Mock 4
Mock 4
A. Mitigation.
B. Escalation.
C. Acceptance.
D. Avoidance
Question No.2
In a Project, initially all changes were going through by strictly
following perform integration change control process. Near the end
of execution, due to heavy work load, CCB is not able to clear all
change requests in time. As a result of which team has started
taking decision on changes requested by stakeholders. What
should the Project Manager do over here to prevent the scope
creep?
A. Business Case.
B. Project Management Plan.
C. Agreement.
D. Project Charter.
Question No.4
A. Settle payment with written assurance from vendor about resolving issues.
B. Take legal action against vendor.
C. Deduct amount equivalent to detect repair and pay that amount as service
order.
D. Keep the project open, delay the closure procedures.
Question No.6
A. Crashing.
B. Fast tracking.
C. Resource Smoothing.
D. Resource levelling.
Question No.7
A. Project Charter.
B. Project Management Plan.
C. Business Case.
D. Agreement
Question No.8
A. Mind mapping.
B. Affinity diagram.
C. Matrix diagram.
D. Decision tree diagram.
Question No. 9
A. Review the Project Calendar to know how long the resource is needed.
B. Check for non-billable resource who can complete assignment assigned
to the resource to be released.
C. Review the RACI to know the current assignment of the resource.
D. Immediately escalate the situation to the higher management.
Question No. 10
A. Control Quality.
B. Manage Quality.
C. Plan Quality Management.
D. Plan Scope Management.
Question No. 13
A. Project Manager.
B. A particular stakeholder who falls under Outward bracket when classified
based on direction of influence.
C. A stakeholder who falls under Upward bracket when classified based on
direction of influence.
D. CCB Team.
Question No. 15
A. Forcing.
B. Problem solving.
C. Reconciliation.
D. Smoothing.
Question No. 17
A. Decision Making.
B. Data Representation.
C. Data Analysis.
D. Decision Analysis.
Question No. 23
A. Planning.
B. Executing.
C. Monitoring and Controlling.
D. Closing.
Question No. 24
A. Develop Team.
B. Manage Team.
C. Monitor Communication.
D. Control Resources.
Question No. 26
A. Accepted Deliverable.
B. Work Performance Information.
C. Verified Deliverable.
D. Change Request.
Question No. 31
During planning, the Project Manager and the team are involved in
the process of identifying and documenting relationships among
the project activities. With the help of a software they are
connecting each activity, other than the first and the last one to at
least one predecessor and successor activity with an appropriate
logical relationship. Which process is getting performed in this
scenario?
A. Sequence Activities.
B. Define Activities.
C. Create WBS.
D. Plan Schedule Management.
Question No. 32
A. Trend Analysis.
B. Document Analysis.
C. Regression Analysis.
D. Meetings.
Question No. 34
In an Internal project initiated by a car manufacturing company,
several Subject Matter Experts have gathered to decide the
outcome of a deliverable regarding its formal acceptance.
Ultimately a decision-making technique that is also been used in
requirement gathering as well as making decisions on Change
Request has been applied to reach a consensus. What decision
making technique has been used in the given scenario?
A. Voting.
B. Inspection.
C. Meetings.
D. Autocratic decision making.
Question No. 35
A. Project Charter.
B. Business Case.
C. Enterprise Environmental Factors (EEF).
D. Organizational Process Assets (OPA).
Question No. 36
A. Business Case.
B. Need Assessment.
C. Project Management Information System (PMIS).
D. Conflict Management.
Question No. 37
A. Basis of Estimates.
B. Resource Calendars.
C. Resource Management Plan.
D. Cost Management Plan.
Question No. 38
A. Conduct Procurements.
B. Develop Project Charter.
C. Plan Procurement Management.
D. Control Procurements.
Question No. 40
A. Histogram.
B. Design for X.
C. Questionnaires and surveys.
D. Scatter diagrams.
Question No. 42
A. Manage Team.
B. Manage Quality.
C. Implement Risk Responses.
D. Manage Project Knowledge.
Question No. 43
A. Define Activities.
B. Define Scope.
C. Estimate Activity Duration.
D. Determine Budget.
Question No. 46
A. Data Analysis.
B. Decision Making.
C. Interpersonal and Team Skills.
D. Data Gathering.
Question No. 56
A. Control Scope.
B. Develop Project Management Plan.
C. Control Resources.
D. Control Quality.
Question No. 58
A. Validate Scope.
B. Control Quality.
C. Monitor and Control Project Work.
D. Control Procurements.
Question No. 60
A. Voting.
B. Nominal group technique.
C. Facilitation.
D. Focus groups.
Question No. 61
A. Networking.
B. Political awareness.
C. Communication styles assessment.
D. Expert Judgement.
Question No. 64
A Project Manager of a large project goes for a long sabbatical
leave just a week before Project kick-off meeting. Tom is the new
Project Manager who has joined as his replacement. As a newly
joined Project Manager, he wants to know what development
approach has been decided to follow in the project. What should
Tom refer to fetch this necessary information?
A. Project Charter.
B. Communication Management Plan.
C. Project Management Plan.
D. Stakeholder Register.
Question No. 65
A. BAC.
B. EAC.
C. ETC.
D. PMB.
Question No. 74
During planning, two team members have disagreement on addition of one of the Solution
requirements in Project Scope Statement. According to one team member if the requirement gets
added, it will be beneficial for the project later. But other team member says addition of such
requirement would increase ambiguity risks of the project that why, it’s better to keep it in the
project exclusion list. Project Scope Statement needs to be finalized soon, so both the team
members reach out to Project Manager for expert opinion. The Project manager after reviewing
everything said “It’s good to see that both of you have agreed most of the contents of the Project
Scope Statement, let’s make it final as of now. Regarding this particular requirement, let discuss
with sponsor post Phase 1”.Which of the following conflict-resolution techniques the Project
Manager applied over here?
A. Smoothing.
B. Compromising.
C. Reconciling.
D. Directing.
Question No. 75
A. SV is negative.
B. SPI = CV.
C. CV is negative.
D. SPI is equal to Zero.
Question No. 78
Tom is a project manager of a software development project which has gone
behind schedule as 2 Testers has suddenly resigned and they are unreachable.
Team after reviewing all Planning documents decided to introduce Automated
testing instead of manual testing for few tasks on critical path. However, this
decision would add two more servers in the project Infrastructure landscape and
network may not have adequate capacity to handle the extra load of these two
servers, which may impact the testing. What is the type of risk mentioned in the
above scenario?
A. Secondary Risk.
B. Residual Risk.
C. Ambiguity risk.
D. Variability Risk.
Question No. 79
The Project Manager of the Buyer organization is not convinced with the cost
estimates provided by the perspective sellers for company’s upcoming
construction project. After meeting with sponsor, the project manager decides to
award the contract to one of the preferred sellers with a clause that seller has to
provide all details of their legitimate direct costs that will be incurred during the
life cycle of the contract for final invoice payment. The contract also states that
the buyer organization will pay a fee of $ 6,000 regardless to the invoiced cost.
What type of contract has been awarded in the above scenario?
A. Change log.
B. Project Management Information System (PMIS).
C. Work Performance Data.
D. Work Breakdown Structure (WBS).
Question No. 81
A. The risk response was not approved by the change control board.
B. The Project Team failed to have a fallback plan.
C. The issue has not been documented in issue log.
D. No action has been taken to implement the risk response.
Question No. 83
A. Prevention.
B. Inspection.
C. Tolerances.
D. Audit.
Question No. 84
The Project Team has done Root Cause Analysis of all defects
detected during inspection. The Project Manager used a tool to
organize and group the results of Root Cause Analysis which he
will present in next Senior Management review meeting. Which of
the following tools has been used by the Project Manager in the
above scenario?
A. Affinity Diagram.
B. Cause and Effect Diagram
C. Mind Mapping.
D. Histogram.
Question No. 85
A. Approve the Change Request and engage Project Team to start the
implementation procedure.
B. Seek help from the Change Control Board.
C. Ask Sponsor to authorize the Change Request.
D. Evaluate the impacts of change on other project constraints
Question No. 86
A. $40,000.
B. $15,000.
C. $25,000.
D. $65,000.
Question No. 87
A. Functional Manager.
B. Project Manager.
C. CCB.
D. Sponsor.
Question No. 88
A. Alternative analysis.
B. Technical performance analysis.
C. Reserve analysis
D. Variance analysis.
Question No. 92
A Construction company has appointed Tom as a project manager of a business-
critical software development project. The company has recently dismissed a
vendor company that consisted of 16 consultants who completed half of the work
in 9 months and spent 82% of the budget of what was originally a 12 Month,
$1,000,000 project. Tom has formed a new team of 8 developers, and they are
completing the rest of the work at the pace that was originally planned, and for
half the price that was originally estimated for each remaining deliverable. What
is the EAC?
A. $ 820,000.
B. $ 952,000.
C. $ 1,320,000.
D. $ 1,070,000.
Question No. 93
The document that formally authorizes the Project
has been created and approved. A new Project
Manager has been appointed and a list of Key-
stakeholders has also been identified as a part of
the process. What should be done NEXT?
A. The newly appointed Project Manager should hold a kick-off meeting.
B. The newly appointed Project Manager should start the preparation of developing
Project Management plan with available list of key stakeholders.
C. The newly appointed Project Manager should update the business case and build a
new implementation strategy.
D. Information on approved project charter should be shared with stakeholders to ensure
common understanding of the key deliverables, milestones and their roles and
responsibilities.
Question No. 94
Phase 1 of the project has been successfully completed.
During planning stage of phase 2, Project Manager and team
along with few key stakeholders are trying to do assessment of
the type and quantities of raw materials necessary to perform
and complete project work. Which of the following tools and
technique cannot be used as a part of this process?
A. Analogous estimating.
B. Parametric estimating.
C. Expert Judgement.
D. Three-point estimation.
Question No. 95
A. The project manager should apply crashing technique to bring the project back on track.
B. The project manager should apply Fast tracking technique to bring the project back on
track.
C. The project manager should soon initiate risk response planning for all open risks.
D. The Project Manager should reduce the project scope for early release.
Question No. 97
You are a project manager of a website development project.
Project team has done initial stakeholder analysis and grouped
all stakeholders according to their level of authority, and level
of concern. Which of the following engagement strategies
should be applicable for end-users who are responsible for
handling day-to-day operational activities?
A. Manage Closely.
B. Keep Informed.
C. Keep Satisfied.
D. Monitor.
Question No. 98
Feedback and Presentations are widely used in
project management as one of the popular tools and
techniques for communication skills. Which of the
following processes use feedback and presentation
as valid tools and techniques?
A. Monitor Stakeholder Engagement.
B. Collect Requirements.
C. Manage Stakeholder Engagement.
D. Monitor Communication.
Question No. 99
The document that shows organization commitment to the project has been
prepared. Portfolio Governing body chairperson and other authorized
representatives are having a meeting to discuss and decide the outcome of
the document that has been prepared. They are also reviewing the Cost-
Benefit analysis, Feasibility study report, and other factors that justified the
requirement of the project. Which of the following documents has been
prepared as per the scenario mentioned above?
A. Program Charter.
B. Business Case.
C. Project Charter.
D. Project Management Plan.
Question No. 100
During Planning, the project management team decided not to
change the project management plan for addressing a risk of
low probability and high impact. Instead additional reserves
are planned in case such situation occurs. What response
strategy has been planned in this scenario?
A. Risk Avoidance.
B. Passive risk Acceptance.
C. Risk Mitigation.
D. Active Risk Acceptance.
Question No. 101
Tom is the recently joined Project Manager of a business complex IT project. After
receiving detailed knowledge transfer from the outgoing senior project manager, he has
started conducting team meeting and actively got involved in maintaining documents like
communication management plan, stakeholder register, and few other necessary project
documents. The outgoing project manager is closely observing all activities of Tom and
in time helping him with suggestions. What Knowledge management technique has
been followed in the above situation?
A. Knowledge Transfer.
B. Knowledge fairs and cafes.
C. Reverse shadowing.
D. Job shadowing.
Question No. 102
A. Closing.
B. Executing.
C. Monitoring and Controlling.
D. Executing and Monitoring and Controlling.
Question No. 103
The Project work has been completed successfully and the customer has confirmed the
formal acceptance of the product that has been delivered. Before releasing the entire
team, the Project Manager engaged the team to document the final lessons learned, so
that future projects can benefit out of it. What should the Project Manager do next?
A. Burndown Chart.
B. Burnup Chart.
C. Why-why Diagram.
D. Run Chart.
Question No. 105
Tom is a Project Manager of a company which has been awarded a project that involves
renovation of a building of a Chemical plant. There are lot of toxic and radioactive
wastes inside the building. What is the best approach the Project Manager can take to
transfer the risk?
A. RACI Chart.
B. Organization breakdown structure (OBS).
C. Work breakdown structure (WBS).
D. Resource breakdown structure.
Question No. 107
A. Stakeholder Register.
B. Enterprise environmental factors (EEF).
C. Resource Management Plan.
D. Risk management Plan.
Question No. 108
Tom is a Project Manager of a Software development project. During execution,
a key stakeholder requests him for a scope change and asks about the correct
change control process that should be followed throughout the project. Which
control document should the Project Manager refer to fetch this necessary
information?
A. Requirement Documentation.
B. Project Scope Statement.
C. Scope Management Plan.
D. Scope baseline.
.
Question No. 110
Jack has been awarded as Project Manager of a new software development
project. He decides to meet another Project Manager who has handled similar
project in the past. But he finds out that the person whom he wants to meet has
left the organization a month back. What should Jack do to gather necessary
information of the past project?
A. Crashing.
B. Fast tracking.
C. Resource leveling.
D. Resource smoothing.
.
Question No. 112
Tom is a newly joined Project Manager of a construction project which is running behind schedule.
The project has few ongoing issues with a preferred vendor who is responsible for supplying cements
for the project. He decides to facilitate a meeting between Buyer and seller management team to
resolve all misunderstandings and create a win-win solution. What should he review to know the
alternate dispute mechanisms applicable for the project?
A. Monitor Risks.
B. Plan Qualitative risk analysis.
C. Plan Risk Responses.
D. Perform Integrated Change Control.
Question No. 114
A. Control Quality.
B. Plan Quality Management.
C. Manage Quality.
D. Plan Scope Management.
Question No. 115
A. Interactive communication.
B. Push communication.
C. Pull Communication.
D. Interpersonal communication.
Question No. 116
Tom is a Project Manager of a software development project which is divided into four phases. Phase
1 of the project didn’t go well as 60% of the deliverables were not accepted by the customer. In a
retrospective meeting, Director of the IT department asks the project manager to furnish all the
reasons that resulted in customer non-acceptance of the verified deliverables. What needs to be
reviewed to know which deliverables were not accepted by customer and the reasons behind such
non-acceptance?
A. Acquire Resources.
B. Plan Procurement Management.
C. Conduct Procurement.
D. Plan Resource Management.
Question No. 118
A. Approve the Change Request and advise the Project manager to add funds in
Management reserve.
B. Discuss the situation with sponsor and ask him to make the final decision.
C. Deny the Change Request since project budget will be impacted.
D. Defer the Change Request and wait until government regulation gets implemented.
Question No. 120
A. Category
B. Event
C. Trigger
D. Quantification
Question No. 121
A. Interviewing.
B. Delphi technique.
C. Assumption analysis.
D. Brainstorming.
Question No. 122
A. Status reports.
B. Email.
C. Voice calls.
D. Face-to-face meetings.
Question No. 124
A. Risk register
B. Risk Report
C. Issue log
D. Lessons Learned Register
Question No. 125
A. Review the Stakeholder Engagement Plan and ensure that the stakeholders are not
affected by this unofficial platform.
B. Review the Communication Management Plan and direct the team not to use this
platform anymore.
C. Immediately arrange communication training for the team and terminate the platform.
D. Ignore the situation as the project is running smoothly.
Question No. 126
A. Bidder conferences.
B. Make or buy analysis.
C. Analytical techniques.
D. Advertising.
Question No. 127
You are a Project Manager of ABC project. Your team members – Jack and Ryan
has successfully passed PMP exam. You are very happy and want to make sure
that the success of the team member gets recognized beyond project level. What
document you should update?
A. Resource leveling.
B. Fast tracking.
C. Crashing.
D. Schedule optimization.
Question No. 130
A. Communication management plan may act as valid input for identify stakeholder
process only after first iteration of the Identify stakeholder process.
B. Change log and Requirement documentation are valid input for identify stakeholder
process.
C. Stakeholder identification process can periodically happen throughout the project on
need basis.
D. Post first iteration of stakeholder engagement process, business document acts as
sources of information about project’s stakeholders.
Question No. 131
During the mid of execution, the customer comes up with new quality
requirements that involves change in project schedule. Any change in
schedule baseline can only be approved through which of the
following processes?
A. Validate Scope.
B. Control Quality.
C. Monitor and Control Project Work.
D. Perform Integrated Change Control.
Question No. 133
During early stage of execution, a new Project Manager has joined the project.
He wants to know; how the outcomes of uncertainties are documented,
maintained, communicated throughout the project. What should the project
manager review to fetch this necessary information?
During the mid of the project, the project manager is trying to ensure
that all information needs of project and its stakeholders are met as
its planned. Which of the following documents would you refer to
confirm the same?
A. Communicated.
B. Acknowledged.
C. Confirmed.
D. Clarified.
Question No. 136
Your project team members have just started to work together after
resolving several interpersonal conflicts. They are now adjusting their
work habits and behaviors to support each other. Which stage of the
Tuckman ladder has your team just entered?
A. Norming.
B. Performing.
C. Forming.
D. Storming.
Question No. 137
A. Do Quantitative analysis
B. Evaluate using simulation technique.
C. Evaluate on a qualitative basis.
D. Evaluate using tornado diagram.
Question No. 139
A German stakeholder joins the team in a multi-phase project. Sponsor has
already informed the project manager that he is important for the project. After
meeting with him, the project manager realizes that the new stakeholder should
be involved in all status meetings and receive confidential information in
association to the project. The project manager adds him in the stakeholder
register. What should he do next?
During a risk review meeting, the project manager learns that a new
company policy has been implemented, which prohibits the use of
overtime. This restriction in hours for the development team
represents a new constraint for the project. Where should this newly
identified constraint be documented?
A. Once baselines, Cost baseline can only be changed with only formal change control
procedure even if Change is minor.
B. Cost baseline include work package Cost estimates as well contingency reserve.
C. The cost baseline is the approved version of the time-phased project budget, excluding
any management reserves.
D. Cost baseline include cost of all control accounts as well as management reserve.
Question No. 145
A. Cost of Quality.
B. Cost of Conformance.
C. Cost of Non-Conformance.
D. Fixed Cost.
Question No. 146
A junior Project Manager asking a senior Project Manager about a document that
is created during execution and is used to evaluate the achievements of the
quality objectives. It may include dedicated checklists and detailed Requirements
traceability matrices. What is the document the junior Project Manager is talking
about ?
A new project manager joins the XGH project. He wants to review the
project team directory as well as the roles and responsibilities of
team members. Which document should he review?
A. WBS.
B. RACI chart.
C. Project Team assignments.
D. Resource Calendar.
Question No. 148
The following skill helps the project manager to reduce tension and
increase co-operation among Project team players in a highly
stressful and demanding project environment. What has been
referred in the given scenario?
Tom is a project manager of ABX project, some of the project deliverables have
been sub-contracted to the vendor CXA. Before signing the contract, the vendor
asked whether they can get a part of the payment in advance before submission
of first set of deliverables. As a Project Manager what should Tom review to give
answer to the vendor ?
You are a Project Manager of a complex and large automation project where you are helping sponsor
to prepare project charter. Only one of your vendor-SQZ from the preferred vendor list has the skill set
to work in such projects. But you have come to know from your senior Management that the SQZ
vendor you are looking for is not well suited for your organization environment. The internal resources
of the organization don’t have technical capability to do this project. What is the best course of action
that you can take here as a Project Manager?
A. Award the contract to the SQZ vendor who has the technical capability.
B. Engage SQZ vendor into a Trial Engagement.
C. Build bid documents and arrange bidder conference with perspective sellers.
D. Train your internal resources on the new technology.
Question No. 152
You are a project manager of GHF project. Currently the project team
is carrying out contingency plan in response to risk triggers. Which of
the following processes is being carried out in the given scenario?
You are a Project Manager of a project where scope is well defined. However,
there is scarcity of resources in your organization, so you award a Fixed price
contract to one of your preferred seller. What risk response strategy you have
applied?
A. Avoid.
B. Share.
C. Transference.
D. Mitigate.
Question No. 156
The following contract clause does not allow for appeals in courts of
law based on performance. What type of contract has been referred
in the given scenario?
A. CPIF.
B. FP-EPA.
C. CPAF.
D. FPIF
Question No. 157
A. Scope Creep.
B. Gold plating.
C. Crashing.
D. Fast tracking.
Question No. 161
You are a Project Manager of a Research and Development project where scope
is very volatile and there is no available in-house talent. You have awarded a
Cost-Plus-Incentive-Fee (CPIF) type of contract to one of your preferred vendor.
The project is negotiated such that if the final costs are less than expected costs,
the sharing formula for cost savings is 75:25. The targeted cost is US$ 100,000
with an 8% incentive fee on the targeted cost. If the project comes in at US$
80,000, what would be the cost of the total contract?
A. $108,000.
B. $93,000.
C. $112,000.
D. $88,000.
Question No. 163
A. Seller proposals.
B. Requirements documentation.
C. Source selection criteria.
D. Procurement contract.
Question No. 164
A. Forming.
B. Storming.
C. Norming.
D. Performing.
Question No. 165
A. Customer, Sponsor.
B. Suppliers, Regulatory bodies.
C. Project Manager, Team members.
D. Competitors, PMO.
Question No. 167
A. Scope baseline.
B. Requirements traceability Matrix.
C. Requirements Documentation.
D. Issue Log
Question No. 168
A. Trend Analysis.
B. A Performance Review.
C. Inspection.
D. Audit.
Question No. 170
A. Scope Verification
B. Three-point estimation
C. Time-boxing
D. Value analysis
Question No. 172
A. Context diagram.
B. SIPOC diagram.
C. Prototype.
D. Brain-writing.
Question No. 176
A. Management reviews.
B. Control Quality.
C. Control point.
D. Validate Scope.
Question No. 177
You are preparing a report for upcoming meeting with the senior
management. The report should show the greatest potential Risk to
your project. You decided to use a tool to illustrate the same. What
kind of tool can be used here?
A. Influence Diagram.
B. Why-Why Diagram.
C. Tornado Diagram.
D. Pareto Chart.
Question No. 178
A. Context Diagram.
B. Prototype.
C. JAD.
D. Requirement Traceability Matrix.
Question No. 179
A. Project Charter.
B. Requirement Documentation.
C. Project Management Plan.
D. Scope Management Plan.
Question No. 180
A. Bench-marking.
B. Market Research.
C. Source selection analysis.
D. Expert judgment.
Question No. 181
While performing project work, Tom, the team player notices that there is a
potential new risk, which could impact the project's critical path. He informally
discusses the same with the project manager, who advises him to do something
immediately What is the most probable suggestion , the project Manager gave to
Tom?
A. Recommend the project be placed on hold for a day to avoid the risk.
B. Document the risk in the risk register.
C. Record the same in issue log.
D. Generate a risk report using quantitative and quantitative analysis of the identified risk
to alert the team of the schedule impacts.
Question No. 183
Tom is a project manager of WSD project who has just completed planning. BU
Head of the company wants Tom to furnish a report that would include
procurement delivery method to be used in the project, type or nature of
agreement considered for the project, phases of procurement Which document
should Tom refer to give appropriate information to the BU head?
A. Risk register.
B. Stakeholder Register.
C. Communication Management Plan.
D. Activity attributes.
Question No. 185
A. Brainstorming.
B. Questionnaires and surveys.
C. Brain writing.
D. Stakeholder Mapping.
Question No. 186
A. Deliverable.
B. Requirement.
C. Product Scope.
D. Process
Question No. 187
A. Scatter Diagram.
B. Fish Bone Diagram.
C. Control Chart.
D. Run Chart.
Question No. 188
A. Technical Risk.
B. Management risk.
C. Commercial risk.
D. External risk.
Question No. 190
A. Voting.
B. Autocratic decision making.
C. Multi-criteria decision analysis.
D. Nominal group technique.
Question No. 191
In the mid of the project, the project manager realizes that the raw materials
available in-house got exhausted, and he needs to purchase raw materials from
outside. What analysis should the Project Manager do FIRST in vendor selection
process, considering the remaining project budget in mind?
A. Alternative Analysis.
B. Variance Analysis.
C. Regression Analysis.
D. Cost-benefit Analysis.
Question No. 192
Senior management has asked the Project Manager of GHF project to provide a
report containing information on acceptable procurement timetable as well as
assumptions planned for resource allocation. What should the Project manager
review first to provide this necessary information?
A project got seriously delayed. Earned value analysis shows that the project
needs to be completed at 15 percent faster rate. To get the project back on track,
management wants to add 3 more people to an activity currently assigned to one
resource. The project manager disagrees to this solution, as nothing such an
increase in number of resources will produce the desired increase in speed and
performance in relation to the project. This is an example of:-
A. Earned value.
B. The law of diminishing returns.
C. Fast tracking.
D. Life cycle costing.
Question No. 194
A. Resisting to change.
B. Building trust.
C. Resolving Conflict.
D. Active listening.
Question No. 195
You are the newly appointed project manager of the ABC organization. Currently
you have been assigned a project which has just moved to the planning stage. A
PMP certified expert clearly explained you that for any modern-day projects you
are required to consider an Enterprise Environmental factor to determine how the
work gets assigned to the people. What should you consider knowing how the
work is assigned to the people?
A. RACI Matrix.
B. Project Management Information System (PMIS).
C. Resource Histogram.
D. Work authorization system.
Question No. 196
A. Cost Aggregation.
B. Cost Baseline.
C. Financing.
D. Project Funding requirements.
Question No. 197
Tom is a Project Manager of a new RPA project. During Risk review meeting,
team identifies a new type of technical risk and updates the necessary
documents. Since, such risks are new to the company, Tom decides to update
this Risk level information in detail so that risk identification process of future
projects can include this new risk in their Risk Identification Checklist. What
should be updated in the mentioned scenario? Choose the best answer.
A. Change Log.
B. Risk Register.
C. Issue Log.
D. Stakeholder Register.
Question No. 200