DSM2020 Paper#16

Uploaded by

Pedro Javier
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views10 pages

DSM2020 Paper#16

Uploaded by

Pedro Javier
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

22nd INTERNATIONAL DEPENDENCY AND STRUCTURE MODELING CONFERENCE,

DSM 2020
CAMBRIDGE, MASSACHUSETTS, USA, 13 – 15 October, 2020

Enhancing Visibility in Agile Program Increment DSMs


Siddharth Bajpai1, Steven D. Eppinger1, Nitin R. Joglekar2
1
Massachusetts Institute of Technology, Cambridge, MA, USA
2
Boston University, Boston, MA, USA

Abstract: Program Increments (PIs) are sequences of consecutive sprints during


SAFe implementation of agile developments. SAFe work is planned at two levels of
granularity: (i) stories, which create tasks (within a sprint team) and account for task
interactions at a fine level of granularity; and (ii) features (often decomposed into
stories), which account for interactions at a coarser level of granularity. A common
practice in PI planning, involving 10-15 teams, is to suppress interactions at the story
level and focus on interactions at the feature level instead. We create two DSMs for
a PI planning process – one based on story interactions, and another based on
feature interactions. We find a nearly 9X increase in interactions at the finer level,
i.e. more granular interaction, compared to a DSM based on coarser level
interaction data. We discuss theory and practice implications for using more
granular DSMs during PI Planning and oversight processes.

Keywords: Agile, Data Granularity, Interactions, Program Increment, SAFe

1 Introduction
Agile development has been envisioned to create expedient processes for incorporating
dynamic customer input into iterative and incremental software development (Agile
Manifesto 2001). The very first tenet of this agile manifesto for “uncovering better ways
of developing software” is valuing “individuals and interactions over processes and tools.”
This paper focuses on management of interactions in development projects that follow a
widely used Scaled Agile Framework (SAFe) approach to agile work (Leffingwell 2008).
Within this framework, interactions are managed through structured processes such as
daily scrum meetings, bi-weekly sprints, periodic Program Increment (PI) planning
workshops – held typically every 10 weeks, and coordination across PIs through scheduled
and nested product planning cycles. Since interactions between tasks create dependencies,
and examination of the network of dependencies may yield important insights for better
project management, we turn to Dependency Structure Matrix (DSM) analysis. Related
research has delved into the question: how can DSM analysis provide insights above and
beyond conventional agile development and information processing practices (Srinivasan
et al. 2019, Bajpai et al. 2019)? These earlier works showed that DSM analyses can provide
insights for alternative organization of dependencies, along with predictions for the impact
of these interactions on development performance.

It is common within SAFe implementations to track different types of data at different


levels of granularity while managing the scope of work, by putting features and stories into
different work containers, as shown in Table 1. Finer granularity in this case is defined as
provision of more details in terms of defining the scope of work precisely. This difference
in scope offers differing level of granularity in terms of interactions between tasks. For

DSM 2020 155


Part IV: Organizational Architectures

instance, team tasks, typically associated with daily scrums, are focused on implementing
use-case stories into software code. An example of a story during development of a user
interface is a “data explorer” that is stored as a table in a data warehouse, along with the
specification, “when a table is selected, display the variable names in it”. Stories are
typically created by decomposing features which customers would use. Building on the
“data explorer” example from above, a related feature that uses “data explorer,” and some
other stories, could be “search a variable name across databases.” Related interaction data
are tracked in information systems, such as issue-tracking databases. These issues and a
backlog of stories and features form the basis of discussions for planning work during daily
scrums and during SAFe Program Increment planning meetings every 10 weeks.

Table 2: Definitions of work containers in SAFe

Scope Unit Description Time Scale Resource Scale


A stakeholder need (specified with Single PI (~ 10
Feature Multiple Teams
coarser level of granularity) weeks)
Single desired functionality formed Single iteration
Story by splitting a feature, (specified over several Single team
with a finer level of granularity) weeks within a PI

The goal of these discussions is to create an artifact known as the PI Planning Board. The
unit of analysis within a Planning Board is features. A stylized example is shown in Figure
1. Dependencies in this board may be temporal (e.g., start of iteration 1.2 will depend on
completion of work in iteration 1.1 for team Dolphins). Dependencies may also be shown
across teams as red strings either within a single iteration (e.g., during iteration 1.3, team
Dolphins provides a significant input to team Iguanas and thus a dependency is identified)
or across iterations. Moreover, teams recognize that these dependencies exist both at the
story and at the feature level while planning for their work within a PI. Therefore, teams
plan for and track interactions at two levels of granularity: stories with finer level of
granularity and features at a coarser level of granularity.

Level of granularity has been shown in the design management literature to have bearing
on system architecture. For example, Chiriac et al. (2011) find that the degree of modularity
can vary for the same system when the system is represented at the two different levels of
granularity. They argue that the level of granularity in decomposition can distort the results
of architectural analysis and care must be taken in defining the system decomposition for
such analysis. Similarly, Maier et al. (2016) discuss the role of abstraction in modeling and
the resulting importance of model granularity. Thompson (2019) describes allied ideas
such as agile project management with Kanban, requirement definition, and resource
planning for development of hardware and software products. However, this literature does
not explore project management implications, such as task sequencing decisions, during
agile PI planning. This motivates our key research question: what is the level of information
loss associated with PI planning when interaction data are aggregated at the feature-level,
rather than at the story-level?

156 DSM 2020


Bajpai, Siddharth; Joglekar, Nitin; Eppinger, Steven

Figure 1: SAFe 5.0 Program Board (source: v46.scaledagileframework.com)

We have designed a field study to collect case evidence on interaction data at two levels of
granularity and populated the two separate PI DSMs using these data. This paper reports
on our field work and its findings. The rest of this paper is organized as follows: section 2
lays down the rationale for modeling PI DSMs, section 3 describes our field study, section
4 describes the two DSMs and provides a statistical comparison using ANOVA analysis.
We find significant differences in the dependency structures across these two DSMs. We
conclude the paper by discussing the implications of these comparisons for theories that
guide PI Planning rationale. We indicate ways in which DSMs based on granular data may
augment and improve conventional PI planning.

2 Modeling Program Increment DSMs

2.1 Program Increment Planning and Program Board


A program increment typically features 5 sprints (i.e., scheduled cycles of iterations). The
first four sprints comprise the planned development work, including integration and testing
as stories are completed by each of the teams. While the fifth sprint includes release of
completed features, it is largely devoted to forward planning for the next PI, including any
advance development required before the PI starts. All this work is executed by typically
10+ teams, collectively termed as the Agile Release Train (ART), which may bring in many
hundreds of stories and 50-100 features into their PI discussion. The PI Planning event is
typically a 2-day face-to-face workshop involving the entire ART and its customer
representatives (or “Business Owners”). The goal is to employ the agile principle of “face-
to-face conversation” (Schwaber 2009). The teams align on a “Program Vision” and
business context, and come up with a shared plan for the program increment. Specifically,
self-organizing agile teams select the features they plan to implement within the PI; these
teams then coordinate to define a mutually agreed plan communicated to business
stakeholders.

DSM 2020 157


Part IV: Organizational Architectures

A key part of teams committing to a common plan is identification and visualization of


dependencies between the work of the various teams, and from features to deliverable
milestones. The tool used for this is known as a Program Board. The board lays out team
names in rows, with each team’s row forming a “swimlane” of work over the course of the
PI. Each team’s features are represented within the swimlane for the team, with the five
sprints laid out in columns. Teams write every feature on a card and place them in their
swimlane within the iteration in which they plan to complete each feature. Dependencies
between teams or milestones are identified by tying cards together with a red string, as
illustrated in the stylized Program Board of Figure 1.

2.2 Modeling Considerations


To facilitate meaningful face-to-face conversation, the representation of coordination
requirements on the Program Board is intentionally limited. Guiding theory behind such
information hiding during development is to improve clarity of message for individual
teams and reduce coordination burden (Yassine et al. 2003, Gomes and Joglekar 2008,
Ebert and Paasivaara 2017, Thompson 2019). Typically, only directly relevant features are
represented within a team’s swim lane on a Program Board. Likewise, significant
dependencies are represented by a string connecting either two features, a feature and a
milestone, or a feature with significant input from another team. This should serve to clarify
what dependencies are, without modifying the SAFe PI Board diagram in Fig 1,

Figure 2. Stylized PI DSM

Teams may have story-level dependencies that are nevertheless important constraints on
the plan. Also, the dependency represented as a string may be unidirectional, bidirectional
or could even create a loop of dependencies. There may be additional risk factors, affecting
the expected success of the PI Plan, not captured on the Program Board. Within these visual
limitations, the ability of individual teams or a system-level owner such as the Release
Train Engineer (who leads the ART) to suggest improvements or management

158 DSM 2020


Bajpai, Siddharth; Joglekar, Nitin; Eppinger, Steven

interventions is also limited. Key milestones are also represented on the Program Board.
Examples of these include system releases (which occur at a fixed schedule, e.g. the first
Monday of every month), major external releases (e.g. a product launch date), or other
fixed externalities (e.g. vendor system updates, regulatory deadlines etc.). Milestones
interact with the plan both as constraints to schedule and sometimes as sources of new
information or change (e.g. feedback after a monthly release).

The type of DSM model we use to represent the structure of a single PI is shown in Figure
2. The DSM includes a sequence of five sprints over the PI, with the team interactions laid
out for each iteration. Interspersed between the sprints are the milestones. This matrix does
not specify features or stories as entities; i.e. it only reveals task interactions between teams.
Additional details for allied DSM modeling choices are described in Bajpai (2020).

3 Field Study

3.1 Site
Swisscom AG is a leading telecommunications provider in Switzerland. Swisscom holds
large market shares of mobile, broadband internet, and TV telecommunication in its
domestic residential and commercial markets. Swisscom is known for its premium quality
offerings, which command a premium price. We studied the PI Planning process for the
Agile Release Train “Data Lake”, which is a part of the Large Solution “Data, Analytics &
AI” (DNA) program. In addition to critical business analytics services, DNA also provides
storage, computation and access infrastructure and services to other Swisscom analysts and
engineers leveraging Swisscom’s data. The Data Lake ART, together with five other ARTs
comprise the DNA Large Solution. Four of these five ARTs are analytics-focused, and one
is focused on developing applications for business users. All six ARTs do their PI Planning
together in a single event.

3.2 Data Collection & Processing Methodology


Data presented in this paper were collected over the course of 4.5 months in 2019 at
Swisscom, the organization which serves both as the research subject as well as the sponsor
for this project. Data were collected for the model described below using three means: 1)
Live observation during a PI Planning session including discussions and agreements
between Data Lake development team members and customer teams; 2) The PI Program
Board (showing features and hard technical dependencies) and team-level planning boards
(showing story-level scheduling) generated during the meeting; 3) Additional interviews
with product owners from eight out of twelve development teams and two of the five other
ARTs.

Our method for aggregation and processing of dependency data is consistent with
established practices for aggregation and comparison of DSM metrices (see Chen and Lin
2003, and DSM literature e.g., Eppinger and Browning 2012). For each individual feature
represented on the Program Board, anticipated interactions needed to successfully
complete the feature in the PI were recorded. There were two sources for the interactions
data: ‘tasks’ in a tracking system (using a software called Jira), and from field interviews.

DSM 2020 159


Part IV: Organizational Architectures

Four categories of interactions were recorded: inputs/ enablers, feature/technical


dependency; coordination and feedback. Team interactions were modeled for each sprint
and across sprints. This means that there were interactions represented between 19 teams
(12 Data Lake engineering teams + 1 architecture team + 5 DNA ARTs + 1 ‘team’
representing Swisscom-wide interactions) over the course of five sprints in the PI. In
addition, three milestone events were also included as entities. This creates a matrix of size
98x98 (i.e. 19*5 + 3). Each cell in the matrix represents an interaction between two teams.
Two groups of interactions captured as DSMs (based on story-level and feature-level data)
allow us to explore our research question in two steps: (i) We assemble two DSMs and
compute a compositive interaction vector for each row of the respective DSM; (ii) We
conduct ANOVA tests to explore if differences in these vectors amount to statistically
significant information loss across these two groups of interactions. Then, we discuss the
implication of this significance on feature-level planning while managing a PI.

Figure 3. Two Sprints of PI DSM Based on Story-Level Data


(Number of Interactions for Full PI DSM Using Story-Level Data = 304)

160 DSM 2020


Bajpai, Siddharth; Joglekar, Nitin; Eppinger, Steven

4 Results
For ease of depiction, we present the first two sprints and one key milestone of the PI in a
39X39 DSM in Figures 3 and 4 based on story- and feature-level data, respectively.
Categories of interactions are shown in different colors as indicated by a legend in Figure
3. A full DSM based on story-level data is shown as Figure 5. Owing to page size
constraints, some details (e.g., row names) are suppressed while patterns of changes in
interactions across sprints can be ascertained.

Figure 4. Two Sprints of PI DSM Based on Feature-Level Data


(Number of Interactions for Full PI DSM Using Feature-Level Data = 32)

4.1 Aggregate Statistics


We have conducted comparisons for the story- and feature-level DSMs using the full
(98x98) matrices. We find that the story-level DSM captures 304 interactions, whereas the
feature-level DSM captures only 32 interactions. In order to assess the statistical
significance of the differences between these two DSMs, we have computed the total
number of interactions in each row (termed as interaction density). Density data are then
normalized between 0 and 1 to create vectors. These normalized vectors are used to
compare the distribution of interactions for two DSMs. Aggregate statistics and ANOVA

DSM 2020 161


Part IV: Organizational Architectures

results are shown in Table 2. They indicate that differences in the distribution of normalized
interaction vectors for the two DSMs (termed as groups in Table 2) are statistically
significant. In this analysis we have weighted all the categories equally. We have also
conducted robustness checks for category weights (e.g., by adjusting relative weights on
inputs versus technical dependencies). Category adjusted results (not shown here for
brevity) are materially consistent with the finding presented in Table 2.

Figure 5. Full PI DSM (98x98) Based on Story-Level Data

5 Implications
This study examines the interaction structure of a PI using DSMs based on different levels
of data granularity. We have identified gaps in literature, in the introduction section, that
draw on intersection of system engineering, SAFe, and agile project management. Our case
work and data analysis bring up follow on opportunities. For instance, research issues
mentioned in section 5.1 may engender new type of theories, extending the literature on
granularity in design (Maier et al. 2016) based on data with finer granularity.

162 DSM 2020


Bajpai, Siddharth; Joglekar, Nitin; Eppinger, Steven

Table 2: ANOVA Single Factor Analysis of Normalized Interaction Vectors

Groups Count Sum Average Variance


DSM Based on Story Level Data 98 41.08 0.42 0.11
DSM Based on Feature Level Data 98 24.10 0.25 0.13
Source of Variation SS df MS F P-value F crit
Between Groups 1.47 1 1.47 12.10 0.0006 3.8898
Within Groups 23.59 194 0.12

Total 25.06 195

5.1 Research Issues

1) Biases in Decision Making: Suppressing within-team interactions in order improve cross


team communication through PI Planning Board is a recommended best practice (Scaled
Agile, 2019). Our analysis shows that this practice results in a systematic
underrepresentation of interactions (32 in the PI Planning Board instead of 304 that
emerged from the more granular data analysis). Detailed analysis of such a sizable
underestimation could enhance our understanding of planning issues: does this
underestimation stem from interactions with teams that are in close physical proximity such
that coordination could managed informally? What is the dynamic impact of initial
underrepresentation of interactions (in sprint 1) on later sprints? And, given this
underrepresentation, is feature-level planning appropriate for managing a PI?

2) Early Information and Limited Look Ahead: The DSM in Figure 3 shows two square
sub-matrices corresponding with the teamwork in sprint 1 and sprint 2. It also shows
another square sub-matrix for sprint 2, below the sprint 1 sub-matrix. We term this sub-
matrix the early information submatrix. It ought to be possible to improve the predictions
for sprint 2 based on the early information submatrix data from sprint 1 (Bajpai 2020).
Figure 5 ascertains that this pattern is repeated in follow on sprints. That is, inter-sprint
decisions before any sprint can be improved by limited look ahead analysis.

3) Adaptive Organization of PI Teams: Agile work and PI planning are set up to enable
adaptive development. Composition of individual teams and interactions between teams
are managed through PI planning, scrums, and scrum-of-scrums meetings. The square
matrices for each sprint shown in Figure 5 could be put through sequencing and clustering
analyses (Eppinger and Browning 2012) to provide guidance for sequencing tasks, and for
adjusting the organizational interfaces between teams suitably. Bajpai (2020) has provided
examples for such analysis.

5.2 Implementation Opportunities

Aside from the research issues listed above, fieldwork suggests it may be the possible to
automate the generation of PI DSMs in order to support PI planning. For instance, data
collected for the story-level DSM in Figure 3 came from a combination of field interviews
and by querying the information captured by software tool (Jira). It ought to possible to
automate the generation of such granular DSMs.

DSM 2020 163


Part IV: Organizational Architectures

6 Conclusion
An overarching theme behind our research is to assess if DSM capabilities can improve the
performance of agile work by enhancing current best practices such as implementation of
Scaled Agile work. We have developed a new type of DSM to account for interactions
during PI planning and oversight. Our analysis shows that it is possible to populate such a
PI DSM with interactions based on (lower) story-level data. This generates a DSM of
interactions that is statistically different from conventional PI Planning Board. Preliminary
findings on analysis of granular interactions also indicates that use of finer granularity
(story-level) data is a fruitful line of enquiry for research on improving the PI processes.

References
Agile Manifesto, 2001. Manifesto for Agile Software Development. https://agilemanifesto.org/
Chiriac, N., Hölttä-Otto, K., Lysy, D., & Suk Suh, E. (2011). Level of Modularity and Different
Levels of System Granularity. Journal of Mechanical Design, 133(10).
Gomes, P.J., Joglekar, N.R. 2008. Linking Modularity with Problem Solving and Coordination
Efforts. Managerial and Decision Economics, 29(5), 443-457.
Bajpai, S. 2020. Planning Large-Scale Agile Development Using a Dependency Structure Mapping
Model, Masters Thesis, MIT, Cambridge, MA.
Bajpai, S., Eppinger, S.D., Joglekar, N.R. 2019. The Structure of Agile Development Under Scaled
Planning and Coordination. In DS 97: Proceedings of the 21st International DSM Conference
(DSM 2019).
Ebert, C., Paasivaara, M. 2017. Scaling Agile. IEEE Software, 34(6), 98-103.
Leffingwell, D. 2007. Scaling Software Agility: Best Practices for Large SAFe Enterprises. Addison-
Wesley. ISBN 978-0321458193.
Maier, J.F.; Eckert, C.M. and Clarkson, P.J. 2016. Model Granularity and Related Concepts. In:
Proceedings of the DESIGN 2016, 14th International Design Conference, pp. 1327–1336.
Chen, S., Lin, L. 2003. Decomposition of interdependent task group for concurrent
engineering Computers & Industrial Engineering, 44(3), 435-459.
Schwaber, K. 2009. Agile Project Management with Scrum. O'Reilly Media,
Inc. ISBN 9780735637900.
Scaled Agile, 2019. https://www.scaledagileframework.com
Srinivasan, R., Eppinger, S.D., Joglekar N.R. 2019. The Structure of DevOps in Product-Service
System Development. Proceedings of the International Conference on Engineering Design
(ICED19), Delft, The Netherlands.
Thompson, K.W. 2019. Solutions for Agile Governance in the Enterprise (SAGE): Agile Project,
Program, and Portfolio Management for Development of Hardware and Software Products.
Sophont Press.
Yassine, A., Joglekar, N., Braha, D., Eppinger, S., Whitney, D. 2003. Information Hiding in Product
Development: The Design Churn Effect. Research in Engineering Design, 14(3), 145-161.

Contact: Prof. Steven Eppinger, Massachusetts Institute of Technology, [email protected]