Chapter Twelve: Completion Procedure: Construction Supervision Manual For Contract Roadworks
Chapter Twelve: Completion Procedure: Construction Supervision Manual For Contract Roadworks
with the contractor, the Engineer and officers should agree with the contractor the pro-
of the maintaining authority at which the lat- gramme for the Period and what resources of
ter have the opportunity to draw attention to plant and labour etc. will be required. He will
any items they consider to be incomplete or then assess his own supervision staffing
unacceptable. If the Engineer agrees that the requirements and agree with his superior in
items are properly subject to rectification the Department what provision is to be made.
under the contract he will include them in his Arrangements also need to be made with the
list of deficiencies prepared for the contrac- contractor for continuing the services of
tor. However, it should be stressed that the accommodation,, transportation and labour
exercise is concerned with work already cov- support, scaling these down to a suitable
ered by contract instructions and, although level.
most contractors will be flexible about under- The contractor's programme of maintenance
taking a small amount of additional construc- should be based on dealing with the list of
tion, this is not the stage at which major extra deficiencies appended to the Certificate of
works should be introduced. Practical Completion or completion
Certificate. However, the list must be pro-
12.05 Preparation of the Certificate gressively updated throughout-the period by
Of Practical Completion or the supervision staff who should be constant-
Completion Certificate ly on the lookout for any additional defects
When the Engineer is satisfied that a suitable and evidence of potential failure.
state of completion has been achieved and It should be stressed that the contractor's
has obtained the contractor's undertaking to works obligation during the period is for
complete the outstanding and remedial defects and noncompletions only - it does not
works, the Certificate of Practical extend to routine or " wear and tear" mainte-
Completion or Completion Certificate should nance unless otherwise stated in the specifi-
be prepared. Form JKR 2035 Pin 2/83 is used cation.
for the purpose and should carry an annex
listing the more important deficiencies to be 12.07 Certification of Completion of
attended to by the Contractor. A copy of an Maintenance.
issued Certificate is given in Figure 12A. The Certificate of Completion of Making
Clause 48 (1) of the Form 203 CEWI, FIDIC Good Defects or Maintenance Certificate,
and I.C.B. Conditions of Contract requires unlike the Certificate of Practical completion
that the Certificate be issued within 21 days or Completion Certificate, does signify ulti-
of the contractors notice requesting it or with- mate acceptance of the works. It is, therefore,
in 21 days of his making good any defects of the greatest importance that any defects
required by the Engineer for "substantial remaining toward the end of the Defects
completion". There is no such stipulation in Liability or Maintenance Period are identi-
the Form 203A "Conditions” fied and put right before the Certificate is
issued. The work of compiling a final list of
12.06 Defects Maintenance Period deficiencies should start approximately two
(Maintenance Period) months before the nominal end of the Period.
The contract does not end with the Certificate
When all remedial and outstanding work has
of Practical Completion or Completion
been completed to the satisfaction of the
Certificate and some members of the supervi-
Engineer the Certificate of Making Good
sion team are usually retained to oversee
Defects or Maintenance Certificate is to be
work executed during the Defects Liability or
prepared on form JKR 203Y / 82. An exam-
Maintenance Period, which start on the date
ple of an issued certificate is given in Figure
of the Certificate. At that time, the Resident
12B. In the case of the Form 203A
Engineer or other officer assigned with con-
Conditions of Contract the procedures for
tinuing site responsibility for the contract
RAHSIA
Preface
This Technical Note sets Out The required format for road project reports
that are to be prepared by the coordinators after the completion of a proj-
ect.
while the basic format as set out should be ffolowed at all time, variations
and changes can be made wherever necessary for specific projects.
RAHSIA
1. Title Page
CAWANGAN JALAN
NAME OF PROJECT
Cost of Project :
Date of Completion :
5.0 Appendix
The appendix should include the following :-
a) location and site plan of the project list
b) as-built plan / profile drawings
c) photographs of instruction aspects of the
construction.
d) other plans etc. as required.
e) as completed detailed abstract
f) list of related file numbers
APPENDIX 12 (2)
Tidak
Baik Se de rhana
BIL KRITERIA Te rbaik Me muaskan
75% - 89% 50% - 74%
90% ke atas 50% ke bawah
2 Pentadbiran (Administration)
3 Perancangan / Kemajuan
(Programming / Progress)
8 Pengawasan Kontraktor-
kontraktor Kecil/ Pembekal
Yang Dinama (Control of
Nominated Sub-Contractors/
SOKONGAN (RECOMMENDATION)