Reticulation - Project FINAL
Reticulation - Project FINAL
Reticulation - Project FINAL
Subject: Reticulation
Henniker ZD 218093713
Sias BJ 220090408
Jantjies AY 220339287
Schoeman HE 220389411
Hoffman BB 216169429
Lecturer: Mr R. Mambwe
Contents
Introduction:..........................................................................................................................................3
Background:...........................................................................................................................................3
Aim & objectives:...................................................................................................................................4
Calculations:..........................................................................................................................................5
a.) AADD Calculations....................................................................................................................5
TAADD Calculations.......................................................................................................................6
b) Suction pipe and delivery pipe both have a diameter of 160 mm.............................................6
c) System Curve.............................................................................................................................8
D) check for cavitation.................................................................................................................10
Conclusions and Recommendations....................................................................................................12
Appendices..........................................................................................................................................13
Background:
In estimating water demand, the selection of an appropriate pump for the water
supply infrastructure is equally important. The pump needs to match the anticipated
water demand while ensuring energy efficiency and optimal performance. To achieve
this, the tombstone curve methodology will be employed. By analysing the system
head and flow rate, the tombstone curve enables the identification of a suitable pump
size that can handle the peak and average demand requirements while minimizing
energy consumption.
Select a suitable pump using the tombstone curve: Once the daily water demand is
established, the report will focus on selecting an appropriate pump for the
infrastructure. The tombstone curve methodology will be employed to match the
water demand requirements with the optimal pump capacity. This approach ensures
that the pump can meet both peak and average demand while optimizing energy
consumption.
Calculations:
a.) AADD Calculations
Abattoir
Cattle = 120 x 0.8 KL/head = 96 kl/d
Sheep = 200 x 0.14 KL/head =28 kl/d
Hospital
Beds = 250 x 0.6 Kl/bed = 150 KL/d
Day School
Students = 600 x 0.06 KL/student = 36 KL/d
Boarding school
Students = 450 x 0.3 KL/student = 135 KL/d
Church
550m2 x 0.3 KL/100m2/d = 1.65 kl/d
Filling Station
400m2 x 0.8 kl/100m2/d = 3.2 kl/d
Standpipes
1050 x 0.025 kl/c/d =26.25 kl/d
Yard connections
2460 x 0.07 kl/c/d = 172.2 kl/d
Low Income housing connections
4000 x 0.09 kl/c/d = 360 kl/d
Residential houses
1200 x 0.23 kl/c/d = 276 kl/d
Lodge
Single room = 70 x 0.3 kl/d = 21 kl/d
Double room = 90 x 0.6 = 54 kl
Fruit processing industry
600 kl/d
TAADD Calculations
Sum of AADD = 1959.3 kl/d
∑ AADD 1959.3
TAADD = =
(1−REAL LOSS %) (1−0.18)
Therefore TAADD = 2389.390 Kl/d
b) Suction pipe and delivery pipe both have a diameter of 160 mm.
2
πD
Area of pipes =
4
2
π x 0.16
=
4
= 0.02 m2
4412.197
Q= = 0.051 m3/s
24 x 60 x 60
Q = VA
Q
V=
A
0.051
V= = 2.55 m/s
0.02
Minor Losses
2
KV
Hm =
2g
2
7 ×2.55
- Meter = = 2.32 m
2 ×9.81
2
0.05 ×2.55
- Bellmouth = = 0.017 m
2 ×9.81
2
0.2× 2.55
- Gate valve = = 0.066 m
2 ×9.81
2
4 × 2.55
- Non-return valve = = 1.326 m
2× 9.81
2
0.45 ×2.55
- Bends = x 5 = 0.746 m
2 ×9.81
2
0.3 ×2.55
- Ball valve = = 0.099 m
2 ×9.81
1.852
10.68× L× Q
Hf = 1.852 4.87
C ×D
C = 150
L = 78 m
D = 0.16 m
1.852
10.68× 78 ×0.051
Hf = 1.852 4.87
150 × 0.16
= 2.36 m
ΣhL = 6.934 m
Hp = 13 + 6.934
Hp = 19.934 m
c) System Curve
Hsystem formula:
Head=Static head + Dynamic head
2
19.935=13+ x ( 360.241 )
6.935=129773.5781 x
∴ x=5.344 ×10−5
−5 2
H sys =13+5.344 ×10 Q
Power = 24.3 kW
NPSH = 3.4 m
Power check:
366
1 ×9.81 ×20 ×
ρgHQ 3600
P= = =24.3 kN
η 0.821
⸫ Power from graph = Power from hand calculations.
1.852
10.68× L× Q
Hf = 1.852 4.87
C ×D
C = 150
L = 70m
D = 0.16 m
1.852
10.68× 70 ×0.051
Hf = 1.852 4.87
150 × 0.16
=2.110m
ΣhL = 3.651m
3
0.0128 m x 13600 kg/m
3 = 0.174m
1000 kg/m
98000 Pa
= 9.990m
1000 x 9.81
NPSHa= 9.990-1-3.651-0.174=5.165
The daily water demand of Grabouw has been determined allowing for an accurate
estimation of water demand, an appropriate pump has therefore been chosen
accordingly. The tombstone curve methodology has also been used to ensure that
the water demand matches with the optimal pump capacity. The tombstone curve in
figure 1 has been used to select an adequate size of 150-250m. This approach has
been used as it allows for the pump to meet both peak and average demand while
optimizing energy consumption as indicated in the report.
Appendices
Figure 1: Tombstone Curves