03010-Specification For Construction
03010-Specification For Construction
03010-Specification For Construction
3. TECHNICAL REQUIREMENTS.............................................................3
3.1 General........................................................................................3
3.2 Pre-Construction Survey..............................................................4
3.3 Right-of-Way (ROW) ...................................................................4
3.4 Crossings.....................................................................................5
3.5 Clearing, Grading and Backfilling of ROW...................................6
3.6 Handling, Hauling, Stringing and Storage..................................10
3.7 Trenching ..................................................................................12
3.8 Pipe Laying and Jointing ...........................................................16
3.9 Backfilling ..................................................................................20
3.10 Tying-In .....................................................................................22
3.11 Special Crossings/Road Crossings ...........................................22
3.12 Final Clean-Up of the Construction Right-of-Way......................24
3.13 Encroachments and Working Near Other Utilities .....................25
3.14 Detectable Warning Tapes ........................................................26
6. DOCUMENTATION .............................................................................30
6.1 Records .....................................................................................30
6.2 As-Built Drawings and Pipe Book..............................................32
1. SCOPE OF SPECIFICATIONS
This specification covers minimum requirements for the construction, installation and
testingof High Density Polyethylene (HDPE) pipes and fittings in rural areas including
route survey,row, excavation, stringing, joint fusion, laying, backfilling, etc.
3. TECHNICAL REQUIREMENTS
3.1 General
CONTRACTOR shall prepare detailed Method Statements (MS), i.e. Construction
Procedures, for all described activities, and submit to ADWEA/ENGINEER for approval.
These MS's shall describe in detail how the CONTRACTOR proposes to perform the
various
activities to ensure compliance with the requirements as set forward in this Specification.
CONTRACTOR shall execute the work, with due care and diligence, in compliance
withinternational practice and all local laws, by-laws, ordinances, regulations, etc.,
provide allplant, services and labour, inclusive of supervision thereof, provide all
materials, excluding thematerials indicated as materials furnished by
ADWEA/ENGINEER in the Agreement, and provide all equipment, appliances or other
articles of whatsoever nature required for the execution of the work, whether of a
temporary or permanent nature.
All works shall be carried out in compliance with the regulations and requirement of the
Emirate of Abu Dhabi.
CONTRACTOR shall take full responsibility for the stability and safety of all operations
carriedout and all methods of work adopted. The CONTRACTOR shall also take full
responsibility for stability and safety of all existing facilities / utilities / roads/etc. affected
by any operation, design and method adopted by CONTRACTOR in executing the work.
CONTRACTOR shall be deemed to have inspected the work area(s) and their
surroundings and to have satisfied himself as to the form and nature thereof, including
sub-surface conditions, hydrological and climatic conditions, the extent and nature of the
work, the materials necessary for the completion of the work and the means of access to
all the work area(s). No claims either by way of cost or time shall be admissible on
account of nonfamiliarity with site conditions due to CONTRACTOR's failure to fully
access and fully allow for possible conditions throughout the contract period at the works
sites or in gaining access to them, before submitting his bid.
CONTRACTOR shall be deemed to have obtained all necessary information as above
mentioned as to risks, contingencies and all other circumstances, which may influence
the work.
CONTRACTOR shall, in connection with the work, provide and maintain at his own cost
all lights, safety barriers, fencing, watchmen (and associate facilities) etc., when and
where necessary as required by ADWEA/ENGINEER or by any duly constituted
Authority and/or by the Authorities having jurisdiction thereof for the protection of the
work and properties or for the safety and the convenience of public and/or others. Not
withstanding the soil type or method of construction indicated in the alignment sheets,
CONTRACTOR shall use the type of construction required by the actual soil conditions
at site at no additional cost to adwea after ADWEA/ENGINEER approval.
3.4 Crossings
Crossing of roads, buried services, etc. with equipment and/or personnel shall only be
permitted after the CONTRACTOR has obtained written approval from the authorities
having jurisdiction and ADWEA/ENGINEER. It shall be CONTRACTOR's responsibility
to acquaint himself with all relevant requirements and regulations of authorities and
governmental bodies having jurisdiction over highways, roads, pipelines, cables and
other services on the Right-of-Way or crossing the Right-of-Way and to obtain their
approval in writing and all necessary permits before commencing work.
Notwithstanding the provision of drawings and specifications by ADWEA/ENGINEER, it
shall also be CONTRACTOR's responsibility to ensure that the Work is performed to the
requirements and specifications of the relevant authorities. In the event that the
requirements and specifications of the authorities are more stringent than
ADWEA/ENGINEER's, then the authorities' requirements shall be performed at no cost
to ADWEA.
Highways, Main-Roads and their verges shall not be used for loading, unloading or
stacking of materials and/or equipment. For secondary roads, such loading/unloading is
permitted only after prior approval from the concerned authorities. CONTRACTOR shall
not close or divert roads without prior approval from ADWEA/ENGINEER and the
concerned authorities.
CONTRACTOR shall never unnecessarily hamper the users of the roads.
The diversion specifications, if required, shall conform to the approval of relevant
authorities and in accordance with the specifications required by them.
For construction methods of crossings reference is made to section 3.11.
ADWEA/ENGINEER.
PE pipe materials shall be stored under cover, protected from direct sunlight and
ensuring
good ventilation. Storage in containers is not recommended.
The materials mentioned above shall during loading, unloading, storage and use always
be handled to prevent any damage, deterioration, adulteration or dispersion and any
health hazard to human beings or livestock or any other damage. When supplied in
containers and envelopes, they shall not be dropped or thrown, or removed by means of
hooks during the handling operations and the containers shall only be disposed of in a
manner authorised by ADWEA/ENGINEER.
During unloading, transport and utilisation, any contact with water, hydrocarbons,
chemicals, mud, earth, dust, crushed stone and any other foreign material shall be
carefully avoided.
CONTRACTOR shall strictly comply with MANUFACTURER's instructions regarding
handling and storage, and in particular the temperature of volatile materials which are
susceptible to change in properties and primary characteristics due to unsuitable
storage.
For materials liable to corrosion while in storage, CONTRACTOR shall exercise proper
care including application of non-hydrocarbon grease or MANUFACTURER-
recommended treatment to areas/surfaces susceptible to rusting, or the provision of air-
conditioning for temperature/humidity control.
Flammable materials shall be stored in special safe storage locations.
3.7 Trenching
3.7.1 Excavation
CONTRACTOR shall excavate the pipeline trench on the surveyed route as staked and
to the design profile.
CONTRACTOR shall not start the ditching operations until the pipeline centreline has
been approved by ADWEA/ENGINEER.
CONTRACTOR shall excavate the pipeline trench within the cleared and graded ROW
using any method approved by ADWEA/ENGINEER. Care shall be exercised to see that
fresh material recovered from trenching operations, intended to be used for backfilling
over the pipe in the trench or at the berms, is not mixed with loose debris or with foreign
or rejected material, required to be removed from site.
Where the pipeline is to be laid in sand dunes, the trench shall be cut so that adequate
trench bottom width is obtained in compliance with the applicable drawings.
Pipe handling shall be in accordance with the requirements of Section 3.6 above.
Exposed PE pipe shall be properly supported and protected from UV light,
environmental attack and mechanical damage.
The induction of stresses in the pipe or in joints during installation shall be avoided. The
following precautions shall be taken :
• Prevent the pipe from being damaged by contact with sharp materials during
installation.
• If the PE pipe is laid by drag, care shall be taken that the drag force is not exceeding
the allowable force as specified by the MANUFACTURER or SUPPLIER of the pipe
material.
• Comply with the minimum allowable bending radii specified in paragraph 3.8.2.
• Ensure that the pipe is uniformly supported.
• Ensure that the trench is in compliance with the requirements of section 3.7 above, and
that proper bedding and padding material is used where required.
• Ensure that no stone or rock impingement exists at the pipe to soil interface.
• If the pipe is laid in a sleeve, ensure that the sleeve ends are fitted in such way that no
stress or cutting effect can be transmitted to the PE carrier pipe.
3.8.3.3 Electrofusion
Barcode labelled or auto recognition electrofusion jointing shall be used and only fittings
incorporating fusion indicators shall be acceptable.
The equipment used for joint construction shall provide fusion data in the form of a print
out specific to each joint, which shall include each joint's unique joint number. These
print outs shall form part of the as built records.
The electrofusion control box shall deliver the correct fusion parameters to the
electrofusion fitting. The power generator shall provide the power requirements of the
control box, taking into account the electrical characteristics of the control box.
Positioning tools shall be used for all types of electrofusion systems to minimise
misalignment and prevent movement during cooling of the joint.
3.8.3.4 Electrofusion Inspection
The inspection (acceptance standards) shall include the following :
• A uniform and efficient scraping over the entire circumference shall be clearly visible
on either side of the socket.
• A dot or line shall be initially marked on the pipe or spigot end to determine/confirm the
depth of penetration. If a clamping/scraping tool is used which indicates the depth of
penetration, then the marking requirement no longer applies. Each pipe or spigot end
shall penetrate completely its relevant part of the electro-socket.
• Melt from the fusion process shall not exude outside the confines of the fitting.
• If the fitting is designed with fusion indicators, after the fusion they shall be in a position
complying with the fitting MANUFACTURER's instructions.
• Alignment clamps shall not be removed before the appropriate cooling time has
elapsed.
• Abnormal displacement of the electric wire coils shall not occur. This shall be checked
prior to commencement of fusion.
10 10-17
16 11-18
22 15-24
28 17-26
32 18-27
45 20-29
57 23-32
Note: Intermediate wall thickness shall be taken as the nearest lower wall thickness.
3.9 Backfilling
3.9.1 General
No backfilling shall be performed until the pipe and appurtenances are at the proper
alignment and depth to provide the required cover. Before any backfilling is commenced
it shall be the CONTRACTOR's responsibility to first secure the approval ofADWEA /
ENGINEER. If any backfilling is done without ADWEA/ENGINEER approval, ADWEA /
ENGINEER shall have the right to require removal of backfill for examination.
CLIENT : AMER GROUP
PROJECT : PORTO OCTOBER
03010 -
17
MASTER SPECIFICATIONS INFRA GROUP
The cost of such uncovering and re-backfilling shall be borne by the CONTRACTOR.
Subject to compliance with the specifications, the backfilling operation shall follow as
closely as practical to the lowering-in of the pipeline, so as to securely position the pipe
in the ground and to prevent damages due to exposure of the pipe surface to
temperature or weather.
A maximum of one hour between lowering in and backfilling is considered acceptable.
The backfill shall be maintained by CONTRACTOR against washouts, etc., until the
completion and final acceptance of the work by ADWEA/ENGINEER.
3.10 Tying-In
3.10.1 Joining Unconnected Sections
Where sections of the line are to be tied-in after the sections are lowered in and
backfilled, the length of pipeline left unbackfilled shall be kept to a minimum to facilitate
the tying-in.
CONTRACTOR shall carry out tie-in jointing, and other associated operations in
compliance with the relevant Specifications herein.
Tie-in joints in restrained sections of the line shall be made when the pipe temperature is
at the minimum, as far as practicable. If necessary to avoid strain in the pipe, sufficient
restrained pipe shall be uncovered to allow slack loops to be held during the line-up and
jointing of the tie-in. Under no circumstances shall the line be left in tension after the tie-
in.
Bell holes made to facilitate jointing shall provide adequate clearance to enable the
jointer to exercise normal jointing ability and skill. The lap of the strings at tie-ins shall be
at least 2 m
3.10.2 Pups
The CONTRACTOR shall perform his work to minimise the number of pups and shall
progressively carry forward and install same between full lengths of pipe. If pipe is to be
added for tie-in, the minimum length that may be used shall be 1.5 meters and two or
more such pups shall not be jointed together.
Minor Road (un-metalled) and track crossing shall be uncased and shall be constructed
by open cut method, with a suitable detour provided for road users.
Crossing of metalled and major roads shall be installed by non-disruptive techniques,
with a suitable detour similarly provided if necessary. PE pipes shall be installed in a
steel casing pipe.
In all cases, the CONTRACTOR shall submit to ADWEA/ENGINEER the proposals for
the installation of the crossings, the schedule, detail of the methods to be used, the type
of equipment and results of any investigations and surveys. Work on the crossing shall
not commence until the CONTRACTOR's methods and procedures have been approved
in writing. A specific "Crossing Drawing" shall be prepared for each major road crossing.
Construction of crossings shall include the provision of warning signs and barricades
and all necessary clearing and grading, excavating, shoring, de-watering, trenching,
boring, welding,coating, lowering, backfilling, clean up, restoration and any further work
required.
Before the installation work of crossings is started, the CONTRACTOR shall provide
suitable trench mesh barricades. Adequate traffic warning signals and/or traffic lights
and suitable diversions shall be provided as directed by ADWEA/ENGINEER and local
authority.
Actual installation of crossings shall comply with the drawings issued for construction by
CONTRACTOR. CONTRACTOR shall fully investigate all details of the crossing and
make all necessary provisions at the time of construction without any cost to ADWEA.
To avoid settlement in open cut crossings, the pipe shall have firm bearing on the
bottom of the trench for a distance of not less than five metres beyond each side of the
crossing ROW limits. This shall be accomplished by compacting the bottom of the trench
and after installation, thoroughly watering the padding and compacting the backfill using
methods approved by ADWEA.
The track sub-surface and surface layers are to be reinstated to the satisfaction of the
relevant authority and in accordance with specification and drawing.
All road crossings shall be provided with concrete safety barriers during construction.
Before the pipeline is placed in service, and before issue of the Provisional Acceptance
Certificate by ADWEA/ENGINEER/ENGINEER, all pipelines shall be disinfected and
flushed as per AWWA C651 or as directed by ADWEA/ENGINEER.
The pipelines shall normally be disinfected at the same time as the hydrostatic tests
performed or as directed by the ADWEA/ENGINEER.
One (1) week before the CONTRACTOR intends to undertake disinfecting/flushing of all
or part of the pipelines, the CONTRACTOR shall submit a detailed proposal for the work
showing the quantity of water required. This quantity of water may be obtained by the
CONTRACTOR from the nearest available ADWEA/ENGINEER source.
The chlorine dose shall be obtained from a chloral solution or other suitable solution to
be approved by the ADWEA/ENGINEER. Samples taken from the pipeline during
disinfection at locations directed by the ADWEA/ENGINEER shall be checked by a
suitable comparator in order to ensure that the sterilising liquid is present throughout the
system and at sufficient concentration.
At the end of the 24 hour period at operating pressure the chlorine concentration shall
be checked. If there is less than 1 mg/l of free available chlorine in the water, more
chloral solution shall be introduced and left for a further 24 hour period after which the
free available chlorine concentration shall be checked again. This procedure shall be
repeated as necessary until the free available chlorine taken after 24 hours exceeds 1
mg/l for all samples taken from the area of pipeline under test. The hydrostatic test shall
not be commenced until this requirement is satisfied.
Should the hydrostatic test fail and repair work involve emptying the pipeline then the
disinfection and subsequent testing procedures shall be repeated in full at the
CONTRACTOR's own expense.
After all hydrostatic testing has been completed and section of pipeline is ready for
handing over in all other respects including the installation of connections where
appropriate, the new pipeline shall be flushed out by potable water from the existing
mains to which the new pipeline or network is or will be connected. Flushing entry and
exit points shall be designed to allow a minimum of 1.0m/s water velocity in the main
pipeline to remove any sand or other debris. The quantity of flushing water shall be
calculated as the equivalent to 3 times the volume of the pipeline to be flushed unless
directed otherwise.
It shall be a condition that the water in the existing network at the point of extraction
shall register a minimum of 0.4 mg/l of free available chlorine when tested with a site
comparator prior to any approval being given to commence flushing. If a reading of less
than this is obtained the ENGINEER shall be informed and the CONTRACTOR
instructed accordingly.
Once flushed, the water in the new pipelines shall be allowed to stand for a further 24
hours.
Samples shall then be taken from locations directed by the ADWEA/ENGINEER and
immediately submitted for chemical and bacteriological testing at the approved
laboratories.
Chemical and bacteriological tests shall normally be undertaken at the Abu Dhabi Water
and Electricity Authority's Laboratory and a charge may be made for testing. All charges
for water sample testing shall be paid by the CONTRACTOR.
The pipeline shall not be considered acceptable until faecal coliforms are undetectable
in a 100 ml sample, the bacterial count is within approved limits, the recorded total
chlorine content is a minimum of 0.2 mg/l and the pH is within acceptable limits.
If the tests show that a satisfactory drinking water standard has not been achieved, the
CONTRACTOR shall repeat the disinfection procedure, tests and flushing, all at his own
expense, until these requirements are met.
The CONTRACTOR is responsible for making himself fully aware of the statutory
requirements for achieving acceptance of bacteriological and chemical standards of the
water in the pipelines under construction.
Flushing water shall be discharged via temporary discharge lines to the surrounding
open desert area or into the existing storm water system or, if feasible, into road tankers.
Discharging of flushing water into the existing storm water system shall be subject to
approval of the relevant Authorities.
Any temporary connections required for flushing shall be at the CONTRACTOR's cost.
All other materials, equipment and labour required for the disinfection, flushing operation
and discharge of water shall also be furnished by the CONTRACTOR and included in
his construction rates.
pipeline or network is complete in all respects and chemical and bacteriological tests
have been successfully concluded.
Handing over to ADWEA/ENGINEER shall only be considered with respect to the
appropriate Clauses for Provisional Acceptance of the WORKS.
6. DOCUMENTATION
6.1 Records
6.1.1 General
CONTRACTOR shall submit daily, weekly, monthly and after completion toADWEA /
ENGINEER various records and reports, for ADWEA/ENGINEER's documentation
purposes during and immediately after the construction.
This shall as a minimum include, but not be limited to the following:
6.1.2 Daily
• Separate progress reports of all crews
• Daily jointing results and repairs (& NDT results as per contract jointing spec)
• Actual weather conditions
• Application for variations, if any
• Next days working programme
• Accidents
• Damages
• Activities required from ADWEA/ENGINEER at short notice
• Material Receipts
6.1.3 Weekly
• Up to date list of confirmed Site Instructions issued by ADWEA/ENGINEER
• Materials 'taken over'
• Material defects and repairs
• Outstanding activities of ADWEA/ENGINEER
• List of installed markers, chainage
• Required approvals from ADWEA/ENGINEER
• Progress planned
• Report of manning of all crews, equipment and plant
• Report of equipment and plant
• Report of accidents
• Report of damages
• Report of Acquired Releases, Permits
• Required materials for next week, etc.
6.1.4 Monthly
Progress report for payment, safety report, report of accidents, security report, health
and environment report, material balance, approved variations.
Further, CONTRACTOR shall provide (for approval if required) ADWEA/ENGINEER
with documents such as but not limited to :
• Schedule for construction work
• Bio-data of key personnel (including foremen)
• (Revised) list of addresses of personnel in particular of medical staff, safety and
security
officers
• (Revised) list of approved paint applicator
• (Revised) list of approved Subcontractors
• Time schedule
• Acquired permits and/or approvals from any Authorities, endowments
• Minutes of meeting with ADWEA/ENGINEER with comments, if any
• Material certificates, material receipts, etc.
• Guarantees from Vendors and Subcontractors
• Calculations, temporary works, buoyancy, blasting, etc.
• Drawings issued by CONTRACTOR
• Vendor drawings
• All 'as built' drawings
• Procedures such as surveying, staking, fencing, etc., jointing procedures, jointer
qualification, installation of crossing, hydrostatic testing, blasting
• Pipe book and jointing records
• Material records and accounting book
• Test Reports
• Material tests (coating, jointing, painting, etc.)
• Water samples
• Cleaning, report before pressure testing
• Hydrostatic and Disinfection test
• Calibration test
• Equipment certificates (dead weight tester, instruments, vessels, equipment, etc.)
CLIENT : AMER GROUP
PROJECT : PORTO OCTOBER
03010 -
27
MASTER SPECIFICATIONS INFRA GROUP
• Jointer number
• Type of jointing
• Limits of valve stations, water crossings, etc.
• Test pressure, date and test (hydrostatic)
• Length to bring forward (pipes and other materials)
• Length brought forward (pipes and other materials)
In order to achieve this CONTRACTOR shall identify all pipe elements. Sample format
of pipe book shall be submitted for ADWEA/ENGINEER approval. Final Pipe Book shall
be submitted to ADWEA/ENGINEER in the form of 1 hard copy (original) and 1 soft copy
on electronic format.