23-ONEIC-MM2021-101-MS-E23-A4 MS For Testing and Commissioning Works
23-ONEIC-MM2021-101-MS-E23-A4 MS For Testing and Commissioning Works
23-ONEIC-MM2021-101-MS-E23-A4 MS For Testing and Commissioning Works
Santosh Bratislav
(Sr. Testing Engineer) (Protection
Manager)
For
ONEIC-MM2021-101-MS-E23 Page 1 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
CONTENTS
1.0 Purpose 03
2.0 Scope 03
5.0 Responsibility 03
ONEIC-MM2021-101-MS-E23 Page 2 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
1.0 PURPOSE
The purpose of this document is to define the tests to be conducted on site for all
HV/LV electrical equipments and to specify the acceptable values.
2.0 SCOPE
5.0 RESPONSIBILITY
I. HSE Advisor shall be Responsible for safety related matters and all the safety
aspects of the site with respective MJEC/Mawarid specifications.
II. Testing and Commissioning Engineer shall be responsible for all kind of testing
and commissioning activities as per the method of statement with respective
MJEC/Mawarid specifications.
I. QUALITY CONTROL
ONEIC-MM2021-101-MS-E23 Page 4 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
NOTE:
➢ SF6 Impurity, Density & Leakage Test will be carried out by the vendor as
per the standard Procedure.
➢ Contact Resistance Measurement Will Be carried out by the Vendor as per
the Standard procedure.
ONEIC-MM2021-101-MS-E23 Page 5 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Check the type and rating of the CT with the specification / Drawings
• The wiring circuit shall be checked to ensure proper termination, core
marking and wiring harness
• Check each CT core is earthed only at one point in the circuit
ON PRIMARY WINDING:
ON SECONDARY WINDING:
ONEIC-MM2021-101-MS-E23 Page 6 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Using 5kV Megger for one minute, between each primary winding to
secondary winding.
WINDING RESISTANCE
• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.
ONEIC-MM2021-101-MS-E23 Page 7 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• The knee point voltage test is done using CPC 100 kit
• The purpose of this test is to confirm knee point voltage of CT with
respect to the protection & metering circuit design in the system as per
the approvals.
ONEIC-MM2021-101-MS-E23 Page 8 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
CT BURDEN TEST
ONEIC-MM2021-101-MS-E23 Page 9 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• The result will be completed automatically and the value will be displayed in
the kit. Save the result. Check the VA result is must be below the Name Plate
• The test is performed on different cores of the CT by the same procedure
GENERAL INSPECTION
• Carryout visual inspection and ensure compliance with the drawings and
vendor manuals.
• Check nameplate ratings and HV, LV terminal markings as per Vendor
drawings.
• Check that the VTs are properly assembled, erected and tightened as per
drawing.
• Check the HV connections are tight and torque checked.
• Check the cable connections on the LV side and the markings.
• Check the equipment grounding (Connections and continuity)
• Check the fuse or MCB rating of secondary side.
ONEIC-MM2021-101-MS-E23 Page 10 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ON PRIMARY WINDING:
• Using 5kV megger for one minute, between each primary winding to
secondary winding.
ON SECONDARY WINDING:
• Using 500V megger for one minute, between each secondary winding to
ground and secondary core to core.
• The secondary windings are connected together and to ground.
ONEIC-MM2021-101-MS-E23 Page 11 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
WINDING RESISTANCE
• The winding resistance test will be done using CPC 100 kit
VT
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.
ONEIC-MM2021-101-MS-E23 Page 12 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• The ratio test and polarity test is done simultaneously by CPC 100 kit
• Measures the capacitive or inductive VT ratio and polarity
• Connect the HV AC voltage output on the primary side and the voltage
measuring lead is connected on the secondary winding
• After entering the primary voltage, secondary voltage and test voltage,
and pressing the Start button, the test card
• Measures amplitude and phase of the voltage on the transformer’s
secondary side
• Calculates the actual ratio, the deviation and the polarity
• The report is generated automatically and saved in appropriate location
ONEIC-MM2021-101-MS-E23 Page 13 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Do injection From both end at same time 1.0Amps R-phase, Confirm the
stability and do the other phases the same
• Confirm the tightness of CT links once again.
3 phase ,415 AC supply has to be used for stability and sensitivity check of 87L .
ONEIC-MM2021-101-MS-E23 Page 15 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• For Testing Bus-Bar Stability the current leads from test kit is connected
to R&Y phases of the testing bay and take one of the feeder as reference
bay and its R&Y phases are shorted according to the site condition.
• The Isolator of testing bay and the reference bay have to be closed to
perform the bus bar stability.
• Circuit Breakers of two bays (testing bay & reference bay) have to be kept
closed.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the current Injection leads in the R-Y Phase of Switch gear at
suitable point.
• Inject test current of 10% rating of Lower CT ratio R-Y. Verify the current
flow in all circuits.
• Verify secondary current in Bus Bar Protection cores and ensure zero
differential current in the Main & Check zone relays.
• Increase the Injection current to suitable range.
• Record the Injected current and all secondary measured currents. Check
the stability is found Ok.
• Repeat the test for Y-B and B-R combination.
• CT polarity shall be reversed to confirm sensitivity Test. Record the voltage
across the stability resistors.
• To know the tripping of CBs the injected current is increased to a value
higher than the setting and the operation of the Bus-Bar Protection shall be
ensured. All the alarms indications & CB operations shall be noted
ONEIC-MM2021-101-MS-E23 Page 16 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Check both end of the cable should have proper clearance from the
surroundings and between the phases.
• Check the other end of the cable properly insulated.
• Check proper barricading.
• Check and confirm phase sequence of the Cable.
• Before and after HV test, Insulation resistance is measured for each
Phases using 5kV megger for one minute.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the Voltage Injection lead in the R Phase of the cable, short and
earth other two phases at suitable point according to the site condition.
• Inject test Voltage for one minute in R Phase. Measure the leakage current
using test kit.
• After completing testing for each Phases, cable should be discharged
using discharge rod for safety measure.
• Repeat the test for remaining Phases.
ONEIC-MM2021-101-MS-E23 Page 17 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Check the type and rating of the CT with the specification / Drawings
• The wiring circuit shall be checked to ensure proper termination, core
marking and wiring harness
• Check each CT core is earthed only at one point in the circuit
ON PRIMARY WINDING:
ONEIC-MM2021-101-MS-E23 Page 18 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ON SECONDARY WINDING:
• Using 5kV Megger for one minute, between each primary winding to
secondary winding.
ONEIC-MM2021-101-MS-E23 Page 19 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
WINDING RESISTANCE
• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.
ONEIC-MM2021-101-MS-E23 Page 20 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
GENERAL INSPECTION
• Carryout visual inspection and ensure compliance with the drawings and
vendor manuals.
• Check nameplate ratings and HV, LV terminal markings as per Vendor
drawings.
• Check that the VTs are properly assembled, erected and tightened as per
drawing.
• Check the HV connections are tight and torque checked.
• Check the cable connections on the LV side and the markings.
• Check the equipment grounding (Connections and continuity)
• Check the fuse or MCB rating of secondary side.
ONEIC-MM2021-101-MS-E23 Page 21 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ON PRIMARY WINDING:
• Using 5kV megger for one minute, between each primary winding to
secondary winding.
ON SECONDARY WINDING:
• Using 500V megger for one minute, between each secondary winding to
ground and secondary core to core.
• The secondary windings are connected together and to ground.
ONEIC-MM2021-101-MS-E23 Page 22 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
WINDING RESISTANCE
• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT VT not CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.
ONEIC-MM2021-101-MS-E23 Page 23 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• The ratio test and polarity test is done simultaneously by CPC 100 kit
• Measures the capacitive or inductive VT ratio and polarity
• Connect the HV AC voltage output on the primary side and the voltage
measuring lead is connected on the secondary winding
• After entering the primary voltage, secondary voltage and test voltage,
and pressing the Start button, the test card
• Measures amplitude and phase of the voltage on the transformer’s
secondary side
• Calculates the actual ratio, the deviation and the polarity
• The report is generated automatically and saved in appropriate location
• Check Bus bar clean and should have proper clearance from the
surroundings and between the phases.
• Check the other end of the cable properly insulated.
• Before and after HV test, Insulation resistance is measured for each
Phases using 5kV Megger for one minute.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the Voltage Injection lead in the R Phase of the bus bar, short and
earth other two phases at suitable point according to the site condition.
• Inject test Voltage for one minute in R Phase. Measure the leakage current
using test kit.
• After completing testing for each Phases, busbar should be discharged
using discharge rod for safety measure.
• Repeat the test for remaining Phases.
ONEIC-MM2021-101-MS-E23 Page 24 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
g) APFC TESTING
• Confirm the Capacitor bank Control auto/manual mode Operation Checks.
• Inject the R&Y 110v Ac supply from 11kV Incomer ,Check the APFC meter
Setting as per the client requirement.
• Inject B phase Current from 11kV incomer feeder and check the
measurement for voltage and current and power factor.
• As per client APFC setting increase/decrease the power factor and check the
Stage's close/open timing as per the setting.
h) CAPACITANCE /INDUCTANCE TEST
• Ensure the Capacitor star point connection and inductor rating and
connection.
• Confirm the selection in Inductance or capacitance in Meter.
• Confirm the connection between meter to equipment ,select the point test as
per the measurement of Inductance and capacitance values.
Insulation Resistance
• Check the tightness of primary connections, secondary connections and
seating arrangements.
• Clean all the insulators both on the primary and secondary side.
• Isolate the cables on primary and secondary side.
• Apply a IR voltage of 5kV between primary to earth for 10 Min. and record
the values at 15 sec, 1Min. and 10 Min.(IR Test voltage as per OEM
Recommendation)
• Apply an IR voltage of 500V between secondary to earth for 10 Min. and
record the values at 15sec, 1 Min. and 10Min.
• Apply an IR voltage of 5kV between primary to secondary for 10 Min. and
record the values at 15sec, 1Min. and 10Min.
• Compare the results with the Factory Test Report.
• IR test should be performed as per manufacturer recommendation.
• Record ambient temperature and humidity
Voltage Ratio Test:
• Apply the 3 Phase 415 Volts supply on the HV side of the Transformer.
3phase ,415 AC supply • Enter the Transformer Name plate Voltage of the HV winding. (Primary)
not acceptable for TX ratio test
, only test kit with approved
• Enter the Transformer Name plate Voltage of the LV winding. (Secondary)
make and model has to be • Start test from maximum tap position to the minimum tap position.
used. • Note down Values for each tap.
• Compare the values with the FAT report and calculate the ratio error.
• Ensure the error is inacceptable limit.
ONEIC-MM2021-101-MS-E23 Page 26 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ONEIC-MM2021-101-MS-E23 Page 27 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
Measured impedance voltage (%) = Rated current at measured tap X Measured voltage X 100
Measured current X Rated voltage at measured tap
Buchholz Relay: Check the operation of the main Buchholz relay alarm, trip
contacts or functioning at specified settings by pumping air into the relay or
draining the oil from the relay. Repeat the same test for OLTC Buchholz relay if
provided. Ensure that the respective relay operates in the control panel and trips
the transformer breaker with the alarm. Reset the relay by normalizing the
buchholz relay
Oil Level Switch: Check for low oil level alarm by actuating the oil switch.
Protection System: Check that all protection relays are set to the
recommended setting. Close the transformer breaker without power and check
for all protection tripping by actuating respective protective relays. Ensure that
all the interlocks and operations are checked as per the approved schematic
drawings.
ONEIC-MM2021-101-MS-E23 Page 28 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Testing time Confirm the Relay LED'S indication and Check Fault
recorder.
ONEIC-MM2021-101-MS-E23 Page 29 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ONEIC-MM2021-101-MS-E23 Page 30 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
READY TO
CAP ISO. OPEN CB OPEN - LED-- OPERATED -
CLOSE
ONEIC-MM2021-101-MS-E23 Page 31 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ONEIC-MM2021-101-MS-E23 Page 32 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
7.4 33KV INTRIP MATRIX : kindly rectify intertrip matrix based on TX Ratio
ONEIC-MM2021-101-MS-E23 Page 33 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
NOT
LVAC UV CB CLOSE HEALTHY REQ. CB OPEN
OPERATED
132 kv
INTERLOCK CONDITIONS
GRID ESOPEN/ CLOSE PSS CB OPEN + PSS ES OPEN
PSS ES CLOSE GRID CB OPEN+ CB IN TEST
PSS CB CLOSE GRID CB CLOSE
PSS CB OPEN GRID CB OPEN
ONEIC-MM2021-101-MS-E23 Page 34 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
ONEIC-MM2021-101-MS-E23 Page 35 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:
• Increase the current up to 50% of rating of CT and record the values in all
relays and meters.
• Switch off the Test kit after recorded the current in various points.
• Repeat the test in all other phases,
ONEIC-MM2021-101-MS-E23 Page 36 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
RISK ASSESSMENT MATRIX
RISK RATE= LIKELIHOOD X CONSEQUENCES
L
I 5 5 10 15 20 25
K
E
L
4 4 8 12 16 20
I
H 3 3 6 9 12 15
O
O
D
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
CONSEQUENCES
CONSEQUENCES LIKELIHOOD
1 No Injuries or Illness 1 Remotely Possible – Unknown
METHODOLOGY occurrence
Low risk 2 Minor Injuries or Illness 2 Remotely Possible – Known Occurrence
Medium risk 3 Over 3 day Injury or Illness 3 Occasional but frequent Occurrence
4 Major Injury or Illness 4 Likely to occur on regular basis
High Risk 5 Fatality 5 Almost Certain
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
NAME OF THE PROJECT / SITE : CONSTRUCTION OF 132/11KV, 2X20MVA PRIMARY SUBSTATION WITH TWO (2 NOS.) 132KV FEEDERS
FROM WADI AL JIZI PLANT TO LASAIL PSS IN AL BATINAH GOVERNORATE (TENDER NO- MM2021-101)
PRE POST
S.NO HAZARD RISK L C CONTROL MEASURE REQUIRED L C RECOVERY
RATING RATING