12.method Statement Slab On Grade
12.method Statement Slab On Grade
2. Location of Activity
3. Work Procedure.
The method statement covers all activities related to the Casting Slab on Grade works.
The works shall be executed in accordance with the following methodology and sequence;
1. Site Planning.
Delivery – fresh concrete shall be batched from the approved supplier of concrete. Concrete will
be delivered direct to the site and to be received by assistant Quality Engineer for checking of
the required criteria of concrete. The assistant QC Engineer will make sure the concrete
delivered is as per the approved design mix for the situated member to be casted.
All data for testing on fresh concrete at site shall be recorded on the concrete pour card
2. Preparation
After the blinding is casted and placement of waterproofing is done, the preparation and casting
for slab on grade shall be done
Fix the reinforcement steel as per the approved drawings, sometimes A393 BRC mesh is
indicated in the drawing and most commonly use in 250mm thick concrete grade slab.
Any loose binder or ties along the splices reinforcement steel shall be re-tightened. Bend inward
the free ends of the binding wire or ties.
Use PVC spacer for vertical bars and concrete spacer for bottom as concrete covers.
Ensure and coordinate with MEP staff for any MEP works required on the area as per approved
drawings.
3. Concrete Pouring
The concrete mixer must be stopped at the check point for the inspection of slump test and to
obtain sample cubes for test.
One set of cubes shall be taken every 50 cubic meter concrete, each set consist of 6 cubes, 3
cubes to be tested on 7th days and 3 cubes to be tested for 28th days.
Extra three cubes can be made for re-checking if in case circumstances may happen.
Unload the concrete within 90 minutes from the batching plant loading time.
Compact the concrete properly by using mechanical vibrators, extra vibrator shall be available in
case of any shortage or mechanical problems.
Use approved hardener material after casting concrete when required. Make sure applications
shall be as per manufacturer’s recommendation.
Use the power float for the smooth finish surface purpose. Store extra power float near the
casting area in case of any mechanical malfunctioning.
Cure the casted area properly with covering concrete with hessian cloth and polythene sheet on
top but before placing the concrete wet the hessian with water.
Cure the concrete by spraying water three times per day for a period of 7 days.
The casted area or member shall be protected by placing barricade to prevent plants and
machineries damaged the concrete.
Concrete pour card shall be filled by Quality Engineer and to be submitted to the Engineer
including concrete delivery notes, this task will be done whenever required.
Concrete cube test report shall be submitted to the Engineer
2
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
4. Safety
Project Engineer:
The Project Manager and the Construction Manager have the responsibility for the overall operations of
this statement. The Project Manager and Construction Manager have the responsibility to implement the
Method statement and to delegate the responsibility to a Site Engineer and the QC Engineer to directly
supervise the work on site. The site Engineer is responsible for ensuring that all the works are executed
in accordance with the specified requirements.
The Project Manager will be responsible for the following.
Plan and schedule the jobs, determine priorities, control workload, inspect projects and keep sufficient time
records for workflow and outputs.
Performs technical responsibilities and make decisions to a substantial extent.
Reviews and interprets proposed designs, drawings, and specifications for appropriateness to required
function and/or standard and initiates revisions.
Ensure that project operations are in compliance with design specifications
To provide all the necessary information to the site team.
Engineer/Supervisor in charge to conduct a toolbox meeting and communicate both the Method Statement
& Risk Assessment to the workers before commencement of the activity.
All safety precautions shall be followed as per established project safety procedure.
Only experienced and skilled labour shall be engaged for carrying out screed work.
People involved in the construction work shall wear PPE such as safety helmets, safety shoes, safety harness,
gloves safety glass, mask etc.as required.
All Hose pipe joints are properly connected and tied with clips.
Safety officer shall check and ensure that all safety precautions are followed.
All the safety equipment’s shall be periodically inspected and checked for its durability before using them to
labor.
Manual handling procedures to be followed
Any incident or near miss incident shall be reported immediately to the concerned safety officer.
3
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
Site Supervisor:
Foreman:
To provide the Site supervisor with daily progress reports and discuss with him planned works for the next
day.
To ensure that all safety measures are maintained at site and workers have proper training for following all
current safety guidelines and housekeeping in accordance with the Main Contractors Safety Officer.
To ensure good housekeeping is practiced and proper tools are being used by the site team.
To ensure that all persons involved in the works are aware of their duties, and that they have enough
understanding of safety procedures.
To conduct frequent toolbox meeting on safety awareness and to maintain a log of all meetings for
inspection.
To keep a record of all toolbox talks.
Liaises with the required personnel at the site for the required inspections with regards to safety.
Attends all the safety coordination meetings.
Ensure that the basic and activity specific PPE is worn regularly by the site working team.
4
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
5. Equipment Requirements
The requirements that will be engaged for Blinding and Concrete work will be as follows:
Site In-charge.
Charge Hand.
Concrete Transit Mixture.
Operator.
Needle Vibrator.
Skilled Labour.
Cylinder Mold
Concrete Pump(If Required).
Concrete Thermometer.
Compactor
5