Solved Problems in Work Measurement 2014
Solved Problems in Work Measurement 2014
WORK MEASUREMENT
2014
Solved Problems in Work Measurement 2014
Nt = (t )(RF)
Formula 2: ST = NT/ 1 – AF
Formula 1 is most often used in practice which assumes that allowances are added to normal time. If
presumes that allowances should be applied to the total work period, then Formula 2 is the correct one.
2|P a g e
Solved Problems in Work Measurement 2014
The number of cycles that must be timed is a function of three things: (1) the variability of the observed
times, (2) the desired accuracy, and (3) the desired level of confidence for the estimated job time. Very
often the desired accuracy is expressed as a percentage of the mean of the observed times. For
example, the goal of a time study may be to achieve an estimate that is within 10 percent of the actual
mean. The sample size needed to achieve that goal can be determined using this formula:
2
z*s
n = ----------------
a (ave. T)
2
Σ(xi – ave x)
s= ----------------
n–1
= sample standard deviation from sample time study
Ave T = average job cycle time from the sample time study
a = desired accuracy percentage
Typical values of z, cumulative probabilities of the Standard Normal Distribution used in this
computation are:
Degree of Freedom (n – 1)
with 5% probability t value
9 2.262
14 2.145
19 2.093
24 2.064
29 2.045
3|P a g e
Solved Problems in Work Measurement 2014
Another alternate formula used when desired accuracy is stated as an amount (e.g. within one minute of
the true mean) instead of a percentage is:
2
zs
n = ----------------
e
Where t = interquartile range (IQR) = Range between the first and third quartiles
After determining the first and third quartiles and the interquartile range as outlined above, then
determining the fences using the following formula:
where Q1 and Q3 are the first and third quartiles, respectively. The Lower fence is the "lower limit" and
the Upper fence is the "upper limit" of data, and any data lying outside these defined bounds can be
considered an outlier. Anything below the Lower fence or above the Upper fence can be considered such
a case. The fences provide a guideline by which to define an outlier, which may be defined in other ways.
The fences define a "range" outside of which an outlier exists; a way to picture this is a boundary of a
fence, outside of which are "outsiders" as opposed to outliers.
Calculation of Rest Allowance for Infrequent Use of Muscular Force (Rohmert, 1973)
R = (W – 5.33)/(W – 1.33)
Notes: A 5.33 kcal/ min (21.3 BTU/ min) limit for acceptable energy expenditure for an 8-hour work day
has been proposed by Bink (1962) while the value of 1.33 kcal/ min (5.3 BTU/ min) is the energy
expenditure during rest.
4|P a g e
Solved Problems in Work Measurement 2014
Work Sampling
Work Sampling Results to Standard Time per Piece
pq
σp = ------
n
Synchronous Servicing
l+m
n = -------------------
l
l+m
n1 <= -------------------
l+w
5|P a g e
Solved Problems in Work Measurement 2014
K1(l + m) +n1K2(1+m)
TECn1 = ------------------------------------
n1
or
(l + m)(K1 + n1K2)
TECn1 = -----------------------------
n1
where TEC = total expected cost per unit of production from one machine
K1 = operator rate per unit of time
K2 = cost of machine per unit of time
n2 = n1 + 1
(K1)(n2)(l + w) + (K2)(n2)(l + w)
TECn2 = -------------------------------------------
n2
or
Random Servicing
Completely random servicing situations are those cases in which it is know when a facility needs to be
serviced or how long servicing takes. Mean values are usually known or can be determined. With these
averages, the laws of probability can provide a useful tool in determining the number of machines to
assign a single operator.
The successive terms of the binomial expansion give a useful approximation of the probability of 0, 1, 2,
3,…, n machines down (where n is relatively small), assuming that each machine is down at random
times during the day and that the probability of downtime is p and the probability of runtime is q = 1 – p.
Each term of the binomial expansion can be expressed as a probability of m (out of n) machines down:
n!
P(m of n) = -------------------------- x pmqn – m
m!(n – m)!
6|P a g e
Solved Problems in Work Measurement 2014
ANSWER SHEET
10. _______ 30. _________ 50. _________ 70. _________ 90. _________
11. _______ 31. _________ 51. _________ 71. _________ 91. _________
12. _______ 32. _________ 52. _________ 72. _________ 92. _________
13. _______ 33. _________ 53. _________ 73. _________ 93. _________
14. _______ 34. _________ 54. _________ 74. _________ 94. _________
15. _______ 35. _________ 55. _________ 75. _________ 95. _________
16. _______ 36. _________ 56. _________ 76. _________ 96. _________
17. _______ 37. _________ 57. _________ 77. _________ 97. _________
18. _______ 38. _________ 58. _________ 78. _________ 98. _________
19. _______ 39. _________ 59. _________ 79. _________ 99. _________
20. _______ 40. _________ 60. _________ 80. _________ 100. _________
7|P a g e
Solved Problems in Work Measurement 2014
1. A set of ratings in which the observer has overestimated the variations in the worker’s rate of working.
3. It may be included in a standard time when the production of a proportion of defective products is
inherent in the process but is perhaps more usually given as a temporary addition to standard times,
per job or per batch, if an occasional bad lot of material has to be worked.
4. A method in which the hands of the stop watch are returned to zero at the end of each element and are
allowed to restart immediately, the time for the element being obtained directly.
5. It is an increment, other than bonus increment, applied to standard time to provide a satisfactory level
of earnings for a specified level of performance under exceptional circumstances.
6. That portion of the elapsed time, excluding the check time, spent on any activity which is not a
specified part of a job.
7. The potential volume of a machine, usually expressed in physical units capable of being produced in
any convenient unit of time, e.g. tons per week, pieces per hour, etc.
8. It is an element which does not occur in every work cycle of the job, but which may occur at regular or
irregular intervals.
9. It is a method of finding the percentage occurrence of a certain activity by statistical sampling and
random observations
8|P a g e
Solved Problems in Work Measurement 2014
11. One who is accepted as having the necessary physical attributes, who possesses the required
intelligence and education, and who has acquired the necessary skill and knowledge to carry out the
work in hand to satisfactory of safety, quantity and quality.
12. The total time in which a job should be completed at standard performance is called --
13. It is usually given to operatives who are not actually engaged in setting-up or dismantling, to
compensate them for time on necessary activities or waiting time at the start and/ or the end of a job
or batch.
14. Elemental Time values which are either considerably higher or lower than the mean of the majority of
observations taken during a time study.
15. This allowance, always a constant, is given to take account of the energy expended while carrying out
work and to alleviate monotony.
16. An element occupying a longer time than that of any other element which is being performed
concurrently is called --
17. The total time from the start to the finish of a time study.
18. It is an element observed during a study which, after analysis, is not found to be a necessary part of
the job.
9|P a g e
Solved Problems in Work Measurement 2014
19. A method in which the hands of the stop watch are allowed to continue to move without returning
them to zero at the end of each element, the time for each element being obtained subsequently by
subtraction.
20. It is an addition to the basic time intended to provide the worker with the opportunity to recover from
the physiological and psychological effects of carrying out specified work under specified conditions
and to allow attention to personal needs.
21. One Time Measurement Unit (TMU) in Methods Time Measurement equals how many minutes?
23. What is the recommended number of observation cycles of a 5 – 10 minutes cycle time?
a. 5 b. 10
c. 15 d. 20
24. The application of techniques designed to establish the time for a qualified worker to carry out a
specified job at a defined level of performance.
25. It is an allowance that may similarly be given for work or waiting time occurring at the end of the day.
26. What is the recommended number of observation cycles of a 1 minute cycle time?
a. 10 b. 15
c. 20 d. 30
27. It may be given to trainee operatives engaged on work for which standard times have been issued, as
a temporary benefit while they develop their ability.
28. It is an element for which the basic time changes in relation to some characteristics of the product,
equipment, or process, e.g. dimension, weight, quality, etc.
10 | P a g e
Solved Problems in Work Measurement 2014
29. A distinct part of a specified job selected for convenience of observations, measurement and analysis
is called --
a. Activity b. Operation
c. Time d. Element
30. The sequence of elements which are required to perform a job or yield a unit of production. The
sequence may sometimes include occasional elements.
31. It is a small allowance of time which may be included in a standard time to meet legitimate and
expected items of work or delays, the precise measurement of which is uneconomical because of
their infrequent or irregular occurrence.
32. A set of ratings in which the observer has underestimated the variations in the worker’s rate of
working.
33. A work measurement technique whereby times established for basic human motions which are
classified according to the nature of the motion and the condition under which it is made are used to
build up the time for a job at a defined level of performance.
34. It is given when the worker has to give attention from time to time to cleaning his machine or
workplace.
35. This is a very quick way of determining sample size where we draw a line from the “percentage
occurrence” ordinate p to intercept the “error (accuracy required)” ordinate (say, 5 percent) and
extend it until it meets the “number of observations” ordinate n, which it intercepts at 300 for the 95
percent confidence level.
36. The instant at which one element in a work cycle ends and another begins.
37. It is an allowance given to compensate for the time taken by any work and any enforced waiting time
which necessarily occurs at the start of a shift or work period before production can begin.
11 | P a g e
Solved Problems in Work Measurement 2014
38. A method for obtaining the time of one or more small elements. Elements are timed in groups, first
including and then excluding each small element, the time for each element being obtained
subsequently by subtraction.
39. An element whose performance time does not vary significantly when changes in the process or
dimensional changes in the product occur.
40. These allowances are added to fixed allowances when working conditions differ markedly for instance
because of poor environmental conditions that cannot be improved, added stress and strain in
performing the job in question, and so on.
41. Portion of the cycle time when the operator is observing a process to maintain the efficient progress of
the operations.
42. It is an allowance given to an experienced worker to compensate him for the time he is required to
spend instructing a trainee, while both are working on jobs for which standard times have been set.
43. The time when a machine is temporarily out of productive use owing to change-over, setting,
cleaning, etc.
45. It is an allowance that may be given to cover the time needed for making alterations to machine or
process settings after completing a run of production.
46. The series of numerical indices given to various rates of working which is linear.
12 | P a g e
Solved Problems in Work Measurement 2014
47. This allowance provides for the necessity to leave the workplace to attend to personal needs such as
washing, going to the lavatory and getting a drink.
49. The time intervals between the start of a time study and the start of the first element observed , and
between the finish of the last element observed and the finish of the study.
50. The stopwatch time readout when the analyst snaps the watch at very end of a time study at the
master clock.
51. Eyron Borlongan, a marketing surveyor, takes an average of 10 minutes to complete a particular
questionnaire. Eyron’s performance rating (pace) is 110% and there is an allowance of 15%.
a. 10 b. 11
c. 11.5 d. 12.65
52. In reference to problem no. 51, what is the standard time for completing this questionnaire given the
allowance is added to its normal time?
a. 10 b. 11
c. 11.5 d. 12.65
53. Alvin Villegas, of Villegas Consulting Group, takes 3 hours and 25 minutes to write an end of month
report. Alvin is rated at 95% of his work pace and the office has a personal time allowance of 8%. There
is no delay time or fatigue time.
a. 3.08 b. 3.25
c. 3.42 d. 3.51
54. In reference to problem no. 53, what is the standard time for writing an end of month report given the
allowance is added to its normal time?
a. 3.08 b. 3.25
c. 3.42 d. 3.51
13 | P a g e
Solved Problems in Work Measurement 2014
55. The two steps in preparing chocolate candy bars are molding and packaging. Personal fatigue and
delay allowances are set at 15%. The molding machine operator is rated at 110% and the packer is
rated at 80%. Observed times per batch are given below.
56. In reference to problem no. 55, determine the standard times for both tasks given the allowances are
added to their normal times.
57. A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker
with an 85% rating produced 12 parts. The worker’s idle time was 10% and the allowance factor was
12%.
a. 3.33 b. 3.73
c. 2.83 d. 2.55
58. In reference to problem no. 57, find the standard time per part for this activity given the allowance is
added to its normal time.
a. 3.73 b. 2.86
c. 3.17 d. 4.18
59. A time study was performed on a particular machine, the results of which are as follows:
Compute the standard time for the operation given the allowances are added to their normal
times.
a. 12.43 b. 13.43
c. 14.34 d. 15.34
14 | P a g e
Solved Problems in Work Measurement 2014
60. Raphael is very organized and wants to plan his day perfectly. To do this, he has his friend Francis
time his daily activities. Here are the results of his timing Raphael on polishing two pairs of black
shoes using the snapback method of timing. Assume 5 percent allowance factor for Raphael to put
something mellow on his iPod.
Observed Times
Element 1 2 3 4 Performance Rating
What is the standard time for polishing two pairs given the allowance is added to its normal time?
a. 2.20 b. 2.48
c. 2.60 d. 2.85
61. A time study was conducted on a job that contains four elements. The observed times and
performance ratings for six cycles are shown:
Assuming an allowance factor of 12.5% based on an eight-hour shift, compute the standard time for
the job given the allowance is added to the total time.
a. 3.92 b. 4.48
c. 3.29 d. 4.84
62. Consider the following 16 observation data: 12, 16, 13, 15, 13, 25, 13, 13, 12, 14, 14, 15, 14, 13, 14,
16, is the value 25 an outlier?
a. Yes b. No
c. Maybe d. Cannot be determined
63. Center for Continuing Education promotes its management development seminars by mailing
thousands of individually composed and typed letters to various firms. A time study has been
conducted on the task of preparing letters for mailing. On the basis of the following observations, the
Center wants to develop a time standard for this task. The firm’s personal, delay, and fatigue
allowance factor is 15%.
Job Element 1 2 3 4 5 PR
a. 13.84 b. 15.36
c. 17.97 d. 19.25
15 | P a g e
Solved Problems in Work Measurement 2014
64. In reference to problem no. 63, compute the standard time given the allowance is added to its normal
time.
a. 15.92 b. 17.66
c. 20.67 d. 22.14
65. A manufacturing company has conducted a time study for ten cycles of a job. The job has five
elements and the total elemental times (minutes) for each element and performance rating factors are
as follows:
1 3.61 1.05
2 4.84 0.90
3 2.93 1.00
4 4.91 1.10
5 1.78 0.95
Compute the standard time using an allowance factor of 18 percent that is added to its normal time.
a. 2.15 b. 2.51
c. 3.15 d. 3.51
66. In reference to problem no. 65, determine the sample size, n, for a time study so there is 98 percent
confidence that the average time computed from the time study is within 4 percent of the actual
average cycle time. The sample standard deviation is 0.23.
a. 40 b. 45
c. 50 d. 55
67. A pilot study of 25 readings for a given element showed that average x = 0.30 and s = 0.09. A 5%
desired acceptable fraction e and an alpha = 0.05 for 24 degrees of freedom for estimating on of the
parameters) yield t = 2.064. What is the sample size to be observed?
a. 145 b. 154
c. 125 d. 152
68. Rommel and Leo recently time-studied a janitorial task. From a sample of 75 observations, they
computed an average cycle time of 15 minutes with a standard deviation of 2 minutes. What is the
computed sample size large enough that one can be 99% confident that the standard time is within 5%
of the true value?
a. 40 b. 45
c. 48 d. 52
16 | P a g e
Solved Problems in Work Measurement 2014
69. Joven Manufacturing has just observed a job in its laboratory in anticipation of releasing the job to the
factory for production. The firm wants rather good accuracy for costing and labor forecasting.
Specifically, it wants to provide a 99% confidence level and a cycle time that is within 3% of the true
value. The data collected so far are as follows:
a. 41 b. 66
c. 84 d. 93
70. The associate dean of the college of business at a technical school has succumbed to faculty
pressure to purchase a new fax machine, although she has always contended that the machine
would have minimal use. She has estimated that the machine will be used only 20 percent of the
time. Now that the machine has been installed, she asked the students in the work measurement
course to conduct a work sampling study to see what the proportion of the time the new fax machine
is used. She wants the estimate to be within 3 percent of the actual proportion, with a confidence
level of 95 percent. Determine the sample size for the work sample.
a. 545 b. 554
c. 638 d. 683
71. The manager of the order distribution center for the Issa Bags Mfg. has a company directive to
downsize his operation. He has decided to conduct work sampling studies of employees in the order
processing department, the warehouse area, and the packaging area. In the warehouse area he has
17 employees who locate items, pull them, and put them on conveyors to the packaging area. A work
sampling study was conducted over a 5-dayperiod to determine the proportion of time warehouse
employees were idle, and out of the 50 random observations, 400 employees were idle?
How many observations should be taken if the manager wants to be 90 percent confident the
estimate is within 5 percent of the actual proportion of time a warehouse employee is idle?
a. 251 b. 271
c. 850 d. 870
72. In reference to problem no. 71, the manager also conducted a work sampling study of the packaging
area and discovered that the 28 employees were idle approximately 37 percent of the time. What is
the required number of packaging area employees so that the manager may redesign his operation to
downsize and be more efficient?
a. 12 b. 14
c. 16 d. 18
17 | P a g e
Solved Problems in Work Measurement 2014
73. The National Bank of Zachary has opened up two new drive-through teller windows outside its main
office building in downtown Zachary. The bank is not sure that it needs both windows open all days
so it has decided to conduct a work sampling study to 11:30 am and 1:00 pm to 3:00 pm. The work
sampling study was conducted at random over a 5-day period and the following observations were
recorded:
Bank management wants the study to be 5 percent accurate with a 95 percent confidence level. How
many additional sample observations should be taken?
a. 377 b. 387
c. 347 d. 357
74. In reference to problem no. 73, if the bank does not want to conduct a study of more than 100
observations, what is the value of z that is equal to the level of confidence could it expect?
a. 1.01 b. 1.03
c. 1.05 d. 1.07
75. The head of the department of management at Benjamin University has noticed that the four
secretaries in the departmental office seem to spend a lot of time answering questions from students
that could better be answered by the college advising office, by the faculty advisors, or simply from
the available literature; that is, course schedules, catalogs, the student handbook, and so on. As a
result the department head is considering remodeling the office with cubicles so students do not have
easy access to the secretaries. However, before investing in this project the head has decided to
conduct a work sampling study to determine the proportion of time the secretaries spend assisting
students.
The head arranged for a graduate assistant to make observations for the work sample, but the
graduate student’s schedule enabled her to make only 300 random observations in the time allotted
for the study. The results of the work sampling study showed that the secretaries assisted 12 percent
of the time, somewhat less than the head anticipated.
Given the number of observations that were included in the work sampling study, what is the value of
z to determine how confident can the department head be that the sample result is within 3 percent of
the actual proportion?
a. 1.40 b. 1.20
c. 1.80 d. 1.60
18 | P a g e
Solved Problems in Work Measurement 2014
76. In reference to problem no. 75, how many fewer or additional observations would be required for the
department head to be 95 percent confident in the work sampling results?
a. 451 b. 453
c. 151 d. 153
77. Mr. DJ Catalog Ordering Company maintains an ordering staff of 30 telephone operators, who take
orders from customers. Management wants to determine the proportion of time that operators are
idle. A work sampling study was conducted at random over a 4-day period, and the following random
observations were recorded:
10/15: 1 6 11 4
2 5 10/17: 12 7
3 4 13 3
4 7 14 3
5 5 15 6
6 2 16 5
10/16: 7 4 17 7
8 3 18 4
9 5 10/19: 19 5
10 6 20 6
If management wants the proportion of time from the work sampling study to be 2 percent accurate
with a confidence level of 98 percent, how many additional sampling observations should be taken?
a. 1820 b. 1840
c. 1850 d. 1860
78. In reference to problem no. 77, based on the time required to take the first 20 observations, how
many days will be required to conduct this study?
a. 365 b. 368
c. 465 d. 468
79. In reference to problem no. 77, if the bank does not want to conduct a study of more than 500
observations, what is the value of z corresponding to the level of confidence could it expect?
a. 1.40 b. 1.20
c. 1.80 d. 1.60
80. In reference to problem no. 77, if the manager discovered that the 30 operators were idle
approximately 22 percent of the time. What is the required number of operators so that the manager
may redesign his operation to downsize and be more efficient?
a. 17 b. 19
c. 21 d. 23
19 | P a g e
Solved Problems in Work Measurement 2014
81. A total of 15 observations have taken on a head baker for a school district. The numerical breakdown
of the baker’s activities is --
2 6 3 4
Based on this information, how many work-sampling observations are required to determine how much
of the baker’s time is spent in “doing”? Assume a 5 percent desired absolute accuracy and 95 percent
confidence level.
a. 384 b. 348
c. 386 d. 368
82. The manager of a small supermarket chain wants to estimate the proportion of time stock clerks
spend making price changes on previously marked merchandise. The manager wants a 98 percent
confidence that the resulting estimate will be within 5 percent of the true value. The preliminary
estimate of sample size is p = 0.50. What sample size should be used?
a. 243 b. 343
c. 443 d. 543
83. In reference to problem no. 82, suppose that in the first 20 observations, stock clerks were found to
be changing prices twice, what is the new sample size for this?
a. 176 b. 186
c. 196 d. 206
84. An analyst has been asked to prepare an estimate of the proportion of time that a turret lathe operator
spends adjusting the machine, with a 90 percent confidence level. Based on previous experience, the
analyst believes the proportion will be approximately 30 percent. If the analyst uses a sample size of
400 observations, what is the maximum possible error that will be associated with the estimate?
a. 3.80% b. 4.80%
c. 5.80% d. 6.80%
85. In reference to problem no. 84, what sample size would the analyst need in order to have the
maximum error be no more than 5 percent?
a. 129 b. 229
c. 321 d. 421
20 | P a g e
Solved Problems in Work Measurement 2014
86. A work sampling study was conducted on a particular machine and the result is provided in the tally
sheet below:
No. of Observations
Running 28
Idle
Broken 6
Out of stock 11
Others 5
At 95% confidence level, the machine is expected to run between __________% and _________ %
of an 8-hour work-shift.
87. Given:
Calculate the standard time per piece of the above data from work sampling study given the
allowance is added to its normal time.
a. 1.43 b. 1.23
c. 1.34 d. 1.32
88. Suppose you want to set a time standard for the baker making her specialty, square donuts. A work
sampling study of her on “donut day” yielded the following results:
What is the standard time per donut given the allowance is added to its normal time?
a. 0.08 b. 0.10
c. 0.12 d. 0.14
21 | P a g e
Solved Problems in Work Measurement 2014
89. Sharee Backpackers is a small-order operation specializing in outdoor camping and hiking equipment
and clothing. In addition to its normal pool of telephone operators to take customer orders, the
company has a group of customer service operators to respond to customer complaints and product
related-inquiries. The time required for customer service operators to handle customer calls differs,
based on an operator’s ability to think fast and quickly recall from memory product information
(without using product description screens on the computer).
The company wants to determine the standard time required for a customer service operator to
complete a call without having to resort to a time study. Instead, management had a work sampling
study of an operator conducted during an 8-hour workday that included 160 observations. The study
showed the operator was talking to customers only 78 percent of the time, and call records indicated
that the operator was handled 120 customer calls during the day.
The customer service manager has indicated that the particular operator that was studied performs
about 110 percent compared with a normal operator. Company policy allows 15 percent personal
time on the job for lunch, breaks, and so on. Determine the standard time per customer call given the
allowance is added to its normal time?
a. 2.85 b. 3.95
c. 4.05 d. 4.15
90. A work sampling study was made of a cargo loading operation for the purpose of developing a
standard time. During the total 120 minutes of observation the employee was working 80% of the time
and loaded 60 pieces of cargo. The analyst rated the performance at 90%. The firm wishes to
incorporate an allowance factor for fatigue, delays, and personal time of 10% of normal work time.
What is the standard time for this operation in minutes per piece given the allowance is added to its
normal time?
a. 1.58 b. 1.85
c. 2.85 d. 2.58
91. A work sampling study of customer service representatives in a telephone company office showed
that a receptionist was working 80 percent of the time at 100 percent PR. This receptionist handled
200 customers during the 8-hour study period. Company policy is to give allowances of 10 percent of
total on-the-job time. Find the standard time per customer given the allowance is added to its total
time.
a. 3.81 b. 3.18
c. 2.31 d. 2.13
92. Timbuktu General Hospital wants to set the standard time for lab technicians to pour a tube specimen
using MTM. The sample tube is in a rack and the centrifuge tubes in a nearby box. A technician
removes the sample tube from the rack, uncaps it, gets the centrifuge tube, pours, and places both
tubes in the rack.
Compute for the total standard time for this task in seconds.
a. 2.6 b. 4.6
c. 6.6 d. 8.6
22 | P a g e
Solved Problems in Work Measurement 2014
93. Consider the following task broken down into 5 MTM elements:
a. 1.36 b. 1.63
c. 2.70 d. 4.52
94. At Derrick Micro Manufacturing, Inc., workers press semiconductors into pre-drilled slots on printed
circuit boards. The elemental motions for normal time used by the company are as follows:
a. 7.2 b. 9.2
c. 11.4 d. 13.4
95. Assume a total cycle time of 4 minutes to produce a product, as measured from the start of the
unloading of the previously completed product to the end of the machine cycle time. Operator
servicing, which includes both the unloading of the completed product and the unloading of the raw
materials, is 1 minute, while the cycle time of the automatic machine cycle is 3 minutes. How many
machines are to be assigned to the operator for this synchronous servicing?
a. 3 b. 4
c. 5 d. 6
96. It takes an operator 1 minute to service a machine and 0.1 minute to walk to the next machine. Each
machine runs automatically for 3 minutes, the operator earns $10 per hour and the machines cost
$20 per hour to run. How many machines that the operator can service?
a. 3 b. 4
c. 5 d. 6
23 | P a g e
Solved Problems in Work Measurement 2014
97. The home security devices produced by a firm are assembled manually in 4 successive steps. Unit
time requirements for these 4 operations are expected to be as follows:
1 64
2 95
3 32
4 142
To satisfy the forecasted demand for the devices, it will be necessary to setup an assembly line which
is capable of yielding an output of 9,000 units in the 40 hours during which the plant operates each
week. What number of workers must be assigned to each operation 2 and 4, if the result is to be a
fairly well balanced line with the required output capacity?
a. 4 and 7 b. 5 and 8
c. 6 and 9 d. 7 and 10
98. Consider a worker lifting a 40-lb load less than once every 5 minutes. The average person’s
maximum strength capability is 100 lb. With the short duration exertion of 0.05 minute, calculate the rest
allowance for this infrequent use of muscular force activity.
a. 5% b. 6%
c. 7% d. 8%
99. A worker is shoveling sand at a rate of 8 kcal/min. How much rest does he need during an 8-hour
shift?
a. 0.20 b. 1.20
c. 2.20 d. 3.20
100. A study reveals that a group of three semiautomatic machines assigned to one operator operates
unattended 80 percent of the time. Operator service time at irregular intervals averages 30 percent of
the time on these three machines. What would be the estimated machine hours lost per eight-hour
day because of lack of an operator?
a. 0.43 b. 1.51
c. 0.97 d. 1.94
101. A man lifts a 25 kg load less than once every 7 minutes. The average man’s maximum strength
capability is 130 lb. With the short duration exertion of 2.4 seconds, calculate the rest allowance for this
infrequent use of muscular force activity.
a. 5% b. 6%
c. 7% d. 8%
102. A man is drilling a hole in concrete pavement at a rate of 6.5 kcal/min. How much rest does he need
for a 6-hour work?
a. 0.34 b. 1.36
c. 2.23 d. 3.27
24 | P a g e
Solved Problems in Work Measurement 2014
103. Assume a total cycle time of 6 minutes to produce a product, as measured from the start of the
unloading of the previously completed product to the end of the machine cycle time. Operator
servicing, which includes both the unloading of the completed product and the unloading of the raw
materials, is 75 seconds. How many machines are to be assigned to the operator for this
synchronous servicing?
a. 3 b. 4
c. 5 d. 6
104. It takes an operator 45 seconds to service a machine and 4 seconds to walk to the next machine.
Each machine runs automatically for 3.5 minutes, the operator earns P65 per hour and the machines
cost P1000 per hour to run. How many machines that the operator can service?
a. 3 b. 4
c. 5 d. 6
25 | P a g e
Solved Problems in Work Measurement 2014
1. A set of ratings in which the observer has overestimated the variations in the worker’s rate of working.
3. It may be included in a standard time when the production of a proportion of defective products is
inherent in the process but is perhaps more usually given as a temporary addition to standard times,
per job or per batch, if an occasional bad lot of material has to be worked.
4. A method in which the hands of the stop watch are returned to zero at the end of each element and are
allowed to restart immediately, the time for the element being obtained directly.
5. It is an increment, other than bonus increment, applied to standard time to provide a satisfactory level
of earnings for a specified level of performance under exceptional circumstances.
6. That portion of the elapsed time, excluding the check time, spent on any activity which is not a
specified part of a job.
7. The potential volume of a machine, usually expressed in physical units capable of being produced in
any convenient unit of time, e.g. tons per week, pieces per hour, etc.
26 | P a g e
Solved Problems in Work Measurement 2014
8. It is an element which does not occur in every work cycle of the job, but which may occur at regular or
irregular intervals.
9. It is a method of finding the percentage occurrence of a certain activity by statistical sampling and
random observations
11. One who is accepted as having the necessary physical attributes, who possesses the required
intelligence and education, and who has acquired the necessary skill and knowledge to carry out the
work in hand to satisfactory of safety, quantity and quality.
12. The total time in which a job should be completed at standard performance is called --
13. It is usually given to operatives who are not actually engaged in setting-up or dismantling, to
compensate them for time on necessary activities or waiting time at the start and/ or the end of a job
or batch.
14. Elemental Time values which are either considerably higher or lower than the mean of the majority of
observations taken during a time study.
27 | P a g e
Solved Problems in Work Measurement 2014
15. This allowance, always a constant, is given to take account of the energy expended while carrying out
work and to alleviate monotony.
16. An element occupying a longer time than that of any other element which is being performed
concurrently is called --
17. The total time from the start to the finish of a time study.
18. It is an element observed during a study which, after analysis, is not found to be a necessary part of
the job.
19. A method in which the hands of the stop watch are allowed to continue to move without returning
them to zero at the end of each element, the time for each element being obtained subsequently by
subtraction.
20. It is an addition to the basic time intended to provide the worker with the opportunity to recover from
the physiological and psychological effects of carrying out specified work under specified conditions
and to allow attention to personal needs.
21. One Time Measurement Unit (TMU) in Methods Time Measurement equals how many minutes?
28 | P a g e
Solved Problems in Work Measurement 2014
23. What is the recommended number of observation cycles of a 5 – 10 minutes cycle time?
a. 5 b. 10
c. 15 d. 20
Answer: b. 10
24. The application of techniques designed to establish the time for a qualified worker to carry out a
specified job at a defined level of performance.
25. It is an allowance that may similarly be given for work or waiting time occurring at the end of the day.
26. What is the recommended number of observation cycles of a 1 minute cycle time?
a. 10 b. 15
c. 20 d. 30
Answer: d. 30
27. It may be given to trainee operatives engaged on work for which standard times have been issued, as
a temporary benefit while they develop their ability.
28. It is an element for which the basic time changes in relation to some characteristics of the product,
equipment, or process, e.g. dimension, weight, quality, etc.
29 | P a g e
Solved Problems in Work Measurement 2014
29. A distinct part of a specified job selected for convenience of observations, measurement and analysis
is called --
a. Activity b. Operation
c. Time d. Element
Answer: d. Element
30. The sequence of elements which are required to perform a job or yield a unit of production. The
sequence may sometimes include occasional elements.
31. It is a small allowance of time which may be included in a standard time to meet legitimate and
expected items of work or delays, the precise measurement of which is uneconomical because of
their infrequent or irregular occurrence.
32. A set of ratings in which the observer has underestimated the variations in the worker’s rate of
working.
33. A work measurement technique whereby times established for basic human motions which are
classified according to the nature of the motion and the condition under which it is made are used to
build up the time for a job at a defined level of performance.
34. It is given when the worker has to give attention from time to time to cleaning his machine or
workplace.
30 | P a g e
Solved Problems in Work Measurement 2014
35. This is a very quick way of determining sample size where we draw a line from the “percentage
occurrence” ordinate p to intercept the “error (accuracy required)” ordinate (say, 5 percent) and
extend it until it meets the “number of observations” ordinate n, which it intercepts at 300 for the 95
percent confidence level.
36. The instant at which one element in a work cycle ends and another begins.
37. It is an allowance given to compensate for the time taken by any work and any enforced waiting time
which necessarily occurs at the start of a shift or work period before production can begin.
38. A method for obtaining the time of one or more small elements. Elements are timed in groups, first
including and then excluding each small element, the time for each element being obtained
subsequently by subtraction.
39. An element whose performance time does not vary significantly when changes in the process or
dimensional changes in the product occur.
40. These allowances are added to fixed allowances when working conditions differ markedly for instance
because of poor environmental conditions that cannot be improved, added stress and strain in
performing the job in question, and so on.
41. Portion of the cycle time when the operator is observing a process to maintain the efficient progress of
the operations.
31 | P a g e
Solved Problems in Work Measurement 2014
42. It is an allowance given to an experienced worker to compensate him for the time he is required to
spend instructing a trainee, while both are working on jobs for which standard times have been set.
43. The time when a machine is temporarily out of productive use owing to change-over, setting,
cleaning, etc.
45. It is an allowance that may be given to cover the time needed for making alterations to machine or
process settings after completing a run of production.
46. The series of numerical indices given to various rates of working which is linear.
47. This allowance provides for the necessity to leave the workplace to attend to personal needs such as
washing, going to the lavatory and getting a drink.
32 | P a g e
Solved Problems in Work Measurement 2014
49. The time intervals between the start of a time study and the start of the first element observed , and
between the finish of the last element observed and the finish of the study.
50. The stopwatch time readout when the analyst snaps the watch at very end of a time study at the
master clock.
51. Eyron Borlongan, a marketing surveyor, takes an average of 10 minutes to complete a particular
questionnaire. Eyron’s performance rating (pace) is 110% and there is an allowance of 15%.
a. 10 b. 11
c. 11.5 d. 12.65
Answer: b. 11
52. In reference to problem no. 51, what is the standard time for completing this questionnaire given the
allowance is added to its normal time?
a. 10 b. 11
c. 11.5 d. 12.65
Answer: d. 12.65
53. Alvin Villegas, of Villegas Consulting Group, takes 3 hours and 25 minutes to write an end of month
report. Alvin is rated at 95% of his work pace and the office has a personal time allowance of 8%. There
is no delay time or fatigue time.
a. 3.08 b. 3.25
c. 3.42 d. 3.51
Answer: b. 3.25
54. In reference to problem no. 53, what is the standard time for writing an end of month report given the
allowance is added to its normal time?
a. 3.08 b. 3.25
c. 3.42 d. 3.51
33 | P a g e
Solved Problems in Work Measurement 2014
Answer: d. 3.51
55. The two steps in preparing chocolate candy bars are molding and packaging. Personal fatigue and
delay allowances are set at 15%. The molding machine operator is rated at 110% and the packer is
rated at 80%. Observed times per batch are given below.
Solution:
Observed Times in Minutes
Task 1 2 3 4
Molding 26 30 29 31
Packing 45 50 35 30
For Molding:
Average for Actual Molding Cycle = 29 minutes
Normal Time = 29 x 110/100 = 31.90 minutes
For Packing:
Average actual Packing time = 40 minutes
Normal Time = 40 x 80/100 = 32 minutes
56. In reference to problem no. 55, determine the standard times for both tasks given the allowances are
added to their normal times.
For Molding:
Standard Time = 31.90 x (1 + 0.15) = 36.68 minutes
For Packing:
Standard Time = 32 x (1 + 0.15) = 36.8 minutes
34 | P a g e
Solved Problems in Work Measurement 2014
57. A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker
with an 85% rating produced 12 parts. The worker’s idle time was 10% and the allowance factor was
12%.
a. 3.33 b. 3.73
c. 2.83 d. 2.55
Answer: d. 2.55
58. In reference to problem no. 57, find the standard time per part for this activity given the allowance is
added to its normal time.
a. 3.73 b. 2.86
c. 3.17 d. 4.18
Answer: b. 2.86
59. A time study was performed on a particular machine, the results of which are as follows:
Compute the standard time for the operation given the allowances are added to their normal
times.
a. 12.43 b. 13.43
c. 14.34 d. 15.34
Answer: b. 13.43
35 | P a g e
Solved Problems in Work Measurement 2014
60. Raphael is very organized and wants to plan his day perfectly. To do this, he has his friend Francis
time his daily activities. Here are the results of his timing Raphael on polishing two pairs of black
shoes using the snapback method of timing. Assume 5 percent allowance factor for Raphael to put
something mellow on his iPod.
Observed Times
Element 1 2 3 4 Performance Rating
What is the standard time for polishing a pair given the allowance is added to its normal time?
a. 2.25 b. 2.45
c. 3.25 d. 3.45
Answer: c. 3.25
61. A time study was conducted on a job that contains four elements. The observed times and
performance ratings for six cycles are shown:
Assuming an allowance factor of 12.5% based on an eight-hour shift, compute the standard time for
the job given the allowance is added to the total time.
a. 3.92 b. 4.48
c. 3.29 d. 4.84
Answer: b. 4.48
36 | P a g e
Solved Problems in Work Measurement 2014
62. Consider the following 16 observation data: 12, 16, 13, 15, 13, 25, 13, 13, 12, 14, 14, 15, 14, 13, 14,
16, is the value 25 an outlier?
a. Yes b. No
c. Maybe d. Cannot be determined
Answer: Yes
Solution:
63. Center for Continuing Education promotes its management development seminars by mailing
thousands of individually composed and typed letters to various firms. A time study has been
conducted on the task of preparing letters for mailing. On the basis of the following observations, the
Center wants to develop a time standard for this task. The firm’s personal, delay, and fatigue
allowance factor is 15%.
Job Element 1 2 3 4 5 PR
a. 13.84 b. 15.36
c. 17.97 d. 19.25
Answer: b. 15.36
Note: Delete those elemental times which are too high or abnormal – A4: 21 and C3: 5
64. In reference to problem no. 63, compute the standard time given the allowance is added to its normal
time.
a. 15.92 b. 17.66
c. 20.67 d. 22.14
Answer: b. 17.66
37 | P a g e
Solved Problems in Work Measurement 2014
65. A manufacturing company has conducted a time study for ten cycles of a job. The job has five
elements and the total elemental times (minutes) for each element and performance rating factors are
as follows:
1 3.61 1.05
2 4.84 0.90
3 2.93 1.00
4 4.91 1.10
5 1.78 0.95
Compute the standard time using an allowance factor of 18 percent that is added to its normal
time.
a. 2.15 b. 2.51
c. 3.15 d. 3.51
Answer: a. 2.15
Solution:
NT = Sum Nt
= 1.819 min
ST = NT(1 + AF)
= 1.819(1 + 0.18)
= 2.15 min
66. In reference to problem no. 65, determine the sample size, n, for a time study so there is 98 percent
confidence that the average time computed from the time study is within 4 percent of the actual
average cycle time. The sample standard deviation is 0.23.
a. 40 b. 45
c. 50 d. 55
Answer: d. 55
Solution:
38 | P a g e
Solved Problems in Work Measurement 2014
67. A pilot study of 25 readings for a given element showed that average x = 0.30 and s = 0.09. A 5%
desired acceptable fraction e and an alpha = 0.05 for 24 degrees of freedom for estimating on of the
parameters) yield t = 2.064. What is the sample size to be observed?
a. 145 b. 154
c. 125 d. 152
Answer: b. 154
Solution:
2
N = [(0.09)(2.064)/(0.05)(0.30)] = 153.3 = 154
68. Rommel and Leo recently time-studied a janitorial task. From a sample of 75 observations, they
computed an average cycle time of 15 minutes with a standard deviation of 2 minutes. What is the
computed sample size large enough that one can be 99% confident that the standard time is within 5%
of the true value?
a. 40 b. 45
c. 48 d. 52
Answer: c. 48
Solution:
N = (zs/ eAveT)2
= ((2.58)(2)/ (0.05)(15))2 = 47.15 samples
69. Joven Manufacturing has just observed a job in its laboratory in anticipation of releasing the job to the
factory for production. The firm wants rather good accuracy for costing and labor forecasting.
Specifically, it wants to provide a 99% confidence level and a cycle time that is within 3% of the true
value. The data collected so far are as follows:
a. 41 b. 66
c. 84 d. 93
Answer: b. 66
39 | P a g e
Solved Problems in Work Measurement 2014
70. The associate dean of the college of business at a technical school has succumbed to faculty
pressure to purchase a new fax machine, although she has always contended that the machine
would have minimal use. She has estimated that the machine will be used only 20 percent of the
time. Now that the machine has been installed, she asked the students in the work measurement
course to conduct a work sampling study to see what the proportion of the time the new fax machine
is used. She wants the estimate to be within 3 percent of the actual proportion, with a confidence
level of 95 percent. Determine the sample size for the work sample.
a. 545 b. 554
c. 638 d. 683
Answer: d. 683
Given:
Solution:
n = ((z/e)2)(p(1 – p))
n = ((1.96/0.03)2)(0.20(1 – 0.20))
n = 682.95 = 683 observations
71. The manager of the order distribution center for the Issa Bags Mfg. has a company directive to
downsize his operation. He has decided to conduct work sampling studies of employees in the order
processing department, the warehouse area, and the packaging area. In the warehouse area he has
17 employees who locate items, pull them, and put them on conveyors to the packaging area. A work
sampling study was conducted over a 5-dayperiod to determine the proportion of time warehouse
employees were idle, and out of the 50 random observations, 400 employees were idle?
How many observations should be taken if the manager wants to be 90 percent confident the
estimate is within 5 percent of the actual proportion of time a warehouse employee is idle?
a. 251 b. 271
c. 850 d. 870
Answer: b. 271
40 | P a g e
Solved Problems in Work Measurement 2014
Given:
Solution:
p = 1–p
= 1 – 0.47
= 53 percent
n = ((z/e)2)(p(1 – p))
2
n = ((1.65/0.05) )(0.53(1 – 0.53))
72. In reference to problem no. 71, the manager also conducted a work sampling study of the packaging
area and discovered that the 28 employees were idle approximately 37 percent of the time. What is
the required number of packaging area employees so that the manager may redesign his operation to
downsize and be more efficient?
a. 12 b. 14
c. 16 d. 18
Answer: d. 18
Solution:
Required no. of packaging area employees = Total no. of packaging area employees
- Number of idle employees
= 28 employees – 10 employees
= 18 employees
41 | P a g e
Solved Problems in Work Measurement 2014
73. The National Bank of Zachary has opened up two new drive-through teller windows outside its main
office building in downtown Zachary. The bank is not sure that it needs both windows open all days
so it has decided to conduct a work sampling study to 11:30 am and 1:00 pm to 3:00 pm. The work
sampling study was conducted at random over a 5-day period and the following observations were
recorded:
Bank management wants the study to be 5 percent accurate with a 95 percent confidence level. How
many additional sample observations should be taken?
a. 377 b. 387
c. 347 d. 357
Answer: c. 347
Solution:
p = 1–p
= 1 – 0.57
= 43 percent
n = ((z/e)2)(p(1 – p))
n = ((1.96/0.05)2)(0.43(1 – 0.43))
n = 376.63 = 377 observations
42 | P a g e
Solved Problems in Work Measurement 2014
74. In reference to problem no. 73, if the bank does not want to conduct a study of more than 100
observations, what is the value of z that is equal to the level of confidence could it expect?
a. 1.01 b. 1.03
c. 1.05 d. 1.07
Answer: a. 1.01
Given
n: 100 observations
p: 43 percent
(1 – p): 57 percent
Degree error: 5 percent
Solution:
n = ((z/e)2)(p(1 – p))
75. The head of the department of management at Benjamin University has noticed that the four
secretaries in the departmental office seem to spend a lot of time answering questions from students
that could better be answered by the college advising office, by the faculty advisors, or simply from
the available literature; that is, course schedules, catalogs, the student handbook, and so on. As a
result the department head is considering remodeling the office with cubicles so students do not have
easy access to the secretaries. However, before investing in this project the head has decided to
conduct a work sampling study to determine the proportion of time the secretaries spend assisting
students.
The head arranged for a graduate assistant to make observations for the work sample, but the
graduate student’s schedule enabled her to make only 300 random observations in the time allotted
for the study. The results of the work sampling study showed that the secretaries assisted 12 percent
of the time, somewhat less than the head anticipated.
Given the number of observations that were included in the work sampling study, what is the value of
z to determine how confident can the department head be that the sample result is within 3 percent of
the actual proportion?
a. 1.40 b. 1.20
c. 1.80 d. 1.60
Answer: d. 1.60
43 | P a g e
Solved Problems in Work Measurement 2014
Given:
n: 300 observations
p: 12 percent
(1 – p): 88 percent
Degree error: 3 percent
Solution:
n = ((z/e)2)(p(1 – p))
76. In reference to problem no. 75, how many fewer or additional observations would be required for the
department head to be 95 percent confident in the work sampling results?
a. 451 b. 453
c. 151 d. 153
Answer: c. 151
Solution:
n = ((z/e)2)(p(1 – p))
n = ((1.96/0.03)2)(0.12(1 – 0.12))
44 | P a g e
Solved Problems in Work Measurement 2014
77. Mr. DJ Catalog Ordering Company maintains an ordering staff of 30 telephone operators, who take
orders from customers. Management wants to determine the proportion of time that operators are
idle. A work sampling study was conducted at random over a 4-day period, and the following random
observations were recorded:
10/15: 1 6 11 4
2 5 10/17: 12 7
3 4 13 3
4 7 14 3
5 5 15 6
6 2 16 5
10/16: 7 4 17 7
8 3 18 4
9 5 10/19: 19 5
10 6 20 6
If management wants the proportion of time from the work sampling study to be 2 percent accurate
with a confidence level of 98 percent, how many additional sampling observations should be taken?
a. 1820 b. 1840
c. 1850 d. 1860
Answer: a. 1820
Given:
Solution:
p = 1 – (1- p)
= 1 – 0.16167
= 83.83334 percent
2
n = ((z/e) )(p(1 – p))
n = ((2.33/0.02)2)(0.83833(1 – 0.83833))
45 | P a g e
Solved Problems in Work Measurement 2014
78. In reference to problem no. 77, based on the time required to take the first 20 observations, how
many days will be required to conduct this study?
a. 365 b. 368
c. 465 d. 468
Answer: b. 368
Solution:
Reqd No. of Days to Conduct the Study (x) = (Reqd Number of Observations X
No. of Initial Observations Days)/
Initial No. of Observations
79. In reference to problem no. 77, if the bank does not want to conduct a study of more than 500
observations, what is the value of z corresponding to the level of confidence could it expect?
a. 1.40 b. 1.20
c. 1.80 d. 1.60
Answer: b. 1.20
Given:
n: 500 observations
p: 83.83334 percent
(1 – p): 16.16666 percent
Degree error: 2 percent
Solution:
2
n = ((z/e) )(p(1 – p))
z = 1.20
46 | P a g e
Solved Problems in Work Measurement 2014
80. In reference to problem no. 77, if the manager discovered that the 30 operators were idle
approximately 22 percent of the time. What is the required number of operators so that the manager
may redesign his operation to downsize and be more efficient?
a. 17 b. 19
c. 21 d. 23
Answer: d. 23
Given:
Solution:
81. A total of 15 observations have taken on a head baker for a school district. The numerical breakdown
of the baker’s activities is --
2 6 3 4
Based on this information, how many work-sampling observations are required to determine how much
of the baker’s time is spent in “doing”? Assume a 5 percent desired absolute accuracy and 95 percent
confidence level.
a. 384 b. 348
c. 386 d. 368
Answer: d. 368
82. The manager of a small supermarket chain wants to estimate the proportion of time stock clerks
spend making price changes on previously marked merchandise. The manager wants a 98 percent
confidence that the resulting estimate will be within 5 percent of the true value. The preliminary
estimate of sample size is p = 0.50. What sample size should be used?
a. 243 b. 343
c. 443 d. 543
Answer: d. 543
47 | P a g e
Solved Problems in Work Measurement 2014
2
n = (2.33/ 0.05) (0.50)(1 – 0.50) = 542.89 = 543
83. In reference to problem no. 32, suppose that in the first 20 observations, stock clerks were found to
be changing prices twice, what is the new sample size for this?
a. 176 b. 186
c. 196 d. 206
Answer: c. 196
84. An analyst has been asked to prepare an estimate of the proportion of time that a turret lathe operator
spends adjusting the machine, with a 90 percent confidence level. Based on previous experience, the
analyst believes the proportion will be approximately 30 percent. If the analyst uses a sample size of
400 observations, what is the maximum possible error that will be associated with the estimate?
a. 3.80% b. 4.80%
c. 5.80% d. 6.80%
Answer: a. 3.80%
85. In reference to problem no. 84, what sample size would the analyst need in order to have the
maximum error be no more than 5 percent?
a. 129 b. 229
c. 321 d. 421
Answer: b. 229
86. A work sampling study was conducted on a particular machine and the result is provided in the tally
sheet below:
No. of Observations
Running 28
Idle
Broken 6
Out of stock 11
Others 5
At 95% confidence level, the machine is expected to run between __________% and _________ %
of an 8-hour work-shift.
48 | P a g e
Solved Problems in Work Measurement 2014
n = ((z/e)2)(p(1 – p))
2 2
50 = ((1.96) /e )(0.56(1 – 0.56)
2
50 = (3.8416/e )(0.2632)
50/0.2632 = 3.8416/e2
2
50e = (0.2632)(3.8416)
e2 = 1.0111/50
e = 0.14
Z 2 / 2 pq (1.96) 2 (0.56)(0.44)
n
e2 e2
(1.96) 2 (0.56)(0.44)
e 0.137591
50
87. Given:
Calculate the standard time per piece of the above data from work sampling study given the
allowance is added to its normal time.
a. 1.43 b. 1.23
c. 1.34 d. 1.32
Answer: b. 1.23
49 | P a g e
Solved Problems in Work Measurement 2014
88. Suppose you want to set a time standard for the baker making her specialty, square donuts. A work
sampling study of her on “donut day” yielded the following results:
What is the standard time per donut given the allowance is added to its normal time?
a. 0.08 b. 0.10
c. 0.12 d. 0.14
Answer: a. 0.08
Solution:
(Total time in min) x (Working time percent)
x Performance index)
Standard time = ----------------------------------------------------- x (1 + Allowance)
Per donut Total number of donuts produced
50 | P a g e
Solved Problems in Work Measurement 2014
89. Sharee Backpackers is a small-order operation specializing in outdoor camping and hiking equipment
and clothing. In addition to its normal pool of telephone operators to take customer orders, the
company has a group of customer service operators to respond to customer complaints and product
related-inquiries. The time required for customer service operators to handle customer calls differs,
based on an operator’s ability to think fast and quickly recall from memory product information
(without using product description screens on the computer).
The company wants to determine the standard time required for a customer service operator to
complete a call without having to resort to a time study. Instead, management had a work sampling
study of an operator conducted during an 8-hour workday that included 160 observations. The study
showed the operator was talking to customers only 78 percent of the time, and call records indicated
that the operator was handled 120 customer calls during the day.
The customer service manager has indicated that the particular operator that was studied performs
about 110 percent compared with a normal operator. Company policy allows 15 percent personal
time on the job for lunch, breaks, and so on. Determine the standard time per customer call given the
allowance is added to its normal time?
a. 2.85 b. 3.95
c. 4.05 d. 4.15
Answer: b. 3.95
Solution:
(Total time in min) x (Working time percent)
x Performance index)
Standard time = ----------------------------------------------------- x (1 + Allowance)
Per call Total number of calls handled
90. A work sampling study was made of a cargo loading operation for the purpose of developing a
standard time. During the total 120 minutes of observation the employee was working 80% of the time
and loaded 60 pieces of cargo. The analyst rated the performance at 90%. The firm wishes to
incorporate an allowance factor for fatigue, delays, and personal time of 10% of normal work time.
What is the standard time for this operation in minutes per piece given the allowance is added to its
normal time?
a. 1.58 b. 1.85
c. 2.85 d. 2.58
51 | P a g e
Solved Problems in Work Measurement 2014
Answer: a. 1.58
91. A work sampling study of customer service representatives in a telephone company office showed
that a receptionist was working 80 percent of the time at 100 percent PR. This receptionist handled
200 customers during the 8-hour study period. Company policy is to give allowances of 10 percent of
total on-the-job time. Find the standard time per customer given the allowance is added to its total
time.
a. 3.81 b. 3.18
c. 2.31 d. 2.13
Answer: d. 2.13
(Total time in min) x (Working time percent)
x Performance index)
Standard time = ----------------------------------------------------- x (1 / 1 – Allowance)
Per customer Total customers handled
92. Timbuktu General Hospital wants to set the standard time for lab technicians to pour a tube specimen
using MTM. The sample tube is in a rack and the centrifuge tubes in a nearby box. A technician
removes the sample tube from the rack, uncaps it, gets the centrifuge tube, pours, and places both
tubes in the rack.
Compute for the total standard time for this task in seconds.
a. 2.6 b. 4.6
c. 6.6 d. 8.6
Answer: d. 8.6
52 | P a g e
Solved Problems in Work Measurement 2014
93. Consider the following task broken down into 5 MTM elements:
a. 1.36 b. 1.63
c. 2.70 d. 4.52
Answer: b. 1.63
Solution:
94. At Derrick Micro Manufacturing, Inc., workers press semiconductors into pre-drilled slots on printed
circuit boards. The elemental motions for normal time used by the company are as follows:
a. 7.2 b. 9.2
c. 11.4 d. 13.4
Answer: a. 7.2
53 | P a g e
Solved Problems in Work Measurement 2014
95. Assume a total cycle time of 4 minutes to produce a product, as measured from the start of the
unloading of the previously completed product to the end of the machine cycle time. Operator
servicing, which includes both the unloading of the completed product and the unloading of the raw
materials, is 1 minute, while the cycle time of the automatic machine cycle is 3 minutes. How many
machines are to be assigned to the operator for this synchronous servicing?
a. 3 b. 4
c. 5 d. 6
Answer: b. 4
l+m
n = -------------------
l
Given:
l = 1 minute
m = 3 minutes
l+m
n = -------------------
l
1+3
n = ----------------- = 4 machines
1
96. It takes an operator 1 minute to service a machine and 0.1 minute to walk to the next machine. Each
machine runs automatically for 3 minutes, the operator earns $10 per hour and the machines cost
$20 per hour to run. How many machines that the operator can service?
a. 3 b. 4
c. 5 d. 6
Answer: a. 3
l+m
n1 <= -------------------
l+w
54 | P a g e
Solved Problems in Work Measurement 2014
K1(l + m) +n1K2(1+m)
TECn1 = ------------------------------------
n1
or
(l + m)(K1 + n1K2)
TECn1 = -----------------------------
n1
where TEC = total expected cost per unit of production from one machine
K1 = operator rate per unit of time
K2 = cost of machine per unit of time
Given:
l = 1 minute
m = 3 minutes
w = 0.1 minute
K1 = $10/hour = 10/60 per minute
K2 = $20 per run
(l + m)(K1 + n1K2)
TECn1 = -----------------------------
n1
(1 + 3)((10/60) + 3(20/60))
TEC3 = -----------------------------------
3
(4)(1.16667)
TEC3 = -----------------------
3
97. The home security devices produced by a firm are assembled manually in 4 successive steps. Unit
time requirements for these 4 operations are expected to be as follows:
1 64
2 95
3 32
4 142
To satisfy the forecasted demand for the devices, it will be necessary to setup an assembly line which
is capable of yielding an output of 9,000 units in the 40 hours during which the plant operates each
week. What number of workers must be assigned to each operation 2 and 4, if the result is to be a
fairly well balanced line with the required output capacity?
55 | P a g e
Solved Problems in Work Measurement 2014
a. 4 and 7 b. 5 and 8
c. 6 and 9 d. 7 and 10
Answer: c. 6 and 9
98. Consider a worker lifting a 40-lb load less than once every 5 minutes. The average person’s
maximum strength capability is 100 lb. With the short duration exertion of 0.05 minute, calculate the rest
allowance for this infrequent use of muscular force activity.
a. 5% b. 6%
c. 7% d. 8%
Answer: c. 7%
Solution:
Given:
f = 40 lbs.
F = 100 lbs.
t = 0.05 min.
99. A worker is shoveling sand at a rate of 8 kcal/min. How much rest does he need during an 8-hour
shift?
a. 0.20 b. 1.20
c. 2.20 d. 3.20
Answer: d. 3.20
56 | P a g e
Solved Problems in Work Measurement 2014
R = (W – 5.33)/(W – 1.33)
Notes: A 5.33 kcal/ min (21.3 BTU/ min) limit for acceptable energy expenditure for an 8-hour work day
has been proposed by Bink (1962) while the value of 1.33 kcal/ min (5.3 BTU/ min) is the energy
expenditure during rest.
Therefore, in an 8-hour shift, the worker would need to rest 8 × 0.4003 = 3.2024 hours
100. A study reveals that a group of three semiautomatic machines assigned to one operator operates
unattended 80 percent of the time. Operator service time at irregular intervals averages 30 percent of
the time on these three machines. What would be the estimated machine hours lost per eight-hour
day because of lack of an operator?
a. 0.43 b. 1.51
c. 0.97 d. 1.94
Answer: 1.94
The successive terms of the binomial expansion give a useful approximation of the probability of 0, 1, 2,
3,…, n machines down (where n is relatively small), assuming that each machine is down at random
times during the day and that the probability of downtime is p and the probability of runtime is q = 1 – p.
Each term of the binomial expansion can be expressed as a probability of m (out of n) machines down:
n!
P(m of n) = -------------------------- x pmqn – m
m!(n – m)!
A total of 1.512 + 0.432 = 1.944 hours are lost per day because of interference.
101. A man lifts a 25 kg load less than once every 7 minutes. The average man’s maximum strength
capability is 130 lb. With the short duration exertion of 2.4 seconds, calculate the rest allowance for this
infrequent use of muscular force activity.
a. 5% b. 6%
c. 7% d. 8%
Answer: b. 6%
57 | P a g e
Solved Problems in Work Measurement 2014
Solution:
Given:
102. A man is drilling a hole in concrete pavement at a rate of 6.5 kcal/min. How much rest does he need
for a 6-hour work?
a. 0.34 b. 1.36
c. 2.23 d. 3.27
Answer: b. 1.36
R = (W – 5.33)/(W – 1.33)
Notes: A 5.33 kcal/ min (21.3 BTU/ min) limit for acceptable energy expenditure for an 8-hour work day
has been proposed by Bink (1962) while the value of 1.33 kcal/ min (5.3 BTU/ min) is the energy
expenditure during rest.
Therefore, in a 6-hour work, the worker would need to rest 6 × 0.22630 = 1.36 hours
58 | P a g e
Solved Problems in Work Measurement 2014
103. Assume a total cycle time of 6 minutes to produce a product, as measured from the start of the
unloading of the previously completed product to the end of the machine cycle time. Operator
servicing, which includes both the unloading of the completed product and the unloading of the raw
materials, is 75 seconds. How many machines are to be assigned to the operator for this
synchronous servicing?
a. 3 b. 4
c. 5 d. 6
Answer: c. 5
l+m
n = -------------------
l
Given:
l+m
n = -------------------
l
1.25 + 4.75
n = --------------------- = 4.8 = 5 machines
1.25
104. It takes an operator 45 seconds to service a machine and 4 seconds to walk to the next machine.
Each machine runs automatically for 3.5 minutes, the operator earns P65 per hour and the machines
cost P1000 per hour to run. How many machines that the operator can service?
a. 3 b. 4
c. 5 d. 6
Answer: d. 6
l+m
n1 <= -------------------
l+w
59 | P a g e
Solved Problems in Work Measurement 2014
K1(l + m) +n1K2(1+m)
TECn1 = ------------------------------------
n1
or
(l + m)(K1 + n1K2)
TECn1 = -----------------------------
n1
where TEC = total expected cost per unit of production from one machine
K1 = operator rate per unit of time
K2 = cost of machine per unit of time
Given:
(l + m)(K1 + n1K2)
TECn1 = -----------------------------
n1
(4.25)(84.41333)
TEC5 = --------------------------
5
(4.25)(101.08333)
TEC6 = --------------------------
6
60 | P a g e
Solved Problems in Work Measurement 2014
REFERENCES
[1] Barnes, R.M., “Motion and Time Study Design and Measurement of Work, Seventh Edition”, John
Wiley & Sons, Inc., 1980
[2] Freivalds Andris, “Niebel’s Methods, Standards, and Work Design, Twelfth Edition”, McGraw Hill
Companies, Inc., 2009
[3] Heizer, J. and Render, B., “Operations Management, Tenth Edition”. Prentice Hall, Inc., 2011
[4] International Labour Organization. “Introduction to Work Study”. ILO Publications, 1979
[5] Jacobs, F.R. et al, “Operations and Supply Chain Management, Thirteenth Edition”, McGraw Hill
Companies, Inc., 2011
[6] Monks, J.G., “Schaum’s Outline of Theory and Problems of Operations Management, Second
Edition”, McGraw Hill Companies, Inc., 1996
[7] Russel, R.S. and Taylor, B.W., III “Operations Management, Third Edition”, Prentice Hall, Inc.,
2000
[8] Stevenson, W.J., “Production/ Operations Management, Fifth Edition”. McGraw Hill Companies,
Inc., 1996
61 | P a g e