Scope: This deals with procedure adopted for die/ tool inspection both for newly
made dies and partly used dies.
Procedure:
a) For New Dies:
1) Receive Dies/Tools and plaster samples - From Tool room
2) Check drawing - For Validity
3) Inspect - As per drawing parameters with calibrated instruments
4) Verify Traceability - As recorded by drawing and as per lab intimation.
5) Record - Actual inspected dimensions
6) Intimate Tool room - For correcting the variations
7) Re-inspect - After Correction by Tool room.
8) Get approval - From Head QA for releasing
9) Intimate Tool room - About acceptance with report .
b) For Old Dies :
1) Receive dies /Plaster Samples – From Tool room with feed back repot
2) Study feed back report - Recommendation for corrections to be
inspected as drawing.
3) Check and verify - For correction carried out by tool room.
4) Record - Actual findings
5) Intimate tool room - For any more corrections if required.
6) Re-inspect - To verify the corrections are carried out.
7) Get approval - From Head QA.