Jobs : Steel box Your company address and contact


Deadline :
Timeline
QTY
:
: 3 Unit
PLEASE PUT YOUR COMPANY LOGO HERE UL-ER
A3 PRINT
1 2 3 (4=1 x 3) 5 6 7 (8=5 x 7) (9=8 +4)
No ITEMS MATERIAL WORK SUB TOTAL REMARKS
QTY UNIT UNIT PRICE SUB TOTAL QTY UNIT UNIT PRICE SUB TOTAL

1 Safety
1.1 COVID Protocol Rapid Test Antigen 1 Lot IDR 1,000,000 IDR 1,000,000 IDR 1,000,000
1.2 PPE (Masker, Hand Gloves) 1 Lot IDR 1,000,000 IDR 1,000,000 IDR 1,000,000
1.3 Safety Officer K3 Umum 1 Lot IDR 1,000,000 IDR 1,000,000 IDR 1,000,000
2 Preparations
2.1 Mob Demob 1.00 Lot IDR 3,000,000 IDR 3,000,000 IDR 3,000,000
2.2 Safety tools preparation (Schafolding, life line, and etc) 1.00 Lot IDR 2,500,000 IDR 2,500,000 IDR 2,500,000
3 Material and Spare part
3.1 Material
Frame Steel Box 1.00 Lot IDR 15,000,000 IDR 15,000,000.00 IDR 15,000,000
Hollow SNI 60 x 60 t2mm - 6m 10.00 btg IDR 415,800 IDR 4,158,000
Plat besi Eser t3mm, 2.4M2 10.00 lbr IDR 1,246,300 IDR 12,463,000
Unp SNI 120 L3m 2.00 btg IDR 899,800 IDR 1,799,600
siku SNI 30 x 30 black steel t3mm 4.00 btg IDR 90,200 IDR 360,800
engsel 1/2 inch 6.00 pcs IDR 20,000 IDR 120,000
As 12 mm 1.00 btg IDR 130,000 IDR 130,000
cat biru 10.00 kg IDR 65,000 IDR 650,000
cat meni 10.00 kg IDR 50,000 IDR 500,000
4 Installation & Commisioning
4.1 Trans delivery & Installation 1.00 Lot IDR 3,000,000 IDR 3,000,000 IDR 3,000,000

5 Finishing & Documentation


5.1 Report & As Build Drawing 1.00 Lot IDR 5,000,000 IDR 5,000,000.00 IDR 5,000,000

TOTAL MATERIAL IDR 22,181,400 IDR 22,181,400.00


TOTAL WORKS IDR 29,500,000.00 IDR 29,500,000.00
PROFIT %
TOTAL QUOTATION EXCLUDED TAX IDR 51,681,400.00

Notes Requirement
1 Safety Induction dilakukan seminggu sebelum hari-H
2 Pengecekan Safety tool dan working tools dilakukan seminggu sebelum hari-H
3 Forklift harus di lengkapi dengan SLO dan SIO dan di lakukan pengecekan seminggu sebelum hari-H
4