Project:Altair Residential Tower, Colombo REV:01
Client:Indocean Developers(Pvt)Ltd Date: 19.03.2016
Main Contractor:Shapoorji Pallonji Lanka (Pvt)Ltd Last updated:
ISSUE: 01 Updated: 03.06.2016
Status Codes : APP-Approved, AAN-Approved As Noted, RR-Revised & resubmit, UR-Under Review/ Awaiting for Approval
Planned Revised Date
Sl
Submittal No. Rev.
Aconex Transmittal
Description Submission Planned Document
Submitted Date of Return
Reply Rec'd Transmittal STATUS
Remarks
No. No. Submission Date No. CODE
date date (Actual)

COMMON SYSTEM FOR ELECRICAL, ELV, FIRE DETECTION


1 ATR-SPLL(MAX)-EL-MST-0004 0 Installation of Slab Conduits 4-Apr-16 6-Jun-16
2 ATR-SPLL(MAX)-EL-MST-0005 0 Installation of Conduits for Brick Wall 2-Jun-16
3 ATR-SPLL(MAX)-EL-MST-0005-A 0 Installation of PVC conduit & accessories (dry wall) 18-May-16 15-Jun-16
4 ATR-SPLL(MAX)-EL-MST-0006 0 Installation of GI conduit & accessories 26-Apr-16 6-Jun-16
5 ATR-SPLL(MAX)-EL-MST-0007 0 Installation of GI trunking 3-Jun-16 11-Jun-16
6 ATR-SPLL(MAX)-EL-MST-0008 0 Installation of GI Tray and Ladders 17-Jun-16
I ELECTRICAL
7 ATR-SPLL(MAX)-EL-MST-0009 0 Installation of electrical system wiring 10-Apr-16 6-Jun-16
8 ATR-SPLL(MAX)-EL-MST-0010 0 Installation of distribution board 23-Jun-16
9 ATR-SPLL(MAX)-EL-MST-0011 0 Installation of transformer 13-Jul-16
10 ATR-SPLL(MAX)-EL-MST-0012 0 Installation of HT panels 23-Jul-16
11 ATR-SPLL(MAX)-EL-MST-0013 0 Installation of HT cables 2-Aug-16
12 ATR-SPLL(MAX)-EL-MST-0014 0 Installation of busbar trunking 12-Aug-16
13 ATR-SPLL(MAX)-EL-MST-0015 0 Installation of LT panels 22-Aug-16
14 ATR-SPLL(MAX)-EL-MST-0016 0 Installation of feeder cables - LV 1-Sep-16
15 ATR-SPLL(MAX)-EL-MST-0017 0 Installation of earthing and equipotential bonding 11-Sep-16
16 ATR-SPLL(MAX)-EL-MST-0018 0 Installation of lightning protection system 21-Sep-16 6-Jun-16
17 ATR-SPLL(MAX)-EL-MST-0019 0 Installation of diesel generators and emergency power plant 1-Oct-16
18 ATR-SPLL(MAX)-EL-MST-0020 0 Installation of UPS 11-Oct-16
19 ATR-SPLL(MAX)-EL-MST-0021 0 Installation of switch, sockets, isolators and light fitting 21-Oct-16
21 ATR-SPLL(MAX)-EL-MST-0022 0 Installation of manhole 31-Oct-16
22 ATR-SPLL(MAX)-EL-MST-0022-A 0 Installation of Air craft warning lamps 20-Jun-16
II COMMON SYSTEM FOR ELV SYSTEMS
23 ATR-SPLL(MAX)-ELV-MST-0023 Laying and termination of Category cables 11-May-16 8-Jun-16
a) CCTV System
24 ATR-SPLL(MAX)-ELV-MST-0024 0 Laying of Co-axial cables 20-Apr-16 8-Jun-16
25 ATR-SPLL(MAX)-ELV-MST-0025 0 Installation and Fixing of Cameras 20-May-16 30-Jun-16
26 ATR-SPLL(MAX)-ELV-MST-0026 0 Installation and Fixing of Head End Equipments 20-May-16 30-Sep-16
27 ATR-SPLL(MAX)-ELV-MST-0027 0 Installation of Intelligent Power Supply System c/w Cabling 20-May-16 20-Aug-16
28 ATR-SPLL(MAX)-ELV-MST-0028 0 Installation of CCTV Monitoring System 20-May-16 25-Aug-16

b) Video Door Phone System


29 ATR-SPLL(MAX)-ELV-MST-0029 0 Installation and Fixing of Floor Controllers 20-May-16 30-Aug-16
30 ATR-SPLL(MAX)-ELV-MST-0030 0 Installation and Fixing of Hand Free Tenant Stations 20-May-16 30-Aug-16
31 ATR-SPLL(MAX)-ELV-MST-0031 0 Installation of Master Control System 20-May-16 30-Aug-16

c) Access Control System


32 ATR-SPLL(MAX)-ELV-MST-0032 0 Installation and Fixing of Car Park Barrier Equipments 20-May-16 30-Aug-16
33 ATR-SPLL(MAX)-ELV-MST-0033 0 Installation and Fixing of Door Monitoring Equipments 20-May-16 30-Aug-16
34 ATR-SPLL(MAX)-ELV-MST-0034 0 Installation and Fixing of Panic Alarming Equipments 20-May-16 30-Aug-16

1 of 2
Annex 01
Description:

METHOD STATEMENT
SUBMISSION LOG FOR
INSTALLATION
Project:Altair Residential Tower, Colombo REV:01
Client:Indocean Developers(Pvt)Ltd Date: 19.03.2016
Main Contractor:Shapoorji Pallonji Lanka (Pvt)Ltd Last updated:
ISSUE: 01 Updated: 03.06.2016
Status Codes : APP-Approved, AAN-Approved As Noted, RR-Revised & resubmit, UR-Under Review/ Awaiting for Approval
Planned Revised Date
Sl
Submittal No. Rev.
Aconex Transmittal
Description Submission Planned Document
Submitted Date of Return
Reply Rec'd Transmittal STATUS
Remarks
No. No. Submission Date No. CODE
date date (Actual)
d) Telephone / DATA /TV System
35 ATR-SPLL(MAX)-ELV-MST-0035 0 Fixing of of Telephone, Data and TV Outlets 20-May-16 30-Sep-16
36 ATR-SPLL(MAX)-ELV-MST-0036 0 Installation and Fixing of Head Ends for the systems 20-May-16 30-Sep-16
37 ATR-SPLL(MAX)-ELV-MST-0037 0

III COMMON SYSTEM FOR FIRE ALARM AND EMERGENCY LIGHTING SYSTEMS
38 ATR-SPLL(MAX)-FA-MST-0038 0 Laying of Fire Rated Cables 11-May-16 2-Jun-16

a) Fire Detection, Alarm & Public Adress System


39 ATR-SPLL(MAX)-FA-MST-0039 0 Installation of Terminal Equipments 20-May-16 30-Sep-16
40 ATR-SPLL(MAX)-FA-MST-0040 0 Installation of Fire Detection, Alarm & Evacuation Panel 20-May-16 30-Sep-16

b) Emergency Lighting System


41 ATR-SPLL(MAX)-FA-MST-0041 0 Installation of Light Fittings 20-May-16 30-Aug-16
42 ATR-SPLL(MAX)-EL-MST-0042 0 Installation of Central battery system 6-Sep-16

No. of
Status
Submissions
Under review 0
Approved 0
Approved with comments 0
Total 0