Summary
Summary
Maharashtra
The FRL of the ongoing Gosikhurd dam is 244 m. The link canal takes off from the
right flank of the ongoing Gosikhurd dam with FSL 243 m and traverses for a length of
478.2 km through Bhandara, Nagpur, Wardha, Amaravati, Akola and Buldana districts of
Maharashtra. The link envisages to bring 413750 ha of CCA under irrigation. Apart from
irrigation, it is also proposed to cater to the future municipal and industrial water
requirements in the command area and the city of Nagpur. About 22 lakh human
population and the industrial water requirements by 2050 AD are proposed to be served
utilizing 253 Mm3.
Total lifting involved is about 80 m in three stages. The total pumping capacity
required is 224 MW and the annual power requirement for these lifting arrangements
works out to 751 MU.
The maximum carrying capacity of the canal is 198 cumec with the corresponding
cross section of 37 m of bed width and 4.65 m full supply depth.
The cost of the project is estimated to be Rs.8294.26 crores at the price level of
2007-08 which includes the cost of head works at Rs.684.75 crores, the cost of
conveyance system at Rs.6410.38 crores, the cost of lifting arrangements Rs.1033.63
crores and the cost of on farm development Rs.165.50 crores. The benefit-cost ratio of
the project works out to 1.96 whereas the internal rate of return works out to 15.90%.
The link canal takes off from the light flank of the proposed Wainganga HEP with
FSL 218 and traverses for a length of 550 km including a tunnel of 29 km between from
RD 354 km to 383 km, through Chandrapur, Yavatmal, Hingoli, parbahan and Beed
districts of Maharashtra. The link canal has been provided with a total static lift of 425 m
in seven stages and is supported by five branch canals and number of cross drainage and
cross masonry works. The design discharge has been kept as 100 cumecs.
The total cost of the project at 2009-10 price level is Rs. 14,149 crores. B.C Ratio
is 0.66 and IRR is 5%.
3. Upper Krishna – Bhima (System of Six Links) [Krishna – Bhima
stabilization] Intra-State Link Project
Krishna Bhima Stabilization Project is conceived to transfer 3256 Mm3 (115 TMC)
of flood waters by gravity from various rivers/streams viz. Kumbhi, Kasari, Warna, Koyna
& Panchaganga in Upper Krishna sub-basin of Krishna basin through a series of links to
cater to the needs of :
Enriching the command areas of existing Nira and Ujjani projects in Upper Bhima
sub- basin and also
The scheme would benefit water short areas in parts of Pune, Satara, Sangli, Beed,
Osmanabad and Sholapur districts in Upper Krishna and Upper Bhima sub-basins. The
project consists of eleven parts. While the first six parts are primarily water transfer links
by gravity, parts 7 to 11 are mainly utilization schemes through certain lift irrigation
schemes and existing reservoirs / canal systems.
Remaining quantum of 1877 Mm3 (66.27 TMC) water is let down in Nira river to be
picked upat proposed Uddhat Barrage for further diversion to Ujjani dam on Bhima,
through a conveyance system of 24.3 Km comprising of 20.6 Km of tunnel and 3.7 Km of
open channel. Out of the waters received at Ujjani dam through Nira-Bhima link canal,
1282 Mm3 (45.27 TMC) is proposed for enrichment of Bhima command of 307593 ha and
to supply domestic water to Sholapur, Baramati, Shrigonda etc. while the remaining 595
Mm3 (21 TMC) is proposed to be utilised under Krishna-Marathwada project as Part – 11
of KBSP, which consists of LIS I with 5 stages of lifting (total static head 239 m) and LIS
II with 6 stages of lifting (total static head 209 m).
The water available for transfer from each and scheme wise water planning and
benefited area under different projects is given below:
The total cost of the Scheme is estimated to be 13576.19 crore based on the
2009-10 price level. The Benefit-Cost ratio works out to 1.16.
Out of the total diversion of 143 Mm3, 70% of water i.e. 100 Mm3 is allocated for
irrigation purpose. The existing Gangapur Irrigation Project provides annual irrigation to
an area of 9509 ha only out of 16505 ha of CCA available. Since the quantum of
diversion is less, new command area for irrigation have not been identified and it is
proposed to irrigate / stabilize the CCA available but not irrigated under the existing
Gangapur Irrigation Project. Remaining 30% of water, around 22 Mm3 would be used for
domestic and 21 Mm3 for industrial needs respectively. This quantity would be supplied to
needy towns around the Gangapur project.
The total cost of the project is estimated as Rs.459.08 crore, at 2008-09 price
level. The link proposal will provide annual irrigation benefits to an area of 15625 ha. The
total energy required for lifting 143 Mm3 of water by around 218 m is 151.35 MU
annually. The power required for pumping is around 32 MW. The Benefit-Cost ratio is
estimated to be 1.44. Internal Rate of Return (IRR) works out to 16.78%.
As per the water balance studies carried out by NWDA, it is possible to divert 14
Mm3 of surplus water available at existing Upper Vaitarna reservoir to Mukane reservoir
by constructing an additional spillway at Saddle dam. This proposal would irrigate an area
of about 1613 ha in Mukane command area in Nasik district.
It is also proposed to divert the surplus waters available at four identified storage
reservoir sites viz. Kalampada, Dulachiwadi, Borachiwadi and Udhare located at down
stream of Upper Viatarna project and upstream of proposed Pinjal project in Vaitarna
basin. The total surplus water available at these four storage reservoirs is 122 Mm3. All
these four storages are proposed to be linked by open cut feeder link canals. The water
from Kalampada storage reservoir will be diverted to Dulachiwadi storage reservoir and
these combined waters and the water available at Udhare storage reservoir will further
diverted into Borachiwadi storage reservoir through open channels by gravity. The total
length of canal involved to interconnect these four reservoirs is 17.42 Km. The waters
received from all the three storages and the contribution of Borachiwadi storage reservoir
would be lifted from Borachiwadi reservoir to Upper Vaitarna reservoir during non
monsoon period (November to May). The total static lift involved is about 353 m in four
stages. The total power requirement would be 35.31 MW and the annual energy
consumption is estimated to be 194.89 MU.
Further, the water from Upper Vaitarna reservoir would be diverted to Vaiki nadi of
Dama valley, by gravity through an outlet proposed on the right flank of Saddle dam.
This proposal would irrigate about 13871 ha of area in Dama project command in Nasik
district.
Out of the total diverted water of 136 Mm3 (14 + 122), about 70% of water i.e. 96
3
Mm is earmarked for irrigation to bring 15484 ha (1613 + 13871) of CCA under
irrigation with 100% intensity and the remaining 30% of water i.e. 40 Mm3 is planned for
municipal & Industrial use in and around the command areas of Mukane and Dama
projects.
The total cost of the project is estimated to be 817.13 crore at 2009-10 price
level, The benefit-cost ratio (BCR) of the project works out to 1.00 where as the IRR
works out to 6.20%.
The waters of Val reservoir (57 Mm3) would be lifted by 180 m in two stages
through a raising main length of 1.94 km and then transferred through a tunnel of 3.08
km length to Upper Vaitarna reservoir to cross the ridge between Damanganga and
Vaitarna basins. Similarly, the waters of Vagh reservoir (45 Mm3) will be lifted by 268 m
lift in three stages through a raising main length of 8.26 km and then transferred through
a tunnel of 1.17 km length to Upper Vaitarna reservoir.
The water from Kalampada reservoir (35 Mm3) will be diverted to Dulachiwadi
reservoir through a lined canal of 3.56 km length by gravity. The water of Dulachiwadi
reservoir (18.50 Mm3) and the water received from Kalampada reservoir will be lifted by
232 m in three stages into Upper Vaitarna reservoir. Further, the water of Udhare
reservoir (31 Mm3) will also be lifted by 240 m in three stages into Upper Vaitarna
reservoir.
The combined waters transferred from the five reservoirs and the balance available
for diversion from Upper Vaitarna reservoir will be transferred to existing Kadva reservoir
through a lined canal of 30.244 km length by gravity. Further, a net quantum of 196.73
Mm3 (after transmission losses) will be diverted into Dev River by 150 m lift in two
stages for further use in Sinnar taluk of Nasik district. Out of this, a quantum of 22.51
Mm3 is earmarked for domestic water supply to serve 4.59 lakh human population &
2.90 lakh live stock, 73 Mm3 for Delhi-Mumbai industrial corridor uses, 41.50 Mm3 for
other industrial uses and 59.73 Mm3 is planned for irrigation to bring 11480 ha under
irrigation in semi-critical drought prone Sinnar taluk under the RBCs of proposed
Sonamba and Phalak reservoirs on Dev river. The transmission losses in the link project
is estimated to be 5.27 Mm3. Further an area of 16840 ha can also be brought under
irrigation with recycled waters received from the regenerated waters of domestic and
industrial uses as per the policy of Govt. of Maharashtra.
It is proposed to transfer the water from all the reservoirs during non-monsoon
period from November to May. The total power requirement to lift the waters from all the
reservoirs is 65.04 MW and the total energy consumption is estimated to be 303.34 MU.
The total cost of the project is estimated to be Rs.2690.23 crores (with Alternative
-I Canal) & Rs.2708.27 crores (with Alternative -II Canal) at 2015-16 price level, which
includes the cost of head works at Rs.1577.75 crores, the cost of conveyance system at
Rs.580.45 crores (with Alt-I canal) and Rs.598.49 crores (with Alt-II) and the cost of
lifting arrangements at Rs.532.03 crores. The annual cost after duly considering the
annual power requirement for lifting arrangements works out to Rs.372.05 crores (with
Alt-I canal) & Rs.374.04 crores (with Alt-II canal). The direct benefits from the link
project due to irrigation, domestic & industrial water supplies, fisheries development and
animal husbandry are estimated to be Rs.616.01 crores. The benefit-cost ratio (BCR) of
the project works out to 1.656 (with Alt-I canal) and 1.647 (with Alt-II canal) where as
the Internal Rate of Return (IRR) works out to 14.38% (with Alt-I canal) and 14.31%
(with Alt-II canal).
7. North Konkan – Godavari Valley Intra–State Link Project
The North Konkan – Godavari Valley Link Project, envisages diversion of surplus
waters available in Patalganga and Ulhas basins through proposed Balganga, Kalu and
Shai reservoirs to Mula river of Pravara sub-basin of Godavari valley by gravity and lift.
In addition, enroute irrigation also proposed in Patalganga basin.
As per the water balance studies carried out by NWDA, Balgaganga (Niphad)
project of Patalganga basin, Shai and Kalu projects of Ulhas basisn are having water
surplus of 146 Mm3, 43 Mm3 and 80 Mm3 at 75% dependability respectively. Out of 146
Mm3 of water surplus available at Balganga project, 120 Mm3 would be diverted through
the proposed Bhokarpada branch canal at RD 17 Km with lift of 30 m. Out of this, 95
Mm3 will be utilised in enroute to irrigate an area of 20000 ha. in Patalganga itself in
Raigad district. 15 Mm3 will be supplied for enroute domestic and industrial uses and the
remaining 10 Mm3 will be lost in transmission. The remaining 26 Mm3 (146 – 120) would
be diverted to Kalu reservoir in Ulhas basin through 86.7 Km long open channel and with
three stages of lifts proposed at RD 0.0 Km, RD 50.0 Km and RD 86.0 Km to lift waters
by 30 m, 60 m and 36 m respectively. About 3 Mm3 will be lost in transmission. A tunnel
length 3.75 Km is proposed from RD 33.25 Km to RD 37 Km.
The total cost of the project is estimated to be Rs.4125.85 crore at 2009-10 price
level, The Benefit-Cost Ratio (BCR) of the project works out to 0.44 whereas the IRR
works out to 1.41%.
8. Koyna – Mumbai City [Koyna Tail Race Water – Mumbai City] Intra-State
Link Project
The “Koyna Tailrace Water – Mumbai City Link Project‟ envisages diversion of net
flows of about 1912 Mm3 for Mumbai Metropolitan City and its suburbs along with
possible enroute towns/villages on left & right side of the link canal, even by lifts not
exceeding 120 m, in all 365 days to meet the municipal and industrial needs as a whole.
Hence, this link canal project is primarily planned & designed as a “Drinking Water
Supply Scheme‟ without giving scope to the irrigation component so as to overcome the
inefficiency & impracticable financial targets in various past studies, as discussed.
Out of 1912 Mm3 (67.50 TMC) of water diversion, a quantum of 785 Mm3 (27.72
TMC) is estimated for drinking water supply to Mumbai Mega City and its suburbs, 66
Mm3 (2.33 TMC) for enroute towns/villages in Ratnagiri and Raigarh districts. A provision
of 10 Mm3 (0.35 TMC) is kept for livestock population under the link canal. 1012 Mm3
(35.73 TMC) of water is planned for industrial purposes and the remaining 39 Mm3 (1.37
TMC) will be lost in transmission.
Since the topography does not permit the gravity flow due to prevailing highly
dissected hills at head works as well as enroute the entire length of the link canal and
also due to the tailrace waters being available at very low level of about +7.50 m, a
pump house with a single stage lift of 38 m and an operation head of 45.373 m is
proposed at canal of take point. Four pumps includidng one standby having a total
installed pump capacity of 66 MW (3 x 22 MW) with ;annual energy requirement of 295
MU are designed. The canal takes off at RD 0.0 Km with FSL 44.90 m flows by gravity in
its entire length and outfalls into a proposed reservoir at RD 200.00 Km with an end FSL
of 29.277 m near Panvel town.
The link canal designed as lined canal of trapezoidal section with rounded corners.
The canal is designed as uniform section throughout the entire reach. The maximum
carrying capacity of the canal is 103 cumec with the corresponding cross sections of 18 m
of bed width and 4.75 m full supply depth. Three intermediate tunnels of total length
17.950 Km (5.700 Km, 10.000 Km, 1.250 Km) are also proposed at RDs 9.750 Km,
43.700 Km and 178.600 Km respectively to cross the highly elevated hills enroute.
The total cost of the project is estimated to be Rs.2238.51 crore. The benefit-cost
ratio (BCR) of the project works out to 1.89 whereas the IRR works out to 18.64%.
Further, it is observed that the yield available below Sriramsagar project is such
that it gives rise to sizeable surplus water after meeting all the surface water
requirements. Transfer of this surplus water available in the lower reaches of the
Godavari to the water-short areas in its upper reaches may not be economically viable.
The inter-state link schemes are framed on the principle of successive substitution.
But there is no substitution of water for the projects in Godavari basin. Hence No surplus
water is available in Godavari basin up to SRSP.
Conclusion
(a)Godavari (SRSP)-Purna-Manjra link proposed by Government of Maharashtra is inter-
state in nature as the location of Sriramsagar project lies in the state of Andhra Pradesh.
(b)Since there is no surplus water in Godavari river at Sriramsagar project as per the
water balance indicated in Para 3.3.9, diversion of water from this reservoir is not
feasible.
(c)Water cannot be diverted from SRSP to u/s areas on exchange of water from the
contemplated Inchampalli-Nagarjunasagar link as this link is a part of the nine link canal
system of the National Prospective Plan.
Apart from the above, a quantum of 5.21 Mm3 of water from the surplus yields
available at the above dam sites is allocated to cater to the irrigation, domestic and
industrial needs of the enroutewater-short areas, conjointly, in the vicinity of the
proposed dam sites in Raigad District of the Middle Konkan region.
The proposed Middle Konkan - Bhima Valley Link Canal system consists of three
Dams on the Middle Konkan rivers viz, 1) at Bhale on Savitri river with FRL +76.00 m, 2)
at Yeral on Kundalika river with FRL +59.00 m and 3) at Utra on Utra nadi, a tributary of
Amba river with FRL +76.00 m.
The total cost of the Project at 2010-11 price level is estimated to be ₹ 319214
lakh which includes the (i) cost of head works at ₹ 13542 lakh, (ii) cost of conveyance
system at ₹ 61863 lakh, (iii) cost of Power–houses, Pump-houses and lifting
arrangements at ₹ 241693 lakh and (iv) cost of On-farmdevelopment works at ₹ 2116
lakh. The annual cost, after duly considering the annual power requirement for lifting
water, works out to ₹ 68478 lakh. The total annual benefits from the link project are
estimated to be ₹ 58438 lakh, which consists of (i) ₹ 16072 lakh from irrigation sector,
(ii) ₹ 41966 lakh as revenue from Municipal & Industrial water supply and (iii) ₹ 400 lakh
as revenue from Power generation. The Benefit-Cost Ratio of the project works out to
0.85. The IRR works out to 13.89 % without considering distributional and employment
effects.
As such, NWDA has carried out studies and proposed diversion of 198 Mm3 from (7
spills of Koyna project in the Monsoon period (65.23% dependable spills at Koyna dam).
The water would be diverted from the reservoir to pond through an approach
channel (500 m) by gravity. Thereafter, the flow would be through the tunnel of length
33.9 km and canal of length 21 km by gravity in to the Ram odha river which is tributary
of the Nira river. The diverted water will be stored in the five proposed tanks. The total
length of link is of about 56 km. Out of the total proposed diversion of 198 Mm3, 133
Mm3 is earmarked for irrigation and 24 Mm3 for domestic needs and 24 Mm3 for industrial
needs. The remaining 17 Mm3 is loss in transmission. A new area of 21,000 ha is
proposed for irrigation in the downstream of Nira Deoghar dam in Upper Bhima sub-basin
which is the proposed command area of Nira.
The total cost of the project is estimated as 913030 lakh at 2011-12 price level.
The cost of Head works, Conveyance system and on farm development is 86926 lakh,
825054 lakh and 1050 lakh respectively. The link proposal will provide annual irrigation
benefits to an area of 21,000 ha in Pune district. The net annual benefits from irrigation,
domestic and Industrial water supply are 18060 lakh, 4342 lakh and 17842 lakh
respectively. Total benefits from the project are 40244 lakh. The annual cost of the
project is worked out as 108428 lakh. The Benefit-Cost ratio is estimated to be 0.37 and
by using discounted cash flow method and @ 10% discounting rate, it is 0.36. The IRR
works out to 3.4%.
Earlier, Sri C.V. Gole Committee of Planning Commission, Government of India has
made studies on feasibility of diversion of water from west flowing rivers. The Committee
assessed water resources of each west flowing river basin and made some proposals for
diversion of surplus waters of west flowing rivers to east side, which are otherwise going
waste into Arabian sea. The Committee submitted its report in February 1978. The
Committee opined that 25 TMC of water of Mulshi lake can be diverted to Bhima basin.
Later, Government of Maharashtra also initiated and carried out studies about
Intra-State links and prioritized them. Mulshi-Bhima link project is one of the first priority
link in their proposal. This link envisages diversion of 25 TMC of water from western
Maharashtra to eastside. The ridge level between Middle Konkan region and Upper Bhima
basin is about 700 m to 800 m. Hence, water diversion is possible only by lift and tunnel
construction.
This report details with the pre-feasibility studies for diversion of 466 MCM (16.5
TMC) of Mulshi water to upper Bhima sub-basin (i.e. into the Pauna river) for irrigation,
drinking water supply and industrial requirements in the water-deficit areas of Rajgarh
and Pune districts of Maharashtra State. This proposal of diversion of 466 MCM of water,
is beneficial to some extent in Rajgarh and Pune districts.Plate-I shows the Index Map of
the Mulshi-Bhima link project.
Water from the Mulshi lake is brought through two tunnels to the hydroelectric
project located at Bhira. The installed capacity of the Bhira power house is 300 MW. The
monthly reases after power generation at Bhira power station during the period from
1976 to 2006 are collected from Government of Maharashtra. The 75% and 50% yields
are worked out for these available 31 years releases as 668.32 MCM (23.60 TMC) and
737.13 MCM (26.00 TMC) respectively.
Mulshi-Bhima envisages to transfer 466 MCM of west ward flowing tail race water
of Ravalje power station (75% of 75% dependable yield at Ravalje power house) to
Bhima basin and the remaining 155 MCM of water (25% of 75% dependable yield) will be
let into the Kundalika river to meet any commitments in the downstream of the
Kundalika river. The requirement for domestic and industrial needs is worked out as 197
MCM in the enroute drought prone areas i.e. Rajgarh district in Middle Konkan region of
Pune district. The remaining water i.e. 269 MCM (including transmission losses) water will
be diverted through the proposed Mulshi-Bhima link to the upper Bhima sub-basin which
is a deficitsub-basin. The diverted water will be utilized for irrigation in upper Bhima sub-
basin which includes transmission losses.
The gross command area (GCA) is identified as 55000 ha under Pauna branch
canal using toposheets and irrigation Atlas of India. Based on the land use statistics
available from the respective water balance studies and the information derived from the
toposheets, 75% of the area i.e. 40000 ha is considered as Culturable Command Area
(CCA). However, keeping in view the quantity of water transferable from the Fore bay
reservoir an area of 40000 ha is considered as CCA under the link canal under the Pauna
branch canal.
i) Diversion weir: This is a proposed diversion weir across the Ravalje power house tail
race channel near Ravalje village of Raigarh district. The FRL of weir is 45.00 m and the
total length of weir is 170 m and the length of the spillway is 40 m.
ii) Conveyance system: The total length of the link is 37.6 km which includes 3.3 km
long tunnel. The proposed quantity of diverted water is lifted in six stages at RD 0 km,
RD 27.3 km, RD 32.3 km, RD 32.8 km, RD 33.3 km, RD 33.8 km, with lifts of 30 m,
91.21 m, 109 m, 109m, 108 m and 109 m respectively. The stretch from RD 2.7km to
RD 27.3 km, the link canal run through pipeline by gravity. From RD 34.3km, the water
flows through tunnel by gravity till it outfalls in the Pauna river which is the tributary of
Bhima river.
iii) Command area proposed: This proposed command area is located in Upper
Bhimasub-basin in the district of Pune in Maharashtra State. The length of the proposed
branch canal is 15 km. The proposed annual irrigation under this project is 40000 ha and
water utilisation is 269 MCM.
The total cost of the project is estimated as Rs.281527 lakhs at 2010-11 price
level. The link proposal will provide annual irrigation benefits to an area of 40000 ha. The
total energy required for lifting 466 MCM of water to the height of 556 m is 1135 MU
annually. The net annual benefits from irrigation, domestic and industrial water supply
are Rs.93335 lakh, Rs.12184 lakh and Rs.64141 lakh respectively. The annual cost of the
project is worked out as Rs.58763 lakh. The power required for pumping is around
175.16 MW. The Benefit-Cost ratio is estimated to be 1.46 and by using discounted cash
flow method @10% is 42. The IRR works out to 14.96%.
13. The Savitri – Bhima Intra-State Link Project
The Government of Maharashtra has entrusted the study of Intra-state river link
proposal to NWDA for transfer of 1133 Mm3 (40 TMC) of water from Savitri Basin to
Bhima valley through the proposed Savitri - Bhima valley link. As per the proposal,
NWDA studied the Hydrology of Savitri Basin and observed that it is possible to divert
715 Mm3 (25 TMC) of water only, to Bhima valley. It is proposed to utilise 7 Mm3 of
water in surrounding areas of Chaudharwadi & Amshet reservoirs in the Savitri Basin for
irrigation & domestic needs. In order to harness a quantum of 708 Mm3 of water
available, it is planned to create two reservoirs namely Chaudharwadi and Amshet on two
independent tributaries of Savitri river. These reservoirs will be inter connected by 5.15
km long tunnel of dia 3.40 m to transfer waters of Chaudharwadi to Amshet reservoir
thereafter, the combined water of 708 Mm3 (25 TMC) will be transferred from Amshet
reservoir to the existing Khadakwasla dam on river Bhima (through tunnel and open
canal) for further utilization in Bhima Valley.
The Savitri - Bhima link canal system proposal consists of two dams viz., (i)
Chaudharwadi on Bhaovira nadi with FRL +100.00 m and (ii) Amshet reservoir
on Kharak/Kal nadi with FRL +75.00 m, both on tributaries of Savitri river. These two
reservoirs are planned to be inter connected by 5.15 km long tunnel, so that the water
from Chaudharwadi reservoir will be let into Amshet reservoir. The total availability of
water from both the Chaudharwadi and Amshet reservoirs is about 708 Mm3 (25 TMC)
and is available for further transfer, after utilizing for irrigation & domestic needs in the
surrounding area of the above two reservoirs in Savitri Basin.
Out of 708 Mm3 (25 TMC) of diverted water to Bhima valley, it is planned to use
495 Mm3 for irrigation and 213 Mm3 for municipal & industrial use. An irrigated area of
86764 ha can be stabilized with the assured water supply of 495 Mm3 for irrigation under
the command of existing Khadakwasla project in the Bhima sub - basin in Pune district of
Maharashtra.
The diversion of water through the link canal is proposed for throughout the year
from June to May to cater to the needs during Kharif, Rabi & summer crops. The
conveyance system is designed for carrying a maximum discharge of 52.74 m3/sec to
meet the required demands.
The total cost of the project including establishment and tools & plants, works out
to ₹ 4744.21 crores at 2010-11 price-level.
The Benefit - Cost ratio is calculated based on annual cost and annual benefit
which works out to 1.15. The IRR of the project with and without distributional and
employment impacts works out to 14.81% and 13.12 % respectively.
14. Kolhapur - Sangli/Sangola Intra-State Link Project
The Kolhapur-Sangli/Sangola Iink project is formulated to utilize the surplus
waters of western Upper Krishna in the drought prone eastern areas in Upper Krishna
and Bhima sub-basins.
The Sangli/Sangola Link project envisages diversion of 2472 MCM of water from
the Shirol barrage across Panchaganga & Mhaisal barrage across river Krishna (to tap
Warna waters) to the eastern areas in Sangli, Solapur and Satara districts. Out of this, a
quantum of 2099 MCM is earmarked for irrigation, 255 MCM is planned to be utilized for
municipal & industrial purposes in the command areas and the remaining 118 MCM will
be lost in transmission.
The link canal takes off from the left flank of the proposed Shirol barrage with FSL
528 M and traverses for a length of 117 km out of which 60 km is open channel and the
rest is by raising mains. the alignment passes through Sangli, Satara and Salapur
districts of Maharashtra. the link canal has been provided with a total lift of 241 m in 4
stages and is supported by 3 branch canals and number of cross drainage and cross
masonry works. it is observed that the demands in rabi season are not met and hence
storage tanks are proposed in the command area. Accordingly, water diversion is limited
to the period from June to September.
The topography doesn‟t permit the gravity flow irrigation through out canal
system, lifting arrangements are provided on link canal in 4 stages. The total pump
capacity required is 1601 MW and the annual power requirement for these lifting
arrangements works out to 3379 MU. The land to be acquired is 989 ha for main canal,
offices and colonies, borrow areas and the structures.
The link canal is designed as lined canal of trapezoidal shape with bottom rounded
corners. The maximum carrying capacity of the canal is 335 cumec with the
corresponding cross section of 41 m of bed width and 6 m full supply depth.
The cost of the project is estimated to be Rs.700304 lakh, which includes the cost
of head works at Rs.11257 lakh, the cost of conveyance system at Rs.323424 lakh, the
cost of lifting arrangements at Rs.349383 lakh and cost of on-farm development ar
Rs.21017 lakh. The annual cost after duly considering the land development and the
annual power requirement for lifting etc. works out to Rs.155091 lakh. The direct
benefits from the link project due to irrigation, municipal & industrial water supplies are
estimated to be Rs.225122 lakh. The Benefit Cost ratio of the project work to 1.45
whereas the Internal Rate of Return works out to 15.30%.
The 18 link proposals together would supplement / irrigate 5580 ha. of command
area under existing minor irrigation tanks in Jalgaon district. About 87 km length of link
canals from the existing canal networks including proposed short links to the existing
minor irrigation tanks have been proposed. Out of the 74 Mm3 of water proposed to be
diverted through the 18 links, 45 Mm3 of water will be utilized for irrigation purpose, 6
Mm3 of water for domestic needs and remaining for ground water recharge purpose.
The total estimated cost of 18 link schemes is Rs.12049 lakh at 2010-11 price
level which includes the cost of head works at Rs.908 lakh, the cost of conveyance
system at Rs.11141 lakh.
The benefit-cost ratio of the project works out to 1.50:1 where as the IRR with &
without employment and distributional effect works out to 15.34% & 13.25%
respectively.
As per the water balance studies carried out by NWDA, it is possible to divert 534
MCM of surplus water available at 75% dependability from twenty proposed small
reservoir to Girna sub- basin by constructing three lift schemes. Scheme-I envisages
inter-connecting six small reservoirs and two water sumps with pipelines and lifting the
surplus water from reservoir to reservoir and finally diverting 159 MCM of water into the
Girna river.
Scheme-2 envisages inter-connecting four small reservoirs and one water sump
with pipelines and lifting the suplus water from reservoir to reservoir and finally diverting
124 MCM of water into the Girna river. Similarly, Scheme-3 envisages inter-connecting
ten small reservoirs and three water sumps with pipelines and lifting the surplus water
from reservoir to reservoir and finally diverting 251 MCM of water into the Girna river. A
tunnel of length 3.8 km would be provided between Bhendshet and Khirdi reservoirs to
cross the hillock area.
This proposal would irrigate an area of 95760 ha in Girna sub-basin. The total
length of pipeline in all the three schemes would be 108 km approximately. the surplus
waters from all the three schemes would be lifted to Girna river, throughout the year in
all the twelve months. The total static lift would be 683 m, 696 m and 1161 m in all the
three schemes respectively. Seven stages of lifts are proposed inScheme-1. Similarly,
seven stages of lifts and eleven stages of lifts are proposed in Scheme-2 andScheme-3
respectively.
The proposal would irrigate 53626 ha in Nasik area, 38304 ha in Jalgaon area and
3830 ha in Aurangabad area of Girna sub-basin. Girna command canal will take off from
main Girna river, downstream of outlet point for irrigating proposed command in
Nasik/Jalgaon/Aurangabad areas. Out of the total diverted water of 534 MCM, about 72%
of water i.e. 384 MCM is earmarked to bring 95760 ha of CCA under irrigation with 100%
intensity and the remaining 28% of water i.e. 150 MCM is planned for domestic and
industrial use in proposed command area. The domestic and industrial requirement of
Jalgaon city by 2059 AD i.e. 86 MCM is also included.
The total power requirement for lifting the water would be 2054 MW and the
annual energy consumption is estimated to be 1307 MU.
The total cost of the project is estimated to be Rs.1005310 lakh at 2010-11 price
level, which includes the cost of head works at Rs.236121 lakh, the cost of conveyance
system at Rs.61543 lakh, the cost of lifting arrangements at Rs.149927 lakh and cost of
on-farm development Rs.3830 lakh. The annual cost after duly considering the annual
power requirement for lifting works out to 148591 lakh. The direct benefits from the link
project due to irrigation, domestic & industrial water supplies are estimated to be
Rs.80738 lakh. The Benefit-Cost ratio of the project works out to 0.54 whereas the IRR
works out to 3.16%.
Gujarat
Transmission losses through canal are worked out to be 98 Mm3. Kalpsar project is
proposed at Gulf of Khambhat to harness water from the rivers that joins it along with
the flood waters from Narmada. These waters thus received at the proposed Kalpsar
project are proposed to be utilised in Saurashtra region by lift (Proposed water utilisation
by Kalpsar project is 6558 Mm3 and corresponding area to be irrigated is 10.54 lakh ha).
Kalpsar project has sufficient carry over storage capacity. Proposed diversion of water
through Damanganga – Kalpsar link is unregulated one. The storage at Kalpsar can meet
the designed requirement of its proposed command and hence, water is proposed to be
delivered into Kalpsar through the link canal can also be used efficiently through Kalpsar
project in Saurashtra by lift.
The Damanganga – Kalpsar link is a transit canal and will pass through developed
and to be developed command areas, as such, water requirement for enroute area is
found to be Nil. The link canal discharge varies from 17 cumec at head to 448 cumec at
tail. Due to water shortage during non monsoon to maintain draft and non suitability of
canal section and type of canal structures en route, navigation through link is not
proposed.
Odisha State
The Mahanadi (Barmul) - Rushikulya link canal is proposed to take off from the tail
race of power house proposed at right bank of Barmul barrage near Barmul village on
river Mahanadi with FSL 55m and will carry 1663 MCM of water for enroute irrigation of
100000 ha of command area in the districts of Nayagarh, Khurda and Ganjam of Odisha
in addition to cater domestic and industrial needs. Out of the 1663 MCM of water, 1380
MCM will be utilized for irrigation and 130 MCM for Domestic and industrial use. The canal
after traversing a total distance of 224.30 km through the districts of Nayagarh, Khurda
and Ganjam of Odisha, outfalls into Rushikulya River at a location downstream of the
confluence of Bada nadi with Rushikulya river near Aska town which is about 15 km
downstream of the existing Rushikulya (Janivilli) weir project.
Mahanadi (Barmul) - Rushikulya link canal will have a trapezoidal section of 19.5
m x 4.50 m for 146.85 km and 12.50 x 4.50 m for remaining 77.45 km and side slopes
1.5 H: 1 V. The canal will have a bed slope 1: 15,000 for the entire length. A total
number of 65 cross drainage works including 45 under tunnels would be provided along
the course of the canal in addition to a total number of 27 road bridges. The schedule of
construction of the link project is planned over a period of five years.
The total cost of the link canal is estimated as 3806.61 crore at 2010-11 price
level. Annual cost of the project works out to Rs 402.43 crore whereas annual benefits
from irrigation, power and municipal use work out to Rs 169.96, 136.32 crore and Rs
106.60 crore respectively and the total annual benefit is Rs 412.88 crore. Thus the
benefit cost ratio works out to be 1.03 and the IRR is estimated to be 5.82%.
The Odisha Government has proposed to construct Nandini dam on Nandini nalla, a
tributary of Harbhangi river in Vamsadhara basin. The main purpose of the project is to
store the water in the proposed Nandini reservoir and supply 56.98 MCM of water to the
existing Harabhangi reservoir through a 4.00 km long covered canal for providing
irrigation to 7225 ha during Rabi season of the Harabhangi command in the adjacent
Rushikulya basin in addition to augment the drinking water supply to Berhampur town to
the extent of 24 MCM of water. The Harabhangi command area is drought prone and the
statistics indicate that number of total droughts occurred during the 31 years period
(1971 to 2001) is 15 and out of which 38.71% is marginal and 9.68 % moderate and
probability of occurrence of drought is 48.39%. This link will be a boon to the people of
this area who otherwise are suffering from frequent droughts.
The water will be first utilized for power generation with installed capacity of 2 MW
to generate 13.92 MU energy annually, before letting into the Harabhangi reservoir. The
proposed FSL of the flow channel at the head is 500.00 m and the FRL of the existing
Harabhangi reservoir is 387.50 m. Four (4) nos. of villages; namely, Buradang,
Karabarhi, Poigurha and Laram will come under submergence of Nandini reservoir
affecting about 214 persons and 48 houses as per 2011 census.
Both the Nandini dam (proposed) and the Harabhangi dam (existing) lies in
Vamsadhara basin and the command area in the Rushikulya basin. Thus, this link project
is an inter basin water transfer link.
The total cost of the link canal is estimated at Rs 195.80 crore at 2011-12 price
level. Annual cost of the project works out to Rs 21.90 crore whereas annual benefits
from irrigation, power and domestic water supply works out to Rs 19.30 crore, Rs 6.96
crore and Rs 9.14 respectively. Thus the benefit cost ratio works out to 1.62 and the IRR
is estimated to be 7%. Thus, this project is techno economically viable.
Jharkhand State
The enroute gross command area of the link project is 7200 ha where as culturable
area is 4320 ha. The intensity of irrigation & delta are kept as 100% & 0.89 respectively.
Total cost of this project is worked out as Rs. 1399 crore at 2008-09 price level
which includes Rs.353 crore for head works, Rs.421 crore for canal & canalization and
Rs.624 crore for power houses at four locations for its generation of about 100 MW of
power across the link canal and about Rs.1 crore for on farm development. Annual cost of
the project is worked out as Rs.164 crore while annual benefits as Rs.670 crore. B.C.
Ratio and IRR works out to be 4.09 and 36.91 % respectively.
The link canal will off take from Sankh river near Bartoli village at an elevation of
640 m and after traversing a total length of 41.2 km, it falls in South Koel river at level of
520 m. There are five falls along link alignment ranging from 16 m to 30 m. It has been
proposed to install three power houses with total hydel power generation of 169.4. MW.
The total cost of project works out to Rs.519 crores at 2008-09 price level. The BC
Ratio & IRR works out to 2.78 & 8.16% respectively.
This project envisages construction of dam on river Barakar near Bhalpahari. The
proposed link canal, 114 km long (including 5 km tunnel) off – take from right bank of
Bhalpahari dam near village Budhdia at an elevation of 237 m and out falls in
Subarnarekha river at level of 257 m. The slope of the canal has been kept as 1:20,000.
The link envisages pumping of water through 30 m at RD 75.7 km. Out of the 760 MCM
of diverted water from Barkar 207 MCM will be utilized for enroute irrigation, 30 MCM for
domestic use and 493 MCM water diverted to Subarnarekha river for industrial navigation
purpose, 30 MCM water will be consumed in transmission losses. Total cost of the
projuect is worked out to Rs.1148 crore at 2008-09 price level. The Benefit Cost Ratio
and IRR works out to 1.23 and 10.66% respectively.
Bihar State
The link canal will provide 8347 MCM of water for irrigation out of which 6082 MCM
in existing command of eastern kosi main canal and remaining 2265 MCM in new
command areas. Provision of 14 MCM of water for domestic and industrial water needs
for enroute village/towns has also been made. Transmission loss in canal will be 73 MCM.
Thus after meeting all the enroute requirements remaining 4148 MCM of water will reach
Mechi river which can be utilized by Government of Bihar to supplement irrigation
demand of Mahananda basin. Even if this water is not used for irrigation purpose in
Mahananda basin, there will be relief from flood in Kosi to some extent as this diversion
of water in Mechi has been proposed during 7 months. i.e. from June to December. The
total cost of the link project has been estimated as Rs. 4441.82 crores at 2008-09 price
level. The B.C Ratio and IRR of the link canal project has been assessed as 1.51 &
15.99% respectively.
27. Barh ( Ganga ) - Nawada Pump Canal Scheme Intra-State Link Project
Barh-Nawada pump canal scheme is an Intra State link proposed by Government
of Bihar for irrigation of drought prone area between Punpun and Kiul rivers. It is
proposed by the State Government to divert about 5733 MCM balance water of Ganga at
Hasan Chak through Goithawa river by lifting water from starting RL 46 m at Ganga to RL
90 m at Nawada. The area falling between 90 m to 140 m contour have already been
covered by Sone-Kiul Link.
As per the study carried out by NWDA the water balance of river Ganga at
Hasanchak during monsoon are 127900 MCM and 166272 MCM respectively at 75% and
50% dependability. The water balance during non monsoon are (-) 46767 & (-) 42755
MCM respectively at 75% and 50% dependability. Hence a reservoir with gross storage
capacity of 4850 MCM is proposed near Masathu village at RD 8.000 km of the proposed
Barh – Nawada pump canal scheme to store surplus waters of Ganga during monsoon
and to utilize the same during non-monsoon for fulfilling the requirements of Barh –
Nawada pump canal scheme of Bihar.
The link canal will provide annual irrigation to an area of 700402 ha (CCA) by
utilizing 4483 MCM of Water. Domestic & industrial requirement enrouote of the link
canal is 1206 MCM.
The total cost of the project is Rs. 12298 crore. Benefits Cost Ratio is 0.92 and IRR
is 8.7%. The scheme is not found techno-economically viable.
Accordingly, the possibilities of linking the rivers from Kohra to Chandravat has
been studied. It came in notice that the catchment area of Kohra upto diversion point is
33% of the Kohra basin & elevation of the link canal alignment from Kohra to Chandravat
is varying from 71 m to 73 m from off takes point to outfall point of the link canal. So
passing the discharge by gravity is not technically possible. Also, the assessed quantity of
the flood discharge upto diversion point is very less. In view of above, the alignment
from Kohra to Chandravat was dropped & alternate alignment for diverting flood water of
Kohra in downstream of Chandravat was examined. Finally, the alignment from Kohra at
Binwalia (downstream of earlier diversion point) to Lalbegi near Debaria was proposed to
be linked up.
The report deals with the PFR study of Kohra – Lalbegi link which envisages
diversion of 80 cumecs of flood water (approx. 50% of flood discharge) of Kohra river (a
tributaries of Burhi Gandak river) to the Gandak river through linking the Kohra & the
Lalbegi rivers so that flood damages in the lower reaches of Kohra & Burhi Gandak river
can be minimized.
The Kohra – Lalbegi link off takes from Kohra river near village Binwalia in district
of West Champaran and outfalls into river Lalbegi near Debaria. Further the river Lalbegi
traverses upto a distance of 9 Km & join near village Bharwalia. The total length of link
canal is 26 Km i.e. 17 Km lined canal and 9 Km river course Lalbegi.
The G & D data of Gandak at Lalbegiaghat have been considered as there is no G &
D site of CWC/State Government on Kohra river. The maximum flood discharge of 164
cumecs has been considered in proportionate to its catchment area upto the diversion
point. Now, about 50% i.e. 80 cumecs of flood water is considered to divert through the
link canal assuming that it would provide benefit to the downstream area of Kohra basin
which is about 40% of the basin area lying in West Champran & East Champaran districts
as well as some relief to downstream area of Burhi Gandak basin. The link canal has been
designed for capacity of 80 cumecs of discharge. Bed width & full supply depth of link
canal are 20 m & 43 m respectively and bed slope of canal is considered as 1:15,000.
The total estimated cost of the link canal project works out to Rs.168.86 crore at
2008-09 price level. The Benefit Cost Ratio of the link project works out to 0.033.
The total length of link canal is 60 Km, out of which initial 1 Km is a lined gravity
canal and the remaining part follows the river course of Belwadhar till its outfall into river
Burhi Gandak.
The total estimated cost of the link project works out to Rs.125.96 crores at 2009-
10 price level. The Benefit Cost Ratio works out to 1.25
The link off takes from Bagmati river near village Malpa of district Khagaria at FSL
38.0 m and outfalls into river Ganga near village Chaidha. The total length of the link
canal is 9.0 Km out of which, the initial reach of 1 Km is a lined gravity canal and
remaining part follows the stream Musharadhar for 3.5 Km and then river Kasraiya for
remaining 4.5 Km till its out fall into river Ganga.
The total estimated cost of the link project works out to Rs.88.93 crore at 2008-09
price level. The Benefit Cost Ratio works out to 1.17.
Further, the Adhwara group of rivers originates in Nepal, carry high discharge and
very heavy silt load. During monsoon period, nearly all the streams get interconnected
and the entire catchment gets inundated. Further, in view of the near flat topography no
suitable sites are available for storage of monsoon water. During non-monsoon period,
there is practically no flow in Adhwara group of rivers. Therefore, diversion of water of
Adhwara group of rivers into the link canal may not be feasible. Thus in view of the non
availability of surplus water in Kosi basin and infeasibility of tapping of Adhwara group of
rivers water due to topographical constraints, the proposal of Kosi-Adhwara-Bagmati link
is not feasible.
From NWDA studies, it is also revealed that the irrigation requirement of the
command area of Muzaffarpur district can be met by integrating the link proposal with
the proposed Kamla Multi Purpose Project of Government of Bihar, near Tetaria village in
Nepal, if Government of Bihar so desires. However, in that scenario the link project will
not remain an intrastate link.
Rajasthan
Considering the surface water availability and requirement in Mahi basin in 2041
AD the Mahi river basin is deficit to the tune of 402.59 MCM at 75% dependability after
accounting for surface water requirement and regeneration. Therefore, there is no water
available in Mahi river basin for further utilisation/ diversion in the basin or out side
basin.
The Wakal, Sabarmati & Sei river sub basins of Sabarmati river basin also have no
surplus water to further transfer. Similarly, the surplus water, if any, of Anas river of
Mahi basin has not been considered for diversion through this link, being as inter state
river having catchment in Madhya Pradesh, Rajasthan & Gujarat.
Total area to be irrigated through this proposal in the Barmer and Jalore districts of
Rajasthan is about 2.333 lakh ha. The total cost of the Mahi – Luni intra state link project
is estimated as Rs. 20,55,531.39 lakhs at the price level 2012.
The annual cost of the project has been works out as Rs. 2,48,063.56 lakhs
whereas annual benefits from the project works out as Rs.71,856.40 lakhs. Thus, the
B.C. Ratio of the link project works out to 0.290.
34. Wakal – Sabarmati – Sei - West Banas to Kameri Intra-State Link Project
Wakal-Sabarmati-Sei-West Banas to Kameri river link project is an Intra-State
proposal in Rajasthan to utilize the surplus waters, if available, in Wakal, Sabarmati & Sei
rivers of Sabarmati river basin in the water deficit Luni river basin in Sirohi district of
Rajasthan.
For assessment of surface water availability of Wakal, Sabarmati and Sei rivers at
the proposed diversion points, rainfall-runoff co-relationship has been developed using
observed data of CWC gauging site at Jotasen across Wakal river. Since adjoining sub-
basins of Wakal basin have same characteristics, therefore, same regression equation
has been used for Sabarmati and Sei sub-basin. In this study all the existing, ongoing,
proposed/identified irrigation as well as industrial & domestic water supply schemes and
the water requirements of Rural as well as livestock population in the upstream
catchment of proposed diversion points of Wakal, Sabarmati & Sei rivers have been
considered for assessing the total water requirement.
Considering the water availability, needs and regeneration, it is estimated that the
surface water balance at Wakal-III dam, Sabarmati irrigation project and Sei Pick up Weir
diversion points at 50% and 75% dependabilities are as under:
Sl. Particulars At 50% At 75%
No. dependability (MCM) Dependability (MCM)
1. At Wakal-III dam across Wakal river (-)53.20 (-)116.61
2. At Sabarmati irrigation project (-)0.60 (-)7.64
across Sabarmati river
3. At Sei Pick up Weir across Sei river (-)5.76 (-)24.74
After assessing the water balance status, it is concluded that Wakal -Sabarmati-Sei-
West Banas to Kameri river link project proposal is not feasible due to deficit surface
water balance at the proposed diversion sites.
Tamil Nadu
Considering the water availability, utilisation and regeneration, the water balance
at Krishnagiri dam site works out to 100 MCM and 222 MCM at 75% and 50%
dependability respectively. However, it is proposed to divert 99 MCM of water from the
flood flows available at 50% dependability through this link scheme.
A tunnel of modified horse shoe section with a radius of 3.10 m for a length of 200
m is proposed at the off-take from the existing Krishnagiri reservoir across Ponnaiyar
river. The link canal takes off from the exit of tunnel and runs for a length of 55.70 km
by gravity with an off-take FSL of 480.00 m and outfalls into Kal ar river which is a
tributary of Palar river near Natrampalli village of Vaniyambadi taluk at FSL of 428.625m.
The canal is designed as lined trapezoidal section, with bottom corners rounded to carry
a discharge of 85.631 cumecs with a uniform bed width of 14.50m and full supply depth
of 3.0m. Uniform bed slope of 1:5000 is adopted for the entire length of the link canal.
The total cost of the project is estimated as Rs.25793 lakhs at 2008-09 price level.
The annual cost of the project works out to Rs.2628 lakhs and the annual benefits from
irrigation work out to Rs.3169 lakhs. The Benefit Cost Ratio is estimated to be 1.21. The
IRR works out to 10.88%.
Karnataka State
The Government of Karnataka has proposed six intra state links viz., 1)Almatti
(Bagalkot) - Malaprabha 2)Malaprabha - Tungabhadra 3)Bedti - Dharma - Varada
4)Bhadra - Vedavati (V.V. Sagar) 5)Diversion from Bedti & Aghanashini to Varada 6)
Barapole - Upper Cauvery.
Bedti-Dharma-Varada Link is one among the above six intra state link for which
pre-feasibility report is taken up by NWDA.
The Bedti - Dharma - Varada link proposal of Governmentof Karnataka envisages
diversion of 566.4 Mm3 (20 TMC) of water to Tungabhadra sub-basin of which 283.2 Mm3
(10 TMC) shall be diverted from the surplus available in Bedti basin and another 283.2
Mm3 (10 TMC) that would be received from Almatti dam for irrigating 129925 ha in
Haveri, Davangere and Bellary districts. The diversion from Bedti basin is in 3 stages,
which involves a tank / dam near Mishrikot village in Kalghatgi taluk, 23 km long canal
and 22 km long tunnel besides increasing the storage capacity of existing Attiveri and
Bachanki tanks and 265 km length of canal for combined distribution of water received
from Bedti basin and Almatti dam. On detailed study it was found that only 51 Mm3 of
water is available for diversion from Bedti basin as against 283.2 Mm3 and the Almatti-
Malaprabha Link is not feasible.
The link canal takes off from the existing Dharma Reservoir and runs for a length
of 72.65 km by gravity with an off take FSL of 585.00 m and outfalls in to a tributary of
Varada river at FSL of 571.337 m. The canal is designed as lined trapezoidal section, with
bottom corners rounded to carry a discharge of 29.936 m3/sec with bed width of 7.5 m
and full supply depth of 2.50 m at off take. Uniform bed slope of 1: 7500 is adopted for
the entire length of link canal. Tunnels are proposed at three locations for a total length
of 6.68 km in the conveyance system to avoid heavy cutting and to cross small hillocks.
The proposed tunnel section is of Modified horse shoe of 6.00 m dia.
The link canal will irrigate an area of 52900 ha annually with an irrigation intensity
of 100 % in Hangal, Savanur and Haveri taluks in Haveri district, Shirhatti and Mundargi
taluk in Gadag district. The annual maintenance cost of command area is considered as
Rs.600/ha for 52900 ha of CCA in the annual cost of the project. The link canal will also
meet the domestic needs of the command area enroute the canal.
As the command area proposed on the left side of Dharma and Varada rivers are
limited to 52900 ha only due to the areas covered by the two ongoing projects viz.,
Shiggaon LIS and Singatalur LIS, it is proposed to deliver 168 Mm3 through the Dharma
river from Dharma Reservoir for augmentation of requirement in the command area of
Singatalur LIS for irrigating 25150 ha.
The total cost of the project is estimated as Rs.250011 lakh at 2015-16 price level.
The annual cost of the project works out to Rs.40524 lakh and the annual benefits from
irrigation and domestic water supply works out to Rs.50256 lakh. The Benefit-Cost Ratio
is estimated to be 1.24. The IRR works out to 11.81%.
Chhattisgarh
37. Pairi (Pairi High Dam) – Mahanadi (Rudri Barrage) Intra-State Link
Project
Pairi (Pairi high dam) – Mahanadi (Rudri barrage) link canal, Pairi- Mahanadi
feeder canal as mentioned by the Govt., of Chhattisgarh takes off from the Pairi high dam
with FSL 333.00 m and runs as a contour canal for a total length of 62.60 km and outfalls
into the existing New Rudri barrage on river Mahanadi. The canal with carrying capacity
of 84 cumecs at head reach will run almost at the boundary of forest area in few reaches
and inside the forest area for certain length. This link canal receives water from
Dhanbura tank across Bosana nalla in middle of the reach. After this the carrying capacity
of the link canal has been increased to 97 cumecs . There is no enroute irrigation
proposed along the link canal. The main purpose of the link canal is to increase
availability of water for meeting the increasing demands of the MRP complex command
area. The entire link project lies in Raipur district of Chhattisgarh state.
The Government of Chhattisgarh proposed Pairi high dam across Pairi river with
FRL 335.000 m, MWL 336.350 m, MDDL 326.440 m with Gross Storage capacity of 540
Mm 3 and live storage capacity of 420 Mm 3. Two more reservoirs are proposed in Pairi
basin on Sondur river at Bankura and Chandanbahar village to store and supply water to
Pairi high dam as per the requirements. Fourth dam is proposed at Dhanbura village on
Bosana nalla from which the link canal receives water
The link canal will provide irrigation to an area of 71853 ha in the district of Raipur
of Chhattisgarh which is the additional area identified by Govt., of Chhattisagrh in the
command of M.R.P.Complex and not covered by irrigation due to insufficient water. The
existing cropping pattern of M.R.P.Complex command with intensity of irrigation of 136%
is only adopted for the new command area also. Thus, the additional annual irrigation
works out to 97720 ha. The irrigation water requirement is worked out to 382.07 Mm3.
Apart from irrigation it is also proposed to provide future domestic and industrial
water requirements in the command area. Additional domestic and industrial
requirements are estimated to be 294 Mm3 and 49.60 Mm3 respectively. The total
domestic and industrial water requirement worked out to 343.60 Mm3. Thus the total
requirement of the link canal works out to 725.67 Mm3.
Transmission losses in the link canal are estimated to be 11 Mm3. The remaining
quantity of 44.03 Mm3 out of the total diverted quantity of 780.70 Mm3 will be utilized
for stabilisation of the existing irrigation system of Mahanadi Reservoir Project Complex
(M.R.P. complex).
The link canal is designed as a lined canal with trapezoidal section with rounded
corners. The design discharge in the canal at head reach is 84.0 cumec upto Bosana
nalla crossing and thereafter the design discharge of the link canal is increased to 97
cumec as the link canal receives contribution from Bosana nalla. Accordingly, the link
canal is divided into two reaches. The maximum carrying capacity of the canal in the first
reach is 84.0 cumec with corresponding cross section of 17.50 m of bed width and 4.0m
of full supply depth with a bed slope of 1 in 20,000. Similarly, the maximum carrying
capacity of the link canal in second reach is 97.00 cumec with corresponding cross
section of 21.00 m of bed width and 4.0m of full supply depth. The bed slope of 1 in
20,000 is kept uniform for the entire length of the link canal. The link canal mostly
passes through forest boundaries, forest area and plain area in some reaches.
In its entire run of 62.600 km, the link canal has been provided with 13 cross
drainage structures, of which 5 are aqueducts and 8 are under tunnels. A total of 28
single lane road bridges have been proposed across the link canal as it passes through
thinly populated areas. A level crossing is proposed across Bosan Nalla so as to receive
water from Dhanbura tank and divert through the link canal.
A total area about 316.72 ha needs to be acquired, of which 185 ha will be for
construction of main canal, 130 ha for borrow areas, 0.67 ha for rehabilitation colonies,
1.05 ha for construction of office and staff colonies. Out of the total land to be acquired,
about 233.72 ha is Patta land and 83 ha is forest land. In all 6 villages are partially
affected and about 84 families consisting of 336 people need to be rehabilitated. Suitable
provision for compensation, afforestation, attractive compensatory package for
rehabilitation and resettlement have been made in the estimate for the construction of
link project.
The climate and ecological conditions of the area remain more or less the same
even after construction of the link canal. No mineral wealth is likely to be lost as a result
of construction of canal.
The link canal would greatly help in improving the general prosperity of the region
on account of introduction of irrigation in about 0.72 lakh ha of area which would
increase the agricultural production nearly by 3 to 4 times. More over the socio economic
objectives i.e., the regional development, equity, employment generation and pollution
control will greatly improve in the vicinity of the project.
Direct net benefits per annum from the link project due to irrigation, domestic and
industrial water supplies in the canal are estimated to be Rs. 30194 lakh. The total cost
of the link canal project is estimated to be Rs. 139445 lakh at 2013-14 price level. Based
on the quantity of water presently planned for utilisation, apportioned cost of the project
is worked out to be Rs. 133736 lakhs. The annual cost has been worked out as per the
standard norms to Rs. 15370 lakh. The Benefit Cost Ratio works out to 1.96 and the IRR
works out to 17.20 %.