislative changes. Before disposal, retention periods should be checked and approved
by the Records Manager.
DOCUMENT CONTROL
Content Coordinator : Head of Asset Engineering Policy & Standards
Number Title
212386_1 Telecommunications External Plant Optical Fibre Construction Drawing Index
212386_2 Telecommunications External Plant Optical Fibre Construction OPGW with Subtransmission
UGOH
212386_5 Telecommunications External Plant Optical Fibre Construction ADSS Termination with 11kV
UGOH
212393_1 Ausgrid Fibre Network Fibre & Duct Arrangement Index Page
212393_2 Ausgrid Fibre Network Fibre Duct Arrangement Typical Size 8 Communications Jointing Pit
212393_3 Ausgrid Fibre Network Fibre Duct Arrangement Typical Pit Construction Load Classification
Class C & Class D
212393_4 Ausgrid Fibre Network Fibre & Duct Arrangement Typical Communications Conduit Breakout
Detail For Each Side of Route for Dual Circuit
212393_5 Ausgrid Fibre Network Fibre & Duct Arrangement Breakout Detail on Same Side of Route for
Dual Circuit Arrangement A
212393_6 Ausgrid Fibre Network Fibre & Duct Arrangement Breakout Detail on Same Side of Route for
Dual Circuit Arrangement B
212393_7 Ausgrid Fibre Network Fibre & Duct Arrangement Distributed Temperature Sensing (DTS)
Typical Breakout Arrangement A
212393_8 Ausgrid Fibre Network Fibre & Duct Arrangement Distributed Temperature Sensing (DTS)
Typical Breakout Arrangement B
212393_9 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
Arrangement A
212393_10 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
Arrangement B
212393_11 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Lay Flat
Arrangement Breakout Details
212393_12 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
To Bypass HV Jointing Pit (Single Circuit)
212393_13 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
- DTS Entering HV Jointing Pit (Single Circuit)
212393_14 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
To Bypass HV Jointing Pit (Double Circuit)
212393_15 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
- DTS Entering HV Jointing Pit (Double Circuit)
212393_16 Ausgrid Fibre Network Fibre & Duct Arrangement Fibre Cable Flow Through Typical
Communications Pit
212393_17 Ausgrid Fibre Network Fibre & Duct Arrangement Combined DTS & Comms Typical Breakout
2 x 2 HV Conduit Arrangement
Number Title
212393_18 Ausgrid Fibre Network Fibre & Duct Arrangement Inline Fibre Hauling Pit Typical
Arrangement
212393_19 Ausgrid Fibre Network Fibre & Duct Arrangement In Road Comms Pit
514020 Lighting Column Concrete Plinth Steel Mould (For Use With Ragbolt Assembly)
Conduits Conduits
protected unprotected
Conduits Conduits
protected unprotected
Figure C1
Figure C2
Figure C3
** Width of Ausgrid allocation depends on the date of roadway dedication. Refer to Annexure D for
further details.
Figure C4
Figure C5
* Width of Ausgrid allocation depends on the date of roadway dedication. Refer to Annexure D for
further details.
All trenches shall be 750mm deep. Refer to Clause 10.10 for standard spacings.
Minimum vertical separation between communications carrier and cable protection covers:
150mm above cable protection covers over low voltage cables or conduits
300mm above cable protection covers over high voltage cables or conduits
For Regional footway allocations prior to 2018, refer to NSW Streets Opening Conference - Guide to Codes
and Practices for Streets Opening 2009 edition.
For footway allocations in Sydney Region prior to 1991, refer to Figure D1.
Approximate
Type of Cable** *Max. Pull Tension (kN**)
Cable Mass (kg/m)
11kV Unarmoured Power Cables
500 CU3 TRXQ 35 CU(WS) Z YQ 11.1 17.9
500 AL3 TRXQ 35 CU(WS) Z YQ 11.0 8.5
500 AL3 P H L YQ 19.2 13.2
400 AL3 TRXQ 35 CU(WS) Z YQ 10.5 7.3
300 AL3 TRXQ 35 CU(WS) Z YQ 9.5 6.2
300 CU3 P H L YQ 13.6 15.0
300 AL3 P H L YQ 13.6 9.3
240 AL3 P H L YQ 11.6 8.1
185 AL3 TRXQ 35 CU(WS) Z YQ 8.2 4.6
185 CU1 TRXQ 70 CU(WS) Z YQ 3.8 2.9
150 CU3 TRXQ 35 CU(WS) Z YQ 7.7 6.8
95 AL3 TRXQ 16 CU(WS) Z YQ 6.6 2.8
630 CU1 TRXQ 120 CU(WS) Z YQ 6.0 7.8
300 CU1 TRXQ 150 CU(WS) Z YQ 4.8 4.8
300 CU1 P H L Z 4.4 5.2
300 CU1 TRXQ 70 CU(WS) Z YQ 4.6 4.1
300 CU1 TRXQ 70 CU(WS) Z 13.8 (for total cable, 1 stocking required) 12.4
YQ/Triplex 4.6 (for each core, 3 stockings required)
185 CU1 P H L Z 3.2 3.5
185 CU1 TRXQ CU(WS) Z YQ / Triplex 12.6 (for total cable, 1 stocking required) 8.9
4.2 (for each core, 3 stockings required)
70 CU1 G TRXQ G 16 CU(WS) YQ 2.2 1.1
35 AL1 G TRXQ G 16 CU(WS) YQ 1.7 0.5
LV Unarmoured Power Cables
240 CU4 XQ Z 6.8 9.81
240 AL4 XQ Z / SAC 6.1 3.9
120 AL4 XQ Z/SAC 4.5 1.8
500 CU1 XQ Z 4.5 4.93
300 CU1 XQ Z 3.1 3.1
185 CU1 XQ Z 1.8 1.9
LV Service and Street Lighting Cables
16 CU2 XQ Z N/A 0.47
16 CU4 XQ Z N/A 0.9
25 CU4 XQ Z N/A 1.3
50 CU4 XQ Z N/A 2.2
Copper 0.07
Note: Maximum pulling tension is limited to 20kN. Please consult the cable manufacturer for
advice if higher pulling tensions are required.
Where a pulling eye is considered necessary, the cable supplier shall be contacted for either fitting
the pulling eye to the cable or providing details of approved pulling eyes.
Before pulling a cable with a pulling eye, the installer shall ascertain from the cable supplier what
maximum sidewall pressure can be applied to the cable and shall ensure that this sidewall
pressure is not exceeded during cable installation.
Cable ends fitted with pulling eyes shall be waterproofed to ensure water does not enter the cables
during installation, regardless of the type of pulling eyes fitted. Waterproofing can be achieved by
shrinking a length of mastic lined heatshrink sleeve, covering the full length of the pulling eye and
overlapping the cable sheath by at least 150mm. Before installing heatshrink sleeves, the pulling
eyes and associated cable ends shall be thoroughly degreased and cleaned. The heatshrink
sleeves used shall be abrasion resistant and shall have a minimum wall thickness of 3mm after
recovery over the pulling eye.
Particular care must be exercised when pulling at the relatively high tensions allowed by the use of
pulling eyes. Large bending radii and adequate support using rollers must be provided to avoid
causing flattening, distortion or other damage to the cables.
Pulling cables into conduits
Prior to pulling cables through Asbestos Cement conduits refer to the appropriate Safe Work
Method Statement.
The pulling tension on cables being pulled into conduits shall not exceed 20kN, including cables
fitted with pulling eyes. Please consult the cable manufacturer for advice if higher pulling tensions
are required.
In addition, the maximum sidewall pressure exerted onto a cable must not exceed the following
values when the conduit is installed in compacted standard bedding or 20:1 sand cement bedding:
3kN/m for a ‘rough bore’ conduit, eg fibre reinforced cement
5kN/m for a ‘smooth bore’ conduit, eg plastic conduits.
For UPVC conduits installed in TSB, dry mix or concrete encased the maximum sidewall bearing
pressure exerted on the cable must not exceed the value specified by the cable manufacturer. At
least 7 days is required for sufficient strength gain of the encasement around the conduits.
The following coefficients of friction are extracted from EPRI Report EL-3333.
Table F1: Coefficients of Friction
Item Stockcode
Cables:
11kV 500 AL3 TRXQ 35 CU(WS) Z YQ 178947
11kV 500 CU3 TRXQ 35 CU(WS) Z YQ 178813
11kV 300 CU1 TRXQ 70 CU(WS) Z YQ 177995
11kV 300 CU1 TRXQ 70 CU(WS) Z YQ/Triplex 179122
11kV 400 AL3 TRXQ 35 CU(WS) Z YQ 177562
11kV 300 AL3 TRXQ 35 CU(WS) Z YQ 177561
11kV 185 AL3 TRXQ 35 CU(WS) Z YQ 177566
11kV 150 CU3 TRXQ 35 CU(WS) Z YQ 177565
11kV 95 AL3 TRXQ 16 CU(WS) Z YQ 177564
11kV 630 CU1 TRXQ 120 CU(WS) Z YQ 90050
11kV 1000 CU1 TRXQ 120 CU(WS) Z YQ 177203
11kV 185 CU1 TRXQ 70 CU(WS) Z YQ/Triplex 181758
11kV 70 CU1 TRXQ 16 CU(WS) YQ 177568
11kV 35 AL1 TRXQ 16 CU(WS) YQ 67140
11kV 185 CU1 TRXQ 70 CU(WS) Z YQ 182311
11kV 300 CU1 TRXQ 150 CU(WS) Z YQ 177304
11kV 300 CU3 P H L YQ 1396
11kV 300 CU1 TRXQ 70 CU(WS) YQ LSZH/Triplex 182474
Pilot cable 4-core Nylon Translay 1.5CU4QQZNY/TR WHITE 78683
Pilot cable 4-core Nylon Translay 1.5CU4QQZNY/TR BLACK 78717
Pilot cable 4-core Nylon Translay 1.5CU4QQZNY/TR BLUE 78766
Pilot cable 4-core Nylon Translay 1.5CU4QQZNY/TR RED 78782
415V 240 AL4 XQ Z/SAC 141739
415V 240 CU4 XQ Z H108589**
415 500 CU1 XQ Z 14258
415V 300 CU1 XQ Z 14266
415V 185 CU1 XQ Z / COM / 4 CABLES (Parrot cable) 151183
415V 185 CU1 XQ Z 61432
240V 16 CU2 XQ Z 174565
415V 16 CU4 XQ Z 148668
415V 50 CU4 XQ Z 149112
** To be used only when the design specifies
UPVC Conduits to AS/NZS 2053.2:
50mm nominal diameter, 4m long, heavy duty rigid UPVC orange conduit 78022
63mm nominal diameter, 4m long, heavy duty rigid UPVC orange conduit 181361
100mm nominal diameter, 3m long, light duty rigid UPVC orange conduit 78154
125mm nominal diameter, 3m long, light duty rigid UPVC orange conduit 78188
125mm nominal diameter, 6m long, light duty rigid UPVC orange conduit 78162
150mm nominal diameter, 6m long, light duty rigid UPVC orange conduit 78147
Item Stockcode
UPVC Conduits to AS/NZS 2053.2 and AS/NZS 1477:
200mm nominal diameter, 6m long, light duty rigid UPVC orange conduit 178771
Heavy Duty Rigid UPVC Orange Bends to AS/NZS 2053.2
Conduit Dia Radius ‘R’ Angle Nominal Bend Length Stockcode
(mm) (m) (degrees) from coupling to coupling ‘L’ (mm)
50 1.2 45 1120 179832
50 1.2 90 2060 179941
50 0.3 22.5 255 181756
50 0.3 45 350 181755
50 0.3 11.25 205 181757
63 6 30 3400 181388
63 6 15 1800 181389
63 1.2 45 1050 182446
63 1.2 90 2000 182448
63 1.2 22.5 580 182445
Light Duty Rigid UPVC Orange Bends to AS/NZS 2053.2:
Conduit Dia Radius ‘R’ Angle Nominal Bend Length Stockcode
(mm) (m) (degrees) from coupling to coupling ‘L’ (mm)
100 0.6 90 1300 77602
100 1 11.25 450 77461
100 1 22.5 700 77487
100 1 90 1950 H8503
125 1 11.25 550 77503
125 1 22.5 800 77529
125 1 90 2000 77610
125 1.8 6 550 77578
125 1.8 11.25 750 77586
125 1.8 22.5 1100 77545
125 1.8 45 1850 77552
125 1.8 90 3400 177101
125 2.3 6 600 177856
125 2.3 11.25 900 177857
125 2.3 22.5 1300 177858
125 2.3 45 2200 177859
125 2.3 90 4050 177860
150 2.5 6 650 179064
150 2.5 22.5 1400 179065
150 2.5 45 2420 179066
150 6 15 2100 178791
150 6 30 3600 181387
150 10 11.25 2100 77560
Item Stockcode
Light Duty Rigid UPVC Orange Bends to AS/NZS 2053.2 and AS/NZS 1477:
Conduit Dia Radius ‘R’ Angle Nominal Bend Length Stockcode
(mm) (m) (degrees) from coupling to coupling ‘L’
(mm)
200 6 15 2100 178772
200 6 22.5 3100 181754
UPVC Couplings to AS/NZS 2053.2:
50mm, light duty rigid UPVC orange coupling 179831
63mm, heavy duty rigid UPVC orange coupling 185461
100mm, light duty rigid UPVC orange coupling H9703
125mm, light duty rigid UPVC orange coupling 179192
150mm, light duty rigid UPVC orange coupling 179191
UPVC Couplings to AS/NZS 2053.2 and AS/NZS 1477:
200mm, light duty rigid UPVC orange coupling 179194
Conduit Reducers:
150mm to 125mm conduit reducer, medium duty PVC white 176823
180mm to 150mm Conduit reducer, UPVC Orange 180482
Heavy Duty Bellmouths:
50mm 180004
100mm 180003
125mm 180002
150mm 180001
63mm 182449
Miscellaneous:
Plug for 50mm heavy duty rigid conduit 179754
Plug for 125mm and 150mm light duty rigid conduit (flower pot) 77750
Plug for 150mm light duty rigid conduit H85126
Plug for 63mm heavy duty rigid conduit 182450
Spacer for 125mm conduit in accordance with Annexure I of this document 65706
Spacer for 150mm conduit in accordance with Annexure I of this document 180486
PVC solvent cement 38463
Conduit sealing putty 75481
Conduit Sealing foam kit 180112
Lubricant:
Aqualift 20L drum 179705
Polymeric Cable Protection Covers, Steel Plates and Warning Tape:
150mm x 1.2m slabs polymeric cable cover 151100
300mm x 1.2m slabs polymeric cable cover 151076
150mm x 20 m rolls polymeric cable cover 151084
300mm x 10 m rolls polymeric cable cover 151092
200mm x 25 m rolls polymeric cable cover H74930
750 x 200 x 6mm Galv. mild steel plate 71464
150mm x 100 m roll orange polythene warning tape to drawing no. 49070 71233
Ragbolt Assembly:
Ragbolt assembly H5880
Item Stockcode
Heatshrink End Caps:
Heatshrink end caps (lined) for cable diameters in the range 3mm to 8mm 62232
Heatshrink end caps (lined) for cable diameters in the range 4mm to 8mm 62166
Heatshrink end caps (lined) for cable diameters in the range 8mm to 17mm 176801
Heatshrink end caps (lined) for cable diameters in the range 13mm to 22mm 62117
Heatshrink end caps (lined) for cable diameters in the range 17mm to 30mm 180005
Heatshrink end caps (lined) for cable diameters in the range 28mm to 50mm 62067
Heatshrink end caps (lined) for cable diameters in the range 38mm to 70mm 62042
Heatshrink end caps (lined) for cable diameters in the range 65mm to 95mm 62026
Heatshrink end caps (lined) for cable diameters in the range 95mm to 115mm 178062
Heatshrink end caps (unlined) for cable diameters in the range 95mm to 115mm 62208
Heatshrink Tubing:
Heatshrink tubing `for cable diameters in the range 14mm to 31mm 60186
Heatshrink tubing for cable diameters in the range 20mm to 45mm 143776
Heatshrink tubing for cable diameters in the range 27mm to 55mm 141721
Heatshrink tubing for cable diameters in the range 50mm to 100mm 169565
Triple End Seals:
Triple End Seal Kit for 95mm2 to 240mm2 Multicore Cables 178442
Triple End Seal Kit for 300mm2 to 500mm2 Multicore Cables 178441
Triple End Seal Kit for 185mm2 to 300mm2 High Voltage Single Core 178443
Polymeric Cables
Triple End Seal kit for 185 to 300 mm2 LV Single Core Polymeric Cables 182467
Cable Clamps for Polymeric Cables:
Nitrile Rubber Liner to be used with all Cable Clamps for Polymeric Cables 179201
Single Core Cable for attachment to Unistrut – 70mm2 179212
Single Core Cable for attachment to Unistrut – 300mm2 179211
Single Core Cable Held in Flat Arrangement – 300mm2 180350
Single Core Cable Held in Flat Arrangement – 185mm2 180291
Single Core Cable Held in Quad Arrangement – 185mm2 LV Parrot Cable 179213
Single Core Cable Held in Trefoil Arrangement – 70mm2 179491
Single Core Cable Held in Trefoil Arrangement – 185mm2 178988
Single Core Cable Held in Flat Arrangement – 630mm2 to 1000mm2 182114
Single Core Cable Held in Trefoil Arrangement – 300mm2 to 630mm2 178987
Single Core Cable Held in Trefoil Arrangement – 1000mm2 182134
Stainless Steel Band Type – Part No ABB:EA-UKR100 177651
Figure H1
Details
Cable: 300mm2 Cu Triplex
Ducts: 125mm UPVC
Backfill: 20:1 sand/cement dry mix
Bedding: thermally stable bedding slurry (TR = 0.9K.m/W or less, fully dry).
* Required cover may vary to suit Council or RMS requirements. Cover could be as high as 1.0m for RMS
roads.
specified
Sub-grade Level
Below sub-grade Varies As specified in 98% MSDD or
Clause 0 95% MMDD
UNCONTROLLED IF PRINTED
Density Index
80%
Standard
Page 99 of 113
Amendment No 5
Unclassified
NW000-S0088
Reinstatement Zone Zone Thickness Material Compaction
width in Requirement
accordance
with
specification .
Finished Surface Levelw
UNCONTROLLED IF PRINTED
70%
Definitions
Network Cables 415V and 11kV cables required to supply parts of Ausgrid's network
other than just the building through which they are passing.
Ductline A group or bank of conduits suitably spaced for required cable ratings
and installed so that heat generated by the cables may be effectively
dissipated. The cables are required to be protected from the effects of
a fire in the building through which they pass, either by encasement in
suitable materials or shielding and separation from sources of fire.
Property requirements
Where a bank of conduits are to be run through a privately owned building, an easement covering
the route and a right of way to permit access must first be negotiated as per NS143 and applicable
Property Branch documents. The easement would normally be a stratum easement, confined to the
boundaries of the materials encasing and supporting the conduits.
Policy
Wherever possible, Network Cables shall be routed through public roads or reserves in accordance
with NS143 Easements and Leases and NS130 Laying Underground Cables up to and including
11kV.
However, where situations arise such that it is difficult to provide supply to all customers in this
manner, Ausgrid may determine that space is required through new or existing buildings for the
construction of a Ductline. This new Ductline would not be intended to exclusively supply the
customers in that building.
In such cases, other network customers are exposed to an additional risk of wider spread loss of
supply in the uncommon event of a fire or catastrophic incident occurring within the building and
impacting on the availability of the Network Cables passing through the Ductline.
It is therefore necessary that a policy be developed and requirements specified to ensure that
Network Cables running through buildings are installed in such a manner that they are protected as
far as possible from accidental damage and the impact of a catastrophic incident. If damaged, the
Network Cables should be installed so that they are capable of being quickly restored to a
serviceable condition.
Functional Requirements
The installation conditions should be such that the performance of the cables is not compromised
by the additional measures required to protect them. The cable protection shall be such that the
cables are capable of being quickly removed or replaced in the event of a major building failure.
Ausgrid’s policy in this regard is as follows:
Where Network Cables are to be run through a Ductline located inside a building, the Ductline
shall be designed to provide at least a 3 hour fire rating (FRL 180/180/180) for the Network
Cables unless special circumstances mitigate the risk of the Ductline being exposed to the fire.
At the end of 3 hours fire exposure, it shall be possible to withdraw existing cables installed in
the Ductline and to install new Network cables without difficulty.
The Ductline and supporting structures shall be protected against a 2 kPa overpressure
generated from within the building area.
Any proposed reduction in the fire protection or overpressure requirements shall be subject to
the written approval of Ausgrid.
Where the above requirements are not fully achievable, or where there is considered a more
significant potential consequence to the cables or conduits being severely damaged, the
relevant section of Ductline shall be readily accessible. The conduit encasement shall be
designed for ease of demolition so that it can be replaced or repaired in order to facilitate the
speedy replacement of Network Cables contained in the Ductline. Alternative solutions such as
the provision of an alternative back up route may also be considered acceptable.
While adequate fire and overpressure protection is to be established for the Ductline, the form
of protection proposed shall not adversely impact on the design cable ratings of the Network
Cables passing through the building. In particular, the thermal resistivity (TR) of the conduit
encasement shall not be greater than that specified for the project.
Any Ductline design that may adversely impact on the designed cable ratings, shall have a
rating assessment completed by the Designer as per NS 272 and the rating assessment shall
be submitted to Ausgrid for review and written approval.
10. All exposed faces along the route of the internal Ductline shall have suitable marking to the
requirements for reduced cover specified in NS130, and approved by Ausgrid.
11. Internal building areas through which the ductline passes shall be suitably ventilated or air
conditioned to allow for effective circulation of air to all exposed faces and to remove heat
generated by the cables. Design information to be provided by Ausgrid shall include the
estimated heat load per metre for the Ductline being designed.
B. Internal Building Areas with LV and HV Conduits Below Ground in Trenches
1. The conduits shall be 150mm (160mm OD) heavy duty UPVC Orange and shall meet the
minimum requirements of NS130 and AS 2053
2. Minimum conduit centre to centre spacing shall be 230mm
3. The conduits shall be encased in Thermally Stable Bedding (TSB) or concrete. Where concrete
is used a high concrete density is required and lightweight aggregate and air entraining agents
shall not be used.
4. A minimum cover of 100mm for the conduits shall be provided to the trench walls and floor.
This cover may be reduced in confined locations subject to approval from Ausgrid. Minimum
cover below the internal floor surface shall all be in accordance with NS130 requirements
including those for reduced cover.
5. Within the building area all conduit trenches shall be provided with a reinforced concrete slab
at the surface with a minimum thickness of 125mm.
6. Marking of the route of the Ductline on the floor surface shall be required as shown in NS130
and approved by Ausgrid for all internal Ductlines.
7. Internal building areas above the conduit trenches shall be suitably ventilated or air conditioned
to allow for effective circulation of air and remove heat generated by the cables.
C. Concrete Requirements
Concrete used for encasement of ductlines shall be specified to ensure that it provides the required
mechanical strength and fire rating, while not adversely impacting the thermal ratings of the cables.
In particular, the following requirements must be adopted in designing the concrete mix:
1. The specific concrete specifications required for the concrete encasement of the Ductline are to
be indicated on the drawings. Ausgrid's requirements, including those indicated below, shall be
referenced.
2. The minimum concrete strength for the encasement shall be 20MPa at fire exposed locations
and shall be indicated on the drawings. To limit the heat of hydration, the cement content
should be minimised to the extent possible given the other design requirements.
3. A low heat of hydration cement (Type LH) and appropriate concrete mix design shall be used
to reduce the risk of the UPVC conduits softening during curing. Other measures to further limit
the temperature rise in the concrete encasement during curing may be acceptable subject to
approval by Ausgrid.
4. Admixtures in the concrete mix shall be subject to the approval of Ausgrid following the
submission of a product specific data sheet. The use of accelerators to speed concrete curing
or admixtures that entrain air will not be approved.
5. The total flyash in the concrete mix (by weight) shall not exceed 5% unless separately
approved by Ausgrid. Flyash reduces the thermal performance of the installed Ductline.
6. Lightweight aggregate and air entraining agents shall not be used.
7. The concrete cover to reinforcement shall comply with AS 3600 to achieve a minimum three (3)
hour (180/180/180) fire rating. Ausgrid requires a minimum concrete cover of 45mm to
reinforcement at any fire exposed face.
8. Reinforcement detailing shall be arranged to reduce the potential for induced currents. In
particular, transverse reinforcement around the Ductline shall not form a closed loop at any
location.
ASPs or contractors wishing to vary concrete mix from approved requirements shall provide
documentation demonstrating that their proposal achieves the specified functional requirements
including Ductline integrity and thermal resistivity (TR) value without increasing the in-situ concrete
curing temperature to a level where conduits are likely to be damaged.
D. Electric and Magnetic Fields (EMFs) and Electromagnetic Interference (EMI)
The selection of the route for network ductlines through buildings should take into account the
possible effects of Electric and Magnetic Fields (EMF) and Electromagnetic Interference (EMI). The
adjacent, current and expected building and land uses and locations of Ductlines and cables
should be evaluated for EMI.
Evaluation by an approved Electrical Engineer is to be undertaken to ensure EMI does not disrupt
sensitive electronic equipment or pose a health risk to persons who continuously occupy adjacent
areas for long periods of time.
An EMI report must be provided as part of the design submission for the proposed Ductline.
Areas of particular relevance include hospitals, particularly operating theatres (Refer to AS/NZS
3003), computer rooms, laboratories, general offices and apartments.
Refer to NS114 for additional requirements and guidance.
Note: Installation of EMI screening is not permitted inside any Chamber Substation, at any HVC
connection, or associated chambers and cable risers. The addition of EMI screening at
other locations must not interfere with access to, maintenance of, air circulation around or
the efficient operation of the Ductline and related equipment.
Where:
ρ = TR in K.m/W (or oC.m/W)
T1 and T2 = Temperatures at the beginning and end of the test period respectively
q = Heat dissipated by the line heat source in watts/m
t1 and t2 = Times at the beginning and end of the test period in minutes
The qualifying factors that apply to the above expression should be noted as:
Thermal probes are not line heat sources and have physical diameters and wall thickness. The
resulting mass and specific volumetric heat of the probes causes non linear relationships between
temperature and log (time differences) at the initialisation of tests.
Scope
The scope of this document covers information relating to the necessary processes for ensuring
that testing of thermally stable materials or soil samples is conducted in a manner that provides
accurate and consistent results regardless of the Testing Laboratory undertaking the tests. In
particular, the document includes information on:
For compacted granular materials, the minimum Proctor density of samples shall be specified by
Ausgrid. If not specified, the value shall be 98% Standard Proctor density. For material submitted
for approval (type testing) the fully dried out TR shall also be determined at 95% and 90% standard
Proctor density.
Sieve analysis may also be required when instigating projects the Testing Laboratory should
confirm that Ausgrid requires sieve analysis results.
AS 1289 5.1.1-2003: Method of Testing Soils for Engineering Purposes – Soil compaction and
dry density Tests.
AS 1289 2.1.1-1992: Method of Testing Soils for Engineering Purposes – Soil moisture content
tests
AS 1289 1.1.1-2001: Method of Testing Soils for Engineering Purposes – Sampling and
preparation of soils.
AS 1012.3.1 – 1993: Methods of Testing Concrete. Determination of properties related to the
consistency of concrete – Slump test
AS 1379 – 1997 Specification and supply of concrete
Moisture migration within the sample under test due to the heat from thermal needles can affect
the rates of temperature rise
Non stable sample temperatures affect the flow of heat generated by the probe
Poor probe surface contact resistance with the surrounding aggregates can influence results
due to situations such as: aggregate size, compaction, cracked samples or incorrectly installed
thermal needles
Poorly prepared samples where in the case of compacted granular materials the density of the
material is inconsistent with the expected density
For these reasons when assessing the resulting values (or more fundamentally, the time periods
over which analysis is to occur) a visual representation of the temperature/log time output must be
referred to, to ensure initial and transient boundary effects have been considered and their effect
on the TR result minimized.
Equipment
Thermal Resistivity Test Instruments.
Refer to part 5 of IEEE 442-1981 Guide for Soil Thermal Resistivity Measurements for general
information on test equipment for use on TR testing.
Whilst the determination and analysis of TR can be achieved using relatively simple equipment,
modern instrumentation usually incorporates constant current power sources and data logging
facilities together with computer assistance to output a TR quantum.
Due to the effects of initial transients and edge effects, only those instruments that can
demonstrate to the satisfaction of Ausgrid that these effects have been considered and eliminated
in the determination of TR shall be approved for carrying out TR measurements.
Thermal needle length to diameter ratio shall be no less than: 30:1.
The contractor may be required to perform a practical demonstration of the instrumentation offered
and shall be required to provide specifications for the equipment to be used for testing samples for
Ausgrid.
A list of the key equipment expected to be required by Testing Laboratory in carrying out TR
measurements for Ausgrid is provided in Table L1.
Sample preparation
The preparation and handling of samples has a great influence on the resulting TR.
Due to the relatively small size of commonly prepared samples the scaling effects on mix
tolerances can lead to inaccuracies when specifying delivered quantities.
The measuring tolerances of equipment and methodologies used to prepare samples shall be
suitably controlled to minimize scaling errors.
The positioning of test probes within the samples being prepared is controlled to prevent
movement of the probes during compaction
The density of the compacted material within the sample is consistent throughout the sample
volume.
Sample compaction is carried out at known moisture contents (as a percentage of dry weight)
For these reasons samples must be prepared in controlled layers where the mass of the material
being compacted within each successive layer volume is known. Quality balances must be used to
accurately measure the mass of material used within the layered samples.
Samples shall be taken from site or prepared from ingredients in accordance with AS 1289.1.1.1.
When placed in the test cylinder, compaction shall be tested in accordance with AS1289.5.1.1.
Compaction rates and the densities must be referenced to standards to ensure repeatability in the
field ie Standard Proctor Test.
Where a dryout curve is being prepared, moisture content shall be tested at the beginning and end
of tests, as well as at additional points in between. Testing for moisture content shall be in
accordance with the requirements of AS1289.2.1.1.
Flowable Samples
The collection and treatment of fluidised samples before solidifying can have marked effect on the
TR of the sample under test. The aggregates within these high slump materials (designed such that
they should flow without mechanical vibration) can easily segregate under vibration. The
consistency of the collected sample under test must be representative of the material installed
within the cable trench and for this reason, further movement/vibration caused by influences such
as but not limited to:
Rodding
Transport
Tapping the sample tube
should be avoided until the material has solidified to prevent aggregate segregation. Collected
samples are usually best left on site until solidified before transporting to a test laboratory for
further testing.
Probe Installation and Collection of Undisturbed Soil Samples
The installation of thermal needles/probes must be done with a view to ensuring good contact
between the needle and the surrounding material without disturbing the soil.
Poor contact between the thermal needle and surrounding material will greatly affect the TR
measurement.
If the sample material is so hard as to require the drilling of a hole to permit installation of the
needle without damage to the needle or disturbance to the sample, the hole shall be of slightly
smaller diameter than the needle to ensure that the needle maintains a good contact with the
sample throughout its length.
The most common method used for collecting undisturbed samples is via driven tubes. These
tubes must comply with the minimum dimensions specified above.
The tubes used must be thin walled (nominally 1.0mm) and driving operations undertaken with
processes that prevent inadvertent compaction of the collected sample.
Note: Driving thermal needles and sample tubes into native soil within the field environment
bring with it the risk of damaging other services. The Contractor’s attention is brought to
the necessity to locate services before driving probes, collection tubes or drilling holes for
needles. The cost of rectification of any damage caused by the contractor in carrying out
probe installation or the collection of samples shall be borne by the contractor.
Storage of samples
The Test Laboratory shall have in place suitable storage facilities for the preservation and storage
of test samples.
Following final tests, samples are usually discarded, however there may be a requirement for
samples to be stored for a period of time for records and/ or retest either by the Test Laboratory or
by others.
The maximum time samples are required to be stored is: 6 weeks.
For samples to be stored by the Test Laboratory, Ausgrid must issue notice to the Test Laboratory
no less than 2 weeks prior the commencement of testing that samples are to be stored. At the
completion of the storage time the Test Laboratory may discard the samples unless within the 6
week storage period notice has been given by Ausgrid that prolonged storage of samples would be
required.
The maximum prolonged period of storage (including the initial 6 weeks) shall be 12 weeks.
The minimum volume to be allocated for the storage of samples shall be 24m3
The storage facility shall be in a cool dry place with security and appropriate filing to prevent the
loss and ensure proper identification of samples for the storage period.
At the end of the storage period the Test Laboratory may discard the samples and/or hand them
over to Ausgrid at Ausgrid’s discretion.
Compaction density to be used on site as a % of the Standard Proctor Density (used to achieve
the type test results for compacted granular materials)
For flowable type mixes only:-
Nominated slump (in the case of fluid type product) to be used on site
Forecast Compressive strength @ 6, 12 and 24 months at the minimum and maximum site
acceptable slump (moisture content) values.
Six cylindrical samples nominally 100mmD * 150mm long shall also be provided for inspection by
Ausgrid.
The type test results (including the 28 day compressive strength results) together with work method
statements (WMS) for their installation for controlled thermal bedding together with samples, shall
be provided no less than 6 weeks prior to first installation.
Quality Management Plans
Testing Laboratories undertaking TR testing must have in place, accredited or approved quality
systems documenting the:
Work method statements for each of the individual processes being undertaken
Test report formats
Equipment list that positively identifies the equipment used and the accuracy of the
instrumentation provided
Right of access
Ausgrid reserves the right to witness any testing being carried out on its behalf, whether this testing
is on site or within laboratories.
Ausgrid reserves the right to audit any testing or equipment that may be used for testing samples
on its behalf. The cost of auditing will be to Ausgrid who will provide reasonable notice to the Test
Laboratory for the audit.
Confidentiality
The Test Laboratory must have in place quality systems to guarantee the confidentiality of tests
carried out on Ausgrid’s behalf.
Table L1: Typical Equipment
2 Thermal needles Thermal probes/needles with a length to diameter ratio of > 30:1
probes capable of withstanding oven temperatures 105oC.
Sized to suit field and laboratory situations.
3 Forced air oven Used for drying out and stage drying samples (at up to 105oC ± 2.5%)
as well as treating soil samples at elevated temperatures prior
disposal in accordance with the NSW department of agriculture
specifications.
4 Balance and calibration ± 0.01% for accurately weighing component materials and mixtures.
test weights
6 Standard proctor These standardized items (to AS 1289 – Methods For Testing Soils
compaction hammer For Engineering Purposes) are used for the laboratory compaction
and test cell and density measurement of samples.
7 Field sample tubes with 50mmd * 150mm long Stainless steel tubes for the collection of
sealing caps undisturbed field samples with “in-situ/natural” density or allowing
uncontrolled drying out of test samples.
8 Laboratory sample For accurately preparing compacted granular samples with consistent
tubes and compaction density throughout the sample.
equipment
9 Slump cone and Used for determining the standard slump of “fluid” materials.
tamping rod
10 Measuring cylinder 0-500ml ± 0.5ml measuring cylinder for accurately measuring the
required moisture component of samples under manufacture.
11 Manuals and work Quality assurance for equipment calibration and work procedures.
instructions
Cement 20
Water 200
Cement 70
Flyash 100
Water 190
Cement 25
Water 105
* SSD = Saturated Surface Dry - the condition of the aggregate in which the pores in each particle
of the aggregate are filled with water but no excess water is on the particle surface.