23-ONEIC-MM2021-101-MS-E23-A4 MS For Testing and Commissioning Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 41

OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

CONSTRUCTION OF 132/11KV, 2X20MVA PRIMARY SUBSTATION WITH TWO (2 NOS.)


132KV FEEDERS FROM WADI AL JIZI PLANT TO LASAIL PSS IN AL BATINAH GOVERNORATE
(TENDER NO- MM2021-101)

METHOD STATEMENT FOR


TESTING AND COMMISSIONING

Client : Mawarid Mining LLC


Consultant : Dawood Engineering Consultancy LLC
Contractor : Oman National Engineering &Investment Company SAOG

0 19.12.2023 ISSUED FOR ONEIC ONEIC DEC


APPROVAL
Rev No. Date Description Prepared By Reviewed By Approved By

Santosh Bratislav
(Sr. Testing Engineer) (Protection
Manager)

For

ONEIC-MM2021-101-MS-E23 Page 1 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

CONTENTS

DESCRIPTION PAGE NO.

1.0 Purpose 03

2.0 Scope 03

3.0 Reference Documents 03

4.0 Tools & Testing Equipments 03

5.0 Responsibility 03

6.0 Control Measures 04

7.0 Testing procedure 05 to 36

8.0 Testing Documents & Calibration /Attachment

ONEIC-MM2021-101-MS-E23 Page 2 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

1.0 PURPOSE

The purpose of this document is to define the tests to be conducted on site for all
HV/LV electrical equipments and to specify the acceptable values.

2.0 SCOPE

This procedure shall be applicable for testing and commissioning of HV/LV


electrical equipments

3.0 REFERENCE DOCUMENTS

4.0 TOOLS & TESTING EQUIPMENTS

- PPE’s & Safety belts.


- Tool box with complete set of tools.
- Calibrated Measuring Instruments

• Primary / Secondary injection kit


• Insulation tester 500V-5kV
• Multimeter
• Leakage Current Tester
• VLF Kit
• Clamp-On meters
• Breaker Analyzer
• Power measurement meter
• CPC 100 test kit

5.0 RESPONSIBILITY

I. HSE Advisor shall be Responsible for safety related matters and all the safety
aspects of the site with respective MJEC/Mawarid specifications.

II. Testing and Commissioning Engineer shall be responsible for all kind of testing
and commissioning activities as per the method of statement with respective
MJEC/Mawarid specifications.

6.0 CONTROL MEASURES:


ONEIC-MM2021-101-MS-E23 Page 3 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

I. QUALITY CONTROL

1) Ensure approved drawings are available at site all the time.


2) Ensure valid calibration certificates are available with the equipment, which
are being used.
3) Ensure approved method of statement /Relay setting calculation
4) Raise inspection request and coordinate client/ consultant for required
inspection.
5) Ensure FAT test Reports are available at site all the time

7.0 TESTING PROCEDURES:


a) TESTING OF GIS:
IR VALUE TEST: Isolators, Circuit Breaker and Bus Bar
• Ensure the equipment under test has been disconnected from supply.
• Discharge the equipment under test before start the IR test
• Close the Isolators and Circuit Breaker to be tested.
• Make ready the Testing Equipment and connect the test leads properly in
the required phase under Test. Short and Ground other phases to Earth.
• Make sure there no device is connected to Earth in the testing portion.
(VT, Earth Switch etc)
• Switch on the Testing Equipment (Megger). Set the test voltage as 5KV
and the time as 1 minute. Before and after HV test
• Start the test and record the value in the Test Report.
• Complete the IR test for other phases and record the values.

ONEIC-MM2021-101-MS-E23 Page 4 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

CIRCUIT BREAKER TIME INTERVAL:

• Connect Test Equipment and leads to breaker as in Instruction Manual


• Remove Earthing from circuit if required.
• Switch on the test equipment and set the Date & Time.
• Select the test mode to be performed (Close, Open, C-O,O-C-O)
• Start the test.
• Operating times of all three poles are measured and displayed
• Record the value in the Test Report
• Make a print and use print type test kit
• Measure the Close and Trip Coil Current
• After Testing Normalize Circuit
• Measure the spring charge Motor Current using Clamp meter when
charging the spring Mechanism.

NOTE:

➢ SF6 Impurity, Density & Leakage Test will be carried out by the vendor as
per the standard Procedure.
➢ Contact Resistance Measurement Will Be carried out by the Vendor as per
the Standard procedure.

ONEIC-MM2021-101-MS-E23 Page 5 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

CURRENT TRANSFORMER TESTING


INITIAL CHECK

• Check the type and rating of the CT with the specification / Drawings
• The wiring circuit shall be checked to ensure proper termination, core
marking and wiring harness
• Check each CT core is earthed only at one point in the circuit

INSULATION RESISTANCE TEST:

ON PRIMARY WINDING:

• Test shall be performed by using appropriate Megger for one minute,


between primary winding to ground and primary winding to secondary
winding. (R-E, Y-E, B-E, R-Each secondary winding, Y-Each secondary
winding & B-Each secondary winding)

ON SECONDARY WINDING:

• By applying 500V in megger for one minute, between each secondary


winding to ground and core to core.
• The secondary windings are connected together and to ground.

ONEIC-MM2021-101-MS-E23 Page 6 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

PRIMARY WINDING TO SECONDARY WINDING

• Using 5kV Megger for one minute, between each primary winding to
secondary winding.

WINDING RESISTANCE

• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.

ONEIC-MM2021-101-MS-E23 Page 7 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

RATIO TESTS AND POLARITY TEST

• The Ratio test will be done using CPC 100 kit


• The purpose of this test is to confirm the ratio marked in the CT nameplate
against the requirement & site test results.
• Set the primary injection kit with loading unit, select suitable current range
in the kit
• After entering primary, secondary current ratio and the test current, the test
is performed
• The ratio and polarity is tested simultaneously in this test
• The result will be completed automatically and the value will be displayed in
the kit. Save the result. Check the Polarity shown in the display is correct.
• The test is performed on different cores of the CT by the same procedure
• Compare the Ratio error with name plate details class

MAG CURVE CHECK (Secondary knee point voltage)

• The knee point voltage test is done using CPC 100 kit
• The purpose of this test is to confirm knee point voltage of CT with
respect to the protection & metering circuit design in the system as per
the approvals.

ONEIC-MM2021-101-MS-E23 Page 8 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

• It is performed in the secondary winding of CT


• The HV leads out from voltage output should be connected to secondary
Wiring of the CT core under test.
• After entering the magnetizing current and Max. Voltage limits the test
has to be start
• Demagnetize the core before and after testing
• The test kit will perform the test automatically and display the Vk, Im and
the curve. Store the result.
• Confirm the readings are according to the name plate details
• Repeat the same procedure for other cores of the CT's to be tested.

CT BURDEN TEST

• The Ratio Burden will be done using CPC 100 kit


• The purpose of this test is to confirm Burden marked in the CT nameplate
against the requirement & site test results.
• Set the primary injection kit with loading unit, select 1.0 current range in the
kit
• After entering primary, secondary current and the test current, the test is
performed
• The Burden is tested in this test

ONEIC-MM2021-101-MS-E23 Page 9 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

• The result will be completed automatically and the value will be displayed in
the kit. Save the result. Check the VA result is must be below the Name Plate
• The test is performed on different cores of the CT by the same procedure

VOLTAGE TRANSFORMER TESTING

GENERAL INSPECTION

• Carryout visual inspection and ensure compliance with the drawings and
vendor manuals.
• Check nameplate ratings and HV, LV terminal markings as per Vendor
drawings.
• Check that the VTs are properly assembled, erected and tightened as per
drawing.
• Check the HV connections are tight and torque checked.
• Check the cable connections on the LV side and the markings.
• Check the equipment grounding (Connections and continuity)
• Check the fuse or MCB rating of secondary side.

INSULATION RESISTANCE TEST

• To obtain values as close as possible to the manufacturer’s specifications


the insulators must be very clean. Select the megger range corresponding
to the ratings of the equipment under test.
• Primary side test voltage is depending on voltage rating of transformer.
• For LV, apply 500 Volts, For 11 kV & above, apply 5.0 KV

ONEIC-MM2021-101-MS-E23 Page 10 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

ON PRIMARY WINDING:

• Test shall be performed by using appropriate megger for one minute,


between each primary winding to ground and primary winding to
secondary winding. (R-E, Y-E, B-E, R-Each secondary winding, Y-Each
secondary winding & B-Each secondary winding)

PRIMARY WINDING TO SECONDARY WINDING

• Using 5kV megger for one minute, between each primary winding to
secondary winding.

ON SECONDARY WINDING:

• Using 500V megger for one minute, between each secondary winding to
ground and secondary core to core.
• The secondary windings are connected together and to ground.

ONEIC-MM2021-101-MS-E23 Page 11 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

WINDING RESISTANCE

• The winding resistance test will be done using CPC 100 kit
VT
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.

ONEIC-MM2021-101-MS-E23 Page 12 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

VT RATIO AND POLARITY

• The ratio test and polarity test is done simultaneously by CPC 100 kit
• Measures the capacitive or inductive VT ratio and polarity
• Connect the HV AC voltage output on the primary side and the voltage
measuring lead is connected on the secondary winding
• After entering the primary voltage, secondary voltage and test voltage,
and pressing the Start button, the test card
• Measures amplitude and phase of the voltage on the transformer’s
secondary side
• Calculates the actual ratio, the deviation and the polarity
• The report is generated automatically and saved in appropriate location

ONEIC-MM2021-101-MS-E23 Page 13 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

b) CONTROL & RELAY PANEL


• Verify all Relays and other accessories are available as per the approved
drawing.
• Check the Earthing of relays and panels
• Check the tightness of all connections and panel
• Check the interconnections from CRP to BBP & GIS
• Extend the AC & DC auxiliary supplies from the approved MCB/Panels.
• Relay testing includes verification of operation of switching device tripping
mechanism and all alarm and inter-trips.
• Protective Relays shall be tested and commissioned in accordance with
manufacturer’s instruction.
• All protection relays shall be tested by means of secondary injection at the
normal settings to verify their operating parameters.
• Secondary Injection of protection relays and instruments.

• Disconnect the secondary shorting of CT for checking the proper working


of relays.
• The secondary injection is done by injecting the current of rated value of
the relay and checks the relays functionality (time delay, instantaneous
operation, alarm operation etc..,)
• After completion of secondary injection testing on relays, meters,
transducers etc.., and Primary injection test shall be conducted to verify the
complete relaying and metering system.

c) LINE DIFF RELAY STABILITY


• Verify all Relays and other accessories are available as per the approved
drawing.
• Check the Earthing of relays and panels
• Check the tightness of all connections and panel
• Do injection from local end 1.0Amps for R-phsae
• Do injection from Remote end 1.0Amps for R-phsae
• Do injection for other Phases from local & Remote end one by one
• Check the differential Current & check the breaker opening operation
ONEIC-MM2021-101-MS-E23 Page 14 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

• Do injection From both end at same time 1.0Amps R-phase, Confirm the
stability and do the other phases the same
• Confirm the tightness of CT links once again.

3 phase ,415 AC supply has to be used for stability and sensitivity check of 87L .

PRIMARY INJECTION TEST


• Confirm the tightness of CT secondary leads tightness in LCC and CRPs.
• The CT secondary circuit should be connected to the relays, meters or it
should be shorted properly in LCC or CRP.
• Confirm the CT circuit has not been kept open anywhere.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the current Injection leads in the R-Phase of Switch gear at
suitable point according to the Site condition.
• Switch on the Primary Injection kit and gradually increase the current up
to 10% rating of Lower CT ratio.
• Identify the cores by shorting the CT secondary in the nearest point of CT.
• Confirm the secondary current flow in all the CT cores and no sound in
the CT.
• Increase the current up to 50% of rating of CT and record the values in all
relays, meters and BBP.
• Switch off the Test kit after recorded the current in various points.
• Repeat the test in all other phases,
• Repeat the test with other Isolator closed
• Normalize the trip isolation links and put the BBP selection switch to IN
position.

ONEIC-MM2021-101-MS-E23 Page 15 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

d) BUSBAR PROTECTION STABILITY TEST:

• For Testing Bus-Bar Stability the current leads from test kit is connected
to R&Y phases of the testing bay and take one of the feeder as reference
bay and its R&Y phases are shorted according to the site condition.
• The Isolator of testing bay and the reference bay have to be closed to
perform the bus bar stability.
• Circuit Breakers of two bays (testing bay & reference bay) have to be kept
closed.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the current Injection leads in the R-Y Phase of Switch gear at
suitable point.
• Inject test current of 10% rating of Lower CT ratio R-Y. Verify the current
flow in all circuits.
• Verify secondary current in Bus Bar Protection cores and ensure zero
differential current in the Main & Check zone relays.
• Increase the Injection current to suitable range.
• Record the Injected current and all secondary measured currents. Check
the stability is found Ok.
• Repeat the test for Y-B and B-R combination.
• CT polarity shall be reversed to confirm sensitivity Test. Record the voltage
across the stability resistors.
• To know the tripping of CBs the injected current is increased to a value
higher than the setting and the operation of the Bus-Bar Protection shall be
ensured. All the alarms indications & CB operations shall be noted

ONEIC-MM2021-101-MS-E23 Page 16 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

• After Sensitivity Test CT polarity shall be reversed and Bus-Bar Stability


once again confirm with Primary Current Injection
• After ensuring the Stability & Sensitivity of Bus-Bar Protection and Breaker
Failure Scheme Checks has to be performed.
• All the required testing and commissioning will be done at site by
Approved Testing/Commissioning Engineers, in presence of Clients.

e) DC HIGH VOLTAGE TEST FOR POWER CABLES

• Check both end of the cable should have proper clearance from the
surroundings and between the phases.
• Check the other end of the cable properly insulated.
• Check proper barricading.
• Check and confirm phase sequence of the Cable.
• Before and after HV test, Insulation resistance is measured for each
Phases using 5kV megger for one minute.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the Voltage Injection lead in the R Phase of the cable, short and
earth other two phases at suitable point according to the site condition.
• Inject test Voltage for one minute in R Phase. Measure the leakage current
using test kit.
• After completing testing for each Phases, cable should be discharged
using discharge rod for safety measure.
• Repeat the test for remaining Phases.

AC HV Test (VLF) to be conducted instead of DC test

*applied voltage and duration not mentioned.

ONEIC-MM2021-101-MS-E23 Page 17 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

f) .TESTING OF CAPACITOR BANK


a) IR VALUE TEST: Isolators, Circuit Breaker and Bus bar
• Ensure the equipment under test has been disconnected from supply.
• Discharge the equipment under test before start the IR test
• Close the Isolators and Circuit Breaker to be tested.
• Make ready the Testing Equipment and connect the test leads properly in
the required phase under Test. Short and Ground other phases to Earth.
• Make sure there no device is connected to Earth in the testing portion.
(VT, Earth Switch etc)
• Switch on the Testing Equipment (Megger). Set the test voltage as 5KV
and the time as 1 minute. Before and after HV test
• Start the test and record the value in the Test Report.
• Complete the IR test for other phases and record the values.

b) CURRENT TRANSFORMER TESTING


INITIAL CHECK

• Check the type and rating of the CT with the specification / Drawings
• The wiring circuit shall be checked to ensure proper termination, core
marking and wiring harness
• Check each CT core is earthed only at one point in the circuit

INSULATION RESISTANCE TEST:

ON PRIMARY WINDING:

• Test shall be performed by using appropriate Megger for one minute,


between primary winding to ground and primary winding to secondary

ONEIC-MM2021-101-MS-E23 Page 18 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

winding. (R-E, Y-E, B-E, R-Each secondary winding, Y-Each secondary


winding & B-Each secondary winding)

ON SECONDARY WINDING:

• By applying 500V in megger for one minute, between each secondary


winding to ground and core to core.
• The secondary windings are connected together and to ground.

PRIMARY WINDING TO SECONDARY WINDING

• Using 5kV Megger for one minute, between each primary winding to
secondary winding.

ONEIC-MM2021-101-MS-E23 Page 19 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

WINDING RESISTANCE

• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.

RATIO TESTS AND POLARITY TEST

• The Ratio test will be done using CPC 100 kit


• The purpose of this test is to confirm the ratio marked in the CT nameplate
against the requirement & site test results.
• Set the primary injection kit with loading unit, select suitable current range
in the kit
• After entering primary, secondary current ratio and the test current, the test
is performed
• The ratio and polarity is tested simultaneously in this test
• The result will be completed automatically and the value will be displayed in
the kit. Save the result. Check the Polarity shown in the display is correct.
• The test is performed on different cores of the CT by the same procedure
• Compare the Ratio error with name plate details class

ONEIC-MM2021-101-MS-E23 Page 20 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

c) VOLTAGE TRANSFORMER TESTING

GENERAL INSPECTION

• Carryout visual inspection and ensure compliance with the drawings and
vendor manuals.
• Check nameplate ratings and HV, LV terminal markings as per Vendor
drawings.
• Check that the VTs are properly assembled, erected and tightened as per
drawing.
• Check the HV connections are tight and torque checked.
• Check the cable connections on the LV side and the markings.
• Check the equipment grounding (Connections and continuity)
• Check the fuse or MCB rating of secondary side.

INSULATION RESISTANCE TEST

• To obtain values as close as possible to the manufacturer’s specifications


the insulators must be very clean. Select the megger range corresponding
to the ratings of the equipment under test.
• Primary side test voltage is depending on voltage rating of transformer.
• For LV, apply 500 Volts, For 11 kV & above, apply 5.0 KV

ONEIC-MM2021-101-MS-E23 Page 21 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

ON PRIMARY WINDING:

• Test shall be performed by using appropriate megger for one minute,


between each primary winding to ground and primary winding to
secondary winding. (R-E, Y-E, B-E, R-Each secondary winding, Y-Each
secondary winding & B-Each secondary winding)

PRIMARY WINDING TO SECONDARY WINDING

• Using 5kV megger for one minute, between each primary winding to
secondary winding.

ON SECONDARY WINDING:

• Using 500V megger for one minute, between each secondary winding to
ground and secondary core to core.
• The secondary windings are connected together and to ground.

ONEIC-MM2021-101-MS-E23 Page 22 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

WINDING RESISTANCE

• The winding resistance test will be done using CPC 100 kit
• The test is performed on the secondary winding of the CT VT not CT
• One terminal in the secondary winding is grounded
• The 1.0 A DC is given as input to the terminals of the secondary winding
• The voltage measuring leads is connected across the terminals
• The test current is given and the test is performed
• The test card displays the winding resistance results and it is saved
• The test is performed on different cores of the CT by the same procedure
• Compare the Test result with Name plate data.

ONEIC-MM2021-101-MS-E23 Page 23 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

VT RATIO AND POLARITY

• The ratio test and polarity test is done simultaneously by CPC 100 kit
• Measures the capacitive or inductive VT ratio and polarity
• Connect the HV AC voltage output on the primary side and the voltage
measuring lead is connected on the secondary winding
• After entering the primary voltage, secondary voltage and test voltage,
and pressing the Start button, the test card
• Measures amplitude and phase of the voltage on the transformer’s
secondary side
• Calculates the actual ratio, the deviation and the polarity
• The report is generated automatically and saved in appropriate location

d) AC HIGH VOLTAGE TEST FOR CAPACITOR BUSBAR

• Check Bus bar clean and should have proper clearance from the
surroundings and between the phases.
• Check the other end of the cable properly insulated.
• Before and after HV test, Insulation resistance is measured for each
Phases using 5kV Megger for one minute.
• Arrange the test kit in proper Location and connect the Auxiliary supply
to the socket with suitable current carrying capacity.
• Connect the Voltage Injection lead in the R Phase of the bus bar, short and
earth other two phases at suitable point according to the site condition.
• Inject test Voltage for one minute in R Phase. Measure the leakage current
using test kit.
• After completing testing for each Phases, busbar should be discharged
using discharge rod for safety measure.
• Repeat the test for remaining Phases.

ONEIC-MM2021-101-MS-E23 Page 24 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

* Applied Voltage and Duration not mentioned

e) CONTACT RESISTANCE TEST: Circuit Breaker and Bus Bar

• Measuring of DC resistance by V/ I principle.


• Connect the Current leads and voltage leads between the two ends of the
bus bar that to be tested (END TO END).and all the CB should be in Service
and closed position.
• Voltage measurement leads should be connected inside the current leads.
• Switch on the Aux power to Test kit.
• Contact resistance of main contacts shall be measured by injecting the
100A of DC Current through the connecting point in each phase (R, Y, and
B) one by one.
• The result displayed on the kit and it should be recorded.
• Repeat the test in other phases.

f) PRIMARY INJECTION TEST


• Confirm the tightness of CT secondary leads tightness.
make sure CT circuit is• The CT secondary circuit should be connected to the relays, meters or it
earthed in one point. Should be shorted properly.
near relay , meter
• Confirm the CT circuit has not been kept open anywhere.
• Arrange the test kit in proper Location and connect the Auxiliary supply to
the socket with suitable current carrying capacity.
• Connect the current Injection leads in the Phases at suitable point according
to the Site condition.
• Switch on the Primary Injection kit and gradually increase the current up to
required range.
• Identify the cores by shorting the CT secondary in the nearest point of CT.
• Confirm the secondary current flow in all the CT cores and no sound in the
CT.
• Increase the current up to 50% of rating of CT and record the values in all
relays and meters.
• Switch off the Test kit after recorded the current in various points.
• Repeat the test in all other phases,
ONEIC-MM2021-101-MS-E23 Page 25 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

g) APFC TESTING
• Confirm the Capacitor bank Control auto/manual mode Operation Checks.
• Inject the R&Y 110v Ac supply from 11kV Incomer ,Check the APFC meter
Setting as per the client requirement.
• Inject B phase Current from 11kV incomer feeder and check the
measurement for voltage and current and power factor.
• As per client APFC setting increase/decrease the power factor and check the
Stage's close/open timing as per the setting.
h) CAPACITANCE /INDUCTANCE TEST
• Ensure the Capacitor star point connection and inductor rating and
connection.
• Confirm the selection in Inductance or capacitance in Meter.
• Confirm the connection between meter to equipment ,select the point test as
per the measurement of Inductance and capacitance values.

7.2 TESTING PROCEDURE FOR TRANSFORMER:

Insulation Resistance
• Check the tightness of primary connections, secondary connections and
seating arrangements.
• Clean all the insulators both on the primary and secondary side.
• Isolate the cables on primary and secondary side.
• Apply a IR voltage of 5kV between primary to earth for 10 Min. and record
the values at 15 sec, 1Min. and 10 Min.(IR Test voltage as per OEM
Recommendation)
• Apply an IR voltage of 500V between secondary to earth for 10 Min. and
record the values at 15sec, 1 Min. and 10Min.
• Apply an IR voltage of 5kV between primary to secondary for 10 Min. and
record the values at 15sec, 1Min. and 10Min.
• Compare the results with the Factory Test Report.
• IR test should be performed as per manufacturer recommendation.
• Record ambient temperature and humidity
Voltage Ratio Test:
• Apply the 3 Phase 415 Volts supply on the HV side of the Transformer.
3phase ,415 AC supply • Enter the Transformer Name plate Voltage of the HV winding. (Primary)
not acceptable for TX ratio test
, only test kit with approved
• Enter the Transformer Name plate Voltage of the LV winding. (Secondary)
make and model has to be • Start test from maximum tap position to the minimum tap position.
used. • Note down Values for each tap.
• Compare the values with the FAT report and calculate the ratio error.
• Ensure the error is inacceptable limit.

ONEIC-MM2021-101-MS-E23 Page 26 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

Vector Group Test:


• The Vector Group test shall be carried out in Normal Tap
• Short the “R” phases or any other same phases of both primary and
secondary windings with wires.
• Apply 3 phase 415V at the primary side
• Measure the voltage between phases of primary and secondary windings
as illustrated below table and record the value.
• Verify and confirm the Vector group

U-V V-v V-w


V-W W-w W-v
W-U U-n W-n

Magnetic Balance Test:


• The Magnetic Balance test shall be carried out in Normal Tap
• Apply 3 phase 415V at the primary side with single pole MCB Control
per phase.
• Switch On All the 3 single pole MCBs
• Switch off the “R” Phase MCB and measure the primary / Secondary
Voltage as per the Test Sheet
• Switch off the “Y” Phase MCB and measure the primary / Secondary
Voltage as per the Test Sheet
• Switch off the “B” Phase MCB and measure the primary / Secondary
Voltage as per the Test Sheet
• Record All the above measured values in the test sheet

Magnetic current measurement test at HV SIDE


• The Magnetic current measurement test shall be carried out in all Tap
• Apply 3 phase 415 Volts supply in the HV winding
• Take the current measurement using clamp meter in the HV side.
• Repeat the test for all taps.
• Note down the values.
Winding Resistance Measurement at HV SIDE
• Select the lowest Tap position of the transformer.
• Connect the test leads C1 & C2 between R-Y of Transformer primary side.
• Switch ON the meter, the meter will read the resistance of Transformer.
Record the values.
• Similarly measure the resistance for Y-B and B-R and record the values.
• Increase the tap to the next position and measure the resistance as above.
• Measure the resistance till the highest tap position.
• Record the ambient temperature in the appropriate column.
• Compare the results with the Factory test reports

ONEIC-MM2021-101-MS-E23 Page 27 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

Winding Resistance Measurement at LV SIDE


• Repeat the above test procedure and measure the resistance and
tabulate the readings. (Note: No need to change the Tap position)
• Compare the results with the Factory test reports.

Measurement of Short Circuit impedance


• A 3 phase 415V supply is applied from HV terminals and LV terminals
are short circuited. The voltage and currents on the HV are measured
simultaneously and percentage impedance on all 3 phases at all the
taps are calculated as below.

Measured impedance voltage (%) = Rated current at measured tap X Measured voltage X 100
Measured current X Rated voltage at measured tap

Mechanical Protection device checks

 Buchholz Relay: Check the operation of the main Buchholz relay alarm, trip
contacts or functioning at specified settings by pumping air into the relay or
draining the oil from the relay. Repeat the same test for OLTC Buchholz relay if
provided. Ensure that the respective relay operates in the control panel and trips
the transformer breaker with the alarm. Reset the relay by normalizing the
buchholz relay

 Pressure Relief Device: Check the pressure relief device operation by


actuating the micro switch operated by the pressure relief device. Ensure the
respective relay operation the control panel and trips the transformer
breaker with alarm. Reset the relay by resetting the PRD.

 Oil Level Switch: Check for low oil level alarm by actuating the oil switch.

 Temperature Switches: Set the temperature switches as per the recommended


settings. Check the operation of the alarm trip and cooler. Control switches by
increasing the temperature of hot oil bath in which the temperature sensors are
immersed. Check for correct operation of auxiliary relays at control panel and
alarm and tripping of the transformer breaker. Also check the start and stop of
cooler fans at specified settings of temperature switches.

 Protection System: Check that all protection relays are set to the
recommended setting. Close the transformer breaker without power and check
for all protection tripping by actuating respective protective relays. Ensure that
all the interlocks and operations are checked as per the approved schematic
drawings.

ONEIC-MM2021-101-MS-E23 Page 28 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

7.3 TESTING PROCEDURE FOR STABILITY TEST:

1) STABILITY /SENSITIVITY TEST:


• Power transformer Rating and details check as per the vendor drawing .
*TX ratio 132/11 • Ensure the Transformer differential relay make and model number as
per the drawings , ensure the transformer testing completed.
• please ensure the transformer & 33/11kv panel side cable connection.
• Apply the 415V at 33kv GIS Transformer feeder bay(before ct's) and
shorted three phase at 11kv main bus side (after ct's)
• Measure the Current 33kV(GIS) and 11kV side(SWGR)
• Change the to Tap Position in No-1 and Measure the Current in
Transformer differential relay (Diff/rest Current) , Check Differential
Current Zero.
• Same like Change the tap No-1 Measurement Change tap position to No-4
& 13, Measure the Current in Transformer differential relay (Diff/rest
Current).
• Tap position no-13 Measure the current in Marshaling box WTI LV& HV
current and LDC Current also and calculate Current same Measured value.
• 33kV Side Reverse the R-Phase Polarity and Measure the differential
current (both Side current should be add) and 33kV & 11kV Circuit
Breaker and Master trip relay should be Trip ,Check Phase of LED in
Relay.
• Same Like Reverse the HV Side Phase -Y & B Polarity and Measure the
differential current (both Side current should be added in relay) and 33kV
& 11kV Circuit Breaker and Master trip relay should be Trip ,Check Phase
of LED in Relay.
• 11kV Side Reverse the R-Phase Polarity and Measure the differential
current (both Side current should be added in relay) and 33kV & 11kV
Circuit Breaker and Master trip relay should be Trip ,Check Phase of LED
in Relay.
• Same Like Reverse the LV Side Phase -Y & B Polarity and Measure the
differential current (both Side current should be added in relay) and 33kV
& 11kV Circuit Breaker and Master trip relay should be Trip ,Check Phase
of LED in Relay.
• HV and LV side Normalize the CT Connection and Switch on the voltage
HV side measure the Differential Current should be zero Normal
Conditions.

• Testing time Confirm the Relay LED'S indication and Check Fault
recorder.
ONEIC-MM2021-101-MS-E23 Page 29 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

2) RESTRICTED EARTH FAULT TEST:


• Please Confirm the REF Relay Wiring and Relay testing completed.
• Check the connection resistor(set the Resistance as per the setting ) and
Metrosil Connection As per the drawing
Transformer ratio is
132/11 • Apply 415V at 33kV GIS transformer Feeder Bay (Before Ct's) and shorted
single phase (R-ph)
• Measure the REF(64R) Relay Current should be zero out-zone fault
condition , Measure the Current at Resistor and Metrosil voltage is zero.
• Switch off the supply and reverse the Polarity Neutral Ct or Feeder Side .
• Switch On the supply and Measured current REF(64R) relay value should
come added the Neutral CT & feeder CT Current ,resistor and Metrosil
Voltage/current Note values. Measurement time remove Trip Coil Fuse
33/11kv Side after measurement insert fuse check Tripping both side .
• Same Like Change the Connection to Other Two Phase Y&B , Measured
current REF(64R) relay value should come added the Neutral CT & feeder
CT Current ,resistor and Metrosil Voltage/current Note values.
Measurement time remove Trip Coil Fuse 33/11kv Side after
measurement insert fuse check Tripping both side .
• Normalize the CT polarity and check the Phase Shorting to Earth One by
One and Check the measurement at relay current should be zero out-zone
fault.
• Testing time Confirm the Relay LED indication and Check Fault recorder.

3) STAND-BY EARTH FAULT TEST:


• Please Confirm the SBEF Relay Wiring and Relay testing completed.
• Apply 415V at 33kV GIS transformer Feeder Bay (Before Ct's) and shorted
single phase (R-ph)
• Measure the SBEF (51NS) relay current, Calculate value of primary side
current check and ensure the Matching with relay Current.(relay
measurement time switch off the trip MCB in11kv side only)
• After Measurement Switch on the tripping coil MCB check tripping 11kV
Circuit breaker and Mater trip relay should be trip ,Check 33kV CRP
panel Annunciator alarm.
• Same like R-phase Change the connection to Other Two Phase and Check
the tripping and measurements.
• Testing time Confirm the Relay LED indication and Check Fault recorder.

ONEIC-MM2021-101-MS-E23 Page 30 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

kindly rectify intertrip matrix based on TX Ratio


7.3 11KV INTRIP MATRIX :

a. 11KV INCOMER & 33KV TRANSFORMER FEEDER TRIP CONDITION'S :


DESCRIPTION 11KV TRIP COIL 11KV F86 TRIP

11KV DIFF PROT. TRIP CB OPEN OPERATED

11KV DIR OC PROT. TRIP CB OPEN OPERATED

11KV DIR. EF PROT. TRIP CB OPEN OPERATED

11KV REF PROT. TRIP CB OPEN OPERATED

11KV SBEF PROT. TRIP CB OPEN OPERATED

33KV 51/51N PROT. TRIP CB OPEN NOT OPERATED

33KV 59N PROT. TRIP CB OPEN NOT OPERATED

b. 11KV CAPACITOR FEEDER TRIP CONDITION'S :


OUTDOOR
11KV TRIP 11KV F86 F27/59 RELAY 11KV E/S
DESCRIPTION ISO.
COIL-01 TRIP LED INTERLOCK
INTERLOCK

EMERGENCY OPERATED CB OPEN OPERATED LED- OPERATED - -

DOOR OPEN CB OPEN OPERATED LED-- OPERATED - -

READY TO
CAP ISO. OPEN CB OPEN - LED-- OPERATED -
CLOSE

11KV CB OPEN - - - - READY TO CLOSE

Over Current/Earth fault


CB OPEN OPERATED LED-- OPERATED - -
trip
Under voltage / Over
CB OPEN OPERATED LED-- OPERATED - -
voltage Trip

c. 11KV OUTGOING FEEDER TRIP CONDITION'S :


DESCRIPTION 11KV TRIP COIL-01 11KV F86 TRIP

Over Current CB OPEN OPERATED

Earth Fault CB OPEN OPERATED

ONEIC-MM2021-101-MS-E23 Page 31 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

1. AUTO RECLOSER RELAY FUNCTION CONDITION'S:


CONDITION FUNCTIONS REMAKS
1 phase fault AR CLOSE OK

1 phase fault within Reclaim time AR LOCKOUT OK

PH-PH fault AR CLOSE OK

PH-PH fault within Reclaim time AR LOCKOUT OK

Earth fault AR CLOSE OK

Earth fault within Reclaim AR LOCKOUT OK

3 phase fault AR LOCKOUT OK


A/R OUT selection
AR LOCKOUT OK
Over current & EF fault
Spring Not Charged AR LOCKOUT OK
SEF and BC AR lockout ok
d. 11KV STATION TRAFO FEEDER TRIP CONDITION'S :
DESCRIPTION 11KV TRIP COIL-01 11KV F86 TRIP

Over Current/Earth fault trip CB OPEN OPERATED

Under voltage / Over voltage Trip CB OPEN OPERATED

e. 11KV BUSCOUPLER FEEDER TRIP CONDITION'S :


DESCRIPTION 11KV TRIP COIL-01 11KV F86 TRIP

Over Current/Earth fault trip CB OPEN OPERATED

Under voltage / Over voltage Trip CB OPEN OPERATED

ONEIC-MM2021-101-MS-E23 Page 32 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

7.4 33KV INTRIP MATRIX : kindly rectify intertrip matrix based on TX Ratio

a. 33KV INCOMER TRIP CONDITION'S :


DESCRIPTION 33KV TRIP COIL-01 33KV TRIP COIL-01 33KV F86 TRIP

33KV 51/51N PROT. TRIP CB OPEN CB OPEN OPERATED

33KV 59N PROT. TRIP CB OPEN CB OPEN OPERATED

33KV BUSBAR PROT. TRIP CB OPEN CB OPEN OPERATED

b. 33KV BUSCOUPLER TRIP CONDITION'S :


DESCRIPTION 33KV TRIP COIL-01 33KV TRIP COIL-01 33KV F86 TRIP

33KV 51/51N PROT. TRIP CB OPEN CB OPEN OPERATED

33KV BUSBAR PROT. TRIP CB OPEN CB OPEN OPERATED

c. 33KV TRANSFORMER TRIP CONDITION'S :


33KV TRIP 33KV TRIP 33KV F86 33KV ANNUNCIAT
DESCRIPTION
COIL-01 COIL-01 TRIP -OR INDICATION

11KV DIFF PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

11KV DIR OC PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

11KV DIR. EF PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

11KV REF PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

11KV SBEF PROT. TRIP CB CLOSE CB CLOSE NOT OPERATED OPERATED

33KV 51/51N PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

33KV 59N PROT. TRIP CB OPEN CB OPEN OPERATED OPERATED

ONEIC-MM2021-101-MS-E23 Page 33 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

7.5 LVAC INCOMER TRIP CONDITION'S :

11KV TRIP 11KV F86 LVAC CB CLOSE


DESCRIPTION LVAC TRIP COIL
COIL-01 TRIP I/L

EMERGENCY OPERATED CB OPEN OPERATED NOT OPERATED CB OPEN

LVAC FAULT TRIP CB OPEN OPERATED NOT OPERATED -

11KV 86 TRIP CB OPEN OPERATED NOT OPERATED CB OPEN

NOT
LVAC UV CB CLOSE HEALTHY REQ. CB OPEN
OPERATED

132 kv

7.7. 33KV GIRD OUTGOING FEEDER & INCOMER PSS INTRIP


MATRIX/CONDITION'S :

a) LOCAL(GRID) /REMOTE(PSS) CB & ES CONDITIONS:

INTERLOCK CONDITIONS
GRID ESOPEN/ CLOSE PSS CB OPEN + PSS ES OPEN
PSS ES CLOSE GRID CB OPEN+ CB IN TEST
PSS CB CLOSE GRID CB CLOSE
PSS CB OPEN GRID CB OPEN

b) GRID (OUTGOING FEEDER)/33KV INCOMER FEEDER CONDITION'S :


PSS TRIP
PSS F86 GRID TRIP GRID F86
DESCRIPTION COIL-01 & REMARK'S
TRIP COIL-01 & 02 TRIP
02
LINE DIFF I> PROT. BOTH END FO
CB OPEN OPERATED CB OPEN OPERATED
TRI COMMUN. OK
LINE DIFF I>> BOTH END FO
CB OPEN OPERATED CB OPEN OPERATED
PROT. TRI COMMUN. OK
PSS BACKUP OC NOT CHECK FO
CB OPEN OPERATED NOT ODPERATED
PROT. TRIP OPERATED COMMUN. FAIL
PSS BACKUP EF NOT CHECK FO
CB OPEN OPERATED NOT OPERATED
PROT. TRIP OPERATED COMMUN. FAIL
GRID BACKUP OC NOT NOT CHECK FO
CB OPEN OPERATED
PROT. TRIP ODPERATED ODPERATED COMMUN. FAIL
GRID BACKUP EF NOT NOT CHECK FO
CB OPEN OPERATED
PROT. TRIP OPERATED OPERATED COMMUN. FAIL

ONEIC-MM2021-101-MS-E23 Page 34 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

7.8.0TESTING OF 415V LVAC:


INSULATION RESISTANCE VALUE TEST: Circuit Breaker and Bus Bar
• Ensure the equipment under test has been disconnected from supply.
• Discharge the equipment under test before start the IR test
• Make ready the Testing Equipment and connect the test leads properly in
the required phase under Test. Short and Ground other phases to Earth.
• Make sure there no device is connected to Earth in the testing portion.
(VT, Earth Switch etc..,)
• Switch on the Testing Equipment (Megger). Set the test voltage & time.
• Start the test and record the value in the Test Report.
• Complete the IR test for other phases and record the values.

I. CONTACT RESISTANCE TEST: Circuit Breaker and Bus Bar

• Measuring of DC resistance by V/ I principle.


• Connect the Current leads and voltage leads between the two ends of the
bus bar that to be tested (END TO END).and all the CB should be in Service
and closed position.
• Voltage measurement leads should be connected inside the current leads.
• Switch on the Aux power to Test kit.
• Contact resistance of main contacts shall be measured by injecting the
100A of DC Current through the connecting point in each phase (R, Y, and
B) one by one.
• The result displayed on the kit and it should be recorded.
• Repeat the test in other phases.

II. PRIMARY INJECTION TEST


• Confirm the tightness of CT secondary leads tightness.
• The CT secondary circuit should be connected to the relays, meters or it
Should be shorted properly.
• Confirm the CT circuit has not been kept open anywhere.
• Arrange the test kit in proper Location and connect the Auxiliary supply to
the socket with suitable current carrying capacity.
• Connect the current Injection leads in the Phases at suitable point according
to the Site condition.
• Switch on the Primary Injection kit and gradually increase the current up to
required range.
• Identify the cores by shorting the CT secondary in the nearest point of CT.
• Confirm the secondary current flow in all the CT cores and no sound in the
CT.

ONEIC-MM2021-101-MS-E23 Page 35 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT TENDER NO.:

COMPANY (S.A.O.G) . MM2021-101

METHOD STATEMENT FOR TESTING & COMMISSIONING OF REV. NO. DATE


HV/LV ELECTRICAL EQUIPMENTS. 00 19.12.2023

• Increase the current up to 50% of rating of CT and record the values in all
relays and meters.
• Switch off the Test kit after recorded the current in various points.
• Repeat the test in all other phases,

* Please attach list of test equipment for approval.

ONEIC-MM2021-101-MS-E23 Page 36 of 36
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
RISK ASSESSMENT MATRIX
RISK RATE= LIKELIHOOD X CONSEQUENCES
L
I 5 5 10 15 20 25
K
E
L
4 4 8 12 16 20
I
H 3 3 6 9 12 15
O
O
D
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
CONSEQUENCES

CONSEQUENCES LIKELIHOOD
1 No Injuries or Illness 1 Remotely Possible – Unknown
METHODOLOGY occurrence
Low risk 2 Minor Injuries or Illness 2 Remotely Possible – Known Occurrence
Medium risk 3 Over 3 day Injury or Illness 3 Occasional but frequent Occurrence
4 Major Injury or Illness 4 Likely to occur on regular basis
High Risk 5 Fatality 5 Almost Certain
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
NAME OF THE PROJECT / SITE : CONSTRUCTION OF 132/11KV, 2X20MVA PRIMARY SUBSTATION WITH TWO (2 NOS.) 132KV FEEDERS
FROM WADI AL JIZI PLANT TO LASAIL PSS IN AL BATINAH GOVERNORATE (TENDER NO- MM2021-101)

ACTIVITY: TESTING AND COMMISSIONING WORK JOB NO: 41078

PRE POST
S.NO HAZARD RISK L C CONTROL MEASURE REQUIRED L C RECOVERY
RATING RATING

• Pre shutdown conduct a walk over


survey to assess the power source ,
chance of multiple feeding, existing
lines which are proximate and can
cause Electromagnetic induction
Availability of
• CEP and Client must be present
throughout the duration. emergency
• TBT to be conducted. rescue team.
Shutdown/ isolation • Fire • Head count of workmen
E 5 E5-H B 3 B3-L Dial 9999(ROP)
1 of an energized • Electrocution • After getting the clearance place
existing line • Fatality discharge rods on both sides of line. In case of
• LOTO system should be followed emergency.
• Complete the task as per schedule
• Take head count of workmen and
Remove the discharge rod
• Re-energize the line
• Use PPE(Helmet mounted induction
sensor, Electric tested hand gloves,
Shock proof foot wear)
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
PRE POST
S.NO HAZARD RISK L C CONTROL MEASURE REQUIRED L C RECOVERY
RATING RATING

• Before charging all the earthing or


discharge rod to be removed.
• During charging the transformer no one
• Fire stand near the transformer location.
During Charging may
• Smoke • Obtain EPTW before start work
Bursting of • TBT prior start of job on approved JSA B
• Electrocution D 5 D5-H 3 B3-L
2 Transformer and procedure and risk involved.
• Fatality
Insulators / • Use of trained & skilled persons for
• Heat
Flashover work
• Burst sound Availability of
• De-energize the circuit
• Provision of Barrication and flash emergency
warning labels rescue team.
• Usage of proper electrical proof PPE
Dial 9999(ROP)
• Workmen should go at pole with help
of FRP ladder and during the work he In case of
must be hooked his safety belt emergency.
• No one stand near the pole when
height work is going on
• Use tool bag to avoid the fall of tool &
tackles or other accessories item like
During charging nut bolt etc.
3 • Major injury D 4 D4-H B 2 B2-L
work at height Fall • Suitable PPE (Safety helmet with
• Fatality
of materials induction tester, Safety Harness, Safety
shoe, Electrical rated rubber hand glove
must be used
• Material shall not be through from
height PP rope shall be used to bring
any material from height to ground
level
OMAN NATIONAL ENGINEERING & INVESTMENT CO (S.A.O.G)
Hazard Effective Management Process
Ref: IMS - 08 - 01 REV 01
PRE POST
S.NO HAZARD RISK L C CONTROL MEASURE REQUIRED L C RECOVERY
RATING RATING
• Before climbing on pole the stability
condition of pole to be checked
The Flush Pole (may • Possible during the string of conductor Availability of
be newly erected / the back stay to be provided in existing emergency
Existing one) may pole to avoid the collapse of pole. rescue team.
4 • Major injuries D 5 D5-H Never try to give more tension beyond B 2 B2-L
fall during •
• Multiple fatalities Dial 9999(ROP)
tensioning of the permissible sag.
conductor to • Try to avoid work on those poles which In case of
achieve the final sag are erected by other agency or not in emergency.
good condition

• Heat stress/Cramp. - Provision of shade area for rest.


• Heat stroke/rashes. - Adequate drinking water.
5 • Sun burns (Skin - Workers rotation.
Heat / Adverse D 3 D3-M A 2 A2-L
redness, tenderness, - Use of PPE to cover legs, arms, head,
weather condition.
swelling, blistering, face (balaclava) &sunglasses to protect
fever, nausea) against UV radiation.
Note:
- Control measures to achieve control of risk to ALARP using a tiered challenge of the hierarchy of controls. Combination of
control options may be appropriate to achieve ALARP.

- DESCRIPTION PREPARED BY CHECKED BY APPROVED BY APPROVED BY


Santosh Indrajeet Mohammad Rajjak
NAME WITH (Construction Manager) DEC
DESIGNATION (Sr. Testing Engineer) (HSE Engineer)

SIGNATURE WITH DATE