Sop Rfi
Sop Rfi
By
Note: Please be careful to select sing-up role and fill all the required details of KYC form. All these details will
locked for your profile after submission of KYC form.
To use this app you’ll need to allow some permissions;
Here you’ve to select “RO” and “UPC”. As per RO & UPC selection, Project name, company name, Contract duration
will be display. Now you’ve to select Designation and then submit the details.
Note: After submitting this request, it is required to get approval on this request from concern PD. After that only
you’ll be able to access all the rights of your role in app
Add a step here on how to get to this page. Homepage > RFI New.
Contractor Login: -
1. On the landing page, the below screen is displayed.
2. For Raising the request user need to click on the, “Proceed For RFI” button as shown in the above screen for selecting the project. After
that below screen will appear, where the user is able to submit a request for the New RFI by clicking on “RFI Submission”.
3. On clicking the “RFI Submission” button, the below screen is displayed where the user will update the required information and
“Submit” the request to AE.
4. After submitted by Contractor, it is display in grid with status “RFI Created”.
After assigning RFI on contractor inspector by company it is visible on inspector mobile app
➢ How to start RFI by contractor inspector
Note: After click on Inspect button another screen is opened and User can take selfie on site and click on start RFI
button for inspection.
Step-5 Most of details are auto fetched by Datalake. Step-6 Upload Images and submit
Fill rest of details
Note: If AE/ IE already submitted inspection then the update status is same is visible on contractor screen.
➢ Check Inspected RFI
Step-1 Click on “RFI submitted by Step-2 Select record and click on Step-3 Last 7 days submitted RFI by
Contractor” View button contractor
AE Login:-
Note: -
➢ Total inspections: - Total Inspections are the total assigned requests to the AE.
➢ Inspections pending on contractor: - Inspection that has been assigned to the contractor and AE, but the
contractor has not yet started the work.
➢ Inspection pending on me: - An inspection that has been assigned to AE but AE hasn't started work yet.
➢ Submitted inspection: - Those inspection that has been already completed by AE.
Step – 3 Select record and click Step – 4 First take selfie & click on start RFI
on select inspect button
Note :- On click inspect button every time user can see selfie screen.
Step – 5 Some of details are auto fetched from Datalake, add comments, upload pictures of worksite & result and select status
Approve / Reject for RFI submission.
➢ Check Inspected RFI
Step – 1 Click on “RFI submitted by AE” Step – 2 Check last 7 days submitted data
9. In Grid, two sections of “Contractor” & “AE” are display.
(a) If AE submit their inspection report from site, then it is reflected in Datalake and “Submit Report” button become
active in data lake from where AE able to upload report from data lake itself.
(b) If “Contractor” submit their inspection report from site then it is reflected in Datalake and “Submit Report” button
becomes active in data lake from where “Contractor” able to upload report from datalake itself.
10.As above, we see that Contractor’s information is submitted by Contractor’s site inspector and it is reflected in data
lake and “Submit Report” button is also become active from where Contractor able to submit report.
11. On clicking the “Submit Report” button, a pop-up is display from where Contractor able to upload report.
12.After uploaded by Site Inspectors from both Contractor & AE inspector, it is display as below.
After submission of report from both “Contractor” & “AE” Login from Datalake, process gets completed.
---END---