Medium Voltage Switchgear Testing Method Statement
Medium Voltage Switchgear Testing Method Statement
– This test is considered as one of the main test, it’s aimed to test:
– This test also is considered as one of the main test and its purpose is
to test:
• CPC100.
• Multi-meter (Fluke).
c- Mechanical checked and visual inspection:
This test aimed to test the closing/opening time for circuit breaker and
to make sure that there is no pole discrepancies between poles (red,
yellow and blue) and CB closing/opening time within acceptable range
according to factory test result.
b- Required equipment:
1. This test aimed to test if bus bar will withstand its withstand
voltage after being installed in the site or it will breakdown
and to check the vacuum bottle integrity, also to measure
leakage current and insulation between CB and ground.
b- Testing equipment required:
1. AC HI-voltage injection machine (100KV, 60HZ).
2. Earthing Rod or Ground Discharge stick (coming with high
pot tester)
3. Megger 5KV DC Supply.
c- Mechanical and visual inspection:
This test aimed to test the trip time characteristic of MCB if it’s within
limits or no and check MCB auxiliary contact if it is available.
b- Required equipment:
• Sverker (used as current source).
• Multi-meter.
c- Mechanical checked and visual inspection:
This test aimed to test relay’s output contact, pick-up and drop off
voltage, operating and resetting time.
b- Required equipment:
This test is aimed to calibrate and adjust the reading of ammeter and
voltmeter test.
b- Required equipment:
FREJA 300
This test aimed to check all current transformer loop, starting from first
panel and distributed in the whole switchgear depending on scheme,
check shorting facility in terminal block [if exist].
b- Required equipment:
This test is aimed to check the whole loop of VT starting from first panel
and distributed in the whole substation depending on scheme (i.e.
metering or protection purpose)
b- Required equipment:
• FREJA.
• Multi-meter.
c- Mechanical check and visual inspection:
This test aimed to test lockout relay which is like muscles of the body
and responsible to trip circuit breaker in case of trip order coming from
protective relay
b- Testing Equipment Requirement:
• Sverker (used as Voltage source and used its voltmeter).
• Fluke [used as Ammeter].
• Miniature Circuit Breaker 2Pole (2MCB).
c- Mechanical check and visual inspection:
This test aimed to test DC supervision relay which supervises the most
important DC loop in the panel (e.g. DC loop of relay binary input and
relay output).
b- Required Equipment:
This test aimed to check that the selected ratio of current transformer is
correct and current transformer relay setting is OK and considered as
back-up test of CT loop.
b- Required equipment:
d- Test connection:
This test is considered as a major test or combined test for the whole
work in switchgear panels and finalizing phase for switchgear panels.
b- Required equipment:
No equipment used.
Inspect for the whole panel if any missing or damage device which can
be resulted from installation.
d- Test procedure:
This test aimed to test function of main relay according to approved final
setting for each one, but here we generally discussed main function
which should be exist in most of approved final setting.
b- Required Equipment:
1. FREJA 300.
2. Multi-meter.
3. Wires.
c- Mechanical check and visual inspection:
1. Freja300
2. Multi-meter (Fluke).
c- Test procedure: