Project Control System Procedure
Project Control System Procedure
1200
Project Control System
Procedures
- 102 -
Project Control System Manual
- 103 -
Project Control System Manual
1.0 General
2.0 Procedures
1 - The Project Customer and the Project Manager jointly determine the control
milestones.
The Project Manager, collaborating with the Project Customer, selects the
project key events and decision points that constitute the master schedule.
Titles, definitions and planned dates are determined for each control
(Level 1 and 2) milestone.
2 - The Project Manager, Associate Project Manager and the Control Account
Manager identify the intermediate milestones.
Based on the defined control milestones, the Project Manager, Associate
Project Manager(s) and the Control Account Manager(s) identify the
important intermediate (Level 3 and 4) milestones of the project.
- 104 -
Project Control System Manual
7 - The Project Manager and Associate Project Manager approve the project detail
schedule.
After PM&IP finalizes the project detail schedule, the Project Manager
and Associate Project Manager(s) review and approve the project detail
schedule.
- 105 -
1
Determine
Project Control
Customer Milestones
1 7
Determine Approve
Project 2
Control / Project
Manager Intermediate Detail
Milestones Schedule
3 5 6 8
Develop Establish
Develop Integrate
Project Project
PM&IP Milestones CA Detail
Detail Schedule
Schedule Schedules
- 106 -
Schedule Baseline
Cost Profile
Timed-Phased
3.1 Schedule Baseline Development Flow Diagram
2 7
Associate Approve
Determine
Project
Project Intermediate
Detail
Milestones
Manager Schedule
2 4
Control Determine Develop
Account Intermediate CA Detail
Milestones Schedule
Manager CA: Control Account
Project Control System Manual
Project Control System Manual
- 107 -
Project Control System Manual
1.0 General
2.0 Procedures
- 108 -
Project Control System Manual
7 - The Project Management team reviews and finalizes the project cost estimate.
The Project Management team reviews the consolidated cost estimate for
the project, and through negotiation, finalizes the estimate. The Control
Account Manager revises the Control Account Plan for each relevant
control account based on the final negotiated cost estimate for the project.
- 109 -
1
Provide
Project Funding
Customer Guidance
2 7
Review/
Determine
Project Finalize
Budget Project Cost
Manager Targets
Estimate
5 6 7 8
Integrate Establish Review/ Establish
CA Initial Finalize Project
PM&IP Cost Project Cost Project Cost Cost
- 110 -
Budget
Timed-Phased
4 7
Associate Review Review/
Initial CA Finalize
Project Cost Project Cost
Manager Estimates Estimate
3 7
Control Develop Review/
Initial CA Finalize
Account Cost Project Cost
Manager Estimate Estimate CA: Control Account
Project Control System Manual
Project Control System Manual
- 111 -
Project Control System Manual
1.0 General
This document defines the procedures and responsibilities for collecting and
reporting cost and schedule performance data and analyzing these data to assess
current and projected future project status. Cost and schedule performance is
measured and reported monthly for each control account and WBS element, as
appropriate.
2.0 Procedures
- 112 -
Project Control System Manual
are prepared by the Chief Financial Officer and are available to the
Control Account Managers and Associate Project Managers for review
and to PM&IP for entering into the performance database.
- 113 -
Project Control System Manual
13 - The Project Manager reviews the Variance Analysis Reports with the Control
Account Managers and Associate Project Managers.
The Project Manager reviews the Variance Analysis Reports with the
Control Account Managers and Associate Project Managers to ensure
accurate variance causes are identified and adequate corrective plans are
established. The Variance Analysis Report form is signed by the Control
Account Manager and the Associate Project Manager/Project Manager.
15 - The Project Manager submits the monthly report to the Project Customer.
The Project Manager reviews the monthly report and submits it to the
Project Customer.
- 114 -
1 10 13 Review 15 Submit
Determine Review
Project Variance Customer
Variance Performance
Manager Analysis Monthly
Thresholds Reports
Report Report
4 9 11 Issue 14 Prepare
Determine Prepare
Variance Monthly
PM&IP Earned Performance
Report Project
Value Reports
Form Report
3 Review 8 10 13 Review
Associate Review Review
Status Variance
Project Cost Performance
Update Analysis
Manager Reports Reports
Report Report
3.1 Performance Reporting Flow Diagram
- 115 -
2 Prepare 7 10 12 Complete
Cost Review Review
Status Cost Performance Variance
Account Update Analysis
Reports Reports
Manager Report Report
6
Chief Prepare
Financial Cost
Office Reports
Timesheets
Performing Purchase
Organization 5 Orders
Travel
Vouchers
Project Control System Manual
Project Control System Manual
- 116 -
Project Control System Manual
1.0 General
The integrated project baseline is the approved technical, schedule and cost plan
for accomplishing all project activities. As the project progresses, this baseline
may change due to Project Customer redirection, internal replanning, or redesign.
Changes are classified according to the extent that they impact the integrated
project baseline. The review process and the approval authority required for a
proposed change depend upon its classification. This document defines the
procedures and responsibilities for requesting, reviewing, and documenting
changes to the integrated project baseline, and to assure timely implementation of
changes once they are approved.
2.0 Procedures
Any project team member may request a change to the technical, schedule, and
cost baselines by generating a Change Request form and submitting it to a
member of the Change Control Board for concurrence.
2 - The Change Control Board member concurs with the Change Request.
The originator must then obtain the concurrence of one member of the
Change Control Board in order for the request to be accepted for
consideration. The concurring member signs the Change Request in the
‘Concurrence’ block.
3 - The Change Control Board member initiates the Change Impact Assessment
process.
If the Change Impact Assessment has not been completed on the Change
Request form, the Change Control Board member assigns actions for
analyses of potential technical, schedule, cost and quality/safety effects of
the proposed change. Primary responsibility is typically assigned to a
Control Account Manager.
- 117 -
Project Control System Manual
4 - The Project Management & Integrated Planning Department enters the Change
Request in the Change Request Log.
After Change Control Board member concurrence is obtained, PM&IP
assigns a number (scheme: FY - sequence #, e.g., 05-001) to the Change
Request and enters it in the Change Request Log as “Open.” PM&IP
maintains this log as a database, updating information each time there is a
change to the status of a Change Request. For Class 1-2 and Class 3
changes, PM&IP distributes the Change Request to members of the
Change Control Board, and places the Change Request on the agenda for
the next Change Control Board meeting.
7 - The Associate Project Manager concurs with the classification of the Change
Request.
The Associate Project Manager reviews the classification assigned by the
Control Account Manager and, if he concurs, signs the adjacent block.
- 118 -
Project Control System Manual
After the Change Request has been generated, impacts have been assessed, and an
approved classification level has been established, it enters the Review Phase
where the proposed change is evaluated and approved by an appropriate authority.
For Class 1-2 Change Requests that will go to the Project Customer, this will be
an external approval process. Class 3-5 Change Requests follow an internal
approval process.
• External Approval
10 - The Change Control Board evaluates the Class 1-2 Change Request.
For Class 1-2 Change Requests, PM&IP distributes the Change Request to
members of the Change Control Board and places the Change Request on
the agenda for the next board meeting. The Change Control Board
evaluates the Class 1-2 Change Request package and recommends action
to the Project Manager.
13 - The Project Manager reviews the Project Customer Change Request actions.
The Project Manager reviews the decisions of the Project Customer and
documents any impacts to the project plans in the Recommendation and
Disposition section of the Change Request.
- 119 -
Project Control System Manual
• Internal Approval
- 120 -
Project Control System Manual
After the Change Request has been reviewed and approved by the appropriate
authority, it enters the Documentation Phase where the proposed change is fully
documented and implemented.
- 121 -
Project Control System Manual
- 122 -
1
Generate
Originator Change
Request
5 6
Control Coordinate Establish
Account Inputs CR
to CIA Class
Manager
3.1 Request Phase Flow Diagram
7
Associate Concur with
Project CR
Class
- 123 -
Manager
4 8
Enter to
Approve
CR into
PM&IP CR REVIEW
CRL
Class PHASE
“Open”
2 3
Change CR: Change Request
Member Initiate
Control CIA CIA: Change Impact Assessment
No Concurs? Yes
Board CRL: Change Request Log
Project Control System Manual
9 14
from Monitor Update to
PM&IP REQUEST CR CRL DOCUMENTATION
PHASE Status “Approved” PHASE
Change 10
Evaluate
Control Class 1-2
Board CR
- 124 -
11 13
Project Review Review
Class 1-2 Customer
Manager CR CR Action
3.2 Review Phase Flow Diagram (External Approval)
12
Project Approve/
Disapprove
Customer Class 1-2 CR
CR: Change Request
CRL: Change Request Log
Project Control System Manual
15 16
Control Evaluate Approve/
Account Class 5 Disapprove
CR Class 5 CR
Manager
13 14
Associate Evaluate Approve/
Project Class 4 Disapprove
CR Class 4 CR
Manager
9 17
from Monitor Update to
PM&IP REQUEST CR CRL DOCUMENTATION
- 125 -
PHASE Status “Approved” PHASE
3.2 Review Phase Flow Diagram (Internal Approval)
10
Change Evaluate
Control Class 3
CR
Board
11 12
Review Approve/
Project Class 3 Disapprove
CR: Change Request
Manager CR Class 3 CR
CRL: Change Request Log
Project Control System Manual
21
Control Implement
Account Change
Order
Manager
19
Associate Update
Project Technical
3.3 Documentation Phase Flow Diagram
Documents
Manager
- 126 -
20
Update
PMB
18
from Issue
PM&IP REVIEW Change
PHASE Order 20
Update
Working
Detail
Schedule
PMB: Performance Measurement Baseline
Project Control System Manual