2.5.3 Module Walkdown and Yard RFLO Certificate
2.5.3 Module Walkdown and Yard RFLO Certificate
A Module will be considered to have reached Yard Module Completion stage once
the following tasks are completed:
All Construction, Pre-commissioning and Commissioning (following
Fabrication Yard scope of work) Work is completed in accordance with the
Fabrication Yard execution plan, module has been walked down, punch listed
and punch items categorized
All Construction, Pre-Commissioning and Commissioning point of view when
all Fabrication Yard activities and requirements (QCF’s) planned to be
performed have been completed and achieved. All the Carry-Over Work and
punch items have been recorded and agreed between CONTRACTOR and
COMPANY (refer to Carry over work Management procedure 3000-D-EC-
000-CN-PRO-0813-00)
Further to the approval of the Marine Warranty Surveyor, the Ready for Load-Out
Certificate (RFLOC) will be issued approving the readiness to commence the loadout
operation pursuant the Article 19 of the AGREEMENT.
A RFLOC Booklet will be issued by CONTRACTOR and shall include at least the
following:
Booklet Index / table of contents
RFLO Certificate
RFI – walk-down duly signed off
Overall module completion status
Exception List
RFC/MRFC/MAOC certificate (Copy of all applicable Sub-Systems involved
in the Module)