Construction Method Statement
Construction Method Statement
P/2017/01110
Received 29/08/2017
Statement
For developing the site at:
Branston, Tatenhill Lane
In brief, the project consists of:
Demolition of two bungalows on Tatenhill Lane to allow access for and the construction of
55 new-build residential houses with associated highways, drainage & service
Infrastructure, hard and soft landscaping.
The Client:
Lioncourt Homes Ltd
3 Apex Park
Warndon
Worcester
WR4 9FN
01905 755167
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
Document Revision Schedule
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
Index:
1.0 Introduction
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
1.0 Introduction
Lioncourt Homes Ltd recognises its responsibility to minimise any potential adverse
environmental impact of our company operations and is committed to upholding its duties as
a good corporate citizen for the greater benefit of the communities in which we operate. To
that end, this plan sets out how it will manage the Company’s Policy objectives and those
potential impacts by considering the following aspects:
• Compliance with current environmental legislation and local and national planning
guidance and building regulations.
• Prevention or minimisation of the emission or release of pollutants
• Protection of the local ecosystems, wildlife habitats and heritage
• Minimising noise levels, traffic nuisance, and disturbance to the public
• The control any accidental spill/release
• Waste reduction by the efficient use of materials (including sustainable, reusable or
recyclable products) and energy
• Ensuring that all wastes, particularly hazardous or contaminated wastes are tested,
transported and disposed of in an environmentally acceptable manner, in accordance
with statutory duty of care requirements
• Encourage our supply chain to comply with this plan
• Incorporation of features, in the design of our houses and developments that
minimise the impact on the environment during their habitation.
• Monitor and review performance
Being a common condition of a planning consent, the production of this construction method
statement sets out to show compliance with the above objectives and thereby satisfactorily
discharge that planning condition.
The project has been notified to the HSE in accordance with the Construction (Design and
Management) Regulations 2015 (CDM 2015). The project has or will continue to be planned,
designed and managed in accordance with CDM 2015 and all other applicable health and
safety legislation e.g. Health and Safety at Work Act 1974, the Control of Noise at Work
Regulations 2005, the Management of Health and Safety at Work Regulations 1999 etc.
In accordance with CDM 2015, Pre-Construction Information has been gathered and passed
to relevant contractors and designers etc. and the Principal Contractor has or will develop this
and the design information into the Construction Phase Plan which is the controlling
document under CDM 2015 to manage all works on the construction project. The Plan and
other health and safety legislation requires risk assessments and potential method
statements to be drawn up to identify control measures needed to mitigate risk and
consequence of construction operations. Lioncourt, as Principal Contractor ensures that all
contractors produce such assessments etc. and plans and monitors its operations in
accordance with such assessments and the Construction Phase Plan and consequently all
relevant legislation.
Once on site, the Site Manager is responsible for monitoring the compliance of its
operations with the Construction Phase Plan and this Construction Management Plan.
Senior Management will periodically inspect this compliance.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
2.0 The Project
2.1 Project Location and Description
The project involves constructing the houses, roads and sewers and all associated hard and
soft landscaping.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
Site Layout Plan
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
2.2 Relevant Planning Condition(s) 15
‘No development shall take place until a Construction Management Plan including details of routing
of construction vehicles, parking facilities for vehicles of site personnel, operatives and visitors,
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
arrangements for loading, storage and unloading of plant and materials, wheel washing facilities,
measures to remove any mud or deleterious material deposited on the highway, and a timetable for
implementation shall be submitted and approved in writing by the Local Planning Authority. The
development shall thereafter only be carried out completed in accordance with the approved details.’
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
4.2 Traffic Route Plan – site access/egress
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
4.3 Traffic Route Plan – deliveries/movements within the site
As 4.2 (Can only be achieved once the full road system is constructed and until
significant occupation makes it safer to adjust)
• A Traffic Management Plan will be drawn up and maintained on site which will also
include pedestrian walkway routes, welfare, first aid and emergency provisions and
others such considerations as required by CDM 2015.
• Circumstances continually change as sites progress and the Traffic Management Plan
is regularly reviewed and updated as necessary.
• A one-way circuit or alternative turning facility will be provide on site to allow
vehicles to depart in a forward gear.
• Site entrance warning signs to be erected at and in advance of site entrance subject
to legal permissions.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
• During the initial stages of demolition and infrastructure construction, contractor’s
vehicles will be parked on a temporary stoned up car park, within the site and
reasonably close to Tatenhill Lane.
• Pending construction of the remaining phase 1 infrastructure sewers and road, the
long-term compound, dedicated vehicle parking and management/welfare facilities
will be installed as annotated.
• Onsite parking will be maximized as the site’s progress allows e.g. car park provision
from site start plus use of driveways away from loading/transport areas and formed
parking areas as and when practicable.
• Sales visitor parking will be provided in hard-standing close to the sales centre with
easy access away from construction activities.
8.2 Vibration
• Those operations that give rise to significant vibration e.g. piling or crushing will be
impact-assessed at design stage and monitored during such operations, if proximity
to existing neighbours or ground conditions are considered to be significant.
• Where practicable, any such operations will be positioned, away from neighbours or
residential areas to reduce the impact.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
9.0 Dust Control
9.1 Dust prevention and control measures
• Site access roads will be constructed up to tarmac basecourse level as soon as possible
to allow clean and cleanable access to working parts of the site and for deliveries and
visitors. Road sweeping attachments or units shall have working water spray devices
whilst in use.
• Dust-producing operations to be suppressed at source e.g. disc-cutting dust-
suppression kits or timber cutting filtered extraction units used.
• High dust producing operations such as crushing will be dust suppressed by
proprietary incorporated water spray devices.
• General dust about the site to be suppressed on site with bowser/sprayer as required.
• Dust control measures will be monitored daily by Site Management.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17
• Anti-climb block and mesh fencing will be erected and maintained around the site and
working areas.
• As areas of the development are completed and made safe, these will be opened up
and the boundary fence of the working zone will be correspondingly moved back.
• Notices will be displayed near site entrance and around the boundary to signify
construction hazards and the restriction of access to unauthorized persons.
• Viewing facility for the public: see-through mesh fencing along main site boundaries.
Form Ref: HSE 099 Title: Construction Method Statement Date of Revision: 26.01.17