139 - Surat Penambahan Ponton Kerja (Berdikari)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Jul-23 Aug-23

M 27 M 28 M 29 M 30 M 31 M 32 M 33 M 34
No. Lokasi Uraian Sat Jumlah Rencana
10 - 16 Jul 23 17 - 23 Jul 23 24 - 30 Jul 23 31 Jul - 06 Ags 23 07 - 13 Ags 23 14 - 20 Ags 23 21 - 27 Ags 23
Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot
A A1
1 Abutment
Pembesian kg 69,780.41 34,890.20 0.14 34,890.20 0.14
Cor fc' 40 Mpa m3 300.97 300.97 0.77
2 Wing Wall -
Pembesian kg 19,875.25 9,937.63 0.04 9,937.63 0.04
Cor fc' 35 Mpa m3 33.28 33.28 0.06
B P1
1 Bored Pile
Pemancangan Pipa casing titik 10.00 2.00 0.05 2.00 0.05 2.00 0.05 2.00 0.05 2.00 0.05
Cor fc' 35 Mpa titik 10.00 2.00 0.25 2.00 0.25 2.00 0.25 2.00 0.25 2.00 0.25
Uji PDA titik 1.00 1.00 -
Pengujian CSL titik 7.00 7.00 0.06
2 Pile Cap
Instal Besi Pile Cap kg 78,850.10 39,425.05 0.16 39,425.05 0.16
Cor fc' 40 Mpa m3 749.57 274.78 0.70
P2
1 Bored Pile
Pre-boring & Pemancangan titik 13.00 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02 1.00 0.01
Cor fc' 35 Mpa titik 13.00 2.00 0.39 2.00 0.39 2.00 0.39 2.00 0.39 2.00 0.39 2.00 0.39 1.00 0.20
Pengujian CSL titik 10.00 10.00 0.08
P3
1 Bored Pile
Pre-boring & Pemancangan titik 12.00 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02 2.00 0.02
Cor fc' 35 Mpa titik 15.00 2.00 0.44 2.00 0.44 2.00 0.44 2.00 0.44 2.00 0.44 2.00 0.44 2.00 0.44
P4
1 Bored Pile
Pre-boring & Pemancangan titik 16.00 - - 4.00 0.03 - 4.00 0.03
Cor fc' 35 Mpa titik 20.00 2.00 0.39 2.00 0.39 2.00 0.39 2.00 0.39 2.00 0.39
P5
1 Bored Pile
Pre-boring & Pemancangan titik 16.00 -
Cor fc' 35 Mpa titik 20.00 2.00 0.29
Jul-23 Aug-23
M 27 M 28 M 29 M 30 M 31 M 32 M 33 M 34
No. Lokasi Uraian Sat Jumlah Rencana
10 - 16 Jul 23 17 - 23 Jul 23 24 - 30 Jul 23 31 Jul - 06 Ags 23 07 - 13 Ags 23 14 - 20 Ags 23 21 - 27 Ags 23
Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot Vol Bobot
P6
1 Pile Cap
PDA titik 1.00 1.00 -
Instal Besi kg 60,635.93 30,317.97 0.12 30,317.97
Cor fc' 40 Mpa m3 538.90 538.90 1.37
2 Pier
Install Besi (2 segmen) kg 35,270.70 17,635.35 0.07 17,635.35 0.07
Cor fc' 40 MPa (2 segmen) m3 238.33 119.16 0.30 119.16 0.30
A2
1 Pile Cap
Instal Besi kg 50,180.64 50,180.64 0.20
Cor fc' 40 Mpa m3 538.90 538.90 1.37
2 Abutment
Instal Besi kg 60,767.00 30,383.50 0.12 30,383.50 0.12
Cor fc' 40 Mpa m3 66.76 66.76 0.17
3 Wing Wall
Instal Besi kg 2,128.13 1,064.07 0.00 1,064.07 0.00
Cor fc' 40 Mpa m3 14.98 14.98 0.04
Pekerjaan Girder
1 Penyediaan Unit Pracetak Gelagar Tipe I bentang 40,68 meter bh 12.00 12.00 1.42
2 Pemasangan Unit Pracetak Gelagar Tipe I bentang 40,68 meter bh 12.00

Master Schedule
Minggu ini 1.411 1.411 1.411 1.764 1.764 1.764 1.764
Komulatif 25.335 26.746 28.157 29.568 31.332 33.096 34.861 36.625
Rencana
Minggu ini - 3.077 1.465 2.709 1.558 3.022 1.789 4.101
Komulatif 21.993 23.458 26.166 27.724 30.747 32.536 36.637
Deviasi (4.753) (4.699) (3.402) (3.608) (2.350) (2.324) 0.012
Realisasi
Minggu ini 3.114
Komulatif 18.915