Acknowledgements
This IOGP Specification was prepared by a Joint Industry Programme 33
Standardization of Equipment Specifications for Procurement organized
by IOGP with support by the World Economic Forum (WEF).
Disclaimer
Whilst every effort has been made to ensure the accuracy of the information
contained in this publication, neither IOGP nor any of its Members past present or
future warrants its accuracy or will, regardless of its or their negligence, assume
liability for any foreseeable or unforeseeable use made thereof, which liability is
hereby excluded. Consequently, such use is at the recipient’s own risk on the basis
that any use by the recipient constitutes agreement to the terms of this disclaimer.
The recipient is obliged to inform any subsequent recipient of such terms.
Please note that this publication is provided for informational purposes and
adoption of any of its recommendations is at the discretion of the user. Except as
explicitly stated otherwise, this publication must not be considered as a substitute
for government policies or decisions or reference to the relevant legislation relating
to information contained in it.
Where the publication contains a statement that it is to be used as an industry
standard, IOGP and its Members past, present, and future expressly disclaim all
liability in respect of all claims, losses or damages arising from the use or
application of the information contained in this publication in any industrial application.
Any reference to third party names is for appropriate acknowledgement of their
ownership and does not constitute a sponsorship or endorsement.
Copyright notice
The contents of these pages are © International Association of Oil & Gas Producers.
Permission is given to reproduce this report in whole or in part provided (i)
that the copyright of IOGP and (ii) the sources are acknowledged. All other rights are
reserved. Any other use requires the prior written permission of IOGP.
These Terms and Conditions shall be governed by and construed in accordance
with the laws of England and Wales. Disputes arising here from shall be exclusively
subject to the jurisdiction of the courts of England and Wales.
Quality Requirements for Centrifugal Pumps
Foreword
This specification was prepared under Joint Industry Programme 33 (JIP33) "Standardization of Equipment
Specifications for Procurement" organized by the International Oil & Gas Producers Association (IOGP) with
the support from the World Economic Forum (WEF). Companies from the IOGP membership participated in
developing this specification to leverage and improve industry level standardization globally in the oil and gas
sector. The work has developed a minimized set of supplementary requirements for procurement, with life
cycle cost in mind, resulting in a common and jointly agreed specification, building on recognized industry and
international standards.
Recent trends in oil and gas projects have demonstrated substantial budget and schedule overruns. The Oil
and Gas Community within the World Economic Forum (WEF) has implemented a Capital Project Complexity
(CPC) initiative which seeks to drive a structural reduction in upstream project costs with a focus on industry-
wide, non-competitive collaboration and standardization. The CPC vision is to standardize specifications for
global procurement for equipment and packages. JIP33 provides the oil and gas sector with the opportunity to
move from internally to externally focused standardization initiatives and provide step change benefits in the
sector's capital projects performance.
This specification has been developed in consultation with a broad user and supplier base to realize benefits
from standardization and achieve significant project and schedule cost reductions.
The JIP33 work groups performed their activities in accordance with IOGP's Competition Law Guidelines
(November 2020).
Table of Contents
1 Scope ....................................................................................................................................................... 4
2 Normative references .............................................................................................................................. 4
3 Terms and definitions ............................................................................................................................... 4
4 Symbols and abbreviations ...................................................................................................................... 5
5 Quality requirements ................................................................................................................................ 5
5.1 Quality management system.......................................................................................................... 5
5.2 Conformity assessment system (CAS) .......................................................................................... 5
6 Certification and traceability ..................................................................................................................... 6
7 Evidence — conformance records ........................................................................................................... 6
Annex A (normative) Purchaser conformity assessment requirements ............................................................ 7
Annex B (normative) Certification traceability and requirements ...................................................................... 9
Introduction
The purpose of this quality requirements specification (QRS) is to specify quality management requirements
and the proposed extent of purchaser intervention activities for the procurement of centrifugal pumps in
accordance with IOGP S-615 for application in the petroleum and natural gas industries.
Purchaser intervention activities are identified through the selection of one of four conformity assessment
system (CAS) levels based on a risk and criticality assessment. The applicable CAS level is specified by the
purchaser in the procurement data sheet or purchase order.
This QRS shall be used in conjunction with the specification (IOGP S-615), the procurement data sheet (IOGP
S-615D) and the information requirements specification (IOGP S-615L) which together comprise the full set of
specification documents. The introduction section in the specification provides further information on the
purpose of each of these documents and the order of precedence for their use.
1 Scope
To specify quality management requirements for the supply of centrifugal pumps to IOGP S-615 including:
c) traceability requirements.
2 Normative references
For the purpose of this document, the documents referenced in IOGP S-615 and those listed below, in whole
or in part, are normatively referenced in this document and are indispensable for its application. For dated
references, only the edition cited applies. For undated references, the latest edition of the referenced document
(including any amendments) applies.
API Specification Q1, Specification for Quality Management System Requirements for Manufacturing
Organizations for the Petroleum and Natural Gas Industry
ISO 29001, Petroleum, petrochemical and natural gas industries — Sector-specific quality management
systems — Requirements for product and service supply organizations
3.1
conformity assessment
demonstration that specified requirements are fulfilled
Note 1 to entry: Conformity assessment (or assessment) includes but is not limited to review, inspection,
verification and validation activities.
Note 2 to entry: Assessment activities may be undertaken at a supplier/sub-supplier's premises, virtually by video link,
desktop sharing, etc. or by review of information.
3.2
conformity assessment system
CAS
system that provides different levels of purchaser interventions to assess and verify vendor conformance to
specified requirements
Note 1 to entry: CAS A applies to the highest risk and associated extent of verification. CAS D is the lowest.
3.3
hold point
H
<conformity assessment> point in the chain of activities beyond which an activity shall not proceed without the
approval of the purchaser or purchaser's representative
3.4
witness point
W
<conformity assessment> point in the chain of activities that the supplier shall notify the purchaser or
purchaser's representative before proceeding
Note 1 to entry: The operation or process may proceed without witness if the purchaser does not attend after the agreed
notice period.
3.5
surveillance
S
<conformity assessment> observation, monitoring or review by the purchaser or purchaser's representative of
an activity, operation, process, product or associated information
3.6
review
R
<conformity assessment> review of the supplier's information to verify conformance to requirements
5 Quality requirements
The vendor shall operate and maintain a quality management system (QMS) that conforms with ISO 9001,
ISO 29001, API Specification Q1 or an equivalent quality management system standard.
5.2.1
The conformity assessment system (CAS) provides different levels of assessment of the vendor's control
activities. The CAS level is defined by the purchaser, using a risk-based approach, and included in the
purchase order/contract. The defined CAS level may be adjusted by the purchaser during manufacture based
on vendor performance and re-assessment of risk.
NOTE For industrial proven solutions, CAS level D is specified unless risk assessment indicates that a more stringent
CAS level is required.
5.2.2
Quality plans and inspection and test plans shall include provision for purchaser's intervention activities based
on the CAS level selected in the procurement data sheet or purchase order. See Annex A.
5.2.3
Vendor performance in meeting the requirements may be routinely assessed during execution of the scope
and where appropriate, corrective action requested and conformity assessment activities increased or
decreased consistent with criticality and risk.
Annex A
(normative)
Purchaser conformity assessment requirements
This annex defines four conformity assessment systems (CAS) or levels of purchaser assessment.
CAS
PURCHASER ASSESSMENT ACTIVITIES
A B C D
1 Planning and control activities
1.1 Kick-off, pre-production and pre-inspection meeting H W W
2 Materials and component manufacturing
2.1 Material certification and traceability (API Standard 610, 6.12.1.8, 6.12.4.3 and 8.2.2.7,
Tables H.2 and H.4 and IOGP S-615, 6.12.1.8 and 8.2.2.7 when specified in IOGP S- W R R R
615D)
2.2 Surfaces of castings inspection (API Std 610, 6.12.2.1) W S - -
2.3 Compliance of welding materials (ASME BPVC II, Part C) S S
2.4 Fabrication
2.4.1 Baseplate manufacture (API Standard 610, 7.3 and IOGP S-615, 7.3) flatness and
W R R
coplanarity of baseplate equipment mounting pads inspection
2.4.2 Compliance review of material test reports to specification S S S -
2.5 Inspection, testing and verification activities (API Std 610, 8.2 and 8.3 and IOGP S-615,
8.2 and 8.3)
2.5.3 Inspector review of welding procedure specification (WPS), procedure qualification
S S S -
records (PQR), NDT personnel and procedures and continuity logs.
2.5.4 Inspection of major weld repairs API Std 610, 6.12.2.3 and IOGP S-615, 6.12.2.3,
H W R -
6.12.2.5)
2.5.5 Pressure casing inspection including all welds associated with the casing (API
Standard 610, Table 14 and IOGP S-615, Table 14) or as specified in IOGP S-615D. H W R -
Inspection timing (API Standard 610, 8.2.2.3)
2.6 Non-destructive examinations of component parts (API Std 610, 6.12.1.4 and 8.2.1.3) if
H W R -
specified in IOGP S-615D
2.7 Positive material identification (API Std 610, 8.2.2.8 and IOGP S-615, 8.2.2.8) and
W S R
other parts specified in IOGP S-615D
2.8 Inspector review of heat treatment certificates S S S -
2.9 Hardness testing and impact tests (API Standard 610, 8.2.2.7 and 6.12.4.5) W S R -
2.10 Shaft and rotors (API Standard 610, 6.6, 9.3.3.1 and 9.3.12.2 d, Tables 17 and 19) W R - -
2.11 Rotating component balancing (API Standard 610, 6.9.3, 9.1.3.6 and 9.2.4) or as
W R
specified in IOGP S-615D
2.12 Wear rings and running clearance verification (API Standard 610, Table 6) W S S
2.13 Cleanliness check prior to final assembly (API Standard 610, 8.2.2.6) if specified in
W S S
IOGP S-615D
2.14 Hydrostatic testing activities (API Standard 610, 8.3.2 and IOGP S-615, 8.3.2) H W W R
2.15 Performance testing (API Standard 610, 8.3.3 and IOGP S-615, 8.3.3) or as specified
H W W R
in IOGP S-615D
CAS
PURCHASER ASSESSMENT ACTIVITIES (continued)
A B C D
2.16 NPSH or submergence testing (API Standard 610, 8.3.4.3 and IOGP S-615, 8.3.4.3) if
H W W R
specified in IOGP S-615D
2.17 Mechanical run testing (API Standard 610, 8.3.4.2 and IOGP S-615, 8.3.4.2) H W W R
2.18 Sound level testing (API Standard 610, 8.3.4.5) if specified in IOGP S-615D H W R R
2.19 Complete unit testing (API Standard 610, 8.3.4.4) if specified in IOGP S-615D H H W R
2.20 Auxiliary equipment testing (API Standard 610, 8.3.4.6) if and as specified in IOGP S
H W R R
615D
2.21 Bearing housing resonance test (API Standard 610, 8.3.4.7) if specified in IOGP S-
H W R R
615D
2.22 Nozzle force and moments testing (API Standard 610, 7.4.24) if specified in IOGP S-
H W R R
615D
2.23 Structural resonance test (API Standard 610, 9.3.9.2) if specified in IOGP S-615D H W R R
2.24 Disassembly after testing (API Standard 610, 8.3.3.9) if specified in IOGP S-615D H W S R
2.25 Hydrodynamic bearing inspection after testing (API Standard 610, 9.2.7.4 and IOGP S-
H W S
615, 9.2.7.4)
2.26 Surface preparation and painting (API Standard 610, 6.12.2.1, 7.4.16, 8.4.3.4 and
H W R
IOGP S-615, 6.1.42 and 9.3.8.3.3) or as specified in IOGP S-615D
3 Release of product or service
3.1 Verify conformity to purchase order including as applicable
Final inspection
IOGP S-615, 6.4.3.5
3.1.1 Complete skid overall dimensions including holding down bolt hole and connection
H W W W
locations
3.1.2 Couplings and guards inspection (API Standard 610, 9.3.8.2.1 and 7.2.3) H W W W
3.1.3 Pump nameplate and rotation arrows inspection (API Standard 610, 6.13 and IOGPS-
H W W W
615, 6.13)
3.2 Loose ship items, spares and special tools inspections as applicable H W W R
3.3 Preparation of preservation, packing and storage (API Standard 610, 8.4 and IOGP S-
H W S
615, 8.4.2) or as specified IOGP S-615D
3.4 Release of equipment H H H H
Key
H: Hold point
W: Witness point
R: Review
S: Surveillance
Annex B
(normative)
Certification traceability and requirements