Load Flow Analysis of Ehv Networks Using Mipower Software A Case Study IJERTV5IS010405
Load Flow Analysis of Ehv Networks Using Mipower Software A Case Study IJERTV5IS010405
IJERTV5IS010405 378
(This work is licensed under a Creative Commons Attribution 4.0 International License.)
Published by : International Journal of Engineering Research & Technology (IJERT)
http://www.ijert.org ISSN: 2278-0181
Vol. 5 Issue 01, January-2016
3. Slack or Swing Bus: Usually this bus is numbered 1 Bus number 4: 11 kV Bus is Voltage controlled (P-V)
for the load flow studies. This bus sets the angular reference bus.
for all the other buses. Since it is the angle difference The load flow is carried out by using MiPower software
between two voltage sources that dictates the real and with fast decoupled method.
reactive power flow between them, the particular angle of the
slack bus is not important. However it sets the reference
against which angles of all the other bus voltages are
measured. For this reason the angle of this bus is usually
chosen as 0. Furthermore it is assumed that the magnitude of
the voltage of this bus is known.
In this paper we have carried out simulation by using fast
decoupled method only.
1. Fast Decoupled method
Generally the power system have very high X/R ratio
[5]. Hence the real power changes are less sensitive to change
in voltage magnitude V but it is more sensitive for changes
in phase angle δ. Whereas the reactive power are more
sensitive to changes in voltage magnitude and less sensitive
for change in phase angle δ. Therefore it is reasonable to set
J2 and J3 of Jacobian matrix to zero. Hence the equation for
ΔP and ΔQ becomes:
= (1)
Δ =- ⁻¹ (3)
Here B′ and B″ are the bus susceptance matrixes i.e.
it is imaginary part of admittance matrix Ybus. The bus Figure 1: Single Line Diagram
susceptance matrix is constant and required to evaluate only The realistic data is considered for the simulation using
once at beginning of the iterations. B′ is the order of (n-1). fast decoupled method and then the simulation results are
For voltage regulated buses the Qi are not specified and hence evaluated analytically.
the corresponding rows and columns of the Ybus matrix are
eliminated, hence we get B″ matrix of the order of (n-1-m) 1. System Data
where ‘n’ is the total number of buses and ‘m’ is the number The realistic system data are considered.
of voltage controlled buses.
The fast decoupled method requires more iteration TRANSFORMER DATA
than N-R method, but the time required is considerably less
and we get rapidly the power flow solutions. Transformer Numbers:
1. 220/132 kV 100 MVA
III. SYSTEM UNDER STUDY Impedance: (0.00501+j0.10028) ohm
Figure 1 shows the single line diagram of the system 2. 220/132 kV 100 MVA
under study. A 220 kV substation is considered. A 220 kV Impedance: (0.00501+j0.10028) ohm
bus is connected to EHV grid. A two 220/132 kV 100 MVA 3. 11/132 kV 15.5 MVA
transformers are connected between 220 kV and 132 kV bus. Impedance: (0.01898+j0.37953)
At 132 kV bus, loads are connected through different 132 kV
lines, which are not shown in diagram. A small scale TRANSMISSION LINE DATA
generation of about 13 MW at 11 kV voltage level is Line 1: 132kV GAPS Bus to 132 kV Sawangi Bus
considered. The 11 kV voltage level is converted to 132 kV Impedance: 0.01899+j0.4521
level by using 11/132 kV, 25 MVA power transformer. At 11 Km: 20.40
kV voltage level the load of 4 MW are considered for
auxiliaries of small scale generation. The buses named as: GENERATOR DATA
Bus number 1: 220 kV Bus (connected to power grid) 1. At 220 kV Sawangi Bus connected to Power grid.
taken as slack bus. 2. At 11 kV GAPS Bus 13 MW, 11 kV Generator is
Bus number 2: 132 kV Bus is Load (P-Q) bus. connected.
IJERTV5IS010405 379
(This work is licensed under a Creative Commons Attribution 4.0 International License.)
Published by : International Journal of Engineering Research & Technology (IJERT)
http://www.ijert.org ISSN: 2278-0181
Vol. 5 Issue 01, January-2016
Ang. In
Node V-Mag MW MVAr Remarks
Degrees
1 (220kV
1.0 0.00 111.443 52.271 Gen
Sawangi)
2 (132 kV Figure 2: Summary result diagram of FD Load Flow
0.9237 -3.56 120 50.00 Load
Sawangi)
3 (132 kV
0.9283 -3.36 0.00 0.00 -
GAPS)
IJERTV5IS010405 380
(This work is licensed under a Creative Commons Attribution 4.0 International License.)
Published by : International Journal of Engineering Research & Technology (IJERT)
http://www.ijert.org ISSN: 2278-0181
Vol. 5 Issue 01, January-2016
= =-
The slack bus voltage is V₁ = 10° and magnitude of 1 1-2 54.12 27.20 0.25 5.18 61
voltage of bus 4 is 1 pu. Starting with initial estimates of 2 1-2 54.12 27.20 0.25 5.18 61
=0 pu and δ2°=0, δ3°=0, the power residuals
3 4-3 10.01 6.749 0.42 0.87 69
computed as
0 0
ΔPᵢ = Pᵢ(sch)- Pᵢ
3. LINE FLOWS AND LINE LOSSES
0 0
ΔQᵢ = Qᵢ(sch)- Qᵢ Sr Forward Power Loss %
Node
.N. MW MVAr MW MVAr Loading
Hence the power flow algorithm given by equation 2
becomes as- 132 kV
Sawangi to
1 -16.51 -9.80 0.0807 -0.707 24
132 kV
GAPS Bus
=-
V. CONCLUSION
In this paper the case study is carried out by using
By solving this eq. we get the voltage phase angles. MiPower software. Then the simulation results are validated
analytically.
Since bus 4 is Voltage controlled bus, the corresponding The fast decoupled method is more superior to N-R
row and column of B bus susceptance matrix are method for the system having high X/R ratio. The number of
eliminated, then we get iteration required is more for fast decoupled method but the
calculations are easier than NR method.
=
After comparing the results obtained from MiPower
software with analytical solution, it is found that the results
The inverse of above matrix is are nearly equal. There is having little difference in the load
flow values which may be due to decimal values used in
= software. Also the MiPower software adjusts the Y bus
matrix for calculation purposes as it is the part of the
software.
It will help system operator for forecasting of load flow
data in the EHV networks.
IJERTV5IS010405 381
(This work is licensed under a Creative Commons Attribution 4.0 International License.)
Published by : International Journal of Engineering Research & Technology (IJERT)
http://www.ijert.org ISSN: 2278-0181
Vol. 5 Issue 01, January-2016
REFERENCES
[1] Sandeep Kaur, A m a r b ir Singh, Dr. Raja Singh Khela, Jasdev Singh
Sandhu, “Load Flow Analysis of IEEE-3 bus system by using Mipower
Software”, International Journal of Engineering Research and
Technology, Vol. 4 Issue 03, March-2015.
[2] Jen-Hao Teng, , “Integration of Distributed Generators into
Distribution Three-Phase Load Flow Analysis”, in Proc. 2005 IEEE
Power Tech, Russia, June 2005.
[3] Ahmed Sharique Anees, Department of Electrical Engineering, lamia
Millia Islamia, New Delhi, “Grid Integration of Renewable Energy
Sources: Challenges, Issues and Possible Solutions”,Power Electronics
(IICPE),2012 IEEE 5th India International conference, pp. 795-800.
[4] M.J.Katira, Student, M. Tech. Final (I.P.S.), K.B.Porate, Assistant
Professor, “Load Flow Analysis of 132 / 11 kV Distribution Sub
Station using Static Var Compensator for Voltage Enhancement – A
Case Study”,TENCON 2009-2009 IEEE Region 10 Conference.
Power System Analysis by Hadi Saadat, 1999, The Mc-Graw Hill
Componies, Inc., pp. 208,240-242.
IJERTV5IS010405 382
(This work is licensed under a Creative Commons Attribution 4.0 International License.)