Chap 4
Chap 4
119
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.48 116.67 56.00
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
b) Machinery
Tractor mount Grader hour 12.00 690.00 8,280.00
110 @ 25 cum per
hour
Three wheel 80-100 hour 30.00 420.00 12,600.00
kN static roller @ 10
cum per hour
Tractor with Rotavator hour 12.00 390.00 4,680.00
25 cum per hour
Water tanker 6 kl hour 5.00 295.00 1,475.00
capacity
c) Material
Well graded granular cum 360.00 470.00 169,200.00
sub-base material as
per Table 400.1
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% 19,904.10
on (a+b+c)
e) Contractor’s profit 21,894.51
@ 10% on (a+b+c+d)
120
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Well graded granular cum 360.00 455.00 163,800.00
sub-base material as
per Table 400.1
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% 19,364.10
on (a+b+c)
e) Contractor’s profit 21,300.51
@ 10% on (a+b+c+d)
121
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
c) Material
Well graded granular
sub-base material as
per Table 400.1
53 mm to 9.5 mm @ cum 144.00 460.00 66,240.00
50 per cent
9.5 mm to 2.36 mm @ cum 57.00 485.00 27,645.00
20 per cent
2.36 mm below @ 30 cum 86.40 300.00 25,920.00
per cent
Water kl 24.00 45.00 1,080.00
d) Overheads @ 10% 15,750.14
on (a+b+c)
e) Contractor’s profit @ 17,325.15
10% on (a+b+c+d)
Cost for 225 cum = 190,576.66
a+b+c+d+e
Rate per cum = 847.01
(a+b+c+d+e)/225
Say Rs. 847.00
(ii) For Grading II Material
Unit = cum
Taking output = 225 cum
(450 t)
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Wet mix plant @ 60 t hour 7.50 1,050.00 7,875.00
capacity per hour
Water tanker 6 kl hour 4.00 295.00 1,180.00
capacity 5 km lead
with one trip per hour
Front end loader 0.9 hour 9.00 787.00 7,083.00
cum bucket capacity
25 cum per hour
Tipper 5.5 cum, 3 trips hour 13.60 275.00 3,740.00
per hour
Motor grader 110 HP hour 4.50 1,350.00 6,075.00
@ 50 cum per hour
Three wheel 80-100 hour 22.50 420.00 9,450.00
kN static roller 10 cum
output
c) Material
Well graded granular
sub-base material as
per Table 400.1
26.5 mm to 9.5 mm @ cum 100.80 470.00 47,376.00
35 per cent
9.5 mm to 2.36 mm @ cum 72.00 485.00 34,920.00
25 per cent
2.36 mm below @ 40 cum 115.20 300.00 34,560.00
per cent
Water kl 24.00 45.00 1,080.00
122
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
d) Overheads @ 10% 15,455.24
on (a+b+c)
e) Contractor’s profit @ 17,000.76
10% on (a+b+c+d)
Cost for 225 cum = 187,008.37
a+b+c+d+e
Rate per cum = 831.15
(a+b+c+d+e)/225
(iii) For Grading III Material
Unit = cum
Taking output = 225 cum
(450 t)
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Wet mix plant @ 60 t hour 7.50 1,050.00 7,875.00
capacity per hour
Water tanker 6 kl hour 4.00 295.00 1,180.00
capacity 5 km lead
with one trip per hour
Front end loader 0.9 hour 9.00 787.00 7,083.00
cum bucket capacity
25 cum per hour
Tipper 5.5 cum, 3 trips hour 13.60 275.00 3,740.00
per hour
Motor grader 110 HP hour 4.50 1,350.00 6,075.00
@ 50 cum per hour
Three wheel 80-100 hour 22.50 420.00 9,450.00
kN static roller 10 cum
output
c) Material
Well graded granular
sub-base material as
per Table 400.1
9.5 mm to 4.75 mm @ cum 100.80 485.00 48,888.00
35 per cent
4.75 mm to 2.36 mm cum 36.00 455.00 16,380.00
@ 12.5 per cent
2.36 mm below @ cum 151.20 300.00 45,360.00
52.5 per cent
Water kl 24.00 45.00 1,080.00
d) Overheads @ 10% 14,832.44
on (a+b+c)
e) Contractor’s profit @ 16,315.68
10% on (a+b+c+d)
Cost for 225 cum = 179,472.49
a+b+c+d+e
Rate per cum = 797.66
(a+b+c+d+e)/225
Say Rs. 797.70
4.2 402 i) Gravel/Soil-Aggregate Base
(Table 400.2) Grading A
123
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/soil-
aggregate base by providing
well graded material, spreading
in uniform layers with Tractor
mount grader on prepared
surface, mixing by mix in place
method with rotavator at OMC,
and compacting with three
wheel 80-100 kN static roller to
achieve the desired density,
complete as per Technical
Specifications Clause 402
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 hour 12.00 690.00 8,280.00
cum per hour
Three wheel 80-100 kN hour 30.00 420.00 12,600.00
static roller @ 10 cum per
hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 hour 12.00 390.00 4,680.00
cum per hour
c) Material
For well graded granular cum 360.00 490.00 176,400.00
sub-base materials as per
Table 400.2
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on 20,599.84
(a+b+c)
e) Contractor’s profit @ 22,659.82
10% on (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 249,258.03
Rate per cum = 830.86
(a+b+c+d+e)/300
Say Rs. 830.90
ii) Gravel/Soil-Aggregate Base
(Table 400.2) Grading B
Construction of granular sub-
base by providing well graded
material, spreading in uniform
layers with Tractor mount grader
on prepared surface, mixing by
mix in place method with
rotavator at OMC, and
compacting with three wheel
80-100 kN static roller capacity
to achieve the desired density,
complete as per Technical
Specification Clause 402
124
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @25 hour 12.00 690.00 8,280.00
cum per hour
Three wheel 80-100 kN hour 30.00 420.00 12,600.00
static roller @ 10 cum per
hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 hour 12.00 390.00 4,680.00
cum per hour
c) Material
For well graded granular cum 360.00 485.00 174,600.00
sub-base materials as per
Table 400.2
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on 20,419.84
(a+b+c)
e) Contractor’s profit @ 22,461.82
10% on (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 247,080.03
Rate per cum = 823.60
(a+b+c+d+e)/300
Say Rs. 823.60
125
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
iii) Gravel/Soil-Aggregate Base
(Table 400.2) Grading C
Construction of granular sub-
base by providing well graded
material, spreading in uniform
layers with Tractor mount grader
on prepared surface, mixing by
mix in place method with
rotavator at OMC, and
compacting with three wheel
80-100 kN static roller capacity
to achieve the desired density,
complete as per Technical
Specification Clause 402
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 hour 12.00 690.00 8,280.00
cum per hour
Three wheel 80-100 kN hour 30.00 420.00 12,600.00
static roller @ 10 cum per
hour
Water tanker 6 kl capacityhour 5.00 295.00 1,475.00
Tractor with Rotavator 25 hour 12.00 390.00 4,680.00
cum per hour
c) Material
For well graded granular cum 360.00 480.00 172,800.00
sub-base materials as per
Table 400.2
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on 20,239.84
(a+b+c)
e) Contractor’s profit @ 22,263.82
10% on (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 244,902.03
Rate per cum = 816.34
(a+b+c+d+e)/300
Say Rs. 816.35
iv) Gravel/Soil Aggregate Sub-base
Nominal Maximum size Grading 80
mm (Table 2.3 of IRC SP 77-2008)
126
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/Soil Aggregate
Sub-base/Base by providing well
graded material of nominal maximum
size grading 80 mm as per Table 2.3
of IRC SP 77-2008, spreading in
uniform layers with tractor nount
approprate grading arrangements on
prepared surface, mixing by mix in
place method at OMC with tractor
mount appropriate rotavator
attachment and compaction with three
wheel 80-100 kN static roller capacity
to achieve the desired density
complete as per specifications
contained in Para 2.2, 3.6 and 3.7 of
IRC SP 77-2008.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
well graded Gravel/Soil cum 360.00 420.00 151,200.00
aggregate base material of
nominal maximum size 80 mm
as per Table 2.3 of IRC SP 77-
2008.
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 18,079.84
e) Contractor’s profit @ 10% on 19,887.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 218,719.36
Rate per cum = (a+b+c+d+e)/300 729.06
Say Rs. 729.20
v) Gravel/Soil Aggregate Sub-base
Nominal Maximum size Grading 40
mm (Table 2.3 of IRC SP 77-2008)
127
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/Soil Aggregate
Sub-base/Base by providing well
graded material of nominal maximum
size grading 40 mm as per Table 2.3
of IRC SP 77-2008, spreading in
uniform layers with tractor nount
approprate grading arrangements on
prepared surface, mixing by mix in
place method at OMC with tractor
mount appropriate rotavator
attachment and compaction with three
wheel 80-100 kN static roller capacity
to achieve the desired density
complete as per specifications
contained in Para 2.2, 3.6 and 3.7 of
IRC SP 77-2008.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
well graded Gravel/Soil cum 360.00 440.00 158,400.00
aggregate base material of
nominal maximum size 40 mm
as per Table 2.3 of IRC SP 77-
2008.
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 18,799.84
e) Contractor’s profit @ 10% on 20,679.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 227,431.36
Rate per cum = (a+b+c+d+e)/300 758.10
Say Rs. 758.30
vi) Gravel/Soil Aggregate Sub-base
Nominal Maximum size Grading 20
mm (Table 2.3 of IRC SP 77-2008)
128
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/Soil Aggregate
Sub-base/Base by providing well
graded material of nominal maximum
size grading 20 mm as per Table 2.3
of IRC SP 77-2008, spreading in
uniform layers with tractor nount
approprate grading arrangements on
prepared surface, mixing by mix in
place method at OMC with tractor
mount appropriate rotavator
attachment and compaction with three
wheel 80-100 kN static roller capacity
to achieve the desired density
complete as per specifications
contained in Para 2.2, 3.6 and 3.7 of
IRC SP 77-2008.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
well graded Gravel/Soil cum 360.00 460.00 165,600.00
aggregate base material of
nominal maximum size 20 mm
as per Table 2.3 of IRC SP 77-
2008.
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 19,519.84
e) Contractor’s profit @ 10% on 21,471.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 236,143.36
Rate per cum = (a+b+c+d+e)/300 787.14
Say Rs. 787.30
4.3 i) Gravel/Soil-Aggregate Surface
Course (Table 400.3)
129
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of granular surface
course by providing well graded
material, spreading in uniform layers
with Tractor mount grader on prepared
surface, mixing by mix in place
method with rotavator at OMC, and
compacting with three wheel 80-100
kN static roller capacity to achieve the
desired density, complete as per
Technical Specification Clause 402
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
For well graded granular sub- cum 360.00 465.00 167,400.00
base materials as per Table
400.3
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 19,699.84
e) Contractor’s profit @ 10% on 21,669.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 238,321.36
Rate per cum = (a+b+c+d+e)/300 794.40
Say Rs. 794.40
ii) Gravel/Soil Aggregate Sub-base
Nominal Maximum size Grading 10
mm (Table 2.3 of IRC SP 77-2008)
130
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/Soil Aggregate
Sub-base/Base by providing well
graded material of nominal maximum
size grading 10 mm as per Table 2.3
of IRC SP 77-2008, spreading in
uniform layers with tractor nount
approprate grading arrangements on
prepared surface, mixing by mix in
place method at OMC with tractor
mount appropriate rotavator
attachment and compaction with three
wheel 80-100 kN static roller capacity
to achieve the desired density
complete as per specifications
contained in Para 2.2, 3.6 and 3.7 of
IRC SP 77-2008.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
well graded Gravel/Soil cum 360.00 480.00 172,800.00
aggregate base material of
nominal maximum size 10 mm
as per Table 2.3 of IRC SP 77-
2008.
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 20,239.84
e) Contractor’s profit @ 10% on 22,263.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 244,855.36
Rate per cum = (a+b+c+d+e)/300 816.18
Say Rs. 816.35
iii) Gravel/Soil Aggregate Sub-base
Nominal Maximum size Grading 5
mm (Table 2.3 of IRC SP 77-2008)
131
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of gravel/Soil Aggregate
Sub-base/Base by providing well
graded material of nominal maximum
size grading 5 mm as per Table 2.3 of
IRC SP 77-2008, spreading in uniform
layers with tractor nount approprate
grading arrangements on prepared
surface, mixing by mix in place
method at OMC with tractor mount
appropriate rotavator attachment and
compaction with three wheel 80-100
kN static roller capacity to achieve the
desired density complete as per
specifications contained in Para 2.2,
3.6 and 3.7 of IRC SP 77-2008.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 116.67 46.67
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 8.00 116.67 933.36
b) Machinery
Tractor mount grader @ 25 cum hour 12.00 690.00 8,280.00
per hour
Three wheel 80-100 kN static hour 30.00 420.00 12,600.00
roller @ 10 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
Tractor with Rotavator 25 cum hour 12.00 390.00 4,680.00
per hour
c) Material
well graded Gravel/Soil cum 360.00 490.00 176,400.00
aggregate base material of
nominal maximum size 10 mm
as per Table 2.3 of IRC SP 77-
2008.
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 20,599.84
e) Contractor’s profit @ 10% on 22,659.82
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 249,211.36
Rate per cum = (a+b+c+d+e)/300 830.70
Say Rs. 830.90
4.4 402(i) Lime Stabilisation for Improving
Subgrade
132
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Laying and spreading available soil in
the subgrade on a prepared surface,
pulverising, mixing the spread soil in
place with rotavator with 2 per cent
slaked lime having minimum 70 per
cent of contents of CaO, grading with
motor grader and compacting with the
smooth wheel road roller at OMC to
the desired density to form a layer of
improved Sub-grade as per Technical
Specification Cluase 403.
133
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
c) Material
Lime t 10.50 6,000.00 63,000.00
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on 8,108.30
(a+b+c)
e) Contractor’s profit @ 8,919.13
10% on (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 98,110.47
Unit = cum
Taking output = 300 cum (525 t)
a) Labour
Mate day 0.48 116.67 56.00
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
b) Machinery
Hydraulic Excavator 0.90 cum hour 5.00 1,100.00 5,500.00
bucket capacity
Tipper 5.5 cum 4 trips per hour hour 14.00 275.00 3,850.00
Motor grader 110 HP @ 50 cum hour 6.00 1,350.00 8,100.00
per hour
Three wheel 80-100 kN Static hour 4.30 420.00 1,806.00
roller @ 70 cum per hour
Tractor with rotavator and blade hour 12.00 390.00 4,680.00
@ 25 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
c) Material
Lime t 21.00 6,000.00 126,000.00
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on (a+b+c) 15,421.70
134
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Cost for 300 cum = a+b+c+d+e 186,602.62
Rate per cum = (a+b+c+d+e)/300 622.01
Say Rs. 622.00
Note: The exact quantity of lime shall be as
per design.
4.6 404 Cement Treated Soil
Sub-Base/Base
Providing, laying and spreading soil on
a prepared sub-grade, pulverising,
adding the designed quantity of
cement to the spread soil, mixing in
place with rotavator, grading with the
motor grader and compacting with the
road roller at OMC to achieve the
desired unconfined compressive
strength and to form a layer of sub-
base/base as per Technical
Specification Clause 404.
Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement
by weight of soil
a) Labour
Mate day 0.48 116.67 56.00
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
b) Machinery
Hydraulic Excavator 0.90 cum hour 5.00 1,100.00 5,500.00
bucket capacity
Tipper 5.5 cum hour 14.00 275.00 3,850.00
Motor grader 110 HP @ 50 cum hour 6.00 1,350.00 8,100.00
per hour
Three wheel 80-100 kN static hour 4.30 420.00 1,806.00
roller @ 70 cum per hour
Tractor with rotavator and blade hour 12.00 390.00 4,680.00
@ 25 cum per hour
Water tanker 6 kl capacity hour 5.00 295.00 1,475.00
c) Material
Cement at site @ 4% (of 525 t) t 21.00 4,900.00 102,900.00
Water kl 30.00 45.00 1,350.00
d) Overheads @ 10% on 13,111.70
(a+b+c)
e) Contractor’s profit @ 10% on 14,422.87
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 158,651.62
Rate per cum =(a+b+c+d+e)/300 528.84
Say Rs. 528.85
Note: The exact quantity of cement shall be
as per design.
135
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
4.7 405 Water Bound Macadam
Sub-base/base
1) WBM Grading 1
Providing, laying, spreading and
compacting stone aggregates of
specific sizes to water bound
macadam specification including
spreading in uniform thickness,
hand packing, rolling with three
wheel 80-100 kN static roller in
stages to proper grade and
camber, applying and brooming,
stone screening/binding
materials to fill-up the interstices
of coarse aggregate, watering
and compacting to the required
density Grading 1 as per
Technical Specification Clause
404.
136
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
e) Contractor’s profit 31,343.50
@ 10% on (a+b+c+d)
137
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Providing, laying, spreading and
compacting stone aggregates of
specific sizes to water bound
macadam specification including
spreading in uniform thickness,
hand packing, rolling with
smooth wheel roller 80-100 kN
in stages to proper grade and
camber, applying and brooming,
stone screening/ binding
materials to fill-up the interstices
of coarse aggregate, watering
and compacting to the required
density grading 2 as per
Technical Specification Clause
405.
Binding Material
Binding Material @ cum 28.80 200.00 5,760.00
0.06 cum per 10 sqm
for Grading 2 material
Water kl 144.00 45.00 6,480.00
138
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
d) Overheads @ 10% 30,218.97
on (a+b+c)
e) Contractor’s profit 33,240.86
@ 10% on (a+b+c+d)
Binding Material
Binding Material @ cum 28.80 200.00 5,760.00
0.06 cum per 10 sqm
for Grading 2 material
Water kl 144.00 45.00 6,480.00
d) Overheads @ 10% 28,339.55
on (a+b+c)
e) Contractor’s profit 31,173.51
@ 10% on (a+b+c+d)
139
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Note: Type A Screening can be used in
Grading 2
140
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
3) WBM Grading 3
Providing, laying, spreading and
compacting stone aggregates of
specific sizes to water bound
macadam specification including
spreading in uniform thickness,
hand packing, rolling with
smooth wheel roller 80-100 kN
in stages to proper grade and
camber, applying and brooming,
stone screening to fill-up the
interstices of coarse aggregate,
watering and compacting to the
required density Grading 3 as
per Technical Specification
Clause 405.
141
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
a) Labour
Mate day 0.68 116.67 79.34
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 15.00 116.67 1,750.05
b) Machinery
Motor grader 110 HP hour 7.20 1,350.00 9,720.00
@ 50 cum per hour for
spreading
142
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Providing, laying, spreading and
compacting stone aggregates of
specific sizes to water bound
macadam specification including
spreading in uniform thickness,
hand packing, rolling with three
wheel 80-100 kN static roller in
stages to proper grade and
camber, applying and brooming,
crushable screening to fill-up the
interstices of coarse aggregate,
watering and compacting to the
required density Grading 1 as
per Technical Specification
Clause 405.
143
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Taking output = 360 cum
a) Labour
Mate day 0.68 116.67 79.34
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 15.00 116.67 1,750.05
b) Machinery
Motor grader 110 HP hour 7.20 1,350.00 9,720.00
@ 50 cum per hour for
spreading
144
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
(A) By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 116.67 1,176.03
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 250.00 116.67 29,167.50
b) Machinery
Three wheel 80-100 hour 45.00 420.00 18,900.00
kN static roller @ 8
cum per hour
Water tanker 6 kl hour 24.00 295.00 7,080.00
capacity
c) Material (Refer
Tables 400.7, 8, 9
and 10)
Aggregate
Grading 2 63 mm to cum 435.60 430.00 187,308.00
45 mm @ 0.91 cum
per 10 sqm for
compacted thickness
of 75 mm
Crushable type such cum 105.59 300.00 31,677.00
as Moorum or gravel
for Grading 2 @ 0.22
cum per 10 sqm
Water kl 144.00 45.00 6,480.00
d) Overheads @ 10% 28,202.19
on (a+b+c)
e) Contractor’s profit 31,022.41
@ 10% on (a+b+c+d)
145
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
c) Material (Refer
Tables 400.7, 8, 9
and 10)
Aggregate
Grading 2 63 mm to cum 435.60 430.00 187,308.00
45 mm @ 0.91 cum
per 10 sqm for
compacted thickness
of 75 mm
Crushable type such cum 105.59 300.00 31,677.00
as Moorum or gravel
for Grading 2 @ 0.22
cum per 10 sqm
Water kl 144.00 45.00 6,480.00
d) Overheads @ 10% 26,322.77
on (a+b+c)
e) Contractor’s profit 28,955.05
@ 10% on (a+b+c+d)
146
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
c) Material (Refer
Tables 400.7, 8, 9
and 10)
Aggregate
Grading 3 53 mm to cum 435.60 440.00 191,664.00
22.4 mm @ 0.91 cum
per 10 sqm for
compacted thickness
of 75 mm
Crushable type such cum 105.59 300.00 31,677.00
as Moorum or gravel
for Grading 3 @ 0.22
cum per 10 sqm
Water kl 144.00 45.00 6,480.00
d) Overheads @ 10% 28,637.79
on (a+b+c)
e) Contractor’s profit 31,501.57
@ 10% on (a+b+c+d)
147
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
d) Overheads @ 10% 26,758.37
on (a+b+c)
e) Contractor’s profit 29,434.21
@ 10% on (a+b+c+d)
148
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
d) Overheads @ 10% on (a+b+c) 7,120.87
e) Contractor’s profit @ 10% on 7,832.96
(a+b+c+d)
Cost for 100 cum = a+b+c+d+e 86,162.55
Rate per cum = (a+b+c+d+e)/100 861.63
Say Rs. 861.65
4.10 407 Construction of Shoulders as per
Technical Specification Clause 407.
A. Earthen Shoulders
The rate as applicable for sub-
grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base
and/or base may be adopted as
per approved design.
C. Paved Shoulders
The rates may be adopted as
applicable for different layers of
pavement depending upon
approved design of paved
shoulders.
149
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
(c) Material
Naturally occurring gravel
(Local materials as per
Table 400.13)
Quantity as per Item cum 384.00 200.00 76,800.00
No.4.1 of Chapter 4
Water kl 30.00 45.00 1,350.00
(d) Overheads @ 10% on 10,646.10
(a+b+c)
(e) Contractor’s profit @ 11,710.71
10% on (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 128,817.86
Rate per cum = a+b+c+d+e/300 429.39
150
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Providing, laying spreading and
compacting local material in block or
large discrete particles, such as
kankar, Laterite, Dhandla etc. as per
Table 400.13 to water bound
macadam specification including
spreading in uniform thickness, hand
packing, rolling with three wheel 80-
100 kN static roller in stages to proper
grade and camber, applying and
brooming requisite type of
screening /binding materials to fill-up
the interstices of laid material watering
and compacting to the required
density as per Clause 405.3 and
Technical Specification Cluase 408.
Unit = cum
Taking output = 360 cum
(a) Labour
Mate day 0.68 116.67 79.34
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 15.00 116.67 1,750.05
(b) Machinery
Motor grader 110 H.P @ 50 hour 7.20 1,350.00 9,720.00
cum/hr for spreading
Three wheel 80-100 kN @ static hour 45.00 420.00 18,900.00
roller 8 cum per hour
Water tanker 6 kl capacity hour 24.00 295.00 7,080.00
(c) Material
Low Grade Aggregate such as cum 435.60 200.00 87,120.00
Kankar, Laterite, Dhandla and
naturally occuring gravels,
quarry waste as per Table
400.13 @ 1.21 cum per 10 sqm
compacted thickness 100 mm
151
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Construction of sub-base using lime-
flyash admixture with granular soil,
free from organic matter/deleterious
material or clayey silts and low
plasticity clays having PI between 5
and 20 and liquid limit less than 25
and commercial dry lime, slaked at
site or pre-slaked with CaO content
not less than 50 per cent, flyash to
conform to gradation as per Clause
4.3 of IRC:SP:20, lime+flyash content
ranging between 10 to 30 per cent, the
minimum un-confined compressive
strength and CBR value after 28-days
curing and 4-days soaking to be 0.75
MPa and 25 per cent respectively, all
as specified in IRC:88 including a lead
upto 1000 m as per Technical
Specification Cluase 409.
Unit = cum
Taking output = 480 cum (720 t,
density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime+Flyash admixture
@ 20% = 0.2 x 720=144 t
Soil = 720-144 = 578 t
(578/1.6 = 360 cum)
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 t
Flyash = 115 t
a) Labour
Mate day 0.28 116.67 32.67
Mazdoor (Unskilled) day 6.00 116.67 700.02
Mazdoor (Skilled) day 1.00 116.67 116.67
b) Machinery
Hydraulic Excavator 0.90 cum hour 6.00 1,100.00 6,600.00
bucket capacity @ 60 cum per
hour for 360 cum soil
Tipper 10 t capacity for carriage hour 16.00 275.00 4,400.00
of soil 578 t
Tipper 10 t capacity for carriage hour 5.50 275.00 1,512.50
of 115 t flyash
Tipper 10 t capacity for carriage hour 3.80 275.00 1,045.00
of 29 t of lime from store to
work site
Loading as per item 1.1 (ii) cum 480.00 18.00 8,640.00
Unloading as per item 1.1 (iv) cum 480.00 11.05 5,304.00
Tractor with disc harrows for hour 6.00 390.00 2,340.00
pulverisation
152
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Motor Grader 110 HP @ 75 per hour 3.20 1,350.00 4,320.00
cent 200 cum per hour for
mixing in-place and grading
Three wheel 80-100 kN static hour 12.00 420.00 5,040.00
roller
Water tanker 6 kl capacity hour 12.00 295.00 3,540.00
c) Material
Lime (Slaked) t 29.00 6,000.00 174,000.00
Compensation for earth taken cum 360.00 40.00 14,400.00
from private source
Water kl 72.00 45.00 3,240.00
d) Overheads @ 10% on (a+b+c) 23,523.09
e) Contractor’s profit @ 10% on 25,875.39
(a+b+c+d)
Cost for 480 cum = a+b+c+d+e 284,629.34
Rate per cum = (a+b+c+d+e)/480 592.98
Say Rs. 593.00
Note: 1 Compensation for earth will vary
from place to place and will have
to be assessed realistically as
per particular ground situation.
In case earth is available from
Govt. land, compensation for
earth will not be required. The
position is required to be clearly
stated in the cost estimate.
Unit = cum
Taking output = 300 cum
(a) Labour
153
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
As per Item No.4.1 of Chapter 4 1,456.04
(b) Machinery
As per Item No.4.1 of Chapter 4 27,035.00
(c) Material
Crushed slag as per Clause
410.4.2 (i)
As per Item No.4.2 of Chapter 4 cum 384.00 235.00 90,240.00
Water kl 30.00 45.00 1,350.00
(d) Overheads @ 10% on (a+b+c) 12,008.10
(e) Contractor’s profit @ 10% on 13,208.91
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 145,298.06
Rate per cum = (a+b+c+d+e)/300 484.33
Say Rs. 483.60
4.15 410 Water Bound Macadam using
crushed slag
Providing, laying, spreading and
compacting crushed slag to water
Bound Macadam specification
including spreading in uniform
thickness, hand packing rolling with
smooth wheel roller 80-100 kN in
stages to proper grade and camber,
applying and brooming requisite type
of screening/binding materials to fill up
the interstees of crushed slag watering
and compacting to the required
density as per Clause 405.3 and
Technical Specification Cluase
410.3.2.
Unit = cum
Taking output = 360 cum
(a) Labour
As per Item No. 4.7(B) of 2,062.73
Chapter 4
(b) Machinery
As per Item No.4.7(B) of 31,920.00
Chapter 4
(c) Material
As per Item No.4.8 (1)(A)(c) of
Chapter 4
Crushed slag as per Clause cum 435.60 235.00 102,366.00
410.4.2 (ii)
Crushable screening cum 108.00 300.00 32,400.00
Water kl 144.00 45.00 6,480.00
(d) Overhead @ 10% on (a+b+c) 17,522.87
(e) Contractor’s profit @ 10% on 19,275.16
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e 212,026.76
Rate per cum = (a+b+c+d+e)/360 588.96
Say Rs. 589.00
154
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
4.16 410 Cement Bound Granular Material
sub-base/base
Providing laying and spreading
granulated blast furnace slag on a
prepared sub-grade pulverising adding
the designed quantitity of cement to
the spread granulated blast furnace
slag mixing in place with rotavator
grading with the mortar grader and
compacting with smooth wheel roller
80-100 kN at OMC to achieve the
desired unconfined compressive
strength and to form a layer of sub-
base/base as per Technical
Specification Clauses 404.3 and
410.4.2.
Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement by
wt of granulated blast furnace slag
(a) Labour
Mate day 0.48 116.67 56.00
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
(b) Machinery
5.50 cum Tipper for carriage of hour 15.00 275.00 4,125.00
GBFS add 10 per cent of cost of
carriage of cover cost of loading
and unloading
Motor grader 110 HP @ 50 cum hour 6.00 1,350.00 8,100.00
per hour
Three wheel 80-100 kN static hour 4.30 420.00 1,806.00
roller @ 70 cum per hour
Tractor with rotavator and blade hour 12.00 390.00 4,680.00
@ 25 cum per hour
Water tanker 6 kl capacity hour 7.00 295.00 2,065.00
(c) Material
Cement (4%) t 21.00 4,900.00 102,900.00
Water kl 42.00 45.00 1,890.00
(d) Overheads @ 10% on (a+b+c) 12,702.20
(e) Contractor’s profit 10% on 13,972.42
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 153,696.67
Rate per cum = (a+b+c+d+e)/300 512.32
Say Rs. 512.30
Note: (i) The exact quantity of cement
shall be as per design
(ii) Granulated ballast slag will be
available free of cost
155
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
4.17 411 Crusher Run Macadam Base
Providing crushed run stone
aggregate greading conforming to
table 400.20 depositing on a prepared
surface by hauling vehicles, spreading
and mixing with a motor grader,
watering and compacting with a three
wheel 80-100 kN static roller as per
Technical Specification Clause 411 to
form a layer of sub-base/base
A) By mix-in-place method
(i) With 53 mm maximum size
of aggregates
Unit = cum
Taking output = 360 cum
(a) Labour
Mate day 0.48 116.67 56.00
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
(b) Machinery
Tractor attached with hour 14.00 390.00 5,460.00
rotavator @ 25 cum
per hour
Motor-Grader 110 H.P hour 6.00 2,230.00 13,380.00
Three wheel 80-100 hour 45.00 420.00 18,900.00
kN static roller @ 8
cum per hour
Water tanker 6 kl hour 6.00 295.00 1,770.00
capacity
(c) Material
Aggregate at site
For 53 mm maximum
size
63 mm to 45 mm @ cum 157.46 430.00 67,707.80
33 per cent
22.5 mm to 5.6 mm @ cum 151.06 475.00 71,753.50
32 per cent
Below 5.6 mm @ 35 cum 116.68 490.00 57,173.20
per cent
Water kl 36.00 45.00 1,620.00
(d) Overheads @ 10% 23,922.05
on (a+b+c)
(e) Contractor’s profit @ 26,314.26
10% on (a+b+c+d)
Cost for 360 cum = 289,456.86
a+b+c+d+e
Rate per cum = 804.05
(a+b+c+d+e)/360
Say Rs. 804.05
(ii) With 37.5 mm maximum
size of aggregates
Unit = cum
Taking output = 360 cum
(a) Labour
Mate day 0.48 116.67 56.00
156
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Mazdoor (Skilled) day 2.00 116.67 233.34
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
(b) Machinery
Tractor attached with hour 14.00 390.00 5,460.00
rotavator @ 25 cum
per hour
Motor-Grader 110 H.P hour 6.00 2,230.00 13,380.00
Three wheel 80-100 hour 45.00 420.00 18,900.00
kN static roller @ 8
cum per hour
Water tanker 6 kl hour 6.00 295.00 1,770.00
capacity
(c) Material
Aggregate at site
For 37.5 mm
maximum size
45 mm to 22.5 mm @ cum 24.12 450.00 10,854.00
5 per cent
22.4 mm to 5.6 mm @ cum 237.60 475.00 112,860.00
50 per cent
Below 5.6 mm @ 45 cum 213.48 490.00 104,605.20
per cent
Water kl 36.00 45.00 1,620.00
(d) Overheads @ 10% 27,090.52
on (a+b+c)
(e) Contractor’s profit @ 29,799.58
10% on (a+b+c+d)
Cost for 360 cum = 327,795.34
a+b+c+d+e
Rate per cum = 910.54
(a+b+c+d+e)/360
Say Rs. 910.55
B) By mixing plant method
(i) With 53 mm maximum size
of aggregates
Unit = cum
Taking output = 225 cum
(450 t)
(a) Labour
Mate day 0.28 116.67 32.67
Mazdoor (Skilled) day 1.00 116.67 116.67
Mazdoor (Unskilled) day 6.00 116.67 700.02
(b) Machinery
Wet mix plant @ 75 t hour 6.00 1,050.00 6,300.00
per hour
Electric generator set, hour 6.00 670.00 4,020.00
125 KVA
Front end loader 1 hour 6.00 787.00 4,722.00
cum bucket capacity
Motor grader 110 HP hour 6.00 2,230.00 13,380.00
Three wheel roller 80- hour 28.13 420.00 11,814.60
100 kN @ 8 cum per
hour
Water tanker hour 3.00 295.00 885.00
Tipper hour 10.00 275.00 2,750.00
157
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
(c) Material
Aggreate at site
For 53 mm maximum
size
63 mm to 45 mm @ cum 98.40 430.00 42,312.00
33 per cent
22.4 mm to 5.6 mm @ cum 94.41 475.00 44,844.75
32 per cent
Below 5.6 mm @ 35 cum 104.18 490.00 51,048.20
per cent
Water kl 18.00 45.00 810.00
(d) Overheads @ 10% 18,373.59
on (a+b+c)
(e) Contractor’s profit @ 20,210.95
10% on (a+b+c+d)
Cost for 225 cum = 222,320.45
a+b+c+d+e
Rate per cum = 988.09
(a+b+c+d+e)/225
Say Rs. 998.10
(ii) With 37.5 mm maximum
size of aggregates
Unit = cum
Taking output = 225 cum
(450 t)
(a) Labour
Mate day 0.28 116.67 32.67
Mazdoor (Skilled) day 1.00 116.67 116.67
Mazdoor (Unskilled) day 6.00 116.67 700.02
(b) Machinery
Wet mix plant @ 75 t hour 6.00 1,050.00 6,300.00
per hour
Electric generator set, hour 6.00 670.00 4,020.00
125 KVA
Front end loader 1 hour 6.00 787.00 4,722.00
cum bucket capacity
Mortar grader 110 HP hour 6.00 2,230.00 13,380.00
Three wheel roller 80- hour 28.13 420.00 11,814.60
100 kN @ 8 cum per
hour
Water tanker hour 3.00 295.00 885.00
Tipper hour 10.00 275.00 2,750.00
(c) Material
Aggreate at site
For 37.5 mm
maximum size
45 mm to 22.5 mm @ cum 15.06 450.00 6,777.00
5 per cent
22.4 mm to 5.6 mm @ cum 148.50 475.00 70,537.50
50 per cent
Below 5.6 mm @ 45 cum 133.00 490.00 65,170.00
per cent
Water kl 18.00 45.00 810.00
158
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
(d) Overheads @ 10% 18,801.55
on (a+b+c)
(e) Contractor’s profit @ 20,681.70
10% on (a+b+c+d)
Cost for 225 cum = 227,498.70
a+b+c+d+e
Rate per cum = 1,011.11
(a+b+c+d+e)/225
Say Rs. 1,011.10
4.18 412 Brick Soling
Laying brick soling layer on prepared
sub-grade with brick on end edging
according to lines, graded and cross-
section shown on the drawing filling
joints with sand and earth, spreading
25 mm thick layer of earth over brick
soling, watering and rolliing the same
with three wheel road roller 80-100 kN
as per Technical Specification Clause
412
Unit = sqm
Taking ouput = 150 sqm
(a) Labour
Mate day 0.52 116.67 60.67
Mazdoor (Unskilled) day 10.00 116.67 1,166.70
Mason 1st Class day 3.00 211.17 633.51
(b) Machinery
Three wheel 80-100 kN static hour 1.00 420.00 420.00
roller
Water tanker hour 1.00 295.00 295.00
(c) Material
Brick 1st Class No. 8,160.00 3.00 24,480.00
Brick 1st Class on edging No. 1,100.00 3.00 3,300.00
Fine Sand cum 5.66 300.00 1,698.00
Water kl 6.00 45.00 270.00
(d) Overheads @ 10% on (a+b+c) 3,232.39
(e) Contractor’s profit @ 10% on 3,555.63
(a+b+c+d)
Cost for 150 sqm = a+b+c+d+e 39,111.89
Rate per sqm = (a+b+c+d+e)/150 260.75
Say Rs. 260.75
159
Reference to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
4.19 413 Stone Set Pavement
Providing and laying stone set
pavement on prepared surface with
sub-base 100 mm thick compacted
Granular Sub-base as per Clause
401.4 and base 75 mm thick
compacted water bound macadam
grading 2 as per Clause 405.3. The
150 mm thick hammer desired stones
are laid in the herring one or stretched
bond pattern. The stones are
compacted into the bedding sand of
40 mm over the WBM base bounded
by edge stone using suitable
compacting device. The gaps are
filled with fine sand stone dust as per
Technical Specification Clause 413.4
Unit = sqm
Taking output = 360 sqm
(a) Labour
Mate day 2.16 116.67 252.01
Mazdoor (Unskilled) day 51.00 116.67 5,950.17
Mason 2nd class for laying sett day 13.00 158.67 2,062.71
stone and edge stone
(b) Machinery
Three wheel 80-100 kN static hour 2.00 420.00 840.00
roller
Water tanker 6 kl capacity hour 1.00 295.00 295.00
(c) Material
(1) Collection of fine sand
3.4x0.285x0.150x1.20 = cum 0.174 300.00 52.20
0.174
(2) Coarse sand
96x3.35x0.04x1.20 = cum 15.437 300.00 4,631.10
15.437 cum
(3) Collection of stone sett
stone
300 mmx200 mmx150 mm Nos 5,168.00 5.75 29,716.00
17x304 = 5168 nos.
(4) Collection of edge stone
450 mmx200 mmx350 mm Nos 464.00 45.00 20,880.00
2x232 = 464 nos.
(5) Water kl 6.00 45.00 270.00
(d) Overheads @ 10% on (a+b+c) 6,494.92
(e) Contractor’s profit @ 10% on 7,144.41
(a+b+c+d)
Cost of 360 sqm = a+b+c+d+e 78,588.52
Rate per sqm = (a+b+c+d+e)/360 218.30
Say Rs. 218.30
160
Analysis of rates
Reference to Description Unit Quantity Rate Amount (Rs.)
MORD (Rs.)
Sr. Specifications
No.
Stone Screening
Type B 11.2 mm for cum 96.01 896.00 86,024.96
Grading 2 @ 0.20 cum
per 10 sqm
Binding Material
Binding Material @ 0.06 cum 28.80 813.00 23,414.40
cum per 10 sqm for
Grading 2 material
Executive Engineer
Nalagarh Division HPPWD
Nalagarh
Analysis of rates
Reference to Description Unit Quantity Rate Amount (Rs.)
MORD (Rs.)
Sr. Specifications
No.
Aggregate
Grading 3 53 mm to cum 435.60 1,096.00 477,417.60
22.4 mm @ 0.91 cum
per 10 sqm for
compacted thickness of
75 mm
Stone Screening
Type B 11.2 mm for cum 86.40 896.00 77,414.40
Grading 3 @ 0.18 cum
per 10 sqm
Water kl 144.00 50.00 7,200.00
d) Overheads @ 10% on 61,436.34
(a+b+c)
Executive Engineer
Nalagarh Division HPPWD
Nalagarh
Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor mount
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel
roller to achieve the desired density, complete as per Technical Specification Clause 401.By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor mount
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel
roller to achieve the desired density, complete as per Technical Specification Clause 401.By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor mount
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel
roller to achieve the desired density, complete as per Technical Specification Clause 401.By Mix in Place Method