MergedATC 3 BuyerPESL2
MergedATC 3 BuyerPESL2
MergedATC 3 BuyerPESL2
Index
FUNDING : DOMESTIC
GeM Bid No: GEM/2024/B/5043723
3.0 The scope of work covered under the subject Packages shall be –
4.0 Duration of contract will be 36 Months from the effective start date of the
contract generated through GeM Portal.
9.0 For proper uploading of the bids on the portal namely https://gem.gov.in
(hereinafter referred to as the ‘portal’), it shall be the sole responsibility of the
bidders to apprise themselves adequately regarding all the relevant
procedures and provisions as detailed at the portal as well as by
contacting from PESL, as and when required, for which contact details are
mentioned below. The Purchaser in no case shall be responsible for any
issues related to timely or properly uploading/submission of the bid.
NOTE: If any seller has any objection / grievance against the additional
clauses or otherwise on any aspect of the bidding documents, they can
raise their representation against the same by using the Representation
window provided in the bid details field in Seller dashboard after
logging in as a seller within 4 days of bid publication on GeM.
10.2 A Single Stage Two Envelope Bidding Procedure will be adopted and will
proceed as detailed in the Bidding Documents.
10.3 Soft Copy Part of the Bids must be uploaded under Single Stage Two
Envelope Bidding Procedure on the portal on or before bid submission
date. The GeM would not allow any late submission of bids through the
portal after due date & time as specified. Bids shall be opened as per
schedule specified in the ATC.
Hard Copy Part of the Bids must be submitted under Single Stage Two
Envelope Bidding Procedure at the address given in IFB at or before 11:00
hours on 12.07.2024. In case Hard copy part of the bid is not received by
the Employer till the deadline for submission of the same prescribed by the
Employer, but the bidder has uploaded the soft copy part of the bid, the
soft copy part of the first envelope bid uploaded on the portal shall be
opened. Such bid will be rejected during preliminary examination.
However, in case of MSEs who are exempted from submission of Bid
Security in line with clause No ITB 1.4, non-submission of Hard copy part
shall not lead to outright rejection of the bid, but the documents required to
be submitted in the hard copy part shall be sought through clarifications as
brought out at Clause No ITB 5.
First Envelope i.e. Techno -Commercial Part (inclusive of both soft copy
part of the bids uploaded on GeM portal and hard copy part of the bids
Bid Security must be submitted either in physical form or paid online (for
details refer Clause ITB 1.4). The aforesaid documents in physical form or
documentary evidence of online payment of the specified amount to
POWERGRID, should be submitted at the address given at para 11.0 below
at or before 1100 Hrs. 12.07.2024.
10.0 PESL reserves the right to cancel/withdraw this invitation for bids without
assigning any reason and shall bear no liability whatsoever consequent
upon such a decision.
10.1 e-Reverse Auction shall be conducted in the subject tender as per the
Clause 9 of ITB.
11.0 All correspondence with regard to the above shall be to the following
address:
This section of the Bidding Documents provides the information necessary for bidders
to prepare responsive bids, in accordance with the requirements of the Employer. It also
provides information on bid submission and uploading the bid on portal, online bid
opening, evaluation and on contract award.
This Invitation for Bids, issued by the Employer is open to all firms including
company (ies), Government owned Enterprises registered and incorporated in
India as per Companies Act, 1956, barring Government Department as well as
foreign bidders/MNCs not registered and incorporated in India and those bidders
with whom business is banned by the Employer.
A Bidder shall not have a conflict of interest. All Bidders found to have a conflict of
interest shall be disqualified. A Bidder may be considered to have a conflict of
interest with one or more parties in this bidding process, if:
e) a Bidder submits more than one bid in this bidding process, either
individually [including bid submitted as a agent/authorized representative
on behalf of one or more manufacturer(s) or through Licensee – Licensor
route, wherever permitted as per the provision of Qualification
Requirement] or as a partner in a joint venture. This will result in the
disqualification of all such bids. However, this does not limit the
participation of a Bidder as a subcontractor in another bid, or of a firm as a
subcontractor in more than one bid; or
g) A Bidder or any of its affiliates has been hired (or is proposed to be hired) by
the Employer as Project Manager for the contract.
# Partial offloading under a Contract and/or Facilitation beyond 10% of the Contract Price
shall be treated as Termination
*For the purpose of working out 50% of the Contract, following shall be taken into account:
(b) Scope of the Contract which primarily relates to the Qualification Requirement (QR)
of the bidder.
The Employer shall be the sole judge in this regard and the Employer’s
interpretation on the aforesaid event(s) shall be final and binding.
1.2. Notwithstanding the above, in case any of the event(s) as per ITB Sub-Clause 1.1
above is encountered afresh even prior to opening of Second Envelope/Price Part
Bid of any package, the bid of such bidder shall be considered as non-
responsive/not eligible for that package
Further, the firm has to be a ‘Class-I local supplier’ as defined under Public
Procurement (Preference to Make in India) Order, 2017 issued by Department for
promotion of Industry and Internal Trade (DPIIT), Ministry of Commerce and
Industry, Government of India vide order dated 15/06/2017, its revision dated
04/06/2020 (PPP-MII Order) read in conjunction with ‘Public Procurement
(Preference to Make in India) to provide for Purchase Preference (linked with local
content) in respect of Power Sector’ order dated 16/11/2021 issued by Ministry of
Power (MoP Order) and subsequent modifications/ amendments if any. ‘Class –I
local supplier’ means a supplier or service provider, whose goods, services or works
offered for procurement, has Local Content equal to 60%.
Firms who are not ‘Class-I local supplier’ shall not be eligible to bid.
The ‘Class-I local supplier’ shall give a self-certification in his bid in the given
format, indicating the percentage of Local Content and certifying that the item
offered meets the Local Content requirement for ‘Class –I local supplier’ and shall
give details of the location(s) at which value addition is made. Further, in case of
packages above Rs. 10 Cr, the ‘Class-I local supplier’ shall provide a certificate
(Attachment-10) from statutory auditor or cost auditor of the company (in the case
of companies) or from a practicing cost accountant or practicing chartered
accountant (in respect of suppliers other than companies) giving the percentage of
Local Content. Any false declaration regarding Local Content by the bidder shall be
a transgression of Integrity Pact and action shall be taken in line with provisions of
the Integrity Pact and in line with the provisions of the PPP-MII Order. Further, in
case price reduction during e-RA, the ‘Class –I local supplier’ shall ensure that the
item offered meets the Local Content requirement considering the revised prices.
1.3. Any Bidder from a country which shares a land border with India will be eligible to
bid only if the Bidder is registered with the Competent Authority as per order no.
F.No.6/18/2019-PPD (Order Public Procurement no.1) dated 23/07/2020 and
However, the aforesaid condition for registration of Bidders from countries (even if
sharing land border with India) shall not be applicable to Bidders from such
countries to which Government of India has extended lines of credit or in which
Government of India is engaged in development projects.
(i) “Bidder” means any person or firm or company, including any member of a
consortium or joint venture (that is an association of several persons, or firms
or companies), every artificial juridical persons not falling in any of the
descriptions of bidders stated hereinbefore, including any agency branch or
office controlled by such person, participating in a procurement process
(ii) “Bidder from a country which shares a land border with India” for this
purpose means:
(iii) The beneficial owner for the purpose of (ii) (d) above will be under:
Explanation-
4. Where no natural person is identified under (1) or (2) or (3) above, the
beneficial owner is the relevant natural person who holds the position
of senior managing official
Further, the successful Bidder shall not be allowed to sub-contract works to any
contractor from a country which shares a land border with India unless such
contractor is registered with the Competent Authority.
The Bidder shall, in its bid, submit a certificate in compliance to DoE order as per
the given format at Attachment - 5.
The Bidder shall furnish, except as exempted herein below, as part of its bid, a bid
security in the amount of INR 14,71,000/- shall be submitted to the Purchaser as per
the terms and conditions of Bidding Documents. The bid security must be
submitted in the form provided in the Bidding Documents.
Micro and Small Enterprises (MSEs) registered with Udyam Registration Portal as
specified by Ministry of Micro, Small and Medium Enterprises are exempted from
submission of Bid Security as per the Provisions of the Public Procurement Policy
for Micro and Small Enterprises (MSEs) order 2012, Notification dated 01/06/2020
and 26/06/2020 read in conjunction with related notifications issued from time to
time for such enterprises. This shall be subject to submission of ‘Udyam Registration
certificate’ with regard to registration with authorities mentioned above in
accordance with the relevant notifications/orders.
Bidder may note that non-submission of Bid Security shall lead to outright rejection
of their Bid.
The bid security shall, at the bidder’s option, be in the form of a crossed bank
draft/pay order /banker certified cheque in favour of Employer/Owner# as
stipulated in SCC in the Form of unconditional Bank Guarantee attached hereto in
the Section VI - Sample Forms and Procedures
In case, pursuant to Ministry of Finance, GOI’s Circular dated 17th July, 2012, the
Bank Guarantee is issued using SFMS Platform by the banks located in India, the
copy of such Bank Guarantee shall be submitted by the bidder along with the First
Envelope. The Account details of PESL for the purpose of Bank Guarantee (towards
Bid Security) to be issued using SFMS Platform are as given below:
Name of the Bank and Address IFSC Code PESL Current A/c
No.
State Bank of India SBIN0017313 41969979816
4th & 5th Floor, Parsvnath Capital
Tower, Bhai Veer Singh Marg, Gole
Market, New Delhi-110001.
ICICI Bank Ltd ICIC0000572 057205000407
Plot no.2, Sector-29
Gurgaon, 122001
Note: Any one of the above account details can be used for the issuance of Bank
Guarantee using SFMS Platform.
1.5. Period
1 of Validity of Bid
.
41.5.1. Bids shall remain valid for the period of Six Months after the date of
opening of Techno - Commercial Part i.e. First Envelope, prescribed
by the Employer, pursuant to ITB Sub-Clause 6.1. A bid valid for a
shorter period shall be rejected by the Employer as being non-
responsive.
Apart from prices which shall be offered ONLY through the GeM portal, the Bidder
shall have to fill and upload the following forms along with their Soft copy part
(Scanned in Pdf) of the bid as part of Technical bid –
(ii) Power of Attorney: A power of attorney, duly notarized, indicating that the
person(s) signing the bid has (ve) the authority to sign the bid and thus the
bid is binding upon the Bidder during full period of its validity.
(vi) Certification by the Bidder as per DoE Order pursuant to ITB Clause 1.3
(Format mentioned at Attachment-5: Land border Sharing)
2.2. Hard Copy part of the Bid: The documents required to be submitted as part
of Hard copy Part of the Bid shall be scanned and uploaded as part of First
Envelope in Soft Copy part of the Bid.
2.2.1. Hard copy part of the bid shall comprise the following documents to be
submitted in sealed envelope at Employer’s address given in IFB.:
(i) Bid Security,
(ii) Power of Attorney
(iii) Integrity Pact
(iv) Affidavit of Self certification regarding Minimum Local Content in
line with PPP-MII order
(v) Certificate from statutory auditor or cost auditor of the company (in the
case of companies) or from a practicing cost accountant or practicing
chartered accountant in line with PPP-MII order. Not Applicable
2.2.4. If the envelope is not sealed and marked as required by ITB above, the
Employer will assume no responsibility for the bid’s misplacement or
premature opening.
2.2.6. The Employer may, at its discretion, extend this deadline for submission of
bids any time prior to opening of bids, in which case all rights and
obligations of Employer and bidders will thereafter be subject to the
deadline as extended. Further the Employer also reserves the right to
extend bid submission timeline or recall the tender if e- Procurement
server/GeM Portal is down (i.e. inaccessible / inoperative) for a prolonged
period of time within the last 24 hours of the bid submission due date.
2.2.7. Late Bids: The bidder shall not be permitted to submit the soft copy part of
the bid by any mode other than uploading on the portal within the specified
deadline for submission of bids. The e-Procurement system would not
allow any late submission of bids through the portal after due date & time
as specified in ITB. In case Hard copy part of the bid is received by the
Employer after the deadline for submission of the same prescribed by the
Employer in the ITB, but the bidder has uploaded the soft copy part of the
bid, the bid will be considered as late bid. In such a case, the soft copy part
of the first envelope bid uploaded on the portal shall be opened in line with
the provisions of Bidding Documents. Such bids will be rejected during
preliminary examination. However, in case of MSEs who are exempted
from submission if Bid security in line with ITB , submission of hard copy
part after the deadline for submission of the same prescribed by the
Employer in the BDS, shall not lead to outright rejection of the bid, but the
documents required to be submitted in the hard copy part shall be sought
through clarifications as brought out at ITB
3.1. Bidders may note that they have to quote the amount on the GeM Portal
only for complete scope of work and for all the items including GST (i.e.
Outsourcing of O&M activities of Transmission Lines associated with
Firozabad cluster ) as mentioned in the Bill of Quantity (BoQ) and offers for
incomplete scope shall be rejected.
3.2. The Amount quoted on the GeM Portal shall be considered as Quoted Price
for Complete Scope of work for the subject package. The Prices shall be
inclusive of GST for entire scope of work.
3.3. The Breakup of prices as per BoQ shall be submitted along with the price
part of bid. If break up of price is submitted along with first envelope, bid
shall be liable to be rejected.
3.4. BoQ is provided to Bidder only for reference purpose and for arriving at the
total price to be quoted on the GeM portal.
Prices quoted by the Bidder shall be FIRM and FIXED. No price variation shall be
applicable to the prices during the currency of the contract.
4. COMPLETION PERIOD:
Duration of contract will be 36 Months from the effective date on the contract
generated through GeM portal.
5. CLARIFICATION OF BIDS:
During evaluation of bids, the Purchaser may, at its discretion, seek the clarification
regarding erroneous/non submission of documents related to/identified in Clause
2.1 (ii), (iv), (v), (vi), (vii), (viii), (x) & (xi) the complete annual reports together with
Audited statement of accounts, Online Payment acknowledgment towards Bid
Security (in cases where online payment has been made prior to the deadline for
submission of hardcopy part of the bids), required to be submitted by the Bidders
as per the provisions of the bidding Documents. The Purchaser may give not more
than 03 days’ notice to the bidders to rectify/furnish such documents, failing which
the bids shall be evaluated as per the data/documents submitted with the bids. The
request for clarification and the response of the bidders shall be in writing, and no
change in the price or substance of the proposal shall be sought, offered or
permitted.
6.1. The Employer will open the First Envelope i.e. Techno – Commercial Part of
the bid on the GeM portal as per the provisions available on GeM portal and
provisions of the Bidding Documents.
6.3. No bid shall be rejected at bid opening. However, opening of bid, whether
or not accompanied with the bid security and/ or Integrity Pact and/, shall
not be construed to imply its acceptability which shall be examined in detail
pursuant to the provisions contained in this ITB.
6.4. On behalf of Employer, the Integrity Pact will be signed by its representative
at the time of Receipt of Hard Copy. One original of the Integrity Pact will
be retained by Employer and the other original will be returned to the
representative of the bidders present during bid opening.
6.5. Bidders who have submitted their bid may view on line tender opening on
the portal from their end. In the event of the specified date for the
submission of bids being declared a holiday for the Employer, the bids will
be opened on the next working day.
7. EVALUATION CRITERIA:
7.2. QUALIFICATION:
2. The determination will take into account the Bidder’s financial, technical
capabilities including production capabilities, in particular the Bidder’s
contract work in hand, future commitments & current litigation and past
performance. It will be based upon an examination of the documentary
evidence of the Bidder’s qualifications submitted by the Bidder in their
bid, as well as other information as the Employer deems necessary and
appropriate. This shall, however, be subject to assessment that may be
carried out, if required, by the Employer as per the provisions of bidding
document. The employer shall be sole judge in this regard.
The determination will also take into account the history of accidents in which
the Bidder is involved in the contracts with the Employer as under:
a) In case of a first fatal accident at site (or adjacent thereto) of bidder during a
financial year, bids submitted by such bidder shall be considered non-responsive
for all regional /site packages across PESL (including consultancy) whose date
of bid opening, originally scheduled and/or actual, falls within the 06 months
period reckoned from the date of the first fatal accident.
c. For every subsequent fatal accident in same financial year bids shall be
considered nonresponsive in the manner as above for additional 12-month
period. This period shall however, in sequence to and shall commence after
expiry of non-responsiveness period on account of earlier accidents.
The Employer will carry out a detailed evaluation of the bids of the qualified
bidders in order to determine whether the technical aspects are in accordance
with the requirements set forth in the Bidding Documents. In order to reach
such a determination, the Employer will examine the information supplied by
the bidders in their bid and other requirements in the Bidding Documents,
taking into account the following factors:
b) any other relevant technical factors that the Employer deems necessary or
prudent to take into consideration.
a) The Second Envelope i.e., Price Part of only those Bidders shall be opened
who are determined as having submitted substantially responsive bids and
are ascertained to be qualified to satisfactorily perform the Contract,
pursuant to qualification and techno commercial evaluation.
b) The comparison shall include the applicable taxes, duties and other levies.
c) Bidders may note that they have to quote amount for complete scope (i.e.
Outsourcing of O&M activities of Transmission Lines associated with
Firozabad cluster as mentioned in the Bill of Quantity (BoQ) and bids for
incomplete scope shall be rejected.
d) The Breakup of prices as per BoQ shall be submitted along with the price
part of bid. If break up of price is submitted along with first envelope, bid
shall be liable to be rejected.
f) Incase the break up of prices as per BoQ is not submitted along with the bid
the same shall be finalised on mutually.
g) The prices of all such item(s) against which the Bidder has not quoted
rates/amount (viz., items left blank or against which ‘-‘ is indicated) in the
Price Schedules will be deemed to have been included in other item(s).
8. Performance Security:
The Contractor shall, within twenty-eight (28) days of the notification of award,
shall furnish performance security(ies) for the due performance of the Contract in
the amount equivalent to Five percent (5%) of the Contract Price, with a validity
upto ninety (90) days beyond the Defect Liability Period.
The Contractor has the option to submit BG (towards Performance Security) using
SFMS Platform.
The Account details of PESL for the purpose of Bank Guarantee (towards
Performance Security) to be issued using SFMS Platform are as given below:
Name of the Bank and Address IFSC Code PESL Current A/c
No.
State Bank of India SBIN0017313 41969979816
4th & 5th Floor, Parsvnath Capital
Tower, Bhai Veer Singh Marg, Gole
Market, New Delhi-110001.
ICICI Bank Ltd ICIC0000572 057205000407
Plot no.2, Sector-29
Gurgaon, 122001
Note: Any one of the above account details can be used for the issuance of Bank
Guarantee using SFMS Platform.
8.1 In case the Contractor fails to submit the Performance Security within 90 Days of
the Notification of Award/GeM Contract, the Employer, without prejudice to any
other rights or remedies it may possess under the Contract, may consider the bid
submitted by the Contractor in future packages as non-responsive in line with the
ITB and/or may terminate the Contract forthwith pursuant to GCC Clause 36
After the RA process, the award of contract(s) shall be made by the buyer keeping
in view the Public Procurement Policy for Micro and Small Enterprises (MSEs)
Order, 2012 and Public Procurement (Preference to Make-in-India) Order, 2017 as
amended from time to time.
10.1. At the same time as the Employer notifies the successful Bidder that its bid
has been accepted, the Employer in consultation with the Bidder will
prepare the Contract Agreement provided in the Bidding Documents,
incorporating all agreements between the parties.
10.2.
The Contract Agreement shall be prepared within twenty-eight (28) days
of the Notification of Award and the successful Bidder and the Employer
shall sign and date the Contract Agreement immediately thereafter.
11. Confidentiality and Contacting the Employer
12.2 The Employer may request the Bidder to withdraw any of the deviations
listed if any in the winning bid.
13.1 Prior to the expiration of the period of bid validity, the Employer will
notify the successful Bidder in writing, that its bid has been accepted. The
notification of award will constitute formation of the contract.
13.2 The Employer shall publish the results on its website, identifying the bid
and Specification numbers and the following information: (i) name of
each Bidder who submitted a Bid; (ii) bid prices displayed as per e-form
at bid opening; (iii) name and evaluated prices of each Bid that was
evaluated; (iv) name of bidders whose bids were rejected and the reasons
for their rejection; and (v) name of the winning Bidder, and the price it
offered, as well as the duration and summary scope of the contract
awarded.
14.1 The Employer reserves the right to accept or reject any bid, and to annul
the bidding process and reject all bids at any time prior to award of
contract, without thereby incurring any liability to the affected Bidder or
bidders or any obligation to inform the affected Bidder or bidders of the
grounds for the Employer’s action.
(a) defines, for the purpose of this provision, the terms set forth below as
follows:
(i) “Corrupt Practice” means offering, giving, receiving, or
soliciting anything of value to influence the action of Employer
official(s) in the procurement process.
(ii) “Fraudulent Practice’” means any act including suppression/
misrepresentation of facts, submissions of forged/ false
documents, making false declarations etc. that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain a
financial gain or benefit, or to avoid an obligation, or to
influence procurement process to the detriment of interest of
the Employer, including collusive practices among bidders
(prior to or after bid submission) to establish bid prices at
artificial, non-competitive levels and to deprive Employer of
the benefits of competitive prices.
or
(b) will reject a proposal for award if it determines that the bidder
recommended for award has, directly or through an agent, engaged
in corrupt, fraudulent, collusive, coercive or obstructive practices in
competing for the contract in question.
(d) will have the right to require that the provision be included in Bidding
Documents and in contracts, requiring Bidders, suppliers, and
contractors and their sub-contractors to permit the Employer to
inspect their accounts and records and other documents relating to
bid submission and contract performance and to have them audited
by auditors appointed by the Employer.
OR
b) Successful Erection and stringing**** of not less than 125 kms cumulatively route
length of 400kV$ or above transmission line cumulatively during last 7 years, as on
the originally scheduled last date of bid submission (soft copy) mentioned
above. i.e. 12.07.2024.
Page 1 of 2
Annexure-A (ITB) Vol-I Gem Bid No: GEM/2024/B/5043723
*** Maximum voltage level of transmission line considered in the package
**** Successful Erection and Stringing means certificate issued by Employer certifying
successful erection and stringing without any adverse remark.
$ One voltage level below than the highest voltage level in the project
(i) MSEs^/ START-UPs^^ meeting the specified requirements at para 1.2(a) above,
shall also be considered qualified if they meet 80% (Eighty percent) of the
requirements specified at para 1.2(b) & para 1.2(c) above.
Page 2 of 2
SECTION – IV
A AMBATI
b560833571fe91a04e49f546a93e1c7
4fdcd85cf6, ou=CS,CID - 4656565,
postalCode=122001, st=Haryana,
cn=CHARANYA AMBATI
Date: 2018.07.24 16:21:10 +05'30'
TABLE OF CLAUSES
Preamble
A. Definitions and Interpretation ................................................................... 1
1. Definitions ...................................................................................................... 1
2. Interpretation ................................................................................................. 5
B. Subject Matter of Contract .......................................................................... 8
3. Scope of Facilities .......................................................................................... 8
4. Time for Commencement and Completion ............................................ 10
5. Contractor’s Responsibilities .................................................................... 10
6. Employer’s Responsibilities...................................................................... 11
C. Payment ......................................................................................................... 12
7. Contract Price ............................................................................................... 12
8. Terms of Payment ........................................................................................ 13
9. Securities ....................................................................................................... 13
10. Taxes and Duties ......................................................................................... 17
D. Intellectual Property ................................................................................... 21
11. Copy Right .................................................................................................... 21
12. Confidential Information .......................................................................... 21
E. Execution of the Facilities .......................................................................... 22
13. Representatives ............................................................................................ 22
14. Work Program .............................................................................................. 24
15. Subcontracting ............................................................................................. 26
16. Design and Engineering............................................................................. 27
17. Plant and Equipment .................................................................................. 29
18. Installation .................................................................................................... 32
19. Test and Inspection ..................................................................................... 50
20. Completion of the Facilities and Operational Acceptance .................. 52
F. Guarantees and Liabilities ........................................................................ 57
21. Completion Time Guarantee..................................................................... 57
22. Defect Liability ............................................................................................ 58
23. Functional Guarantees................................................................................ 61
Preamble
1. Definitions
1.1 The following words and expressions shall have the meanings
hereby assigned to them:
(e) “Completion” means that the Facilities (or a specific part thereof
where specific parts are specified in the SCC) have been
completed operationally and structurally and put in a tight and
clean condition and that all works in respect of pre-
commissioning of the Facilities (or a specific part thereof where
specific parts are specified in the SCC) has been completed
(wherever required, as per Technical Specifications) and
Commissioning followed by Trail – Operation has been
completed, as provided in GCC Sub-Clause 20.1 (Completion of
Facilities) hereof.
(bb) “Site” means the land and other places upon which the Facilities
are to be installed, and such other land or places as may be
specified in the Contract as forming part of the Site.
2.1 Contract
2.1.1 The Contracts to be entered into with the successful Bidder shall be
as under:
2.1.2 The award of two separate Contracts shall not in any way dilute the
responsibility of the Contractor for the successful completion of the
facilities as per Specification and a breach in one Contract shall
automatically be construed as a breach of the other Contract(s) which
will confer a right on the Employer to terminate the other Contract(s)
also at the risk and the cost of the Contractor.
2.1.3 The Contract will be signed in two originals and the Contractor shall
be provided with one signed original and the rest will be retained by
the Employer.
2.1.4 The Contractor shall provide free of cost to the Employer all the
engineering data, drawing and descriptive materials submitted with
the bid, in at least two (2) copies to form a part of the Contract
immediately after Notification of Award.
All documents forming part of the Contract (and all parts thereof) are
intended to be correlative, complementary and mutually
explanatory, subject to Article 1.2 (Order of Precedence) of the
Contract Agreement. The Contract shall be read as a whole.
The singular shall include the plural and the plural the singular,
except where the context otherwise requires.
2.5 Headings
2.7 Amendment
2.10 Non-Waiver
2.11 Severability
“Origin” means the place where the materials, equipment and other
supplies for the Facilities are mined, grown, produced or
manufactured, and from which the services are provided. Plant and
equipment are produced when, through manufacturing, processing
or substantial and major assembling of components, a commercially
recognized product results that is substantially different in basic
characteristics or in purpose or utility from its components.
2.13.1 Unless otherwise stated in the Contract, all notices to be given under
the Contract shall be in writing, and shall be sent by personal
delivery, special courier, telegraph, facsimile or Electronic Data
Interchange (EDI) to the address of the relevant party set out in the
Contract Agreement, with the following provisions:
(b) Any notice sent by special courier shall be deemed (in the
absence of evidence of earlier receipt) to have been delivered
ten (10) days after dispatch. In proving the fact of dispatch, it
shall be sufficient to show that the envelope containing such
notice was properly addressed, stamped and conveyed to the
postal authorities or courier service for transmission by special
courier. Provided further that whenever the postal authorities
or courier service provide a proof of delivery, the same shall
also be applicable for presenting the fact of dispatch.
(d) Either party may change its postal, facsimile or EDI address or
addressee for receipt of such notices by ten (10) days‟ notice to
the other party in writing.
3. Scope of Facilities
3.3 The supply of Mandatory Spare Parts, if any, shall be included in the
Contract. Beside the aforesaid Mandatory Spares parts, the
Contractor shall ensure the availability of spare parts required for the
operation and maintenance of the Facilities to the Employer for a
minimum period of 15 years from Completion of the Facilities. The
Contractor shall carry sufficient inventories to ensure an ex-stock
supply of consumable spares for the plant and equipment. If so
desired by the Employer, the Contractor shall submit the
specifications, price and the terms and conditions relating to the
supply thereof for such spares identified by the Employer with
validity period of 6 months within 30 days of receipt of request from
Employer for its consideration and placement of order.
3.5 In case the Contractor fails to supply the spares parts in accordance
with the terms stipulated above, the Employer shall sanction the
Contractor declaring them ineligible for a stated period of time for
future projects.
4.1 The Contractor shall commence work on the Facilities from the
Effective Date of Contract and without prejudice to GCC Sub-Clause
21.2 hereof, the Contractor shall thereafter proceed with the Facilities
in accordance with the time schedule specified in the corresponding
Appendix – 4 (Time Schedule) to the Contract Agreement.
4.2 The Contractor shall attain Completion of the Facilities (or of a part
where a separate time for Completion of such part is specified in the
Contract) within the time stated under Time for Completion or
within such extended time to which the Contractor shall be entitled
under GCC Clause 34 hereof.
5. Contractor’s Responsibilities
5.2 The Contractor confirms that it has entered into this Contract on the
basis of a proper examination of the data relating to the Facilities
(including any data as to boring tests) provided by the Employer,
and on the basis of information that the Contractor could have
obtained from a visual inspection of the Site (if access thereto was
available) and of other data readily available to it relating to the
Facilities as of the date twenty-eight (28) days prior to bid
submission. The Contractor acknowledges that any failure to
acquaint itself with all such data and information shall not relieve its
responsibility for properly estimating the difficulty or cost of
successfully performing the Facilities.
5.3 The Contractor shall acquire in its name all permits, approvals
and/or licenses from all local, state or national government
authorities or public service undertakings in the country where the
Site is located that are necessary for the performance of the Contract,
including, without limitation, visas for the Contractor‟s and
Section – IV: General Conditions of Contract Page 10
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
Subcontractor‟s personnel and entry permits for all imported
Contractor‟s Equipment. The Contractor shall acquire all other
permits, approvals and/or licenses that are not the responsibility of
the Employer under GCC Sub-Clause 6.3 hereof and that are
necessary for the performance of the Contract.
5.4 The Contractor shall comply with all laws in force in India. The laws
will include all local, state, national or other laws that affect the
performance of the Contract and bind upon the Contractor. The
Contractor shall indemnify and hold harmless the Employer from
and against any and all liabilities, damages, claims, fines, penalties
and expenses of whatever nature arising or resulting from the
violation of such laws by the Contractor or its personnel, including
the Subcontractors and their personnel, but without prejudice to
GCC Sub-Clause 6.1 hereof.
5.6 The Contractor shall permit the Employer to inspect the Contractor‟s
accounts and records relating to the performance of the Contractor.
6. Employer’s Responsibilities
6.1 The Employer shall ensure the accuracy of all information and/or
data to be supplied by the Employer as described in the
corresponding Appendix - 6 (Scope of Works and Supply by the
Employer) to the Contract, except when otherwise expressly stated in
the Contract.
6.2 The Employer shall be responsible for acquiring and providing legal
and physical possession of the Site and access thereto, and for
providing possession of and access to all other areas reasonably
required for the proper execution of the Contract, including all
requisite rights of way, as specified in the corresponding Appendix –
6 (Scope of Works and Supply by the Employer) to the Contract
Agreement. The Employer shall give full possession of and accord all
rights of access thereto on or before the date(s) specified in that
Appendix.
6.3 The Employer shall acquire and pay for all permits, approvals
and/or licenses from all local, state or national government
authorities or public service undertakings in the country where the
Site is located which such authorities or undertakings require the
Employer to obtain them in the Employer's name, are necessary for
Section – IV: General Conditions of Contract Page 11
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
the execution of the Contract (they include those required for the
performance by both the Contractor and the Employer of their
respective obligations under the Contract), including those specified
in Appendix 6 (Scope of Works and Supply by the Employer) to the
Contract Agreement.
6.4 If requested by the Contractor, the Employer shall use its best
endeavors to assist the Contractor in obtaining in a timely and
expeditious manner all permits, approvals and/or licenses necessary
for the execution of the Contract from all local, state or national
government authorities or public service undertakings that such
authorities or undertakings require the Contractor or Subcontractors
or the personnel of the Contractor or Subcontractors, as the case may
be, to obtain.
6.6 The Employer shall be responsible for the continued operation of the
Facilities after Taking Over, in accordance with GCC Sub-Clause
20.1.5.
6.7 All costs and expenses involved in the performance of the obligations
under this GCC Clause 6 shall be the responsibility of the Employer.
C. Payment
7. Contract Price
7.3 Subject to GCC Sub-Clauses 5.2 and 6.1 hereof, the Contractor shall
be deemed to have satisfied itself as to the correctness and
sufficiency of the Contract Price, which shall, except as otherwise
provided for in the Contract, cover all its obligations under the
Contract.
8. Terms of Payment
8.2 All payments under the Contract shall be made in Indian Rupees.
9. Securities
9.2.1 The Contractor shall, within twenty-eight (28) days of the notification
of contract award, provide a security in an amount equal to as
follows:
a. 110% (one hundred ten percent) of the amount of Advance for Supply
of Goods; and
9.3.1 The Contractor shall, within twenty-eight (28) days of the notification
of award, provide a performance security for the due performance of
the Contract in the amount equivalent to Ten percent (10%) of the
Contract Price, with a validity upto ninety (90) days beyond the
Defect Liability Period. The same shall be extended by the Contractor
time to time till ninety (90) days beyond the actual Defect Liability
Period, as may be required under the Contract.
c) The period of delay for the above purpose shall be the time
elapsed between the due date for submission of performance
security as per the Contract and the date of performance security.
9.3.1.3 The above extension of Defect Liability Period or deduction shall not
relieve the Contractor from any of his obligations and liabilities
under the Contract.
9.3.3 Reduction in the security pro rata to the Contract Price of any part of
the Facilities is not admissible. However, if the Defects Liability
Period has been extended on any part of the Facilities pursuant to
GCC Sub-Clause 22.8 hereof, the Contractor shall issue an additional
security in an amount proportionate to the Contract Price of that
part. The security shall be returned to the Contractor immediately
after its expiration, provided, however, that if the Contractor
pursuant to GCC Sub-Clause 22, is liable for an extended warranty
obligation, the performance security shall be reduced to ten percent
(10%) of the value of the component covered by the extended
warranty.
9.5 Indemnity
9.5.2 In case of divisible Contracts, where the Employer hands over his
equipment to the Contractor for executing the Contract, then the
Contractor shall, at the time of taking delivery of the equipment
through Bill of Lading or other despatch documents, furnish trust
Receipt for Plant, Equipment and Materials and also execute an
Indemnity Bond in favour of the Employer in the form acceptable to
the Employer for keeping the equipment in safe custody and to
utilize the same exclusively for the purpose of the said Contract.
Samples of proforma for the Trust receipt and Indemnity Bond are
enclosed under Section VI (Sample Forms and Procedures). The
Employer shall also issue a separate Authorization Letter to the
Contractor to enable him to take physical delivery of plant,
equipment and materials from the Employer as per proforma
enclosed under Section VI (Sample Forms and Procedures).
10.1 The Contractor shall be entirely responsible for payment of all taxes,
duties, licence fees and other such levies legally payable/incurred
until delivery of the contracted supplies to the Employer.
10.2 The Contractor shall be solely responsible for the taxes that may be
levied on the Contractor's persons or on earnings of any of his
employees and shall hold the Employer indemnified and harmless
against any claims that may be made against the Employer. The
Employer does not take any responsibility whatsoever regarding
taxes under Indian Income Tax Act, for the Contractor or his
personnel. If it is obligatory under the provisions of the Indian
Income Tax Act, deduction of Income Tax at source shall be made by
the Employer.
The Input Tax Credit (ITC) available, if any, under GST as per the
relevant Government laws wherever applicable has been taken into
account by the Contractor.
10.4 Ex-works price for the supply of goods viz. Equipment/items by the
Contractor is excluding GST, if any, payable. The GST will be
reimbursable (along with subsequent variation if any), by the
Employer on the supplies made by the Contractor but limited to the
tax liability on the transaction between the Employer and the
Contractor.
Further the price for supply of services viz. Installation and training
are excluding GST, if any, payable. The GST will be reimbursable
(along with subsequent variation if any), by the Employer on the
supplies made by the Contractor but limited to the tax liability on the
transaction between the Employer and the Contractor.
10.5 Employer would not bear any liability on account of any other taxes,
duties, levies applicable locally.
10.8 The Contractor shall comply with all tax laws in force in India. The
Contractor shall indemnify and hold harmless the Employer from
and against any and all liabilities, interest, damages, claims, fines,
penalties and expenses of whatever nature arising or resulting from
the violation of such tax laws by the Contractor or its personnel,
including the Subcontractors and their personnel.
10.11 For the purpose of the Contract, it is agreed that the Contract Price
specified in Article 2(Contract Price and Terms of Payment) of the
Contract Agreement is based on the taxes, duties, levies and charges
prevailing at the date seven (07) days prior to the last date of bid
submission (hereinafter called “Tax” in this GCC Sub-clause 10.7). If
any rates of Tax are increased or decreased, a new Tax is introduced,
an existing Tax is abolished, or any change in interpretation except
for classification related purpose, or application of any Tax occurs in
the course of the performance of the Contract, which was or will be
assessed on the Contractor in connection with performance of the
Contract, an equitable adjustment of the Contract price shall be made
D. Intellectual Property
12.1 The Employer and the Contractor shall keep confidential and shall
not, without the written consent of the other party hereto, divulge to
any third party any documents, data or other information furnished
directly or indirectly by the other party hereto in connection with the
Contract, whether such information has been furnished prior to,
during or following termination of the Contract. Notwithstanding
the above, the Contractor may furnish to its Subcontractor(s) such
Section – IV: General Conditions of Contract Page 21
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
documents, data and other information it receives from the Employer
to the extent required for the Subcontractor(s) to perform its work
under the Contract, in which event the Contractor shall obtain from
such Subcontractor(s) an undertaking of confidentiality similar to
that imposed on the Contractor under this GCC Clause 12.
12.2 The Employer shall not use such documents, data and other
information received from the Contractor for any purpose other than
the operation and maintenance of the Facilities. Similarly, the
Contractor shall not use such documents, data and other information
received from the Employer for any purpose other than the design,
procurement of Plant and Equipment, construction or such other
work and services as are required for the performance of the
Contract.
12.3 The obligation of a party under GCC Sub-Clauses 12.1 and 12.2
above, however, shall not apply to that information which
12.4 The above provisions of this GCC Clause 12 shall not in any way
modify any undertaking of confidentiality given by either of the
parties hereto prior to the date of the Contract in respect of the
Facilities or any part thereof.
12.5 The provisions of this GCC Clause 12 shall survive termination, for
whatever reason, of the Contract.
13. Representatives
13.1 If the Project Manager is not named in the Contract, then within
fourteen (14) days of the Effective Date, the Employer shall appoint
and notify the Contractor in writing of the name of the Project
Manager. The Employer may from time to time appoint some other
person as the project Manager in place of the person previously so
appointed, and shall give a notice of the name of such other person
to the Contractor without delay. The Employer shall take all
reasonable care to see that no such appointment is made at such a
Section – IV: General Conditions of Contract Page 22
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
time or in such a manner as to impede the progress of work on the
Facilities. The Project Manager shall represent and act for the
Employer at all times during the currency of the Contract. All
notices, instructions, orders, certificates, approvals and all other
communications under the Contract shall be given by the Project
Manager, except as herein otherwise provided.
13.2.2 The Contractor‟s Representative shall represent and act for the
Contractor at all times during the currency of the Contract and shall
give to the Project Manager all the Contractor‟s notices, instructions,
information and all other communications under the Contract. All
notices, instructions, information and all other communications
given by the Employer or the Project Manager to the Contractor
under the Contract shall be given to the Contractor‟s Representative
or, in its absence, its deputy, except as herein otherwise provided.
The Contractor shall not revoke the appointment of the Contractor‟s
Representative without the Employer‟s prior written consent, which
shall not be unreasonably withheld. If the Employer consents thereto,
the Contractor shall appoint some other person as the Contractor‟s
Representative, pursuant to the procedure set out in GCC Sub-Clause
13.2.1.
The Contractor may execute the Contract in accordance with its own
standard project execution plans and procedures to the extent that
they do not conflict with the provisions contained in the Contract.
15. Subcontracting
15.2 The Contractor shall select and employ its Subcontractors for such
major items from those listed in the lists referred to in GCC Sub-
Clause 15.1.
15.3 For items or parts of the Facilities not specified in the corresponding
Appendix (List of Approved Subcontractors) to the Contract
Agreement for Supply Contract(s), the Contractor may employ such
Subcontractors as it may select, at its discretion.
15.4 The Contractor shall furnish the details of items, components, raw
materials, services etc. procured from MSEs and consumed for
Section – IV: General Conditions of Contract Page 26
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
completion of scope of works under the contract. The details shall be
furnished as per the format enclosed at Section VI, Forms, Volume-I
of the bidding documents at the time of raising bills for payment
against the supplies made/works done.
16.1.1 The Contractor shall execute the basic and detailed design and the
engineering work in compliance with the provisions of the Contract,
or where not so specified, in accordance with good engineering
practice.
16.3.1 The Contractor shall prepare (or cause its Subcontractors to prepare)
and furnish to the Project Manager the documents listed in
Appendix-7 (List of Documents for Approval or Review) to the
Contract Agreement for its approval or review as specified and as in
16.3.2 Within twenty one (21) days after receipt by the Project Manager of
any document requiring the Project Manager's approval in
accordance with GCC Sub-Clause 16.3.1, the Project Manager shall
either return one copy thereof to the Contractor with its approval
endorsed thereon or shall notify the Contractor in writing of its
disapproval thereof and the reasons therefor and the modifications
that the Project Manager proposes.
16.3.3 The Project Manager shall not disapprove any document, except on
the grounds that the document does not comply with some specified
provision of the Contract or that it is contrary to good engineering
practice.
16.3.5 If any dispute or difference occurs between the Employer and the
Contractor in connection with or arising out of the disapproval by
the Project Manager of any document and/or any modification(s)
thereto that cannot be settled between the parties within a reasonable
period, then such dispute or difference may be referred to an
Arbitrator for determination in accordance with GCC Sub-Clause 39
hereof. If such dispute or difference is referred to an Arbitrator, the
Project Manager shall give instructions as to whether and if so, how,
performance of the Contract is to proceed. The Contractor shall
proceed with the Contract in accordance with the Project Manager‟s
Section – IV: General Conditions of Contract Page 28
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
instructions, provided that if the Arbitrator upholds the Contractor‟s
view on the dispute and if the Employer has not given notice under
GCC Sub-Clause 39 hereof, then the Contractor shall be reimbursed
by the Employer for any additional costs incurred by reason of such
instructions and shall be relieved of such responsibility or liability in
connection with the dispute and the execution of the instructions as
the Arbitrator shall decide, and the Time for Completion shall be
extended accordingly.
16.3.7 The Contractor shall not depart from any approved document unless
the Contractor has first submitted to the Project Manager an
amended document and obtained the Project Manager‟s approval
thereof, pursuant to the provisions of this GCC Sub-Clause 16.3. If
the Project Manager requests any change in any already approved
document and/or in any document based thereon, the provisions of
GCC Clause 33 shall apply to such request.
17.2.1 The Employer shall, at its own risk and expense, transport each item
to the place on or near the Site as agreed upon by the parties and
make such item available to the Contractor at the time specified in
the program furnished by the Contractor, pursuant to GCC Sub-
Clause 14.2, unless otherwise mutually agreed.
17.2.3 Yards and store provided by the Contractor for stacking and storage
of materials shall be open for inspection by the Employer as and
when required. The cost of handling and storage shall be to the
Contractor‟s account.
17.2.4 Upon receipt of such item, the Contractor shall inspect the same
visually and notify the Project Manager of any detected shortage,
defect or default. For the material being arranged by the Employer
and supplied to the Contractor for erection, are received short,
broken or damaged, an entry shall be made in the delivery register of
the railway authorities/road transporter as far as possible and a
report of the same giving full details of shortage and damages along
with a copy of report entered in the delivery register of the road
transporter/railways shall be submitted by the Contractor to the
Project Manager and Employer‟s consignee immediately. The
Employer shall immediately remedy any shortage, defect or default,
or the Contractor shall, if practicable and possible, at the request of
the Employer, remedy such shortage, defect or default at the
Employer‟s cost and expense. After inspection, such item shall fall
under the care, custody and control of the Contractor. The provision
of this GCC Sub-Clause 17.2.4 shall apply to any item supplied to
remedy any such shortage or default or to substitute for any
defective item, or shall apply to defective items that have been
repaired.
17.3.1 The Contractor shall at its own risk and expense transport all the
Plant and Equipment and the Contractor‟s Equipment to the Site by
the mode of transport that the Contractor judges most suitable under
all the circumstances.
17.3.3 Upon dispatch of each shipment of the Plant and Equipment and the
Contractor‟s Equipment, the Contractor shall notify the Employer by
telex, facsimile or Electronic Data Interchange (EDI) of the
description of the Plant and Equipment and of the Contractor‟s
Equipment, the point and means of dispatch, and the estimated time
and point of arrival in the country where the Site is located, if
applicable, and at the Site. The Contractor shall furnish the Employer
with relevant shipping documents to be agreed upon between the
parties.
Upon shipment, the Contractor shall notify the Employer with full
details of the dispatch and shall furnish the documents as specified
in the corresponding Appendix - 1 (Terms and Procedures of
Payment) to the Contract Agreement
17.4.2.2 The packing, marking and documentation within and outside the
packages shall comply strictly with such special requirements as
shall be expressly provided for in the Contract and, subject to any
subsequent instruction ordered by the Employer consistent with the
requirements of the Contract.
18. Installation
18.1.1 Bench Mark: The Contractor shall be responsible for the true and
proper setting-out of the Facilities in relation to bench marks,
reference marks and lines provided to it in writing by or on behalf of
the Employer.
If, at any time during the progress of installation of the Facilities, any
error shall appear in the position, level or alignment of the Facilities,
the Contractor shall forthwith notify the Project Manager of such
error and, at its own expense, immediately rectify such error to the
reasonable satisfaction of the Project Manager. If such error is based
on incorrect data provided in writing by or on behalf of the
Employer, the expense of rectifying the same shall be borne by the
Employer.
(a) The Contractor shall provide and employ on the Site in the
installation of the Facilities such skilled, semi-skilled and
unskilled labor as is necessary for the proper and timely
execution of the Contract. The Contractor is encouraged to use
local labor preferably from weaker sections of society
particularly SC & ST persons, that has the necessary skills.
(c) The Contractor shall at all times during the progress of the
Contract use its best endeavors to prevent any unlawful, riotous
or disorderly conduct or behavior by or amongst its employees
and the labor of its Subcontractors.
(d) The Contractor shall, in all dealings with its labor and the labor
of its Subcontractors currently employed on or connected with
the Contract, pay due regard to all recognized festivals, official
holidays, religious or other customs and all local laws and
regulations pertaining to the employment of labor.
18.2.1 All Contractor‟s Equipment brought by the Contractor onto the Site
shall be deemed to be intended to be used exclusively for the
execution of the Contract. The Contractor shall not remove the same
from the Site without the Project Manager‟s consent that such
Contractor‟s Equipment is no longer required for the execution of the
Contract.
18.2.3 The Employer will, if requested, use its best endeavors to assist the
Contractor in obtaining any local, state or national government
permission required by the Contractor for the export of the
Contractor‟s Equipment imported by the Contractor for use in the
execution of the Contract that is no longer required for the execution
of the Contract.
Section – IV: General Conditions of Contract Page 33
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
18.3 Site Regulations and Safety
Such Site regulations shall include, but shall not be limited to, rules
in respect of security, safety of the Facilities, gate control, sanitation,
medical care, and fire prevention.
18.3.1.1 During continuance of the contract, the Contractor and his sub-
contractors shall abide at all times by all applicable existing labour
enactments and rules made thereunder, regulations notifications and
byelaws of the State or Central Government or local authority and
any other labour law (including rules), regulations bye laws that may
be passed or notification that may be issued under any labour law in
future either by the State or the Central Government or the local
authority. The employees of the Contractor and the Sub-contractor in
no case shall be treated as the employees of the Employer at any
point of time.
18.3.1.2 The Contractor shall keep the Employer indemnified in case any
action is taken against the Employer by the competent authority on
account of contravention of any of the provisions of any Act or rules
made thereunder, regulations or notifications including
amendments.
(c) Employee P.F. and Miscellaneous Provision Act 1952: The Act
provides for monthly contribution by the employer plus
workers @10% or 8.33%. The benefits under the Act are:
(i) Pension or family pension on retirement or death, as the
case may be.
(ii) Deposit linked insurance on death in harness of the
worker.
(iii) Payment of P.F. accumulation on retirement/death etc.
(d) Maternity Benefit Act 1951: The Act provides for leave and
some other benefits to women employees in case of confinement
or miscarriage etc.
(e) Contract Labour (Regulation & Abolition) Act 1970: The Act
provides for certain welfare measures to be provided by the
Contractor to contract labour and in case the Contractor fails to
provide, the same are required to be provided, by the Principal
Employer by law. The Principal Employer is required to take
Certification of Registration and the Contractor is required to
(g) Payment of Wages Act 1936: It lays down as to by what date the
wages are to be paid, when it will be paid and what deductions
can be made from the wages of the workers.
(h) Equal Remuneration Act 1979: The Act provides for payment of
equal wages for work of equal nature to Male and Female
workers and for not making discrimination against Female
employees in the matters of transfers, training and promotions
etc.
(i) Payment of Bonus Act 1965: The Act is applicable to all
establishments employing 20 or more employees. The Act
provides for payments of annual bonus subject to a minimum of
8.33% of wages and maximum of 20% of wages to employees
drawing Rs. 3500/- per month or less. The bonus is to be paid to
employees getting Rs. 2500/- per month or above upto Rs.
3500/- per month shall be worked out by taking wages as Rs.
2500/- per month only. The Act does not apply to certain
establishments. The newly set-up establishments are exempted
for five years in certain circumstances. Some of the State
Governments have reduced the employment size from 20 to 10
for the purpose of applicability of this Act.
(j) Industrial Dispute Act 1947: the Act lays down the machinery
the procedure for resolution of Industrial disputes, in what
situations a strike or lock-out becomes illegal and what are the
requirements for laying off or retrenching the employees or
closing down the establishment.
(m) Child Labour (Prohibition & Regulation) Act 1986: The Act
prohibits employment of children below 14 years of age in
certain occupations and processes and provides for regulation
of employment of children in all other occupations and
processes. Employment of Child Labour is prohibited in
Building and Construction Industry.
(p) Factories Act 1948: The Act lays down the procedure for
approval at plans before setting up a factory, health and safety
provisions, welfare provisions, working hours, annual earned
leave and rendering information regarding accidents or
dangerous occurrences to designated authorities. It is applicable
to premises employing 10 persons or more with aid of power or
20 or more persons without the aid of power engaged in
manufacturing process.
Section – IV: General Conditions of Contract Page 37
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
18.3.2 Protection of Environment
Salient features of some of the major laws that are applicable are
given below:
The Public Liability Insurance Act, 1991, This provides for public
liability insurance for the purpose of providing immediate relief to
the persons affected by accident occurring while handling hazardous
substances and for matters connected herewith or incidental thereto.
Hazardous substance means any substance or preparation which is
defined as hazardous substance under Environment (Protection) Act,
1986, and exceeding such quantity as may be specified by notification
by the Central Government.
(iv) The Contractor shall conduct health and safety programme for
workers employed under the Contract and shall include
information on the risk of sexually transmitted diseases,
including HIV/AIDS in such programs.
18.3.3.2 The Contractor shall ensure proper safety of all the workmen,
materials, plant and equipment belonging to him or to Employer or
to others, working at the Site. The Contractor shall also be
responsible for provision of all safety notices and safety equipment
required both by the relevant legislations and the Project Manager, as
he may deem necessary.
18.3.3.3 The Contractor will notify well in advance to the Project Manager of
his intention to bring to the Site any container filled with liquid or
gaseous fuel or explosive or petroleum substance or such chemicals
which may involve hazards. The Project Manager shall have the
right to prescribe the conditions, under which such container is to be
stored, handled and used during the performance of the works and
the Contractor shall strictly adhere to and comply with such
instructions. The Project Manager shall have the right at his sole
discretion to inspect any such container or such construction
plant/equipment for which material in the container is required to be
used and if in his opinion, its use is not safe, he may forbid its use.
No claim due to such prohibition shall be entertained by the
Employer and the Employer shall not entertain any claim of the
Contractor towards additional safety provisions/conditions to be
provided for/constructed as per the Project Manager‟s instructions.
Further, any such decision of the Project Manager shall not, in any
way, absolve the Contractor of his responsibilities and in case, use of
such a container or entry thereof into the Site area is forbidden by the
Project Manager, the Contractor shall use alternative methods with
the approval of the Project Manager without any cost implication to
the Employer or extension of work schedule.
18.3.3.7 The Contractor shall be fully responsible for the safe storage of his
and his Sub-Contractor‟s radioactive sources in accordance with
BARC/DAE Rules and other applicable provisions. All
precautionary measures stipulated by BARC/DAE in connection
with use, storage and handling of such material will be taken by the
Contractor.
18.3.3.9 Where explosives are to be used, the same shall be used under the
direct control and supervision of an expert, experienced, qualified
and competent person strictly in accordance with the Code of
Practice/Rules framed under Indian Explosives Act pertaining to
handling, storage and use of explosives.
18.3.3.10 The Contractor shall provide safe working conditions to all workmen
and employees at the Site including safe means of access, railings,
stairs, ladders, scaffoldings etc. The scaffoldings shall be erected
under the control and supervision of an experienced and competent
person. For erection, good and standard quality of material only
shall be used by the Contractor.
18.3.3.12 Before the Contractor connects any electrical appliances to any plug
or socket belonging to the other Contractor or Employer, he shall:
18.3.3.15 No repair work shall be carried out on any live equipment. The
equipment must be declared safe by the Project Manager and a
permit to work shall be issued by the Project Manager before any
repair work is carried out by the Contractor. While working on
electric lines/equipment, whether live or dead, suitable type and
sufficient quantity of tools will have to he provided by the
Contractor to electricians/workmen/officers.
The Contractor shall deploy one dedicated Safety Staff(s) for every
200 kms of a Transmission Line Project.
The name and address of such Safety Officers of the Contractor will
be promptly informed in writing to Project Manager with a copy to
Safety Officer-In charge before he starts work or immediately after
any change of the incumbent is made during currency of the
Contract.
18.3.3.19 The Project Manager shall have the right at his sole discretion to stop
the work, if in his opinion the work is being carried out in such a
way that it may cause accidents and endanger the safety of the
Section – IV: General Conditions of Contract Page 43
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
persons and/or property, and/or equipment. In such cases, the
Contractor shall be informed in writing about the nature of hazards
and possible injury/accident and he shall comply to remove
shortcomings promptly. The Contractor after stopping the specific
work can, if felt necessary, appeal against the order of stoppage of
work to the Project Manager within 3 days of such stoppage of work
and decision of the Project Manager in this respect shall be
conclusive and binding on the Contractor.
Safety Rules
18.3.3.22 The Contractor shall follow and comply with all Employer Safety
Rules, relevant provisions of applicable laws pertaining to the safety
of workmen, employees, plant and equipment as may be prescribed
from time to time without any demur, protest or contest or
reservations. In case of any discrepancy between statutory
requirement and Employer Safety Rules referred above, the latter
shall be binding on the Contractor unless the statutory provisions are
more stringent.
18.3.3.24 If the Contractor does not take adequate safety precautions and/or
fails to comply with the Safety Rules as prescribed by the Employer
or under the applicable law for the safety of the equipment and plant
or for the safety of personnel or the Contractor does not prevent
Section – IV: General Conditions of Contract Page 45
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
hazardous conditions which cause injury to his own employees or
employees of other Contractors or Employer‟s employees or any
other person who are at Site or adjacent thereto, then the Contractor
shall be responsible for payment of a sum as indicated below to be
deposited with the Employer, which will be passed on by the
Employer to such person or next to kith and kin of the deceased:
18.3.3.26 The amount paid/ recovered from the Contractor on account of non-
compliance to Safety measures shall be deposited in the „Safety
Corpus Fund‟, if not specified otherwise, established by the
Employer. The „Safety Corpus Fund‟ shall be used for augmentation
of Safety measures in construction works, capacity building of
workers, development of working conditions of workers like
providing tents/ mobile toilets/ caravans, safety tools & plants etc.
and undertaking such other activities which will facilitate in
reducing the accidents. However, the Contractor shall have no claim
in this regard and the Employer shall be sole judge in this regard.
18.3.3.27 If the Contractor observes all the Safety Rules and Codes, Statutory
Laws and Rules during the currency of Contract awarded by the
Employer and no accident occurs then Employer may consider the
performance of the Contractor and award suitable „ACCIDENT
FREE SAFETY MERITORIOUS AWARD‟ as per scheme as may be
announced separately from time to time.
18.3.3.28 The Contractor shall also submit „Safety Plan‟ as per proforma
specified in Section – Sample Forms and Procedures of the Bidding
Documents alongwith all the requisite documents mentioned
therein and as per check-list contained therein to the Engineer In-
Charge for its approval within 60 days of award of Contract.
18.4.1 The Contractor shall, upon written request from the Employer or the
Project Manager, give all reasonable opportunities for carrying out
the work to any other contractors employed by the Employer on or
near the Site.
18.4.2 If the Contractor, upon written request from the Employer or the
Project Manager, makes available to other contractors any roads or
ways the maintenance for which the Contractor is responsible,
permits the use by such other contractors of the Contractor‟s
Equipment, or provides any other service of whatsoever nature for
such other contractors, the Employer shall fully compensate the
Contractor for any loss or damage caused or occasioned by such
other contractors in respect of any such use or service, and shall pay
to the Contractor reasonable remuneration for the use of such
equipment or the provision of such services.
18.4.4 The Contractor shall notify the Project Manager promptly of any
defects in the other contractors‟ work that come to its notice, and that
could affect the Contractor‟s work. The Project Manager shall
determine the corrective measures, if any, required to rectify the
situation after inspection of the Facilities. Decisions made by the
Project Manager shall be binding on the Contractor.
The Contractor shall provide and maintain at its own expense all
lighting, fencing, and watching when and where necessary for the
proper execution and the protection of the Facilities, or for the safety
of the owners and occupiers of adjacent property and for the safety
of the public.
19.1 The Contractor shall at its own expense carry out at the place of
manufacture and/or on the Site all such tests and/or inspections of
the Plant and Equipment and any part of the Facilities as are
specified in the Contract.
19.3 Whenever the Contractor is ready to carry out any such test and/or
inspection, the Contractor shall give four weeks advance notice of
such test and/or inspection and of the place and time thereof to the
Project Manager. The Contractor shall obtain from any relevant third
party or manufacturer any necessary permission or consent to enable
the Employer and the Project Manager (or their designated
representatives) to attend the test and/or inspection.
19.4 The Contractor shall provide the Project Manager with a certified
report of the results of any such test and/or inspection.
19.5 The Project Manager may require the Contractor to carry out any test
and/or inspection not required by the Contract, provided that the
Contractor‟s reasonable costs and expenses incurred in the carrying
out of such test and/or inspection shall be added to the Contract
Price. Further, if such test and/or inspection impedes the progress of
work on the Facilities and/or the Contractor‟s performance of its
other obligations under the Contract, due allowance will be made in
respect of the Time for Completion and the other obligations so
affected.
19.6 If any Plant and Equipment or any part of the Facilities fails to pass
any test and/or inspection, the Contractor shall either rectify or
replace such Plant and Equipment or part of the Facilities and shall
repeat the test and/or inspection upon giving a notice under GCC
Sub-Clause 19.3.
Section – IV: General Conditions of Contract Page 50
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
19.7 If any dispute or difference of opinion shall arise between the parties
in connection with or arising out of the test and/or inspection of the
Plant and Equipment or part of the Facilities that cannot be settled
between the parties within a reasonable period of time, it may be
referred to an Arbitrator for determination in accordance with GCC
Sub-Clause 39.
19.8 The Contractor shall afford the Employer and the Project Manager, at
the Employer‟s expense, access at any reasonable time to any place
where the Plant and Equipment are being manufactured or the
Facilities are being installed, in order to inspect the progress and the
manner of manufacture or installation, provided that the Project
Manager shall give the Contractor a reasonable prior notice.
19.9 The Contractor agrees that neither the execution of a test and/or
inspection of Plant and Equipment or any part of the Facilities, nor
the attendance by the Employer or the Project Manager, nor the issue
of any test certificate pursuant to GCC Sub-Clause 19.4, shall release
the Contractor from any other responsibilities under the Contract.
19.10 No part of the Facilities or foundations shall be covered up on the
Site without the Contractor carrying out any test and/or inspection
required under the Contract. The Contractor shall give a reasonable
notice to the Project Manager whenever any such part of the
Facilities or foundations are ready or about to be ready for test
and/or inspection; such test and/or inspection and notice thereof
shall be subject to the requirements of the Contract.
20.1.1.1 As soon as the Facilities or any part thereof has, in the opinion of the
Contractor, been completed operationally and structurally and put in
a tight and clean condition as specified in the Technical
Specifications, excluding minor items not materially affecting the
operation or safety of the Facilities, the Contractor shall so notify the
Employer in writing.
20.1.2 Pre-Commissioning
20.1.2.1 Within seven (7) days after receipt of the notice from the Contractor
under GCC Sub-Clause 20.1.1.1, the Project Manager shall deploy the
operating and maintenance personnel and other material if so
specified in the corresponding Appendix – 6 (Scope of Works and
Supply by the Employer) to the Contract Agreement for
Precommissioning of the Facilities or any part thereof.
20.1.2.4 The Project Manager shall, within fourteen (14) days after receipt of
the Contractor‟s notice under GCC Sub-Clause 20.1.2.3, notify the
Contractor in writing of any defects and/or deficiencies.
20.1.2.5 If the Project Manager notifies the Contractor of any defects and/or
deficiencies, the Contractor shall then correct such defects and/or
deficiencies, and shall repeat the procedure described in GCC Sub-
Clause 20.1.2.2. If in the opinion of the Contractor, the Facilities or
any part thereof is now ready for Commissioning, the Contractor
shall again notify the Project Manager in writing. If further defects
and/or deficiencies are not notified by the Project Manager and if the
Section – IV: General Conditions of Contract Page 52
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
Project Manager is satisfied that the Precommissioning of Facilities or
that part thereof have been successfully completed, the Project
Manager shall, within seven (7) days after receipt of the Contractor‟s
such notice, advise the Contractor to proceed with the
Commissioning of the Facilities or part thereof.
20.1.2.6 If the Project Manager fails to inform the Contractor of any defects
and/or deficiencies within fourteen (14) days after receipt of the
Contractor‟s notice under GCC Sub-Clause 20.1.2.4 or within seven
(7) days after receipt of the Contractor‟s notice on completion of
repeat procedure under GCC Sub-Clause 20.1.2.5, then the
Precommissioning of the Facilities or that part thereof shall be
considered to have been successfully completed as of the date of the
Contractor‟s notice.
20.1.2.8 In the event that the Contractor is unable to proceed with the
Precommissioning of the Facilities pursuant to Sub-Clause 20.1.2 for
reasons attributable to the Employer either on account of non-
availability of other facilities under the responsibilities of other
contractor(s), or for reasons beyond the Employer's control, the
following provisions shall apply:
20.1.2.9 In the event that the period of suspension under GCC Sub-Clause
20.1.2.8 actually exceeds one hundred eighty (180) days, the
Employer and the Contractor shall mutually agree to any additional
compensation payable to the Contractor.
20.1.2.10 As and when, after the period of suspension under GCC Sub-Clause
20.1.2.8, the Contractor is notified by the Project Manager that the
Facilities are ready for Precommissioning, the Contractor shall
proceed without delay in performing all activities and obligations
under the Contract.
20.1.3 Commissioning
20.1.3.4 As and when, after the period of suspension under GCC Sub-Clause
20.1.2.8, the Contractor is notified by the Project Manager that the
Facilities are ready for Commissioning, the Contractor shall proceed
without delay in performing all activities and obligations under the
Contract.
20.1.4.3 At any time after the events set out in GCC Sub-Clause 20.1.4.2 have
occurred, the Contractor may give a notice to the Project Manager
requesting the issue of an Taking Over Certificate in the form
provided in the Bidding Documents or in another form acceptable to
the Employer in respect of the Facilities or the part thereof specified
in such notice as of the date of such notice.
20.1.4.4 The Project Manager shall within twenty-one (21) days after receipt
of the Contractor's notice, issue an Taking Over Certificate.
20.1.5.3 Upon Taking Over of the Facilities or any part thereof, the Employer
shall be responsible for the care and custody of the Facilities or the
relevant part thereof, together with the risk of loss or damage
thereto, and shall thereafter take over the Facilities or the relevant
part thereof.
20.2.1.1 The Guarantee Test (and repeats thereof), if any specified in the SCC
and/or the Technical Specification, shall be conducted by the
Contractor after successful Trial – Operation of the Facilities or the
relevant part thereof to ascertain whether the Facilities or the
relevant part can attain the Functional Guarantees specified in the
Contract Documents or if otherwise required as per the Technical
Specifications. The Contractor's and Project Manager's advisory
personnel may witness the Guarantee Test. The Contractor shall
promptly provide the Employer with such information as the
Employer may reasonably require in relation to the conduct and
results of the Guarantee Test (and any repeats thereof).
20.2.1.2 If for reasons not attributable to the Contractor, the Guarantee Test of
the Facilities or the relevant part thereof cannot be successfully
completed within the time stipulated in the Technical Specifications
the period for completing the same shall be as agreed upon by the
Employer and the Contractor.
20.2.2.2 At any time after any of the events set out in GCC Sub-Clause
20.2.2.1 have occurred, the Contractor may give a notice to the
Project Manager requesting the issue of an Operational Acceptance
Certificate in the form provided in the Bidding Documents or in
another form acceptable to the Employer in respect of the Facilities or
the part thereof specified in such notice as of the date of such notice.
20.2.2.3 The Project Manager shall within twenty-one (21) days after receipt
of the Contractor's notice, issue an Operational Acceptance
Certificate.
20.2.2.5 If within twenty one (21) days after receipt of the Contractor's notice,
the Project Manager fails to issue the Operational Acceptance
Certificate or fails to inform the Contractor in writing of the
justifiable reasons why the Project Manager has not issued the
Operational Acceptance Certificate, the Facilities or the relevant part
thereof shall be deemed to have been accepted as at the date of the
Contractor's said notice.
21.2 If the Contractor fails to comply with the Time for Completion in
accordance with Clause GCC 21 for the whole of the facilities, (or a
part for which a separate time for completion is agreed) then the
Contractor shall pay to the Employer a sum equivalent to half
percent (0.5%) of the Contract Price plus GST payable thereon for the
whole of the facilities, (or a part for which a separate time for
completion is agreed) as liquidated damages for such default and not
as a penalty, without prejudice to the Employer's other remedies
under the Contract, for each week or part thereof which shall elapse
between the relevant Time for Completion and the date stated in
Taking Over Certificate of the whole of the Works (or a part for
which a separate time for completion is agreed) subject to the limit of
five percent (5%) of Contract Price plus GST payable thereon for the
whole of the facilities, (or a part for which a separate time for
completion is agreed). The Employer may, without prejudice to any
other method of recovery, deduct the amount of such damages from
any monies due or to become due to the Contractor. The payment or
deduction of such damages shall not relieve the Contractor from his
obligation to complete the Works, or from any other of his
obligations and liabilities under the Contract.
21.3 No bonus will be given for earlier Completion of the Facilities or part
thereof.
22.1 The Contractor warrants that the Facilities or any part thereof shall
be free from defects in the design, engineering, materials and
workmanship of the Plant and Equipment supplied and of the work
executed.
22.2 Unless otherwise specified in SCC, the Defect Liability Period shall be
twelve (12) months from the date of Taking Over /Completion of
Facilities (or any part thereof).
22.3 The Contractor‟s obligations under this GCC Clause 22 shall not
apply to
(a) any materials that are supplied by the Employer under GCC
Sub-Clause 17.2, are normally consumed in operation, or have a
normal life shorter than the Defect Liability Period stated herein
22.4 The Employer shall give the Contractor a notice stating the nature of
any such defect together with all available evidence thereof,
promptly following the discovery thereof. The Employer shall afford
all reasonable opportunity for the Contractor to inspect any such
defect.
22.5 The Employer shall afford the Contractor all necessary access to the
Facilities and the Site to enable the Contractor to perform its
obligations under this GCC Clause 22. The Contractor may, with the
consent of the Employer, remove from the Site any Plant and
Equipment or any part of the Facilities that are defective if the nature
of the defect, and/or any damage to the Facilities caused by the
defect, is such that repairs cannot be expeditiously carried out at the
Site.
If such part fails the tests, the Contractor shall carry out further
repair, replacement or making good (as the case may be) until that
part of the Facilities passes such tests.
22.8 If the Facilities or any part thereof cannot be used by reason of such
defect and/or making good of such defect, the Defect Liability
Period of the Facilities or such part, as the case may be, shall be
extended by a period equal to the period during which the Facilities
or such part cannot be used by the Employer because of any of the
aforesaid reasons.
22.8.1 At the end of the Defect Liability Period, the Contractor's Liability
ceases except for latent defects. The Contractor's liability for latent
defects warranty shall be limited to period of ten (10) years from the
end of Defect Liability Period. For the purpose of this clause, the
latent defects shall be the defects inherently lying within the material
or arising out of design deficiency, which do not manifest themselves
during the Defect Liability Period defined in this GCC Clause 22, but
later.
22.9 Except as provided in GCC Clauses 22 and 29, the Contractor shall be
under no liability whatsoever and howsoever arising, and whether
under the Contract or at law, in respect of defects in the Facilities or
Section – IV: General Conditions of Contract Page 60
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
any part thereof, the Plant and Equipment, design or engineering or
work executed that appear after Defect Liability Period except for the
liability towards obligations that may survive in terms of the
Contract after Defect Liability Period, except where such defects are
the result of the gross negligence, fraud, criminal or willful action of
the Contractor.
23.1 The Contractor guarantees that the Facilities and all parts thereof
shall attain the Functional Guarantees specified in the Technical
Specifications, subject to and upon the conditions therein specified.
23.2 If, for reasons attributable to the Contractor, the minimum level of
the Functional Guarantees specified in the Technical Specifications
are not met either in whole or in part, the Contractor shall at its cost
and expense make such changes, modifications and/or additions to
the Plant or any part thereof as may be necessary to meet at least the
minimum level of such Guarantees. The Contractor shall notify the
Employer upon completion of the necessary changes, modifications
and / or additions, and shall request the Employer to repeat the
Guarantee Test until the minimum level of the Guarantees has been
met. If the Contractor eventually fails to meet the minimum level of
Functional Guarantees, the Employer may consider termination of
the Contract pursuant to GCC Sub-Clause 36.2.2 and recover the
payments already made to the Contractor.
23.4 In case the Employer exercises its option to accept the equipment
after levy of liquidated damages, the payment of liquidated damages
under GCC Sub-Clause 23.3, upto the limitation of liability specified
Section – IV: General Conditions of Contract Page 61
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
in the SCC, shall completely satisfy the Contractor‟s guarantees
under GCC Sub-Clause 23.3, and the Contractor shall have no further
liability whatsoever to the Employer in respect thereof. Upon the
payment of such liquidated damages by the Contractor, the Project
Manager shall issue the Operational Acceptance Certificate for the
Facilities or any part thereof in respect of which the liquidated
damages have been so paid.
24.1 The Contractor guarantees that the Equipments, named in the SCC,
shall attain the rating and performance requirements specified in
Appendix – 8 (Guarantees, Liquidated Damages for Non –
Performance) to the Contract Agreement, subject to and upon the
conditions therein specified.
24.3 In case the Employer exercises its option to reject the equipment, the
Contractor shall at its cost and expense make such changes,
modifications and/or additions to the equipment or any part thereof
as may be necessary to meet the specified guarantees. The Contractor
shall notify the Employer upon completion of the necessary changes,
modifications and/or additions, and shall request the Employer to
repeat the Test until the level of the specified guarantee has been
met.
24.4 Whenever the Employer exercises its option to accept the equipment
after levy of liquidated damages, the payment of liquidated damages
under GCC Sub-Clause 24.2, upto the limitation of liability specified
in the SCC, shall completely satisfy the Contractor‟s guarantees
under GCC Sub-Clause 24.2, and the Contractor shall have no further
liability whatsoever to the Employer in respect thereof.
25.1 The Contractor shall, subject to the Employer‟s compliance with GCC
Sub-Clause 25.2, indemnify and hold harmless the Employer and its
employees and officers from and against any and all suits, actions or
administrative proceedings, claims, demands, losses, damages, costs,
and expenses of whatsoever nature, including attorney‟s fees and
expenses, which the Employer may suffer as a result of any
infringement or alleged infringement of any patent, utility model,
registered design, trademark, copyright or other intellectual property
right registered or otherwise existing at the date of the Contract by
reason of: (a) the installation of the Facilities by the Contractor or the
use of the Facilities in the country where the Site is located; and (b)
the sale of the products produced by the Facilities in any country.
Such indemnity shall not cover any use of the Facilities or any part
thereof other than for the purpose indicated by or to be reasonably
inferred from the Contract, any infringement resulting from the use
of the Facilities or any part thereof, or any products produced
thereby in association or combination with any other equipment,
plant or materials not supplied by the Contractor, pursuant to the
Contract Agreement.
25.2 If any proceedings are brought or any claim is made against the
Employer arising out of the matters referred to in GCC Sub-Clause
25.1, the Employer shall promptly give the Contractor a notice
thereof, and the Contractor may at its own expense and in the
Employer‟s name conduct such proceedings or claim and any
negotiations for the settlement of any such proceedings or claim. If
the Contractor fails to notify the Employer within twenty-eight (28)
days after receipt of such notice that it intends to conduct any such
proceedings or claim, then the Employer shall be free to conduct the
same on its own behalf. Unless the Contractor has so failed to notify
the Employer within the twenty-eight (28) day period, the Employer
shall make no admission that may be prejudicial to the defense of
any such proceedings or claim.
25.3 The Employer shall indemnify and hold harmless the Contractor and
its employees, officers and Subcontractors from and against any and
all suits, actions or administrative proceedings, claims, demands,
losses, damages, costs, and expenses of whatsoever nature, including
Section – IV: General Conditions of Contract Page 63
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
attorney‟s fees and expenses, which the Contractor may suffer as a
result of any infringement or alleged infringement of any patent,
utility model, registered design, trademark, copyright or other
intellectual property right registered or otherwise existing at the date
of the Contract arising out of or in connection with any design, data,
drawing, specification, or other documents or materials provided or
designed by or on behalf of the Employer.
(a) the Contractor and the Employer shall not be liable to the other
party for any indirect or consequential loss or damage, loss of
use, loss of production, or loss of profits or interest costs,
provided that this exclusion shall not apply to any obligation of
the Contractor to pay liquidated damages to the Employer and
G. Risk Distribution
28.1 The Contractor shall be responsible for the care and custody of the
Facilities or any part thereof until the date of Taking Over Certificate
pursuant to GCC Clause 20 or, where the Contract provides for
Completion of the Facilities in parts, until the date of Completion of
the relevant part, and shall make good at its own cost any loss or
damage that may occur to the Facilities or the relevant part thereof
from any cause whatsoever during such period. The Contractor shall
also be responsible for any loss or damage to the Facilities caused by
the Contractor or its Subcontractors in the course of any work carried
out, pursuant to GCC Clause 22. Notwithstanding the foregoing, the
Contractor shall not be liable for any loss or damage to the Facilities
or that part thereof caused by any use or occupation by the Employer
or any third party (other than a Subcontractor) authorized by the
Employer of any part of the Facilities.
29.1 The Contractor shall indemnify and hold harmless the Employer and
its employees and officers from and against any and all suits, actions
or administrative proceedings, claims, demands, losses, damages,
costs, and expenses of whatsoever nature, including attorney‟s fees
and expenses, in respect of the death or injury of any person or loss
of or damage to any property (other than the Facilities whether
accepted or not), arising in connection with the supply and
installation of the Facilities and by reason of the negligence of the
Section – IV: General Conditions of Contract Page 65
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
Contractor or its Subcontractors, or their employees, officers or
agents, except any injury, death or property damage caused by the
negligence of the Employer, its contractors, employees, officers or
agents.
29.2 If any proceedings are brought or any claim is made against the
Employer that might subject the Contractor to liability under GCC
Sub-Clause 29.1, the Employer shall promptly give the Contractor a
notice thereof and the Contractor may at its own expense and in the
Employer‟s name conduct such proceedings or claim and any
negotiations for the settlement of any such proceedings or claim.
30. Insurance
(II) The Contractor shall take the policy in the joint name of
Employer and the Contractor. All these policies shall
indicate Employer as the beneficiary. The policy shall be
kept valid till the date of the Operational Acceptance of
the project and the period of the coverage shall be
determined with the approval of the Employer.
i) Earthquake
ii) Terrorism
iii) Escalation cost (approximately @10% of sum
insured on annual basis)
iv) Extended Maintenance cover for Defect Liability
Period
v) Design Defect
vi) Other add-on covers viz., 50-50 clause, 72 hours
clause, loss minimization clause, waiver of
subrogation clause (for projects of more than 100
Section – IV: General Conditions of Contract Page 68
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
crores, cover for offsite storage/fabrication (over
100 crores).
The Contractor shall ensure that all the vehicles deployed by the
Contractor or its Subcontractors (whether or not owned by
them) in connection with the supply and installation of the
Facilities in the project are duly insured as per RTA act. Further
Section – IV: General Conditions of Contract Page 69
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
the Contractor or its Subcontractors may also take
comprehensive policy (own damage plus third party liability) of
each individual vehicles deployed in the project on their own
discretion in their own name to protect their own interest.
(II) The policy may either be project specific covering all men
of the Contractor and its Subcontractors. The policy shall
be kept valid till the date of Operational Acceptance of
the project.
30.5 The Employer shall at its expense take out and maintain in effect
during the performance of the Contract those insurances specified in
the corresponding Appendix – 3 (Insurance Requirements) to the
Contract Agreement, in the sums and with the deductibles and other
conditions specified in the said Appendix. The Contractor and the
Contractor‟s Subcontractors shall be named as co-insureds under all
such policies. All insurers‟ rights of subrogation against such co-
insureds for losses or claims arising out of the performance of the
Contract shall be waived under such policies. The Employer shall
deliver to the Contractor satisfactory evidence that the required
insurances are in full force and effect. The policies shall provide that
not less than twenty-one (21) days‟ notice shall be given to the
Contractor by all insurers prior to any cancellation or material
modification of the policies. If so requested by the Contractor, the
30.6 If the Contractor fails to take out and/or maintain in effect the
insurances referred to in GCC Sub-Clause 30.1, the Employer may
take out and maintain in effect any such insurances and may from
time to time deduct from any amount due the Contractor under the
Contract any premium that the Employer shall have paid to the
insurer, or may otherwise recover such amount as a debt due from
the Contractor. If the Employer fails to take out and/or maintain in
effect the insurances referred to in GCC 30.5, the Contractor may take
out and maintain in effect any such insurances and may from time to
time deduct from any amount due the Employer under the Contract
any premium that the Contractor shall have paid to the insurer, or
may otherwise recover such amount as a debt due from the
Employer.
30.8 Further all equipment and materials being supplied by Employer for
the erection (as per Technical Specification) shall be kept insured by
the Contractor against any loss, damage, pilferage, theft, fire, etc.
from the point of unloading up to the time of taking over by
Employer including handling, transportation, storage, erection,
testing and commissioning etc. The premium paid to the Insurance
company by the Contractor for such insurance shall be reimbursed
by Employer to the Contractor. The Contractor shall obtain
competitive quotation for such insurance and shall take prior
approval from Employer before taking the insurance. The insurable
Section – IV: General Conditions of Contract Page 72
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
value of the equipment being supplied by Employer shall be
intimated to the Contractor for arranging the insurance.
31.1 If, after the date seven (07) days prior to the date of Bid Opening, any
law, regulation, ordinance, order or by-law having the force of law is
enacted, promulgated, abrogated or changed in India (which shall be
deemed to include any change in interpretation or application by the
competent authorities) that subsequently affects the costs and
expenses of the Contractor and/or the Time for Completion, the
Contract Price shall be correspondingly increased or decreased,
and/or the Time for Completion shall be reasonably adjusted to the
extent that the Contractor has thereby been affected in the
performance of any of its obligations under the Contract. These
adjustments shall be applicable for all transactions between the
Employer and the Contractor for supply of goods and services under
the Contract but shall not be applicable on procurement of raw
materials, intermediary components etc. by the Contractor for which
the Employer shall be the sole judge. Notwithstanding the foregoing,
such additional or reduced costs shall not be separately paid or
credited if the same has already been accounted for in the price
adjustment provisions where applicable, in accordance with the
Appendix-2 to the Contract Agreement.
32.1 “Force Majeure” shall mean any event beyond the reasonable control
of the Employer or of the Contractor, as the case may be, and which
is unavoidable notwithstanding the reasonable care of the party
affected, and shall include, without limitation, the following:
32.4 The party who has given such notice shall be excused from the
performance or punctual performance of its obligations under the
Contract for so long as the relevant event of Force Majeure continues
and to the extent that such party‟s performance is prevented,
hindered or delayed. The Time for Completion shall be extended in
accordance with GCC Clause 34.
33.1.1 Subject to GCC Sub-Clauses 33.2.5 and 33.2.7, the Employer shall
have the right to propose, and subsequently require, that the Project
Manager order the Contractor from time to time during the
performance of the Contract to make any change, modification,
addition or deletion to, in or from the Facilities (hereinafter called
“Change”), provided that such Change falls within the general scope
of the Facilities and does not constitute unrelated work and that it is
technically practicable, taking into account both the state of
advancement of the Facilities and the technical compatibility of the
Change envisaged with the nature of the Facilities as specified in the
Contract.
33.1.2 The Contractor may from time to time during its performance of the
Contract propose to the Employer (with a copy to the Project
Manager) any Change that the Contractor considers necessary or
desirable to improve the quality, efficiency or safety of the Facilities.
The Employer may at its discretion approve or reject any Change
Section – IV: General Conditions of Contract Page 74
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
proposed by the Contractor, provided that the Employer shall
approve any Change proposed by the Contractor to ensure the safety
of the Facilities.
33.2.2 The Contract Price for (i) the items for which quantities have been
indicated as lumpsum or lot or set and/or (ii) where the quantities
are to be estimated by the Contractor shall remain constant unless
there is change made in the Scope of Work by Employer. The
quantities and unit prices (i) subsequently arrived while approving
the Bill of Quantities (BOQ)/Billing breakup of lumpsum
quantities/lot/Set and/or (ii) estimated by the Contractor shall be
for on account payment purpose only. In case additional quantities,
over and above the quantities in BOQ/billing breakup and /or
estimated by the Contractor, are required for successful completion
of the scope of work as per Technical Specification, the Contractor
shall execute additional quantities of these items for which no
additional payment shall be made over and above the lumpsum
Contract Price. In case quantities of these items supplied at site are in
excess of that required for successful completion of scope of work,
such additional quantities shall be the property of the Contractor and
they shall be allowed to take back the same from the site for which
no deduction from the lumpsum Contract Price shall be made.
Further, in case actual requirement of quantities for successful
completion of scope of work is less than the quantities identified in
the approved BOQ /billing breakup and/or estimated by the
Contractor, the lumpsum contract price shall remain unchanged and
no deduction shall be made from the lumpsum price due to such
reduction of quantities.
For the said purpose, the Contract Price means the Contract Price of
the Facilities notwithstanding the Construction of the Contract.
33.2.4 If rates and prices of any change are not available in the Contract, the
parties thereto shall agree on specific rates for the valuation of the
change and all matters therein related to the change. Based on the
same, the Employer shall, if it intends to proceed with the Change,
issue the Contractor with a Change Order.
33.2.5 The Employer shall issue the Contractor with a Change Order
pursuant to GCC Sub-Clause 33.2 by way of amendment to the
Contract or in any other manner deemed appropriate. Even if the
Employer and the Contractor cannot reach agreement on the price
for the Change, an equitable adjustment to the Time for Completion,
or any other matters related to the Change Proposal, the Employer
may nevertheless instruct the Contractor to proceed with the Change
Section – IV: General Conditions of Contract Page 76
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
by issue of a “Pending Agreement Change Order” (“Pending
Agreement Amendment”).
If the parties cannot reach agreement within sixty (60) days from the
date of issue of the Pending Agreement Change Order, then the
matter may be referred to the Arbitrator in accordance with the
provisions of GCC Clause 38 & 39.
Upon receipt of the Request for Change Proposal, the parties shall
follow the procedures outlined in GCC Sub-Clauses 33.2.1 and 33.2.5.
However, should the Employer choose not to proceed, the
Contractor shall not be entitled to recover the costs of preparing the
Request for Change Proposal.
34.1 The Time(s) for Completion specified in the SCC shall be extended if
the Contractor is delayed or impeded in the performance of any of its
obligations under the Contract by reason of any of the following:
(c) any suspension order given by the Employer under GCC Clause
35 hereof or reduction in the rate of progress pursuant to GCC
Sub-Clause 35.2 or
34.3 The Contractor shall at all times use its reasonable efforts to
minimize any delay in the performance of its obligations under the
Contract.
35. Suspension
35.1 The Employer may request the Project Manager, by notice to the
Contractor, to order the Contractor to suspend performance of any or
all of its obligations under the Contract. Such notice shall specify the
obligation of which performance is to be suspended, the effective
date of the suspension and the reasons therefor. The Contractor shall
thereupon suspend performance of such obligation (except those
obligations necessary for the care or preservation of the Facilities)
until ordered in writing to resume such performance by the Project
Manager.
36. Termination
36.1.1 The Employer may at any time terminate the Contract for any reason
by giving the Contractor a notice of termination that refers to this
GCC Sub-Clause 36.1.
(a) cease all further work, except for such work as the Employer
may specify in the notice of termination for the sole purpose of
protecting that part of the Facilities already executed, or any
work required to leave the Site in a clean and safe condition
(c) remove all Contractor‟s Equipment from the Site, repatriate the
Contractor‟s and its Subcontractors‟ personnel from the Site,
Section – IV: General Conditions of Contract Page 79
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
remove from the Site any wreckage, rubbish and debris of any
kind, and leave the whole of the Site in a clean and safe
condition
or
then the Employer may, without prejudice to any other rights it may
possess under the Contract, give a notice to the Contractor stating the
nature of the default and requiring the Contractor to remedy the
same. If the Contractor fails to remedy or to take steps to remedy the
same within fourteen (14) days of its receipt of such notice, then the
Employer may terminate the Contract forthwith by giving a notice of
termination to the Contractor that refers to this GCC Sub-Clause 36.2.
(a) cease all further work, except for such work as the Employer
may specify in the notice of termination for the sole purpose of
protecting that part of the Facilities already executed, or any
work required to leave the Site in a clean and safe condition
(d) to the extent legally possible, assign to the Employer all right,
title and benefit of the Contractor to the Facilities and to the
Plant and Equipment as of the date of termination, and, as may
be required by the Employer, in any subcontracts concluded
between the Contractor and its Subcontractors
36.2.4 The Employer may enter upon the Site, expel the Contractor, and
complete the Facilities itself or by employing any third party. The
Employer may, to the exclusion of any right of the Contractor over
the same, take over and use with the payment of a fair rental rate to
the Contractor, with all the maintenance costs to the account of the
Section – IV: General Conditions of Contract Page 83
Vol.-I/S&I/GCC-DCB/Rev 3 – June 2018
Employer and with an indemnification by the Employer for all
liability including damage or injury to persons arising out of the
Employer‟s use of such equipment, any Contractor‟s Equipment
owned by the Contractor and on the Site in connection with the
Facilities for such reasonable period as the Employer considers
expedient for the supply and installation of the Facilities.
36.2.6 If the Employer completes the Facilities, the cost of completing the
Facilities by the Employer shall be determined.
If such excess is greater than the sums due the Contractor under
GCC Sub-Clause 36.2.5, the Contractor shall pay the balance to the
Employer, and if such excess is less than the sums due the Contractor
under GCC Sub-Clause 36.2.5, the Employer shall pay the balance to
the Contractor. For facilitating such payment the Employer shall
encash the Bank Guarantees of the Contractor available with the
Employer and retain such other payments due to the Contractor
under the Contract in question or any other Contract that the
Employer may have with the Contractor.
36.3 In this GCC Clause 36, the expression “Facilities executed” shall
include all work executed, Installation Services provided, and all
Plant and Equipment acquired (or subject to a legally binding
obligation to purchase) by the Contractor and used or intended to be
used for the purpose of the Facilities, up to and including the date of
termination.
36.4 In this GCC Clause 36, in calculating any monies due from the
Employer to the Contractor, account shall be taken of any sum
previously paid by the Employer to the Contractor under the
Contract, including any advance payment paid pursuant to the
corresponding Appendix (Terms and Procedures of Payment) to the
Contract Agreement.
37. Assignment
37.1 Neither the Employer nor the Contractor shall, without the express
prior written consent of the other party (which consent shall not be
unreasonably withheld), assign to any third party the Contract or
any part thereof, or any right, benefit, obligation or interest therein or
thereunder.
I. Resolution of Disputes
38.1 If any dispute of any kind whatsoever shall arise between the
Employer and the Contractor in connection with or arising out of the
Contract, including without prejudice to the generality of the
foregoing, any question regarding its existence, validity or
termination, or the execution of the Facilities, whether during the
progress of the Facilities or after their completion and whether before
or after the termination, abandonment or breach of the Contract, the
parties shall seek to resolve any such dispute or difference, to the
extent possible, amicably by mutual consultation.
38.2.2 In the event the Project Manager fails to notify his decision as
aforesaid within thirty (30) days, the Contractor, if he intends to go
for Arbitration, shall notify his intention to the Project Manager
within 30 days of expiry of the first mentioned period of thirty days
failing which it shall be deemed that there are no dispute or
difference between the Employer and the Contractor.
39. Arbitration
Sole Arbitration
If the parties fail to appoint sole arbitrator within sixty (60) days after
receipt of a notice from the other party invoking Arbitration, the
appointment of sole arbitrator shall be done by Courts as per the
provisions of Indian Arbitration and Conciliation Act, 1996 or any
statutory modification thereof.
39.5 The decision of the sole arbitrator/ the majority of the arbitrators, as
the case may be, shall be final and binding upon the parties. In the
event of any of the sole arbitrator/ any of the aforesaid arbitrators
dying, neglecting, resigning or being unable to act for any reason, it
will be lawful for the parties to nominate another sole arbitrator/
another arbitrator in place of the outgoing arbitrator.
The following bid specific data shall amend and/or supplement the provisions in the
General Conditions of Contract (GCC)
12. GCC 2.14 Replacing Clause GCC 2.14 (Governing Law & its Jurisdiction)
22. GCC 5.1 Replacing GCC Clause 5.1 with the following:
The Contractor shall execute the ‘Outsourcing of O&M activities of
Transmission Lines associated with Firozabad cluster’ with due
care and diligence in accordance with the Contract.
23. GCC 5.5 Clause 5.5: Stands Deleted.
Terms of Payment:
Other Conditions:
2. The payment to the Contractor under the Contract
will be made by the owner/ Employer’ as per the guidelines
and conditions specified hereunder.
36. GCC 9.3.4 For this package bids from Joint Venture is not permitted.
Hence, clause 9.3.4 of GCC stands deleted.
37. Additional Add new sub Clause GCC 9.3.5
Clause GCC
9.3.5 No interest shall be payable by the Employer on the performance
Security.
38. Additional Adding New Sub-Clause GCC 9.3.6:
Clause 9.3.6 During execution of contract the Contractor, after submission of
Performance Security in form of a crossed bank draft/pay order
/banker certified cheque/ online payment may opt to furnish the
Performance Security in form of bank guarantee for the same
amount and as per same terms of the Contract. On acceptance by
the Employer/Employer of Performance Security submitted in the
form of Bank Guarantee following receipt of confirmation from the
issuing Bank, the said amount shall be refunded.
39. GCC 9.4 (b) Supplementing Sub-Clause GCC 9.4 (b) is replaced with the
following:
Note: Any one of the above account details can be used for the
issuance of Bank Guarantee using SFMS Platform.
52. GCC 18.3.1.4 18.3.1.4 Salient features of some major laws applicable to
establishments engaged in building and other construction works:
…………………..
53. GCC 18.3.1.4 Replace the para 18.3.1.4 (a) with the following:
(a)
(a) Employee’s Compensation Act 1923: The Act provides for
compensation in case of injury by accident arising out of and
during the course of employment.
54. GCC 18.3.3 Adding New Sub Clause GCC 18.3.3 as below:
Safety
1.4 If the contactor does not take adequate safety precautions and
/ or fails to comply with the safety rules as prescribed under
1 Maintenance In-
charge 4,000
2 Maintenance
Engineer 2,400
3 Diploma Engineer 2,000
4 Fitter/Electrician 1,400
65. GCC 30.1(b) Replace the existing Provision GCC 30.1(b) as below:
40.3 The Contractor shall indemnify the Employer, its officers and
employees from and against all actions, claims, demand, suits
and proceedings by the third party for the acts/omissions of
the Contractor and all costs, charges, expenses, losses,
damages, duties, taxes, penalties, levies, and all other
liabilities which the Employer may be liable to pay, incur or
sustain as a result of performance or non-performance,
observance or non-observance by the Contractor of any of the
terms and conditions of the Contract.
73. Add New The mechanism of Dispute resolution through Conciliation shall
Clause GCC: be available in cases where the amount involved in the dispute
Conciliation exceeds INR 1 Cr.
41.1
74. GCC 41.2 The settlement of Disputes through conciliation mechanism shall
be done by the Conciliation Committee of Independent Experts
(CCIE) constituted by Ministry of Power, Govt. of India as per the
procedure outlined in its OM dated 29.12.2021 as detailed herein
below and its subsequent amendments/modifications (if any).
75. GCC 41.2.1 Each member of CCIE would be paid a sum of Rs. 50,000/- as
sitting fee per sitting. In addition, Rs. 5,000/- per sitting will be
paid for local transport charges for each day of proceeding. The
conciliation proceedings shall be completed in each case through
5 sittings in a period of not more than three months from the date
the reference made to the CCIE. In exceptional cases, if any dispute
so merits, the time period may be extended at the discretion of
Conciliation Committee (with reasons to be recorded in writing),
for a further period of three months. In case, a particular dispute
requires more than 5 sittings, the same may be held at the
discretion of the CCIE but with a cap on payment of fee for 5
sittings only. The local transport charges shall, however, be paid
as provided for each day of sitting beyond the 5 sittings.
76. GCC 41.2.2 The CCIE shall hold day to day sitting at the Headquarter of the
Employer or New Delhi and may hold as many sittings every
month as it deems appropriate keeping in view the volume of
work.
77. GCC 41.2.3 All expenditure incurred on the conciliation proceedings
including payment of fees to the Conciliators, office space, logistic,
78. GCC 41.3 The procedure of CCIE shall not be treated as alternate arbitration
proceedings where both parties come with Statement of
claims/defence, arguments/counter arguments, rejoinders,
written submissions etc., aided by their respective lawyers. The
forum of CCIE is a conciliation forum, where mutual give and take
constitutes the essence, rather than strict legal positions of the
parties. Hence, the parties are expected to be brief and to the point
before the committee with regard to their respective stance and
view the exercise in the spirit of conciliation / settlement.
79. GCC 41.4 The Standard Operating Procedure for the conciliation mechanism
shall be as follows:
80. GCC 41.5 In cases of disputes pending before the Arbitration Tribunals or
the Courts, both of the parties (i.e. Employer and Contractor) need
to agree to explore the possibilities of conciliation through the
Conciliation Committee of Independent Experts. In case of such
agreement, an appropriate reference shall be made to the
Conciliation Committee, upon which the Committee shall proceed
to examine such reference(s). The option of resolution through
conciliation through CCIE would be open only in the event of the
parties withdrawing from arbitration proceedings and
undertaking to forego their rights to proceed for further arbitration
in the subject matter. However, other legal remedies would be
open to the parties in the event of the conciliation proceedings not
being successful.
81. GCC 41.6 During settlement of disputes and conciliation proceedings, both
parties shall be obliged to carry out their respective obligations
under the Contract.
Confidentiality:
The Contractor and its personnel deployed in the works under the subject contract shall
hold all information, data, material, instructions, communications, the terms &
conditions of business as strictly confidential, whether received in writing or oral form
from PESL. Any technical / business information that the Contractor’s employees
SAMPLE FORMS
((To be stamped in accordance with Stamp Act, the Non-Judicial Stamp Paper should be in the name of
the issuing Bank. For the purpose of verification/confirmation of this Bank Guarantee by the Employer,
the Bank shall indicate 2 official email ids of the authorized signatories from Issuing Branch and also of
the designated higher office (Corporate Office, Zonal Office etc)in the covering letter of the Bank
forwarding the Bank Guarantee.)
WHEREAS M/s. …. (Insert name of Bidder)…… having its Registered/Head Office at …..
(Insert address of the Bidder) ……….. (Hereinafter called "the Bidder" which expression shall
include its successors, administrators, executors and assigns) has submitted its Bid for the
performance of the Contract for ‘Outsourcing of O&M activities of Transmission Lines
associated with Firozabad cluster, under GeM BID NO: GEM/2024/B/5043723 (Hereinafter
called "the Bid")
KNOW ALL PERSONS by these present that WE …….. (insert name & address of the issuing
bank) ……… having its Registered/Head Office at …..…….(insert address of registered office of
the bank)…….. (hereinafter called "the Bank" which expression shall include its successors,
administrators, executors and assigns), are bound unto ……(insert name of Employer)…..
(hereinafter called "the Employer") in the sum of ....................(insert amount of Bid Security in
figures & words).......................... ............................……………. for which payment well and truly
to be made to the said Employer, the Bank binds itself, its successors and assigns by these
presents.
Sealed with the Common Seal of the said Bank this ............... day of ............... 20....
(1) If the Bidder withdraws its bid during the period of bid validity specified by the Bidder
in the Bid Form; or
(2) In case the Bidder does not withdraw the deviations proposed by him, if any, at the cost
of withdrawal stated by him in the bid and/or accept the withdrawals/rectifications
pursuant to the declaration/confirmation made by him in Attachment – Declaration of
the Bid; or
(3) If the Bidder does not accept the corrections to arithmetical errors identified during
preliminary evaluation of his bid pursuant to ITB; or
(4) If, as per the requirement of Qualification Requirements the Bidder is required to submit
a Deed of Joint Undertaking and he fails to submit the same, duly attested by Notary
Public of the place(s) of the respective executants (s) or registered with the Indian
Embassy/High Commission in that Country, within ten days from the date of intimation
of post – bid discussion; or
(5) In the case of a successful Bidder, if the Bidder fails within the specified time limit
(i) To sign the Contract Agreement, in accordance with ITB Clause 10, or
(ii) To furnish the required performance security, in accordance with ITB Clause 8.
or
WE undertake to pay to the Employer up to the above amount upon receipt of its first written
demand, without the Employer having to substantiate its demand, provided that in its
demand the Employer will note that the amount claimed by it is due to it, owing to the
occurrence of any of the above-named CONDITIONS or their combination, and specifying the
occurred condition or conditions.
This guarantee will remain in full force up to and including ……….. (insert date in line with
ITB Clause 13)…….., and any demand in respect thereof must reach the Bank not later than
the above date.
1. Our liability under this Bank Guarantee shall not exceed _________ (value in
figures)____________ [_____________________ (value in words)____________].
3. We are liable to pay the guaranteed amount or any part thereof under this Bank
Guarantee only & only if we receive a written claim or demand on or before ________
(validity date) __________
For and on behalf of the Bank
Signature_______________________
Name_______________________
Designation_______________________
POA Number_______________________
Fax Number_______________________
email ____________________________
Common Seal of the Bank______________________
Witness:
Signature_______________________
Name_______________________
Address______________________________
email ____________________________
Note:
1. In case the bid is submitted by a Joint Venture, the bid security shall be in the name of
the Joint Venture and not in the name of the Lead Partner or any other Partner(s) of
the Joint Venture.
“This Guarantee is subject to Uniform Rules for Demand Guarantee, ICC publication
No. 758.”
3. At the time of issuance of the Bank Guarantee (including its extensions) through
SFMS facility, the issuing bank will input the IFSC code of Beneficiary Bank as
mentioned at ITB clause 16.3 in BDS in their Trade Finance Portal.
“This Guarantee has been issued using SFMS Platform and the requisite
communication in this regard has been forwarded to the Beneficiary Bank.”
Attachment-2
Page 1 of 3
Dear Sir,
1.0 In accordance with the relevant provisions of the bidding documents inter-
alia including for assessment of capacity and capability, we furnish herewith
our data/details/documents along with other information, as follows
Note:
1. Information regarding events at Sl. No. 1 to 5 shall be furnished for events occurred
during last one year under the contract(s) executed by you for POWERGRID/PESL
(Owned as well as Consultancy)
*2. In case POWERGRID/PESL has issued a letter in this regard wherein the firm has
been put on hold from award of further contract(s) for a specified period and this
specified period of hold is yet to expire, the bidder shall indicate “Yes” against this
event.
**3. For the purpose of working out 50% of the Contract, following shall be taken into
account suitably:
(b) Scope of the Contract which primarily relates to the Qualification Requirement
(QR) of the bidder as illustrated below:
@4. Regarding Sl. No. 6, in case of ‘Yes’, following information shall be submitted
additionally:
Attachment-2
Page 3 of 3
Printed Name :
Date :
Designation :
Place :
INTEGRITY PACT
Between
POWERGRID Energy Services Ltd. (A wholly Owned Subsidiary of Power Grid Corporation
of India Limited) incorporated under the Companies Act, 2013, having its Registered Office
at Plot No. – 29, Sec 44, Gurugram- 122001 (Haryana) through its Office at Plot No. – 42, Sec
44, Gurugram- 122001 (Haryana)
hereinafter referred to as
"PESL",
and
__________________________________________________________________________
[Insert the name of the Sole Bidder/Lead Partner of Joint Venture]
___________________________________________________________________________
and
___________________________________________________________________________
"The Bidder/Contractor"
Preamble
In order to achieve these goals, PESL and the above named Bidder/Contractor enter
into this agreement called 'Integrity Pact' which will form a part of the bid.
(c) PESL will exclude from evaluation of Bids its such employee(s) who has
any personal interest in the Companies/Agencies participating in the
Bidding/Tendering process and all known prejudiced persons.
(1) The Bidder/Contractor commits itself to take all measures necessary to prevent
corruption. The Bidder/Contractor commits itself to observe the following
principles during its participation in the tender process and during the contract
execution:
e) The Bidder/Contractor will, when presenting his bid, disclose any and
all payments made, or committed to or intends to make to agents,
brokers or any other intermediaries in connection with the award of the
contract and/or with the execution of the contract.
(2) The Bidder/Contractor will not instigate third persons to commit offences
outlined above or be an accessory to such offences.
Section III- Disqualification from tender process and exclusion from future
contracts
(1) If the Bidder, before contract award, has committed a transgression through a
violation of Section II or in any other form such as to put his reliability or
credibility as Bidder into question, PESL may disqualify the Bidder from the
tender process or terminate the contract, if already signed, for such reason.
(3) If the Bidder/Contractor can prove that he has restored/recouped the damage
caused by him and has installed a suitable corruption prevention system,
PESL/POWERGRID may revoke the ban prematurely.
(1) If POWERGRID/PESL has disqualified the Bidder from the tender process
prior to the award under Section III, PESL is entitled for forfeiture of the Bid
Guarantee under the Bid.
(2) If PESL has terminated the contract under Section III or if PESL is entitled to
terminate the contract under Section III, PESL shall be entitled to forfeit the
Contract Performance Guarantee of this contract, in full or part thereof as may
be decided, besides resorting to other remedies under the contract.
(1) The Bidder shall disclose in its Bid any transgressions occurred in the last 10
years with any other Public Sector Undertaking or Government Department
or any other Company, in any country, that may impinge on the Anti-
corruption principle.
(2) If the Bidder makes incorrect statement on this subject, it can be disqualified
from the tender process or the contract, if already awarded, can be terminated
for such reason and further action can be taken in line with POWERGRID’s
policies.
(2) PESL will disqualify from the tender process any bidder who does not sign this
Pact or violate its provisions.
(2) The panel of IEMs shall review independently and objectively, whether and
to what extent the parties comply with the obligations under this agreement.
The panel of IEMs has right of access to all project documentation. The panel
of IEMs may examine any complaint received by them and submit a report to
Chairman-cum-Managing Director, POWERGRID, giving joint findings, at
the earliest. The panel of IEMs may also submit a report directly to the CVO
and the CVC, in case of suspicion of serious irregularities attracting the
provisions of the PC Act.
(3) The IEM is not subject to instructions by the representatives of the parties and
performs his functions neutrally and independently. He / She reports to the
Chairman-cum-Managing Director, POWERGRID.
(4) The Bidder(s)/Contractor(s) accepts that the IEM has the right to access
without restriction to all documentation of POWERGRID related to this
contract including that provided by the Contractor/Bidder. The
Bidder/Contractor will also grant the IEM, upon his / her request and
demonstration of a valid interest, unrestricted and unconditional access to their
documentation. The same is applicable to Subcontractors. The IEM is under
contractual obligation to treat the information and documents of the
Bidder(s)/Contractor(s)/Subcontractor(s) with confidentiality.
(5) POWERGRID will provide to the IEMs information as sought by him / her
which could have an impact on the contractual relations between POWERGRID
and the Bidder/Contractor related to this contract. The IEMs shall also sign
declaration on ’Non-Disclosure of Confidential Information’ and of
‘Absence of Conflict of Interest’. In case of any conflict of interest arising at
a later date, the IEM shall inform Chairman-cum-Managing Director,
POWERGRID and recuse himself/herself from that case
(6) As soon as the IEM notices, or believes to notice, a violation of this agreement,
he / she will so inform the Chairman-cum-Managing Director, POWERGRID
and request the Chairman-cum-Managing Director, POWERGRID to
discontinue or take corrective action, or to take other relevant action. The IEM
can in this regard submit non-binding recommendations. Beyond this, the IEM
has no right to demand from the parties that they act in a specific manner,
refrain from action or tolerate action. However, the IEM shall give an
opportunity to POWERGRID and the Bidder/Contractor, as deemed fit, to
present its case before making its recommendations to POWERGRID.
(7) The IEM will submit a written report to the Chairman-cum-Managing Director,
POWERGRID within 8 to 10 weeks from the date of reference or intimation to
him by POWERGRID and, should the occasion arise, submit proposals for
correcting problematic situations.
(10) The word ‘IEM’ would include both singular and plural.
(*) This Section shall be applicable for only those packages wherein the IEMs have been
identified in Section – I : Invitation for Bids and/or ITB: Conditions of Contract, Volume-
I of the Bidding Documents.
This Pact begins when both parties have legally signed it. It expires for the Contractor
after the closure of the contract and for all other Bidder's six month after the contract
has been awarded.
(1) This agreement is subject to Indian Law. Place of performance and jurisdiction
is the establishment of PESL/POWERGRID. The Arbitration/Conciliation
clause provided in the main tender document / contract shall not be applicable
for any issue / dispute arising under Integrity Pact.
(5) Issues like Warranty/Guarantees etc. shall be outside the purview of IEMs.
# CVO shall be applicable for packages wherein IEM are not identified in Section
IFB/BDS of Condition of Contract, Volume-I. IEM shall be applicable for packages
wherein IEM are identified in Section IFB/BDS of Condition of Contract, Volume-
I.
(7) Should one or several provisions of this agreement turn out to be invalid, the
remainder of this agreement remains valid. In this case, the parties will strive
to come to an agreement to their original intentions.
Name:____________________________ Name:____________________________
Designation:_______________________ Designation:_______________________
Witness 1 :_________________________ Witness 1 :_________________________
__________________________________ __________________________________
__________________________________ __________________________________
__________________________________ __________________________________
__________________________________ __________________________________
Attachment-4
Format for Affidavit of Self certification regarding Local Content in line with PPP-
MII order and MoP order), if applicable, to be provided on a non-judicial stamp
paper of Rs. 100/-.
Date:
That I will agree to abide by the terms and conditions of the Public Procurement
(Preference to Make in India) Order, 2017 of Government of India issued vide
Notification No:P-45021/2/2017 -BE-II dated 15/06/2017, its revision dated
16/09/2020 (hereinafter PPP-MII order),
That the local content for all inputs which constitute the said goods/services/works
has been verified by me and I am responsible for the correctness of the claims made
therein.
That the ‘Local Content ‘as defined in the PPP-MII order and MoP order in the
goods/services/works supplied by me for Outsourcing of O&M activities of
Transmission Lines associated with Firozabad cluster is ……… percent (%).
Page 1 of 2
Attachment-4
That the value addition for the purpose of meeting the ‘Local Content ‘has been
made by me at ……………………… (Enter the details of the location(s) at which value
addition is made).
That in the event of the local content of the goods/services/works mentioned herein
is found to be incorrect and not meeting the prescribed Local Content criteria, based
on the assessment of procuring agency (ies)/POWERGRID/Government Authorities
for the purpose of assessing the local content, action shall be taken against me in line
with the PPP-MII order, MoP order and provisions of the Integrity pact/ Bidding
Documents.
I agree to maintain the following information in the Company's record for a period
of 8 years and shall make this available for verification to any statutory authority.
Page 2 of 2
Attachment-5
Dear Sir,
We have read and understood the provisions of Order no. F.No.6/18/2019-PPD (Order
Public Procurement no.1) dated 23/07/2020 regarding “Restriction under Rule 144(xi) of
General Financial Rules” and F.No.6/18/2019-PPD (Order Public Procurement no.2) dated
23/07/2020 regarding “Exclusions from Restriction under Rule 144(xi) of General
Financial Rules” issued by Public Procurement Division, Department of Expenditure,
Ministry of Finance, Government of India [hereinafter collectively “DoE Order’’] and any
subsequent modifications/Amendments, if any.
Particularly, we, the Bidder, have read the clause regarding restrictions on procurement
from a ‘Bidder of a country which shares a land border with India’ and on sub-
contracting to contractors from such countries.
We certify that we, the bidder and/or our subcontractor/sub vendor is/are not from
such a country or, if from such a country, has been registered as per provisions of the
Bidding Documents with the Competent Authority and will not subcontract any work to
a subcontractor/sub vendor from such countries unless such subcontractor/sub vendor
fulfils all requirement in this regard and is eligible to be considered. [Where applicable,
evidence of valid registration by the Competent Authority shall be attached.]
Place: Designation:
Page 1 of 1
Attachment-6
Page 1 of 1
Dear Sir,
5. We also confirm that the Employer may verify the supporting documents/
details in connection with above declarations. We further understand that in
case of any unethical practices inter-alia including any misrepresentation of
facts, submission of false and/or forged details/ documents/ declaration by
us, we may be debarred from the participation in Employer’s tenders in
future as considered appropriate by Employer and our Bid Security/ Contract
Performance Guarantee shall be forfeited besides taking other actions as
deemed appropriate.
Place : Designation :
Attachment-7
Page 1 of 5
Dear Sir,
1. We declare that we are aware of and have gone through the "Code of Business
Conduct and Ethics for Senior Management Personnel" and "Code of Business
Conduct and Ethics for Board Members" of POWERGRID (hereinafter
referred to as the "Code of Conduct"). We further understand that as per the
"Code of Conduct", Senior Management Personnel including Board Members,
who have retired/ resigned from POWERGRID/PESL, shall not accept any
appointment or post, as detailed in the referred "Code of Conduct", within 1
year from the date of cessation of service/ directorship unless approved by
the competent authority.
Date of
Date of
joining and
Sl. Name of the person with designation in Retirement/
designation
No. POWERGRID/PESL resignation from
in our
POWERGRID/PESL
organisation
1
3
Attachment-7
Page 2 of 5
*In case the date of joining in the bidder's organization of such ex-employee is
within 1 year from the date of retirement/ resignation from POWERGRID/PESL, No
Objection Certificate/ approval from the competent authority must be furnished
along with the bid or subsequent through clarification pursuant to ITB 5.
We hereby authorize the Purchaser to make all our payments through Electronic Fund Transfer
System. The details for facilitating the payments are given below:-
Registered Office:
Branch Office:
Correspondence Address:
Status – Company/others
Designation
8 Contact Details
Landline(s):
Mobile(s):
Email ID :
Address of Branch:
Account No.:
Type of Account:
I/We hereby declare that the particulars given above are correct and complete. If the transaction
is delayed or credit is not affected at all for reasons of incomplete or incorrect information, I/We
would not hold the Purchaser responsible.
Printed
Date :
Name :
Place : Designation :
Note:
1. "Code of Business Conduct and Ethics for Senior Management Personnel" and "Code of
Attachment-7
Page 5 of 5
Business Conduct and Ethics for Board Members” are available on POWREGRID's website
https://www.powergrid.in
2.The information in similar format should be furnished for each partner of joint venture in
case of joint venture bid.
3. In case bidder has furnished no details on ex-employees of POWERGRID or has left blank
or has indicated '-' against the same, it shall be deemed that they have not employed any
such person in their organization.
Attachment-8 (QR)
To:
Bidders’s Name & Address:
Contract Services
Dear Sir,
In support of the Qualification Requirements (QR) for bidders, stipulated in Annexure-A (ITB) Volume-I & Additional Information required as per ITB of the Bidding Documents, we furnish
herewith our QR data/details along with other information, as follows herewith our stipulations have been reproduced in italics for ready reference, however, in case of any discrepancy the QR
as given in BDS shall prevail).
[For details regarding Qualification Requirements of a Joint Venture, please refer para 4.0 below.]
We are furnishing the following details/document in support of Qualifying requirement for the subject package.
c) The place of incorporation (for bidders who are corporations); or the place of registration and the nationality of the Owners (for applicants who are partnerships or individually-
owned firms).
a) Written power of attorney of the signatory of the Bid to commit the bidder.
GENERAL INFORMATION
Bidder is required to provide general information as per the following format.
TECHNICAL EXPERIENCE
Qualification Criteria
Qualification of bidder will be based on meeting the minimum passing criteria specified below regarding the Bidder’s technical Experience, and Financial Position as
demonstrated by the Bidder’s responses in the corresponding Bid Schedules.
The Employer may assess the capacity and capability of the bidder, to ascertain that the bidder can successfully execute the scope of work covered under the package within
stipulated time period. This assessment shall inter-alia include (i) document verification; (ii) details of works executed, works in hand, anticipated in future; (iii) manpower and
financial resources; (iv) past experience and performance; (v) customer feedback; (vi) banker’s feedback etc.
PESL reserves the right to waive minor deviations if they do not materially affect the capability of the Bidder to perform the contract.
1 Experience
Technical Experience
a) Bidder should have successfully completed satisfactory O&M* of minimum 250kM** route length of 765kV*** or above transmission line in a single (1) Contract of minimum
duration of 2 years or cumulatively in two (2) Contracts of minimum duration of 1 year each during last 7 years as on the originally scheduled last date of bid submission (soft
copy) i.e. 12.07.2024
1.1
OR
b) Successful Erection and stringing**** of not less than 125 kms cumulatively route length of 400kV$ or above transmission line cumulatively during last 7 years, as on the
originally scheduled last date of bid submission (soft copy) mentioned above. 12.07.2024
Using the following format, each Bidder (individual firms ) is requested to list the experience as detailed above, on the basis of which the Bidder wishes to qualify. The
information is to be summarised using following format for each experience of the Bidder
(The bidder shall attach documentary evidence, such as copies of utility certificates for completed contracts and copies of award letters etc. for ongoing contracts in support of his
experience as listed in the following proforma for each Contract in table given below).
Format-A:
Format for the Bidder in support of meeting the requirement of para 1.1, Annexure-A to ITB of the Bidding Documents)
Work-01
Name of Bidder
Details of Work:
Telephone No.
Fax No.
Work-02
Name of Contract (executed during the last 7 years as on the
1
date of bid opening):
E-mail ID
Telephone No.
Fax No.
2.1 Financial Qualification Data:
A. NET WORTH
B Turnover details:
C Liquid Assets
LA (in Rs. Lakh)
Details of evidence of
having Liquid assets (LA)
Or
Details of evidence of
access to or availability of
credit facilities
Audited balance sheet and income statements for the last five years as per the following:
Years preceding to the bid
A Audited Balance Sheet and Income Statements enclosed
opening
BETWEEN
and
(2) M/s .............. (Name of Contractor) ..........., a company incorporated under the laws of
Companies Act 1956 and having its Principal place of business at ………....(Address of
Contractor) ............................... and Registered Office at ………....(Registered address of
Contractor) ............... (hereinafter called "the Contractor" and also referred to as “…..(insert
abbreviated name of the Contractor) ……..”)
or
Joint Venture (JV) of M/s ................. (Name of Lead Partner) .................. (the Lead Partner of
JV), a company incorporated under the laws of Companies Act 1956 and having its Principal
place of business at ………....(Address of Lead Partner) ............................... and Registered Office
at ………....(Registered address of Lead Partner) ........................ and M/s ................. (Name of Other
Partner) .................. (the Partner of JV), a company incorporated under the laws of Companies
Act 1956 and having its Principal place of business at ………....(Address of Other Partner)
............................... and Registered Office at ………....(Registered address of Other Partner)
........................ (hereinafter called "the Contractor" and also referred to as “Joint Venture”/the
‘JV””)
(Applicable only in case of Joint Venture)
WHEREAS the Employer desires to engage the Contractor for providing all the services
inter-alia including …….................….. (Indicate brief scope of work) ............................... for the
complete execution of the …… (insert name of Package alongwith name of the Project)……. as
detailed in the Contract Document ("the Facilities"), and the Contractor has agreed to such
engagement upon and subject to the terms and conditions hereinafter appearing.
Page 1
1.1 Contract Documents (Reference GCC Clause 2.2)
The following documents shall constitute the Contract between the Employer and the
Contractor, and each shall be read and construed as an integral part of the Contract:
VOLUME – A
VOLUME – B
VOLUME – C
(Only relevant extracts are attached herewith for easy reference. Should the
circumstances warrant, the original Bid along with the enclosures thereof, shall be
referred to.).
In the event of any ambiguity or conflict between the Contract Documents listed
above, the order of precedence shall be the order in which the Contract Documents
are listed in Article 1.1 (Contract Documents) above.
1.3.1 Capitalized words and phrases used herein shall have the same meanings as are
ascribed to them in the General Conditions of Contract/Special Conditions of
Contract.
The Employer hereby agrees to pay to the Contractor the Contract Price in
consideration of the performance by the Contractor of its obligations hereunder. The
Contract Price shall be the aggregate of .……. (amount in words) .................
(...............(amount in figures) ….. ........), or such other sums as may be determined in
accordance with the terms and conditions of the Contract. The break-up of the
Contract price is as under:
Page 2
Sl. Price Component Amount
No.
1. Total Price for entire scope of work
Total for Contract Price
The detailed break-up of Contract Price is given in the relevant Appendices hereto.
The terms and procedures of payment according to which the Employer will
reimburse the Contractor are given in Appendix 1 (Terms and Procedures of
Payment) hereto.
The Time of Completion of Facilities as provided in the GeM Contract i.e., from
…………………
Article 4. Appendices
Reference in the Contract to any Appendix shall mean the Appendices attached
hereto, and the Contract shall be read and construed accordingly.
List of Appendices
Appendix 1 Terms and Procedures of Payment
Appendix 2 Price Adjustment
Appendix 3 Insurance Requirements
Appendix 4 Time Schedule
Appendix 5^ Summary of Detailed Price Break-up
Appendix 5A^ Detailed Price Break-up (Price Component)
Appendix 6^ Integrity Pact
[^ to be appended at the Stage of Contract Award.]
IN WITNESS WHEREOF the Employer and the Contractor have caused this Agreement to be
duly executed by their duly authorized representatives the day and year first above written.
Page 3
Signed by for and Signed by for and
on behalf of the Employer on behalf of the Contractor
........................................ ........................................
Signature Signature
.............................................. ..............................................
Title Title
in the presence of in the presence of
Page 4
Appendix-1
In accordance with the provisions of GCC/SCC Clause 8.1 (Terms of Payment), the
Employer shall pay the Contractor in the following manner and at the following times, on
the basis of the Price Break-up given in the section on price schedules. Payments will be
made in the currencies quoted by the Bidder unless otherwise agreed between the parties.
1. TERMS OF PAYMENT
In addition to the Conditions stipulated under GCC/SCC Clause 8.1, the following
terms & Conditions will apply.
1.1A It would be mandatory for contractor to fulfill the following conditions as per
terms & conditions of Contract:
a) signing the Contract Agreement.
b) Performance Securities in line with GCC Clause 9.3.1, and
1.1B 1. Progressive Payments shall be released on Monthly basis against the work done
during the month shall be released upon submission of following documents.
(i) Joint Measurement Certificate duly certified by the Enginee -In-charge.
(ii) Detailed GST invoice in duplicate indicating award letter no. and date and shall
be raised in favour of Engineer-in-Charge for verification & processing of payment.
(iii) Submission of Acknowledged duplicate copy of NOA/Contract for release of
first payment.
(iv) Submission of CPG and Statutory insurances for release of first payment.
(v) Submission of SLA along with respective Debit/Credit Note (if required)
Other Conditions:
1. The payment to the Contractor under the Contract will be made by the
owner as per the guidelines and conditions specified hereunder.
1. List of personnel deployed for PESL work (To be submitted with each
Bill).
Page 5
2. Payment disbursement sheet for the previous month, consisting of
name, total pay, deductions, and net amount paid, e-payment order
No., date & name of bank with signatures of employee along with a
certificate that the contract labors have been correctly paid.
d. GST shall be paid by PESL upon submission of invoice as per GST act on
monthly basis. For payment of GST, Reverse charge, if applicable, shall be
deposited by PESL as applicable as per GST Rules/Act. All GST payment
shall be against GST invoices/debit notes raised by the Contractor as specified
under the GST Act and related Rules, Notifications, etc as notified by the
Government in this regard. In the event that the Contractor fails to provide
the invoice/debit note in the form and manner prescribed under the GST Act
and Rules, the Employer shall not be liable to make any payment against such
invoice/debit note. Payment towards taxes & duties shall be released by the
Employer directly to the Contractor.
f. The payment shall be regulated as per accepted rate only. Contractor shall not
be entitled to any extra payment compensation or remuneration relating to
work done during unfavourable weather or relating to any special
arrangements made to complete the work as per schedule of items.
g. No extra payment shall be made to the contractor for working on the holiday
and during odd hours.
2. PAYMENT PROCEDURES
Page 6
All invoices/claims shall be raised by the Contractors in the name of Owner.
The Employer shall make payments promptly within thirty (30) days of submission of
an invoice/claim by the Contractor, complete in all respects and supported by the
requisite documents and fulfillment of stipulated conditions, if any. All the payment
shall be released to the Contractor directly.
All payments to be made directly to the Contractor shall be made by the Employer
though electronic payment mechanism (e-payment) for which necessary details shall
be tied up during execution of the Contract. However, a request for payment to be
released through cheque shall be considered on case to case basis and merit of the
same.
Note: Pro-rata shall refer to functionally complete part(s) of the facilities, for which unit
rates are identified in the contract.
Prior to submission of bills in physical form, the Contractor shall submit its bills
using POWERGRID’s Vendor Bill Tracking System as per procedure detailed herein
below. Further, the Contractor may also track the status of its bills using
POWERGRID’s ‘On-line Vendor Bill Tracking System’. To use this system the
Contractor is required to get itself registered once online at POWERGRID’s ERP
Portal with the link URL (https://etender.powergrid.in). Once registered, the
Contractor may track status of bills submitted, passed and paid by POWERGRID’s
Corporate Centre and Regional Office(s) under this Contract and other Contracts
awarded on it by POWERGRID by following the method detailed herein below:
a) Once registered, the Contractor can log-in to POWERGRID’s Vendor Bill Tracking
System (BTS) with Vendor Log-In ID and Password.
c) The physical bills alongwith printed copy of e-mail received from BTS (unique BTS
number) shall be submitted by the Contractor.
Page 7
BTS ( as the case may be) shall be returned to the Contractor by POWERGRID,
which can be viewed under the tab “Invoice Returned”.
e) The day the payment is made, a mail stating the “Bill number, net payment amount
and details of the bank from where the payment has been made” will be sent to the
Contractor.
f) The status of Bill submitted by the Contractor can be checked through the BTS
number under tab “Invoice Submitted”.
**End of Appendix-1**
Page 8
Appendix – 2
PRICE ADJUSTMENT
Not Applicable.
**End of Appendix-2**
Page 9
Appendix-3
INSURANCE REQUIREMENTS
The above policy shall be obtained before commencement of Maintenance work as and
when required. The cost of insurance premium at each instance shall be reimbursed to
the Contractor by the employer based on the documentary evidence for the premium
paid. The contractor shall finalize the insurer from the lowest quoted Insurers and shall
take the consent from the employer before finalizing the Insurance Premium amount
and Insurer.
The policy should cover all physical loss or damage to the facility at site during storage,
erection and commissioning covering all the perils as provided in the policy as a basic
cover and the add on covers if any.
The Contractor shall take the policy in the joint name of Employer and the Contractor.
The policy shall indicate Employer as the beneficiary. The policy shall be kept valid till
the date of the taking over of site by Employer and the period of the coverage shall be
determined with the approval of the Engineer In-Charge of Employer
Third Party Liability cover with cross Liability within Geographical limits of India as on
Add-on cover to the basic EAR cover:
The third-party liability add-on cover shall cover bodily injury or death suffered by
third parties (including the Employer’s personnel) and loss of or damage to property
(including the Employers’ property and any parts of the Facilities which have been
accepted by the Employer) occurring in connection with scope of work.
If during the execution of Contract, the Employer requests the Contractor to take any
other add-on cover(s)/ supplementary cover(s) in aforesaid insurance, in such a case,
the Contractor shall promptly take such add-on cover(s)/ supplementary cover(s) and
the charges towards such premium for such add-on cover(s)/ supplementary cover(s)
shall be reimbursed to the Contractor on submission documentary evidence of payment
to the Insurance company. Therefore, charges towards premium for such add-on
cover(s)/ supplementary cover(s) are not to be included in the Contract Price.
Page 10
(I) Workmen Compensation Policy shall be taken by the Contractor in
accordance with the statutory requirement applicable in India. The
Contractor shall ensure that all the workmen employed by the Contractor
or its Subcontractors for the project are adequately covered under the
policy.
(II) The policy may either be project specific covering all men of the
Contractor and its Subcontractors. The policy shall be kept valid till the
date of Operational Acceptance of the project. Alternatively, if the
Contractor has an existing „Workmen Compensation Policy‟ for all its
employees including that of the Subcontractor(s), the Contractor must
include the interest of the Employer for this specific Project in its existing
“Workmen Compensation Policy”.
(III) Without relieving the Contractor of its obligations and responsibilities
under this Contract, before commencing work the Contractor shall insure
against liability for death of or injury to persons employed by the
Contractor including liability by statute and at common law. The
insurance cover shall be maintained until all work including remedial
work is completed including the Defect Liability Period. The insurance
shall be extended to indemnify the Principal for the Principal‟s statutory
liability to persons employed by the Contractor. The Contractor shall also
ensure that each of its Subcontractors shall effect and maintain insurance
on the same basis as the „Workmen Compensation Policy‟ effected by the
Contractor.
(IV) The contractor shall take adequate Group Insurance and Workman
Compensation as per act applicable for the said work for its deployed
manpower during execution of contract. The expenditure incurred
towards premium for such policies shall be borne by the contractor
without any additional cost to the Owner. It shall be obligatory on the
part of the contractor to provide a copy of group insurance/ Workman
Compensation policy for the manpower deployed before commencement
of work to the Engineer In-Charge of Owner. The above policies should
be valid throughout the duration of the contract.
(V) The Contractor shall mandatorily cover its deployed personnel under ESI.
Locations where ESI benefits are not extended/ if employees are not
covered under ESI, the Contractor shall make available equivalent
insurance coverage under the provisions of Employees Compensation
Act (EC Act 1923). The Contractor shall also take Mediclaim policy of Rs.
Two Lakhs towards medical coverage for each of its staff deployed in
SPV/PESL location under the subject contract. The Contractor shall
arrange for necessary ESI / EC cover & medical even for any staff
deployed for very short duration. The expenditure incurred towards
contributions/ premium for such policies shall be borne by the
Page 11
Contractor without any additional cost to the Employer. It shall be
obligatory on the part of the Contractor to provide a copy of ESI Cards/
Employee Compensation (EC) policy and group medical insurance/
Mediclaim for the manpower deployed before commencement of work to
the Engineer In-Charge of Employer. The above policies should be valid
throughout the duration of the contract.
(VI) The Contractor shall ensure that all legal dues, including Employees
Compensation against Employee Compensation Policy, is paid to the
legal heir of the deceased/injured within the time frame as per Employee
(Workmen) Compensation Act. If Contractor failed to deposit the
Compensation amount to the concerned Compensation Commissioner,
equivalent amount shall be with-held from running bills of Contractor
and PESL shall submit the same to Commissionerate office without
delay.
**End of Appendix-3**
Page 12
Appendix-4
TIME SCHEDULE
**End of Appendix-4**
Page 13
6. PERFORMANCE SECURITY FORM
NOA/Contract No.....................................
…………..[Name of Contract]…………………….
signed on ..............(insert date of the Contract)…..... between you and M/s ................. (Name
of Contractor) ..................,
(or)
vide notification of award issued on …….(insert date of the notification of award)….. by you
to M/s ................. (Name of Contractor) ..................
Or
signed on ..............(insert date of the Contract)…..... between you and M/s ................. (Name
of Contractor) ..................,
(or)
vide notification of award issued on …….(insert date of the notification of award)….. by you
to M/s ................. (Name of Contractor) ..................
Page 14
………....(Registered address of Associate)
........................................................................................, the Associate of the Contractor for
executing the Facilities concerning …….................….. (Indicate brief scope of work)
............................... for the complete execution of the …… (insert name of Package
alongwith name of the Project)…….. [Applicable for Bank Guarantees to be issued by
Contractor against those Contracts awarded to their Associate]
By this letter we, the undersigned, ………(insert name & address of the issuing bank) ………,
a Bank (which expression shall include its successors, administrators, executors and
assigns) organized under the laws of .................................... and having its Registered/Head
Office at …..…….(insert address of registered office of the bank)……..... do hereby
irrevocably guarantee payment to you up to ………………………….. i.e., ten percent (10%)
of the Contract Price until ninety (90) days beyond the end of Contract Period i.e., upto and
inclusive of ……………. (dd/mm/yy).
We undertake to make payment under this Letter of Guarantee upon receipt by us of your
first written demand signed by your duly authorized officer declaring the Contractor to be in
default under the Contract and without cavil or argument any sum or sums within the above
named limits, without your need to prove or show grounds or reasons for your demand and
without the right of the Contractor to dispute or question such demand.
Our liability under this Letter of Guarantee shall be to pay to you whichever is the lesser of
the sum so requested or the amount then guaranteed hereunder in respect of any demand
duly made hereunder prior to expiry of the Letter of Guarantee, without being entitled to
inquire whether or not this payment is lawfully demanded.
This letter of Guarantee shall remain in full force and shall be valid from the date of issue
until ninety (90) days beyond the end of Contract Period of the Facilities i.e. upto and
inclusive of ……………. (dd/mm/yy) and shall be extended from time to time for such period
(not exceeding one year), as may be desired by M/s. ……………………… on whose behalf
this Letter of Guarantee has been given.
Except for the documents herein specified, no other documents or other action shall be
required, notwithstanding any applicable law or regulation.
Our liability under this Letter of Guarantee shall become null and void immediately upon its
expiry, whether it is returned or not, and no claim may be made hereunder after such expiry
or after the aggregate of the sums paid by us to you shall equal the sums guaranteed
hereunder, whichever is the earlier.
All notices to be given under shall be given by registered (airmail) posts to the addressee at
the address herein set out or as otherwise advised by and between the parties hereto.
We hereby agree that any part of the Contract may be amended, renewed, extended,
modified, compromised, released or discharged by mutual agreement between you and the
Contractor, and this security may be exchanged or surrendered without in any way impairing
or affecting our liabilities hereunder without notices to us and without the necessity for any
additional endorsement, consent or guarantee by us, provided, however, that the sum
guaranteed shall not be increased or decreased.
No action, event or condition which by any applicable law should operate to discharge us
from liability hereunder shall have any effect and we hereby waive any right we may have to
apply such law so that in all respects our liability hereunder shall be irrevocable and, except
as stated herein, unconditional in all respects.
Page 15
Notwithstanding anything contained herein:
1. Our liability under this Bank Guarantee shall not exceed _________ (value in
figures)____________ [_____________________ (value in words)____________].
3. We are liable to pay the guaranteed amount or any part thereof under this Bank
Guarantee only & only if we receive a written claim or demand on or before
________ (validity date) __________.”
Signature_______________________
Name_______________________
Designation_______________________
POA Number_______________________
Fax Number_______________________
email ____________________________
Signature_______________________
Name_______________________
Address______________________________
email ____________________________
Note :
1. For the purpose of executing the Bank Guarantee, the non-judicial stamp papers of
appropriate value shall be purchased in the name of Bank who issues the ‘Bank
Guarantee’.
2. The Bank Guarantee shall be signed on all the pages by the Bank Authorities
indicating their POA nos. and should invariably be witnessed.
Page 16
1. The Bank Guarantee should be in accordance with the proforma as provided.
However, in case the issuing bank insists for additional paragraph regarding
applicability of ICC publication No: 758, the following may be added at the end
of the proforma of the Bank Guarantee [i.e., end paragraph of the Bank
Guarantee preceding the signature(s) of the issuing authority(ies) of the Bank
Guarantee]:
“This Guarantee has been issued using SFMS Platform and the requisite
communication in this regard has been forwarded to the Beneficiary Bank.”
Page 17