Planning Scheduling Monitoring and Control 1st Edition
Planning Scheduling Monitoring and Control 1st Edition
Monitoring and
Control
All rights reserved. No part o this publication may be reproduced, stored in a retrieval system, or
transmitted, in any orm or by any means, without the express permission in writing o the
Association or Project Management. Within the UK exceptions are allowed in respect o any air
dealing or the purposes o research or private study, or criticism or review, as permitted under
the Copyright, Designs and Patents Act, 1988, or in the case o reprographic reproduction in
accordance with the terms o the licences issued by the Copyright Licensing Agency. Enquiries
concerning reproduction outside these terms and in other countries should be sent to the Rights
Department, Association or Project Management at the address above.
v
For use by APM individual and corporate members only
Contents
3 Scope management 21
3.1 Denition o scope management 21
3.2 Purpose o scope management 21
3.3 The scope management process 22
3.3.1 Dening the scope 22
3.3.2 Describing the scope 22
4 Requirements management 25
4.1 Denition o requirements management 25
4.2 Purpose o requirements management 25
4.3 Process o dening requirements 25
4.3.1 Requirement description 26
4.3.2 Factors to consider when dening
requirements 26
4.3.3 Inputs into requirements management 27
4.4 The requirements management process 27
4.4.1 Capture and dene requirements rom all
stakeholders 27
4.4.2 Link requirements to the product breakdown
structures and work breakdown structures
where appropriate 27
4.4.3 Decompose requirements 28
4.5 Works inormation (WI) 29
4.6 Statement o work (SOW) 30
5 Stakeholder management 31
5.1 Denition o stakeholder management 31
5.2 Purpose o stakeholder management 31
5.3 Managing stakeholders through the project 31
6 Project amiliarisation 33
vi
For use by APM individual and corporate members only
Contents
vii
For use by APM individual and corporate members only
Contents
viii
For use by APM individual and corporate members only
Contents
ix
For use by APM individual and corporate members only
Contents
x
For use by APM individual and corporate members only
Contents
xi
For use by APM individual and corporate members only
Contents
xii
For use by APM individual and corporate members only
Contents
xiii
For use by APM individual and corporate members only
Contents
xiv
For use by APM individual and corporate members only
Contents
xv
For use by APM individual and corporate members only
Contents
xvi
For use by APM individual and corporate members only
Contents
xvii
For use by APM individual and corporate members only
Figures and tables
Figures
1.1 The importance o planning and control in project management 2
3.1 Types and relationships o breakdown structures 23
4.1 Design and development V model 28
7.1 Top-down vs. bottom-up planning 44
7.2 Rolling wave planning 46
7.3 Agile planning 47
7.4 Setting early and late curves 50
7.5 Interpreting ‘S’ curves 51
8.1 Creating a breakdown structure level 1 54
8.2 Creating a breakdown structure level 2 54
8.3 Creating a breakdown structure level 3 55
8.4 Types and relationships o breakdown structures repeated 56
8.5 Sample product breakdown structure 58
8.6 Work breakdown structure 59
8.7 Work breakdown structure dictionary (deence) 62
8.8 Work package content sheet (construction) 63
8.9 Organisation breakdown structure 64
8.10 Responsibility assignment matrix 66
8.11 Example o a RACI 69
8.12 Cost breakdown structure 70
11.1 Cost estimating process 78
12.1 Time measured in nancial periods 85
12.2 Generating a cost orecast using a banana curve 86
13.1 The scheduling process in the context o planning, monitoring
and control 94
13.2 Relationship o dierent densities in schedules 97
13.3 A hierarchy o plans and planning documents 98
14.1 Distorting the time/cost/quality triangle 105
14.2 Types o time-phased schedules and their relationship 106
14.3 A sample procurement schedule 108
14.4 Time-phased procurement schedule 110
xviii
For use by APM individual and corporate members only
Figures and tables
xix
For use by APM individual and corporate members only
Figures and tables
xx
For use by APM individual and corporate members only
Figures and tables
Tables
2.1 Examples o requirements and acceptance criteria 17
6.1 Sources o project inormation 33
8.1 Explanation o RACI codes 68
12.1 A simple cost budget 84
13.1 Features associated with density o schedules 95
15.1 Example o activity descriptions 114
16.1 Example o three-point estimate 148
xxi
For use by APM individual and corporate members only
Figures and tables
Picture credits
The ollowing illustrations have been adapted rom originals published by Taylor
Woodrow/Vinci Construction: Figure 8.8, Figure 13.2, Figure 13.3, Figure 14.3,
Figures 17.4 to 17.10, Figures 21.1 to 21.6, Figure 22.4, Figure 22.14, Figure
24.1, Figure 26.1, Figures 26.7 to 26.8, Figure 31.1
The ollowing illustrations have been adapted rom originals published by BAE
Systems: Figure 8.7, Figure 17.3
The ollowing illustrations have been adapted rom originals published by Turner
& Townsend: Table 25.1, Figure 25.2, Figure 25.3
Figure 4.1 courtesy o Neil Curtis
Figure 14.4 courtesy o Balour Beatty
Illustration on p. 329 courtesy o Simon Taylor/Paul Kidston
All other illustrations are courtesy o the APM PMC SIG
xxii
For use by APM individual and corporate members only
‘Planning is an unnatural process; it is much more un to do
something. The nicest thing about not planning is that ailure comes
as a complete surprise, rather than being preceded by a period o
worry and depression.’
Sir John Harvey Jones
Planning has been part o my lie or so many years now. I trained as a mechanical
engineer, and the last assignment o my apprenticeship was within the construc-
tion planning department o British Steel’s piping division (1974 is a long time ago
now, unortunately!). That experience captured my imagination and I decided to
embark on a career as a planning engineer. My many experiences since have
taught me how vitally important it is to plan how a project, programme, portolio
or business will be delivered.
Sir John Harvey Jones’ quote ‘The nicest thing about not planning is that ailure
comes as a complete surprise, rather than being preceded by a period o worry
and depression’ reveals a culture still buried deep within many organisations’ and
individuals’ approach to project or business delivery today. However, when you
have been involved in the ‘complete surprise’ you realise that i the team involved
had opted or the ‘worry and depression’ this would have prompted action and
led to a more successul outcome.
Fortunately, my involvement in successully delivered projects or programmes
ar outweighs my ailing project experiences, and, when looking back, success
usually comes down to good denition, preparation and planning rom inception
onwards. The Kuwait reconstruction (1991/1992) and London 2012 Olympic
(2008 to 2012) programmes were two big highlights in my career, where the
challenge was to achieve delivery within very clearly dened timescales under
the highest possible level o public scrutiny.
For these programmes, the creation and maintenance o an integrated suite o
plans/schedules allowing project/programme-level decision making to be
eective was a key part o the delivery success which both commentators at the
time and historians since have recorded.
Now, as a result o the considerable eorts o the APM Planning, Monitoring
and Control (PMC) Specic Interest Group (SIG), organisations and programme/
project teams will have a guide covering all aspects o planning, rom preparing
to undertake a project to executing that project, controlling its sae delivery to
budget, time and quality.
xxiv
For use by APM individual and corporate members only
Foreword
I believe that this publication has captured the best practices or planning and
will become the reerence document o note or organisations and their teams
during uture project deliveries.
David Birch
Head o capital delivery project controls – National Grid
Formerly head o programme controls – ODA delivery partner CLM
(2008–2012)
12 June 2014
xxv
For use by APM individual and corporate members only
Preace
Sir John Harvey Jones said that ‘Planning is an unnatural process . . .’ and we all love
this quote, as it says something that we recognise about human nature. In this guide
we contend that planning is partly a process, a ‘science’ i you like. But there is also
an art to planning, one which requires good ideas, experience, deep thought and
creative thinking, particularly around business planning, consideration o options
and choosing methodologies. This book discusses the art o planning, but places an
emphasis on the scientic side o planning – the processes o scheduling, risk
analysis, management o change (and so on) – in what we hope is a practical manner.
The guide was conceived ater the ormation o the Planning, Monitoring and
Control (PMC) Specic Interest Group (SIG) in late 2010 to ll a gap in published
APM knowledge. It was intended to cover all planning aspects o preparing to
undertake a project, executing a project, controlling its delivery to budget, time
and quality, and delivering it saely. The guide was to be about planning in the
widest sense o the word. Just as with the ormation o the PMC SIG, its aim has
been to bring together dierent project specialisms, rather than ocus on a
particular area o specialist knowledge.
Ater much discussion and debate, a basic structure or the guide was agreed
upon, and content started to be written. By late 2013 a large amount o material
had been gathered but momentum had fagged, so a sub-committee o the SIG
was ormed to pull together all the material and ll the gaps that inevitably still
existed at that point. An intense period o writing and re-writing, as individuals
and as a group, ollowed.
xxvi
For use by APM individual and corporate members only
Preace
Paul Kidston
Lead author
June 2014
xxvii
For use by APM individual and corporate members only
Acknowledgements
This guide was discussed, debated and drated over a number o years, but written
and nalised by a small team who ormed a sub-committee o the Association or
Project Management’s Specic Interest Group ‘Planning, Monitoring and Control’,
consisting o:
Lead author: Paul Kidston (Head o project control, Taylor Woodrow Civil
Engineering)
Co-author: Keith Haward (Associate director, Turner & Townsend)
Jenn Browne (Programme manager, Ministry o Deence)
Carolyn Limbert (Principal planner, Harmonic Ltd)
Simon Taylor (Head o planning, Transport or London)
Additional material and comments were provided by: Alan Bye (Rolls-Royce);
Andrew Chillingsworth (Atkins Rail, ormerly o Turner & Townsend); Breda Ryan
(Jacobs PMCM UK Inrastructure, ormerly o Heathrow Airport Limited); Claire
xxviii
For use by APM individual and corporate members only
Acknowledgements
Dedication
This book is dedicated to the memory o Rebecca Evans, a much respected SIG
member and contributor to this guide.
xxix
For use by APM individual and corporate members only
Peer review
The guide was widely peer reviewed by people with a wide range o experience
rom outside the SIG, and we are grateul to the ollowing, who provided signi-
cant comments and suggestions:
From the Rhead group, Pete Mill, Steve Higheld, John Nixon and Robin
Smoult; Ben Whitlock (Babcock International Group); James Manthorpe, Louise
Arrowsmith and Sarah Cummins, all o Taylor Woodrow. From the Cross Industry
Planning and Project Controls (CIPPC) group, Mark Singleton (Balour Beatty
Construction Services UK), Franco Pittoni (Parsons Brinkerho) and Phil Budden
(Costain) all provided useul suggestions.
xxx
For use by APM individual and corporate members only
Purpose
Note
Within this guide, text highlighted in blue means that the term thus highlighted is
reerred to in the glossary.
xxxi
For use by APM individual and corporate members only
For use by APM individual and corporate members only
For use by APM individual and corporate members only
1
Overview
This book oers tried and tested techniques and principles covering these aspects
o project management. It introduces some lesser-known and emerging practices,
some o which will move into mainstream project management in the years
to come.
The book is structured into ve main sections refecting these requirements,
and a brie introduction to each section and chapter ollows.
Part One o this guide describes the principal processes that dene the project,
and answers these questions.
1
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The rst topic dealt with is the creation o the business case (Chapter 2). This
is the starting point in the lie o any project, and it is a vital step in ensuring that
the project is viable, aordable and desirable. It sets the scene or all that ollows
– the planning, scheduling, monitoring and control, and, not least, the delivery o
the project.
Assuming the business case is approved, the scope o the project must be
dened and agreed with all stakeholders (Chapter 3). Dening the scope will
begin the process o making key decisions about the project, dening and
selecting rom various options until a preerred solution is agreed and approved.
Once the scope has been agreed, the details o the requirements are
determined. See Chapter 4 (Requirements management).
Stakeholder management (Chapter 5) is dealt with briefy, as the responsibility
or this alls mainly on the project manager (see Sot Issues – Project Management
Time in Figure 1.1).
Chapter 6, the nal chapter in Part One (Project amiliarisation), is a checklist
o the project documentation that has been created during the denition stage.
These are the key documents that must be read and understood to enable the
planning – and subsequent processes detailed in the guide – to be carried out in
an inormed way.
2
For use by APM individual and corporate members only
Overview
Chapter 7 introduces planning – the team approach to working out how to deliver
the project. Ater discussing and dening the dierence between planning and
scheduling (a point worth making to help dene the two terms) – these terms
are oten used interchangeably, but they are two very dierent processes and
require dierent skill sets – the opening chapter o this section goes on to discuss
the principal components that will make up the overall project plan – the various
schedules and narratives. It is important to understand these at the planning
stage, and, whilst they are introduced here, they will be covered in urther detail
in Part Four.
Chapter 8 denes and discusses the purpose o the various breakdown
structures that are used in project management. We also propose a method o
creating these structures. Chapter 9 introduces the concept o dependency
management. This theme is returned to in Part Four, when the specics o
schedule dependencies are dened in greater detail.
A critical concern o all project management must be the highest standards o
health, saety and environmental management (Chapter 10). We cannot do
justice to this topic in a book aimed across all industries, but it is a very important
aspect when planning any project. It will have a undamental infuence on the
project – how it is planned, designed/engineered and constructed.
Finally, in Chapters 11 and 12, we discuss the cost-estimating process and the
budgeting process that ollows it. The ormer is an essential step in the denition
and planning (and, indeed, scheduling) o the project. The latter is essential in the
creation o targets and baselines that will orm the basis o monitoring and control.
3
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
planner’s role is to orm these thoughts into a coherent schedule, and then to
communicate it eectively. This will include:
Part Three commences with a chapter (13) setting the scene; it discusses the
purposes o scheduling and some o the basic philosophies and structures.
Chapter 14 describes the various types and purposes o schedules that might be
used on a project.
Chapter 15, entitled Schedule design, details the various elements o a
schedule that need to be considered prior to commencement o any scheduling:
or example, what type o activity should be used, or what coding and other
structures should be applied.
Chapter 16 addresses the construction o the schedule. It is this guide’s
contention that all scheduling starts with the creation o a logic-linked network.
On simple projects a bar (or Gantt) chart may suce, but we have chosen to
describe these as outputs, or communication tools, rather than scheduling tools
in their own right. We believe this is consistent with current practice. Within this
chapter we discuss not only networks but also how durations may be calculated,
the importance o considering and scheduling resources, and how schedules are
interaced with other stakeholders.
Chapter 17 ollows with a number o suggestions about how the schedule is
communicated – rom the aorementioned bar charts through to line o balance
and time chainage charts that are useul in particular circumstances. One very
important and sometimes overlooked document is the schedule narrative. This
document serves to explain and clariy the planning and scheduling eort that
has resulted in the (suite o) schedule(s) that have been created. Without this,
the project cannot be clearly understood. We suggest appropriate contents or
this narrative.
The nal part o the generic process is schedule review (Chapter 18), describing
the basic and detailed checks that should be made on the plans and schedules.
Turning once again to the question o who owns the programme, the nal
two chapters o this part (Chapters 19 and 20) deal with two emerging practices
that have an important part to play in sharing the planning and the schedule
with the project team: the agile approach, used mainly in sotware development,
and the building inormation modelling (BIM) approach or use in asset design,
4
For use by APM individual and corporate members only
Overview
construction and management. The latter is mandated or use in all government
procurement activity rom 2016, so it is very likely to grow in signicance over the
coming years.
The rst question (Where are we?) may be decomposed into urther questions
such as: Are we on schedule? I not, where have the delays occurred? What
caused the delay? Who is responsible, and what eect will it have on the project?
Finally, what can be done to recover?
The second question (What has it cost to get here?) may also be broken down
into similar questions: Where and why did any over or under spend occur? Who
is responsible and how will we recover?
The question ‘Where are we going?’ may be considered in terms o time
(When are we going to nish?), cost (What is it going to nally cost?) and quality
(Will the nished product do what we intended?). The analysis o current trends
will enable orecasting and/or challenge on these matters.
The ourth and nal question (How can we correct any problems?) also
requires project-specic experience and very oten innovative thinking, topics
that this guide does not, indeed cannot, cover. The monitoring and control
process provides the basis or asking the right questions, and perhaps the basis
or answering them.
The chapter on baselines (Chapter 21) could be a section in its own right, as it
is the pivot between the planning and scheduling eort and the processes o
monitoring and control. It is, however, a useul introduction to perormance
management, and touches on issues o change and other orms o control that
are dealt with later in this part o the book.
Perormance reporting (Chapter 22) covers the collection o progress and cost
inormation and how this is turned into useul management data. Various
5
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
reporting techniques are discussed: rst, variance reports that simply measure
dierences, exposing them (hopeully) to potential management action; second,
a category that we have called ‘perormance analysis methods’ that includes
potentially the most valuable reporting o all, earned value analysis. As stated in
the earlier purpose section o this guide, this book does not supersede the APM’s
own Earned Value Handbook, and readers with a urther interest in this subject
should reer to that guide. However, this guide does cover the basic principles o
earned value.
Cost control is given its own chapter (Chapter 23), and, although it is covered
with some brevity, the undamental principles are discussed.
Ater the project has started, the project needs to react to progress made and
re-plan as necessary. This is oten the driver o short-term planning (although
breaking plans into greater levels o detail (or ‘densities’) is also a unction o
this). In Chapter 24, we outline this process.
Chapters 25 and 26 discuss two processes that will actually be active
throughout the whole lie o the project. The ormer discusses change
management, and the latter gives an overview o risk management. This chapter
provides details o the QSRA and QCRA processes, which are the quantitative
analyses o schedule and cost, respectively (hence the acronyms). These are tools
that check the initial and ongoing robustness o the project plans.
The last chapter in Part Four (Chapter 27) discusses orensic analysis and delay
and disruption analysis.
6
For use by APM individual and corporate members only
Overview
7
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
enough to deliver the project eciently, but scaled to suit the size and complexity
o the project as appropriate.
Some research and eort are required to ensure that the tools used and their
conguration are suitable or the organisation or project and the team who will be
using them. In some industry sectors a big consideration will be client expecta-
tions, and this cannot be ignored.
8
For use by APM individual and corporate members only
Part One
Denition
11
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Each o the economic options must be appraised in terms o costs, benets, risks
and opportunities. Having considered the options, this section should then
clearly present the recommended option to the sponsors/stakeholders.
12
For use by APM individual and corporate members only
Business case
• return on investment;
• improved productivity;
• lower maintenance costs;
• saer operations;
• providing essential services;
• training or increased productivity;
• enhanced customer experience.
2.3.1.6 Timescale
Dierent parts o the business case are emphasised at dierent lie cycle stages:
• initiation stage: consider the dierent options and include a summary o each
option;
• planning stage: the case must be made or the preerred option, with detailed
costs and benets or each to clearly show why the preerred option is
recommended;
13
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• execution stage: the project progress is compared with the business case to
ensure that the project continues to deliver the expected benets, and or an
acceptable cost;
• closeout/handover: comparison between the project outcome and that
dened in the business case. Have the dened benets o the project been
achieved, or are they going to be achieved?
However, the two key stages are the time over which the project will be run and
the period over which the benets will be realised. The ormer is required to
understand cash-fow orecasting, periods o disruption etc., and the latter to
acilitate the cost/benet analysis.
Anything that delivers more savings than it costs will produce a positive net
nancial eect, and this should be quoted with the relevant back-up data.
2.3.1.8 Resources
Ideally, projects should be possible to carry out using existing resources.
Where there are insucient internal resources to deliver the project, proposals
must be made to either recruit additional, or acquire external, resources to
complete the work. This aspect can clearly have a major impact on the viability
o a project.
14
For use by APM individual and corporate members only
Business case
• a summary o major risks identied with the project and their likely impact,
including any mitigation plans;
• the nancial provision or risk, including the method or its evaluation;
• the nancial benets o realising opportunities, including the method or their
evaluation.
Risks and opportunities considered in this section should include risks to cost,
time, health and saety, the environment, reputational damage, the eects on
third parties and so on, as is relevant to the particular sector or organisation.
I the project is considered too risky, then the project sponsor may decide to
not proceed.
15
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
availability that may actor into the business case, such as the ability to
expend money, or other constraints, such as the availability o key resources.
In addition, inormation or inclusion in the business case, such as resource
histograms or high-level schedules, should be provided.
16
For use by APM individual and corporate members only
Business case
The business case may contain a summary list o key project milestones relevant
to stakeholders (acceptance events).
17
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The procurement strategy should consider the ollowing, but these will dier
rom organisation to organisation:
• Funding processes: how will unding be obtained or the project, and what
type o approvals will be required and when?
• Contract procurement ramework: will the project require new procurement
(because o the size, complexity or specialist nature o the project), or will an
existing ramework o suppliers be used?
• Contracting strategy: what type o contracts will be used?
• Financing constraints: are there any constraints on the nancing o the project?
I so, cash-fow orecasting may be required, as will the introduction o
spending caps.
• Risk and contingency processes: how will the project obtain and draw down
(allocate) risk and contingency monies?
• Security issues: sensitivity o inormation and security concerns will infuence
the procurement strategy. Security around intellectual property rights may be
a concern.
The business case should dene how the scope o the project will be
procured. For example, i the business need is or a rapid delivery o the
project it may be appropriate to select the shortest procurement route, single
source procurement, existing supply chain ramework, as opposed to
competitive tender.
The commercial project manager or project procurement proessional should
both have input into the business case and understand it. Much o the activity
associated with developing the business case will typically be undertaken as part
o the wider project management process. However, i large or key elements o
the project are likely to be sourced rom outside the customer, the role o
procurement is to provide support and inormation, so that inormed early
decisions, even i only ‘in principle’, can be taken.
Project managers must understand the development o the project procurement
strategy in terms o how to break a project down into packages o work, and what
actors to consider when giving direction on how individual providers will be
selected, paid and rewarded, risks allocated, etc. Investing time in developing the
strategy both increases the likelihood o the individual packages being successul
and, more importantly, allows the business to review how the packages t together
to deliver the overall benets.
18
For use by APM individual and corporate members only
Business case
19
For use by APM individual and corporate members only
For use by APM individual and corporate members only
Scope and requirements denition are the processes that ensure the project
includes all the work required to complete it, and then dene that work. They
dene the structures that enable the planning, scheduling and budgeting
exercises to be undertaken in a structured manner. This will acilitate the control
o the project as it enters its execution phases.
The management o scope should rigorously prevent ‘scope creep’. This is the
colloquial term given to any scope that is added or undertaken which is not
validated and authorised via the project’s scope denition or change control
process.
These processes control how the project scope is developed and veried.
They clearly dene who is responsible or managing the project’s scope and act
as a guide or controlling the scope.
21
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• build method;
• brainstorming;
• accurate/agreed requirement setting and capture;
• stakeholder/end-user management (interviews, analysis);
• key assumptions management (creating an assumptions list);
• product analysis;
• options analysis;
• acilitated workshops.
The project manager is responsible or carrying out renement and agreement o
the scope with the project executive, sponsor, programme manager, end-user
and other key stakeholders to ensure that the project delivers a relevant and
appropriate solution. It is essential that these key individuals sign up to their
agreement o scope and that this is recorded in the project management plan.
Once the scope has been agreed it should be put under a ormal change
control process, as scope creep and uncontrolled change are common causes o
project ailure.
• Product breakdown structure (PBS): Whilst not all industries and sectors
will use a PBS, it can be used as an interim step towards generating a WBS. It
is developed at the start o the project when the product or outcomes have
been scoped and agreed. The PBS breaks down all necessary outcomes o
a project.
22
For use by APM individual and corporate members only
Scope management
23
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Work breakdown structure (WBS): The WBS breaks down or groups all
activities within a project. A WBS can be urther broken down into work
packages and planning packages.
• Organisation breakdown structure (OBS): This is a hierarchical structure
showing organisational accountability or the project and does not need to
refect the organisational structure o the company, just the project accountab-
ility. The OBS is dened down to the level o management control required in
the WBS. Roles are usually used in the OBS rather than names (e.g. engineer-
ing manager).
• Responsibility assignment matrix (RAM): The RAM designates the responsib-
ility o work packages to a team or individual. The RAM is a cross-reerence o
the WBS and OBS.
• Cost breakdown structure (CBS): The CBS provides a nancial view o
the project and splits the project scope into its individual cost components.
The CBS oten highlights any nancial coding used or the business accounting
system and any booking codes associated with each element o the project.
• Resource breakdown structure (RBS): The RBS organises the project
resources in a hierarchical list that is used to plan and control the project. The
structure is not usually identical to the CBS, but there will be a relationship
between them.
24
For use by APM individual and corporate members only
4.1 Denition o requirements management
Requirements management is the process o capturing, assessing and justiying
stakeholders’ wants and needs.
It requires the capture o requirements via a structured process. This process
should incrementally break down the requirements in a hierarchical manner,
considering dierent conditions and scenarios. The requirements, once dened,
must be validated with the project sponsor and/or key stakeholders to ensure the
ull scope has been captured.
Requirements management is an ongoing process that is maintained
throughout the project lie cycle.
25
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
26
For use by APM individual and corporate members only
Requirements management
27
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
28
For use by APM individual and corporate members only
Requirements management
should also be agreed upon. This could include analysis, inspection, demonstra-
tion or test, or simulation. A clearly dened requirement increases the chances o
the project sponsor being able to make a clear decision regarding acceptance
ater completion.
Requirements may be traded where appropriate, to balance time, cost, quality
and saety parameters within the scope o work, using an approved change
control process.
Once requirements have been clearly dened and agreed, they should be
clearly documented, and the strategy or the delivery o the requirements should
be detailed within the PEP and the schedule.
The requirements should be baselined beore commencing the design and
delivery process.
There are a number o design approaches, but or the majority o projects a
validation and verication requirements matrix (VVRM) is a useul model to map
the user requirements and system design, in order to acilitate the project
assurance process; compliance with requirements may be achieved by linking
the VVRM to tests, trials, demonstration, analysis and inspections within the
relevant plan and then to the project schedule.
Key review points should be identied (or example preliminary design review,
critical design review), where certain requirements must be met beore the
project proceeds urther. At these reviews, requirements and acceptance criteria
should be validated prior to testing to ensure that they are still appropriate. I not,
they can be amended through the relevant change process.
The VVRM should be updated as requirements are met through their
acceptance criteria.
Handover and closeout o all requirements and assumptions should be
captured in a ormal acceptance process
29
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
30
For use by APM individual and corporate members only
5.1 Denition o stakeholder management
Stakeholders are the organisations or people who have an interest or role in the
project, or are impacted by it. Stakeholder management is the ormal management
o these interests, including the management o the relationships and monitoring
the delivery o commitments made to the stakeholders.
31
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
a relevant and appropriate solution. It is essential that these key individuals sign
up to their agreement o scope and that this is retained or record purposes.
Stakeholders must be identied, their level o interest and power to infuence
the project analysed, and plans devised or their management. Stakeholder
management is an iterative process which starts during project concept.
Stakeholders should be managed to ensure that a positive relationship with
the project is built and maintained.
Stakeholder management becomes more complex when stakeholders’ views
are not consistent throughout the lie cycle o the project as changes occur in
their opinions, roles and views regarding the project.
The project’s communication plan should be employed as a tool or stakeholder
management. It may include who the stakeholders are and their communication
needs, and who is responsible or their management and planned responses.
Stakeholder management needs to consider interaces with third parties or
outside infuences.
32
For use by APM individual and corporate members only
When approaching the planning o a project, it is important to gain a wide appre-
ciation o important actors that may infuence the project’s success, its approach
or its complexity. Although a planner will not be expected to know the nite
technical detail o the project, planners should have an appreciation o each
element o the project. Areas where the project team typically may need to gain
a high level o understanding are listed in Table 6.1.
The contract, especially identied • Key dates, contract dates, risk ownership,
risks and key deliverables restrictions, limitations on working conditions,
and any other requirements
Stakeholders • Who are the ‘key players’ that will impact the
success or ailure o the project? How does this
infuence the plans?
(Continued)
33
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
External interaces, i.e. those that • Supply o critical resources, e.g. utilities,
will not be covered by the project power supply
schedule
Gateways and stage approvals • Critical to a lot o projects. Find out what
approval stages are required, e.g. or design
or unding
34
For use by APM individual and corporate members only
Part Two
Planning
• understand the need, problem or opportunity that the project will address and
the benets that it will deliver;
• dene what has to be accomplished and delivered, typically stated in terms o
scope, time, budgets and quality;
• develop a plan to deliver the project.
Planning is the activity o determining how raw materials and other resources are
delivered into a desired outcome. It is also the process that will deliver a compet-
itive edge to organisations competing to win contracts to deliver work.
37
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
38
For use by APM individual and corporate members only
Introduction to planning
39
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Above all, planning is about communicating the sequence, method and time
required to complete the project deliverables.
• Ensure that the planning exercise is properly led, and that all input rom the
project team and other stakeholders is considered, reviewed and included as
appropriate. This should assist in achieving buy-in o the project team. Planning
should never be an isolated exercise.
• Ensure that the right people are made available to contribute to the planning
process in the manner described above.
• Ensure that a structured approach is taken, so that the ull scope o the project
is planned and that it ties back to all the contractual requirements.
• Ensure that adequate time is allowed to undertake the planning exercise.
• Ensure that there is proper understanding o the scope and all commitments,
and that, during the planning exercise, all dependencies are identied and
described and all interaces are understood.
• Ensure all assumptions are dened, documented and taken into account.
• Ensure that adequate scheduling resources such as people and inormation
(e.g. estimating norms), along with an adequate project controls system, are
available to convert the planning exercises into understandable schedules,
reports and other documentation.
• Planning and control systems will always ail i the human actors are
ignored.
• Ensure that the scheduling disciplines discussed in this guide are applied by
the scheduler(s) to clearly dene, describe and communicate the plan, both in
terms o clarity and in terms o appropriate distribution. In practice, no one
technique will likely give a denitive answer in terms o both planning and
control. Good practices are set up by careul selection o the right tools or the
project.
• Ensure that all actors surrounding the project are taken into account. This will
include logistics planning, stakeholder management and the availability o
suitably trained and numerous resources.
• Ensure all project risks are understood and taken into account, and that any
identied risk mitigations are included in the schedule.
40
For use by APM individual and corporate members only
Introduction to planning
41
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• dening constraints;
• establishing priorities;
• dening and documenting assumptions.
A key part o planning is creating the project schedule. (This is oten reerred to
as the programme, but, in order to avoid conusion with programmes o work
and other uses o the word ‘programme’, it is common to use the term ‘schedule’,
and this guide uses this convention.)
Collectively, these documents do all orm part o the schedule, and links between
these documents and the master/working schedule must be actively managed
and updated.
It is not useul to manage all this in the specialist scheduling sotware, because
it increases the size o the schedule to less manageable proportions (it is likely to
be a high-density level o detail). It would also make it harder or the project
manager to access the data, thus detracting rom the main purpose o the schedule.
42
For use by APM individual and corporate members only
Introduction to planning
chainage charts, line o balance graphs, etc. – these are dynamic, logic-linked,
usually critical path views o the schedule or the physical and deliverable works.
43
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
44
For use by APM individual and corporate members only
Introduction to planning
45
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
It should be noted that each wave end-point is a guide, and, when scheduling
out work, each work package should be planned to its natural conclusion, rather
than cut at a specic point in time to meet the wave end date. The waves may
relate to phases o the project as shown in the illustration above.
46
For use by APM individual and corporate members only
Introduction to planning
• There is the possibility that, in uture rolling waves, the granularity can be
manipulated to display an intended critical path, rather than the actual critical
path or the project.
• Lack o detail in uture phases may hinder adequate risk analysis.
• Critical path activities are unclear until detail is ully understood in uture
waves.
• Thus, there is a high probability that the project end date may be aected ater
each wave o detail is added.
47
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
scheduled later in the uture might be shown as single releases, using a longer
duration.
Not all activities are constrained to sprints; or example, procurement activities
or activities involving external stakeholders.
There is a common misconception that is it not possible to reliably develop and
use a baseline or an agile project, but this is not the case. Welcoming change
does not mean undisciplined or ad hoc delivery. The project still has a vision, a
timescale in which the vision needs to be achieved, and a budget. The planning
o the sprints is guided by the project vision.
A baseline provides the basis or speciying expected outcomes o each
iteration. As a result, customers have the ability to hold the team accountable to
the project vision at the end o each iteration and version release.
Being agile means that there is less resistance to changing the schedule; the
highest priority is to satisy the customer by early and continuous delivery o
valuable sotware. Delivery can be prioritised, using the MoSCoW technique, to
ensure the prioritisation o critical aspects o the solution:
• Must have: These are the requirements that are completely non-negotiable.
Without them, the project will not provide a solution to the customer’s
problem. Wherever possible, these are the requirements that are developed
rst, to gain customer trust and condence in the system, providing early
unctionality.
• Should have: These are the requirements that are still important, but, with
some pain, could in the worst case be taken out; however, there would need
to be ‘work-arounds’ and stakeholder management and buy-in to remove
these requirements rom the scope o the project.
• Could have: These are the ‘nice to have’ requirements. Without them,
the project solution will still deliver; however, there is value to adding
these requirements or a more complete system. These are the requirements
which, i time or cost becomes tight, are the rst to be cut out o the
scope.
• Won’t have (this time): These are the requirements that have been agreed by
the customer and project team to be non-essential, and are thereore being
let out o the scope o the project deliberately. This is not to say, however, that
i the project is awarded an extension, or i there is a delay elsewhere, some o
these non-essential requirements cannot be added in at a later date i they do
not detract rom the main project priorities.
48
For use by APM individual and corporate members only
Introduction to planning
Once the strategy has been decided upon, it will direct the rest o the planning,
estimating and scheduling eorts o the project, potentially imposing constraints
and other limitations on the schedule and methods to be adopted.
Dierent strategies can be described with diering planned value curves. The
basic possibilities are based on the critical path method (CPM), which calculates
two sets o dates based on the same schedule logic (an early completion and a
late completion or each activity). The combination o these orms an envelope in
which the works can logically be completed without delaying the desired project
completion date (see Figure 7.4).
Relying purely on CPM, the curves produced would not make achievable plans:
• The early curve, though logically possible, relies on every aspect going
perectly to plan, the absence o risk realisation and the availability o unlimited
resource. This never happens. This curve is oten reerred to as the P0 plan, P0
reerring to zero percent probability o achievement.
49
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Working to the late curve may be logically achievable, but will allow no
deviation rom plan, as all foat has been eliminated. I a delay to an activity
were to occur, delivery on time or to budget with the existing logic and
assumptions would be impossible. Attempting to work to this curve would
be to assume that no risk will be realised.
50
For use by APM individual and corporate members only
Introduction to planning
51
For use by APM individual and corporate members only
For use by APM individual and corporate members only
8.1 Denition o breakdown structures
Breakdown structures are tools used to break down the project into smaller
elements to acilitate the delegation o responsibility.
8.3.2 Level 2
The next step is to break out the structure into more manageable levels to make
the planning process easier. In the example, the product is now broken down into
phases.
53
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
54
For use by APM individual and corporate members only
Breakdown structures
55
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
56
For use by APM individual and corporate members only
Breakdown structures
57
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The next step is to identiy the plans and reports needed to manage products
in the project.
A PBS is drawn in a hierarchical structure rom the top down. The rst
box summarises the overall product, with the subsequent branches showing
intermediate products such as assemblies, sub-assemblies and components or
parts.
It may be useul to break down products into specialist products, which are
those products required to meet the scope or requirement, and management
products, such as reports and plans.
58
For use by APM individual and corporate members only
Breakdown structures
59
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The WBS provides a common ramework or the development o the planning
and control o a project. It divides work into denable work packages rom which
a statement o work can be developed and technical, schedule, cost and resource
reporting can be established. Individual work packages or areas o the WBS may
be broken down urther to give better schedule segregation.
A WBS code must be applied in order to identiy the work packages within the
project in a logical manner. This then orms the basis or accurate reporting and
mapping o time, cost and resources.
Each section o the WBS or work package can then be assessed to:
60
For use by APM individual and corporate members only
Breakdown structures
• The sum o the work at the ‘child’ level must equal 100% o the work represen-
ted by the ‘parent’.
• The WBS should not include any work that alls outside the actual scope o the
project, i.e. it cannot include more than 100% o the work.
61
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
works. In other words, it is a tool to identiy scope gaps or overlaps and assist in
their elimination.
62
For use by APM individual and corporate members only
Breakdown structures
63
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
64
For use by APM individual and corporate members only
Breakdown structures
• First, identiying the organisational structure or the resources involved in the
project.
• This should then be broken out into the areas or departments, sub-areas or
sub-departments and down to the role that will be accountable or a WBS
element.
• This is then drawn out as a hierarchical organisational tree, showing the
reporting lines and communication paths.
65
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
It is used to show the accountability or the various work packages or activities
within the project team.
The RAM can orm the basis or scheduling activities and is a key input when
developing the network diagram or Gantt chart.
66
For use by APM individual and corporate members only
Breakdown structures
The OBS will be combined with the WBS to create a RAM. Generally, it is
shown as a grid with the WBS elements on the let-hand side and the OBS
resources across the top, marked at the appropriate intersections to indicate who
is doing what. (Sometimes the RAM is drawn the other way around, with the
WBS at the top and the OBS at the let.)
67
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
A = Accountable Approves the completed work and is held ully accountable or it.
Usually one accountable role
68
For use by APM individual and corporate members only
Breakdown structures
69
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
standard and thereore imposed upon the project. In practice, this could infuence
(or possibly hinder) the project reporting system, so it needs to be taken into
account in the establishment o all breakdown structures. Indeed, it may be
necessary in these circumstances to put a project specic cost collection system
in place, which will require serious design and specication, as well as new
business processes and training.
The CBS is sometimes known as the ‘£ RAM’, or example in the deence
sector.
70
For use by APM individual and corporate members only
Breakdown structures
machinery, materials and equipment. Any resource that incurs a cost should be
included in the RBS.
71
For use by APM individual and corporate members only
For use by APM individual and corporate members only
9.1 Denition o dependency management
Dependency management is the process o monitoring and controlling the key
interaces on a project.
• suppliers;
• disciplines;
• client;
• third parties;
• sub-contractors;
• other agencies (more typically in Ministry o Deence projects).
• approval gateways;
• design reviews;
• client assurance reviews;
• consultation;
• discipline integration/coordination.
73
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Since the consequences o interaces can include delays to the ‘receiving’ party,
or acceleration to the ‘giving’ party, there can be expensive consequences i they
are not well managed. The creation o a separate schedule to enable proactive
management o dependencies is discussed in Chapter 16.
74
For use by APM individual and corporate members only
Health, saety and environment (HSE) is a key area o risk that needs to be
planned and managed. Since it is important and strategic in terms o project
success, it must be driven rom the very top o the organisation and be given at
least equal status to other disciplines when planning a project. Considering HSE
at the planning level allows all activities required to complete the project to be
allowed or, and, perhaps more importantly, saety to be considered when meth-
odologies are derived, such that any unnecessary saety risks are planned out o
the project.
It should be recognised that all change must be considered in the light o HSE
concerns, as accidents and near misses are requently caused by last-minute
changes o plan, which by their nature may not have received ull consideration
in the way that long-planned activities have.
From a scheduling point o view, it is important to consider any health, saety
and environmental aspects that will need to be incorporated into the schedule.
Whilst this guide is not a comprehensive guide to HSE issues, this section touches
on some important issues to be considered in the planning and scheduling o a
project.
75
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
services to ensure that the eect on the public and these services is considered
and their requirements must be complied with. When designing the schedule, it
is important to do so with the relevant level o saety in mind. For example, the
aorementioned industries would all require labour to have special training/
security clearance prior to being able to work on site.
It is essential that project working areas are established with a clear set o rules
and responsibilities:
• Ensure that sae protection is provided to all workorces, and saety zones are
created around dangerous operations.
• Ensure segregation o workorce and public – in particular, sae access and
egress o large vehicles and plant rom construction sites or assembly plants.
• Segregation within the project environment is also essential where it can be
managed – or example, the separation o machines and people.
• Ensure the security o the project.
As part o the planning, method selection and scheduling process, saety items
should be considered. Any hazards that are identied must be reported to the
relevant authorities or line management.
This guide does not seek to give industry-specic advice, but the principle o
considering HSE in the strategic and tactical planning o work is an obligation on
all involved in planning.
76
For use by APM individual and corporate members only
11.1 Denition o cost estimating
Cost estimating is the process used to quantiy the cost o services, materials and
resources required to deliver a project.
An estimate should be robust and repeatable. The estimate should contain the
source inormation used to calculate the estimate and associated assumptions.
77
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
11.4.1.1 Planning
The planning stage is the earliest stage in scope development. Typically
estimates are termed ‘conceptual’ or ‘pre-conceptual’ and will rely primarily
on approximate methods. Estimates prepared at this stage o the planning
process may be termed order o magnitude (OM) or rough order o magnitude
(ROM).
78
For use by APM individual and corporate members only
Cost estimating
11.4.1.2 Preliminary
The preliminary stage is the next stage in scope denition. Preliminary estimates
should use denitive methods or the next stage o scope denition; however, it
is acceptable to use approximate methods or those areas o scope remaining
undened.
11.4.1.3 Denitive
The denitive stage is the nal stage in scope development. Denitive estimates
are prepared using denitive (detailed) estimating methods.
11.4.2.1 Optioneering
Optioneering estimates are prepared to establish the cost dierences between
two or more alternative strategies in order to arrive at ranking o alternatives to
inorm an economic decision. Both approximate and denitive methods are
appropriate or these types o estimates, depending on the level o scope deni-
tion. These are described later in this section.
79
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
An estimate should contain both a robust base estimate and a realistic contin-
gency budget.
80
For use by APM individual and corporate members only
Cost estimating
an item/activity used in the prior project as the basis or the cost o a similar item/
activity in the new project. Adjustments are made to account or dierences in
relative size/complexity o perormance, design or operational characteristics.
This approach works well or derivative or evolutionary projects but is unsuitable
or radical changes or substantially dierent projects.
81
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
82
For use by APM individual and corporate members only
12.1 Denition o budgeting
Budgeting is the process o allocating appropriate budgets to dierent parts o
the work breakdown structure. Budgets are oten expressed in terms o money,
but may equally be described in terms o other resources such as labour, plant or
materials.
83
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
84
For use by APM individual and corporate members only
Budgeting
85
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
86
For use by APM individual and corporate members only
Budgeting
87
For use by APM individual and corporate members only
For use by APM individual and corporate members only
Part Three
Scheduling
‘The key is not to prioritise what’s on your schedule, but to schedule your
priorities.’
Stephen Covey
91
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Thus, scheduling:
• helps make decisions about strategies and methods considered as part o the
planning process;
• ocuses management attention on the most important issues and activities;
• considers work calendars;
• considers time contingency;
• starts at strategic level and is decomposed into medium and short-term
scheduling;
• denes the sequence o activities with which the project goals can be accom-
plished;
• quanties the resources required and cost to be expected as a result o project
execution;
• clearly denes the scope o work;
• optimises the use o resources.
92
For use by APM individual and corporate members only
Introduction to scheduling
93
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
94
For use by APM individual and corporate members only
Table 13.1 Features associated with density o schedules
Density Timescale Activity Typical Budget/ Logic Lags Calendars Cost Contingencies Comment
names activity resource (example) allocation
duration loading
Low – the +1 year Will tend Per each Major Logic May be Generic Major Since Adequate level
highest rom to be element budget links o included working budgetary durations will o detail or
level(s) o now elemental, groups various or week with groups be calculated easibility
schedule describing types will illustrative statutory such as using checks only; in
key parts be used purposes; and designer, empirical later schedules
o the to best negative typical contractor, data, a high appropriate
project describe lags should industry client costs degree o level o detail
the never be holidays contingency or strategic
sequence used even included is required. overview
at this level Quantitative picture only
schedule risk
analysis may
be applied to
determine
Medium 3months A urther Indicative Allocated Mainly Some lags Activity- Cost Risk should Sucient detail
– 1 year denition duration: to nish to may exist, based coding be reduced o allocation to
rom into key 4–8 activities start links though the calendars should be with greater particular
now parts or weeks. or (FS) will proportion estab- clarity. Clear contractors or
products Durations rst-pass be used will be lished at identication other resources
o the may be baseline much this stage o the risk to allow pricing
project derived reduced (foat) owner and resource
rom at this level allocation
typical
outputs
(Continued)
High – the Next 3 Clear, Indicative Baseline Mainly Rarely Resource- All Clear Adequate or
lowest months unambigu- duration: set and nish to acceptable; based resources identication detailed
level(s) o ous and 2–4 weeks not start links generally calendars must be o the risk description,
schedule precise Durations subject to (FS) will replaced in place i identied (foat) owner creation o
with will be change be used by activities relevant and all at this level. day-to-day
reerence derived with FS relevant Design or schedules, and
to specic rom links activity variation risks progress
location or outputs coded should not be reporting.
resource and required at Detailed design
discussion this level is complete and
methods
dened and
agreed
97
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
98
For use by APM individual and corporate members only
Introduction to scheduling
levels o detail comes the risk o errors. Complex logic can hide errors, which will
be harder to pick up in a very large schedule.
Also, very large schedules are less likely to be read and/or used. It is important
to remember the target audience. The schedule should be in adequate detail or
the correct monitoring o the project.
99
For use by APM individual and corporate members only
For use by APM individual and corporate members only
14.1 Schedule types: time-based
There are a number o dierent types o time-phased schedule, created at various
stages and by various parties with subtly diering purposes and aims. In order or
a project to have clarity, it is important or these to be limited to the key schedules
described below.
14.1.1.1 Purpose
• To provide an outline o the project parameters in terms o scope and time.
• To dene project gateway stages, including key ‘go/no-go’ points.
• To illustrate the approvals required or the project to proceed.
• To incorporate key dates over the lie o the project.
• To identiy a high-level critical path or the project.
• To show the key integration events and acceptance points.
101
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
14.1.2.1 Purpose
• To assist in the pricing o the tender.
• To identiy and communicate the methodologies and timescale or delivering
the project.
• To demonstrate good practice to the reviewing authority/customer/client.
• To show the level o resources required to complete the works.
• To dene key technologies being proposed and their levels o maturity.
• To dene inormation-required dates.
• To show inputs required rom third parties.
• To show all key interaces.
• To make adequate allowances or risk and schedule uncertainty.
• To dene the procurement strategy.
• To clearly show any works by others.
• To include all utilities and statutory undertakings.
102
For use by APM individual and corporate members only
Types o schedule
measured against it. In all contracts there should always be a ‘current’ contract
schedule. There may be changes throughout a project, but, once instructed,
these should be included in the contract schedule.
This is the schedule against which the cause and cost o any delays are
calculated. It is the schedule that is used as the basis or all monthly or period
progress reporting, so it should be at a suitable level o detail. Contract schedules
are likely to be medium-density schedules.
14.1.6.1 Purpose
The working schedule directs delivery in the optimum sequence, on time and to
cost. Thus, the purpose is to manage the activities that are to be undertaken on
an ongoing basis.
103
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Advantages:
• easy to do and understand;
• ocuses the project team on early delivery.
• Disadvantages:
• requires rebalancing o the time/cost/scope/ quality triangle (Figure 14.1);
• requires sotware;
• purely tactical, no strategic view;
• distracts rom ‘one version o the truth’ reporting;
• dilutes ocus, as there is more than one schedule to consider and under-
stand;
• may engender complacency i it is known that the target schedule is not the
denitive schedule.
104
For use by APM individual and corporate members only
Types o schedule
105
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
106
For use by APM individual and corporate members only
Types o schedule
107
For use by APM individual and corporate members only
Figure 14.3 A sample procurement schedule
The spreadsheet example shown in Figure 14.3 has the advantage that it can
be set up to automatically update some o the data. Also, spreadsheets are
generally more accessible to read and update than bar charts, which require
scheduling sotware.
An alternative way o displaying the procurement schedule is to adopt a more
traditional time-phased approach, as illustrated in Figure 14.4, which is best
displayed in scheduling sotware.
However, the choice o which method to adopt is a matter o personal
preerence.
109
For use by APM individual and corporate members only
Figure 14.4 Time-phased procurement schedule
113
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
15.3.1.2 Structure
The structure o an ID may well repeat some or all activity codes, but it
can provide a shorthand that the scheduler can use, or example, to trace logic.
Care should be taken not to over complicate the structure and the use o letters
to abbreviate the names o parts o the project (lie cycle stages, geographic
areas, etc.).
Structuring activity IDs can oten be tailored to the project; thereore, it is
recommended to use abbreviations that can be understood, or example lie
cycle stages such as DE, CN, TC or design, construct, and test and commission.
Other structures to consider when generating activity IDs are:
• geographic location;
• section o work;
• who does the work?
114
For use by APM individual and corporate members only
Schedule design
• Project manager: It is dicult to predict where the PM’s eort will be ocused
on a daily or weekly basis, as it is generally ocused on areas that need support,
which oten change regularly. Scheduling these activities into a high-density
schedule would be very time-consuming and would not add value to the
overall logic structure. It is thereore appropriate to assign a LOE activity or
the PM spanning the lie o the project, as they are helping to acilitate the
project’s success.
• Planner/Scheduler: Although there may be repetitive work due to the regular
reporting cycle which can be predicted and scheduled, it does not add value
to the schedule to itemise these activities in a low level o detail; thereore,
LOE is appropriate.
15.3.3.3 Hammocks
A hammock is a summary activity that will expand and contract depending on the
activities that it is linked to. Hammock tasks are very similar to level o eort
(LOE) tasks, diering only in the ollowing:
• A hammock task does not have a calendar assigned to it, whereas a LOE task can
have a specic calendar attached (or example, part-time scheduling support).
115
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
I the scheduling sotware does not have a step unction embedded, then it is
advised to capture the objective criteria in a notes eld held within the tool or
transparency and visibility.
15.3.6 Calendars
Calendars are used to dene the amount o working and non-working time
throughout the duration o the project. They are used to determine when the
work will be carried out, e.g. night-working or weekends only.
Generally, they show the normal working week, e.g. Monday–Friday,
8.00–5.00 with 1 hour or lunch. This would result in an 8-hour day and
40-hour working week. In the UK, the 8 standard bank holidays would
be included. Industry holidays are usually 1 week at Easter and 2 weeks at
Christmas.
Consider the level o time unit being used (i.e. an 8-hour day may be used,
whatever the real hours are) and decide what is appropriate or the project. In
other words, and in general terms only, work is oten planned in days regardless
o the sotware that may calculate duration in hours.
118
For use by APM individual and corporate members only
Schedule design
• A schedule can use multiple calendars, or both activities and resources.
• Take care that calendars are correctly assigned, dened and maintained.
• It is important to clearly dene which activities take place on which calendar.
• An activity cannot take place on multiple activity calendars; i there is a need
to show such working, then the activity needs to be duplicated so that
each individual activity occurs solely on one calendar. An example o this
could be a situation where a joint team are working on a piece o work
shared between two nations, say the UK and Spain. The Spanish take
most o August o on holiday, whereas the UK continues to work.
Separate calendars, and hence separate activities, would be needed to
show this.
119
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Leads and lags should not have calendars allocated to them. I a logic link
needs to be on a specic calendar, then this should be an activity (dummy
task).
120
For use by APM individual and corporate members only
There are a number o techniques o scheduling, and these are allied to methods
o presentation. Scheduling is undertaken using logic-linked networks and the
critical path method o analysis. This is based on either the arrow diagram method
or, as is more usual in modern sotware, the precedence diagram method. The
network methods are central to all others in modern planning; the other
techniques discussed here may be considered to be alternative means o present-
ation, albeit they were originally independent techniques.
122
For use by APM individual and corporate members only
Building the schedule: network analysis
123
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
124
For use by APM individual and corporate members only
Building the schedule: network analysis
125
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The rst activity is given an early start date (Day 1). With the duration, it is then
possible to calculate the early nish date (Day 10). Thus, early start + duration
= early nish.
The second activity can start ater the rst activity has completed (Day 11).
This calculation proceeds orward through the network, eventually calculating
the earliest possible nish date or the whole network o activities.
Note that i an activity is dependent on more than one activity, it is important
to remember to ensure that the calculations have been completed on all preceding
activities. The ull orward pass will, thereore, be calculated in Figure 16.5.
126
For use by APM individual and corporate members only
Building the schedule: network analysis
Starting rom the last activity in the network, the latest nish is set to the same
value to determine the early nish. Then rom the late nish the duration is
subtracted to calculate the late start date. This calculation then proceeds
backwards through the network. On completion o the backward pass, the
resulting data appears as in Figure 16.6.
127
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
the example the critical path is Task 1–Task 2–Task 3–Task 6. Any delay to any o
these activities will delay the completion o the project.
Note also that, in the example below, a delay o 2 days to Task 4 and/or Task 5
will also delay the project, and will also have the eect o changing the critical
path to Task 1–Task 4–Task 5–Task 6.
128
For use by APM individual and corporate members only
Building the schedule: network analysis
129
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
16.1.12 Float
Float is sometimes reerred to as ‘slack’, or example in some scheduling sotware,
but this guide will use the more widely accepted term ‘foat’. Figure 16.11 illus-
trates foat types.
130
For use by APM individual and corporate members only
Building the schedule: network analysis
131
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
to achieve the required date, you will need to recover the time in uture activities/
sequences.
132
For use by APM individual and corporate members only
Building the schedule: network analysis
133
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Care should be taken when using this type o relationship. It is not as simple as
the Finish to Start link. I activity 3 starts, but is stopped or slows down or any
reason, can activity 4 really proceed unhindered? Thus these links may oten be
used with:
134
For use by APM individual and corporate members only
Building the schedule: network analysis
It is dicult to give an example o where such a link could be valid. (An example
sometimes given is activity 7 in Figure 16.15 being ‘mix epoxy resin’ and activity
8 being ‘apply epoxy resin’, but it is hard to imagine planning at this level
o detail in most situations.) These types o links are likely to be used as a
convenience rather than a true description o logic. For this reason, they should
be avoided.
135
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
a dummy activity rather than a lag. This will have the added advantage that an
appropriate calendar can be applied to the dummy activity.
The use o lags and leads is thereore, in most cases, poor scheduling practice,
and they must not be used in high-density scheduling, because as previously
stated they are illogical. (Figure 16.16 illustrates that activity 12 cannot start until
2 days beore activity 11 completes, but this is an illogical statement – the uture
is uncertain, but or this to work you have to know 2 days in advance that Activity
11 is going to complete on a particular day.)
136
For use by APM individual and corporate members only
Building the schedule: network analysis
• as late as possible;
• mandatory start;
• mandatory nish/deadline;
• (must) start on;
• (must) nish on;
• start on or ater/start no earlier than;
• nish on or ater/nish no earlier than;
• start on or beore/start no later than;
• nish on or beore/nish no later than.
Note: The dierent scheduling sotware may use slightly dierent terminology
or these constraints; or example, tick-boxes; ‘holding pin’; ‘start on a new day’.
It is important to understand the ways scheduling tools use constraints. This is
particularly important where you need to import schedules rom dierent sources
into the master schedule.
Care should be taken in the use o multiple constraint dates, as they can give
misleading results when the project is scheduled, especially i used in combination.
For example, using ‘start on or beore’ and ‘start on or ater’ constraints on the
same activity or logical sequence would create a result you might not anticipate
or notice i you have not appreciated the combination.
It should be noted that i a constraint date is imposed on an activity then foat
calculations will use that constraint date to calculate the ‘late nish’ date or the
activity.
I there is not enough time to do the work and to meet the constraint date,
then a negative foat value will be calculated. Conversely, i there is more than
enough time to do the work and meet the constraint date, then a positive foat
value will be generated. It is worth noting that dierent toolsets (or scheduling
sotware) can handle this in dierent ways. Problems may arise when moving
data rom one sotware product to another. Dierent results are very likely except
in the case o very simple schedules.
137
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
138
For use by APM individual and corporate members only
Building the schedule: network analysis
139
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
140
For use by APM individual and corporate members only
Building the schedule: network analysis
141
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
142
For use by APM individual and corporate members only
Building the schedule: network analysis
143
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
144
For use by APM individual and corporate members only
Building the schedule: network analysis
145
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
146
For use by APM individual and corporate members only
Building the schedule: network analysis
147
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Note: the PERT calculation noted above is the most commonly used, although there are alternative
calculations, such as the three-point estimate, which is calculated as (P+M+O)/3.
148
For use by APM individual and corporate members only
Building the schedule: network analysis
16.2.3 Comparative
Projects o a similar type are used to estimate durations, making appropriate
adjustments or scope (i.e. dierences in quantities). Other specic dierences
such as logistical dierences, local climate, and local resource availability must be
assessed and adjustments made accordingly.
149
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
16.2.5 Resource-dependent
Resource-dependent activities, although constraining, are a good way o deriving
robust assumptions. Here the limitations are around labour, plant, supply o
materials, access to site, etc.
The planner or estimator uses known outputs or the available resource to
calculate the estimated duration or an activity (see Table 16.5).
150
For use by APM individual and corporate members only
Building the schedule: network analysis
WBS. Discreet work packages will be feshed out against the overall scope o the
project. It is important that all elements o work required to deliver the project
benets capability is included within the schedule. Other aspects to be included
are, assumptions on tasks, duration, sequence, logical dependencies, interaces
(both internal and external) and costs.
Getting a head start can greatly improve your chance o developing a good
schedule; some companies may categorise their projects by discipline or asset
type, which makes the process o using existing data much easier.
It is important to realise that assumptions are simply guesses around the
uture, and thereore can be incorrect. I a specic task is on the critical path, then
this may cause delay or increased cost to the project. Key assumptions around
activities that can have this eect should be assessed or impact and entered into
the risk register. The register should also record the quantied impact in time and
cost (along with the corresponding mitigation strategy) which can assist in getting
additional unds and/or resources.
151
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• labour;
• plant or equipment;
• materials;
• acilities, such as specialist test sites.
In some cases, e.g. high-level budgeting exercises, you may wish to use money
as a discrete resource which is not aligned to labour, plant and equipment, or
materials. Each o the resources may drive the project pace by constraining the
output that can be achieved – or example, a spending cap to a point in time will
determine how much work can be completed up to that point. Where resources
do constrain the project delivery rate, they are known as ‘critical resources’. It is
likely that the relative importance o each will vary depending on project type,
but also rom project to project.
An important consideration may be the relationship between resources and
project logistics. Resources generally require space within which to operate,
whereas materials need space to be stored.
• determine (low or medium density) or validate (at high density) the duration o
each activity;
• promote the consideration o the fow o resources (people, trades or sub-
contractors) within the schedule, which will lead to more realistic and
achievable outputs;
• lead to an understanding o peak resource requirements, including human
resource requirements, unding requirements and peak material supply
requirements;
• ascertain the availability o specialist equipment (which may be actored in by
use o resource calendars) – this may require advance booking;
152
For use by APM individual and corporate members only
Building the schedule: network analysis
153
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The diagram above (Figure 16.28) shows resource levels peaking at 42, but
the build-up to those peaks does not look realistic in most circumstances; an
exercise is required to smooth the build-up and fow o resources.
154
For use by APM individual and corporate members only
Building the schedule: network analysis
155
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
156
For use by APM individual and corporate members only
Building the schedule: network analysis
• that all schedules cover all the scope (as appropriate to them)
• that all data is consistent between schedules (dates, logic, etc.).
• identication;
• coding;
• integration and impact analysis;
• impact resolution.
16.5.1 Identication
The project PBS, WBS and RACI will help identiy interaces, as they give
a high-level view o work packages, as well as their interaces with external
157
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
16.5.2 Coding
Given the size and complexity o modern projects, robust codiying o interaces
is recommended. This could be done with an appropriate activity ID or an activity
code. Careul thought must be given to ensuring the coding and naming conven-
tions. It is best to use abbreviations that are readily understood by those reading
them (i.e. they relate to the project and work package), thus aiding identication
and communication. Given that in a project there will be many hundreds o inter-
aces, this can greatly increase the chances o slippage due to external infuences.
An example dependency code may be:
‘INTPROJ0011.1.1001A’, where:
• INT=Interace;
• PROJ001=Project ID;
• 1.1.1=Related WBS ID;
• 001=Interace No;
• A=’Deliver By’ interace.
In the case o interace IDs it is a good idea to use both A and B, which
denotes whether it is a ‘deliver by’ (A) or a ‘need by’ (B) interace. In the
example given, INTPROJ0011.1.1001A would have a corresponding partner,
INTPROJ0011.1.1001B.
It is important to note that, even though there are two separate interaces, they
are undamentally the same thing, and simply represent two separate points o
view about when a single event will occur or the purpose o managing variances.
Some interaces may also include other activity codes, which may denote
project lie cycle, location and department, but the activity ID will ensure it is
visible on a standard layout and is easily picked out rom the project schedule.
158
For use by APM individual and corporate members only
Building the schedule: network analysis
159
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
16.5.3.1.1 Advantages
• Easy to see the context around the dependency, as it is already within its native
WBS node
• Ease o visibility within the project schedule ocuses the team.
16.5.3.1.2 Limitations
• Impact o changes may be dicult to analyse i the schedule is very large. In
these cases, it may be better to consider the use o the external integration
method.
160
For use by APM individual and corporate members only
Building the schedule: network analysis
management o interaces. Not only does it provide a clear picture o all inter-
aces, but it also allows variance management and impact analysis to happen
outside the live scheduling environment. This aids schedule stability.
In this method there are a total o our separate milestones representing the
same event. Two are held within each o the project schedules in their corres-
ponding WBS nodes, and two are held within the interace schedule. When
movement occurs in interace ‘A’, the variance can be clearly seen and tracked.
Once all the interaces have been updated, you can then assess the impact by
adding logic to the dependency schedule (Figure 16.33).
It is important to ensure that all the dependences are linked to their corres-
ponding partner beore the critical path is calculated, as one dependency path
can lead through many others. Once the logic linking exercise is complete, you
can then schedule the plan (Figure 16.34).
The driving logic rom Project 1 will now fow through the dependency
schedule and into Project 2 in order to drive the schedule’s critical path. (Most
enterprise scheduling systems will have the ability to logically link across separate
projects, but system capability must be checked, as it is an essential requirement
or this method.)
161
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
16.5.3.2.1 Advantages
• Manages change in a stable and controlled way that will not disrupt the stability
o underlying projects.
• Makes schedule movement and variances easy to identiy.
• Clearly denes dependency management as an important part o the schedule.
16.5.3.2.2 Limitations
• Requires robust data quality control measures.
• Requires dedicated resources to execute and manage.
162
For use by APM individual and corporate members only
Building the schedule: network analysis
• Dependency ID: Unique ID that only reerences either the ‘deliver by’ or the
‘need by’ event.
• Dependency name: Standard naming conventions as described in this guide
should be adhered to.
• Agreed target date: The date that has been agreed by both projects/parties
and is subject to ormal change control.
• Current orecast: Schedule logic-driven orecast date representing the most
up-to-date position.
• Variance: Dierence between target and orecast. This is compared with
the dependency threshold and rated with a RAG ormat (red, amber and
green) accordingly, to ocus management attention on the most critical
issues.
• Threshold: Number o days + or – that a dependency can move without
causing an issue with the receiving party (this can, in some cases, only apply to
movement one way).
• Reason: Driving issue responsible or the move.
• Mitigation: Action resulting rom the dependency management meeting to
resolve issue.
163
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
I the movement is real and the project team is unable to mitigate the slippage,
then the receiving project must look to uture work to absorb delay by doing
things dierently or use available project foat. Once this has been agreed by
both projects, the new dependency date can be changed through the ormal
change control process.
• Resource buer: the additional lead time given to critical resources to orewarn
a particular resource that a critical activity is approaching.
• Feeder buer: the additional time allocated at the end o tasks within a
schedule.
• Project buer: the additional time allocated at the end o a project schedule.
164
For use by APM individual and corporate members only
Building the schedule: network analysis
this may help reduce overall project duration by allowing activities to start earlier.
This, in turn, allows the ollow-on activities to start earlier.
It is more commonly used on basic or repetitive types o project, but, with
appropriate care, may be used on all types. Full buy-in o all parties is, however,
essential, and is likely that contract issues will need to be considered. For example,
on NEC3 contracts (NEC – New Engineeering Contract) the use o time risk
allowance is specically mentioned in order to bring realism into the contractors’
schedule. The use o Buers as described is less likely to be useul on those
projects involving a signicant degree o sub-contracting.
165
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
166
For use by APM individual and corporate members only
The results o the scheduling may be presented in a number o ways:
167
For use by APM individual and corporate members only
Figure 17.1 A simple bar chart
170
For use by APM individual and corporate members only
Figure 17.3 Using milestones to give clarity to the schedule
172
For use by APM individual and corporate members only
Communicating the schedule
or example by increasing resources on these two tasks, can be examined and
put into practice as appropriate (Figure 17.5).
173
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• The diagram below (Figure 17.6) shows the basic elements o a time chainage
chart.
174
For use by APM individual and corporate members only
Communicating the schedule
• Time is dened in appropriate periods down the side o the illustrated chart.
The start o the project is usually shown at the top o the chart and the end at
the bottom.
• The distance is shown horizontally in the illustrated chart, and may include the
chainage (location dened in metres) or named geographic locations, as
appropriate.
• At the top o the chart a simple representation or map o the project may be
shown to aid visualisation.
• Sotware is available that allows an automatic update rom standard scheduling
sotware.
175
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The completion o the haul roads allows the construction o both the retaining
wall and the bridge:
The road can commence once the bridge is nearing completion; or the
purposes o this example, we assume this has to be built in one continuous
operation. The rst option considers the operation rom (say) north to south.
However, by reconsidering this operation and constructing it rom south to
north, an earlier start can be made and a month saved rom the overall duration
o the construction schedule.
176
For use by APM individual and corporate members only
Communicating the schedule
177
For use by APM individual and corporate members only
Figure 17.11 Example o a time chainage diagram or a new railway
17.4.1 Scope
A description o the work scope should be included, covering design, procure-
ment, development strategy, implementation phase and testing and commission-
ing, as appropriate.
179
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
17.4.6 Stakeholders
Any stakeholders’ interest in the schedule should be identied and described.
17.4.7 Resources
Resources used in execution o the schedule should be described in the schedule;
the narrative should note any resource constraints or special resource requirements,
in particular highlighting any scarce resources that pose a threat to the delivery
o the project i they are unavailable. Any special measures required need to be
identied. Resource histograms may be a useul communication tool to indicate the
resources to be deployed:
• labour;
• major items o plant or equipment;
• major items o material.
17.4.9 Assumptions
A description o the key assumptions that aect the management o time, in
order to explain and enhance understanding o the schedule.
17.4.10 Calendars
Calendars which underpin the schedule should be listed and described as part o
the narrative. A summary o those used in the schedule should be provided. It
should reer to the days/hours to be worked, and describe any exceptional
calendars used. For example, there may be separate calendars or:
180
For use by APM individual and corporate members only
Communicating the schedule
181
For use by APM individual and corporate members only
For use by APM individual and corporate members only
18.1 Denition o schedule review
Schedule review is the process that conrms that the schedule is t or purpose:
i.e. that it can be used to direct and accurately monitor the work. In general, there
are two stages:
• planning checks;
• scheduling checks.
183
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Planning checks deal with the practicality o the plans to direct the completion o
the project. Scheduling checks check the integrity o the time model, to ensure
that it fows correctly and can be used to orecast accurate dates.
The primary consideration must be the practical content o the schedule, but
some useul integrity checks are also discussed in this section.
In order to review a schedule, it is important to be able to read and interpret it.
184
For use by APM individual and corporate members only
Figure 18.1 Components o a schedule or review
18.3.2.2 Timescale
The timescale can be used to display calendar dates in various levels o detail,
and/or ordinal dates. The timescale can usually be expanded to aid visibility o
a particular timerame, or contracted to give an overview o a wider portion o
time.
The schedule should also display the data date. The data date is the
point up to which project progress is updated. It is also the point rom
which any network analysis would be calculated when ‘re-scheduling’ the
project.
186
For use by APM individual and corporate members only
Schedule review
18.3.3.2 Calendars
It is important to understand what calendars and work patterns have been used
when building the schedule. (This can be displayed in the data table.) The
calendars used will infuence overall duration o activities (and hence the project),
the ability to accelerate the project, and the understanding o the critical path.
18.3.3.5 Risk
When reviewing the schedule, it is important to understand the associated risks.
These should be ound in or added to the project risk register.
187
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
18.4.1 Administration
• Check that all headers and ooters are correct, with current date and revision
number.
• It is good practice or the header or ooter to also include elds or layout, lter,
project ID, project name, username, version number, etc. applied to the
printed version.
• Check that the schedule has been checked and approved or issue.
• Presentation: Is the schedule laid out logically and easy to read? (For example,
are contract and key dates shown clearly, perhaps in their own section at the
start o the schedule?)
188
For use by APM individual and corporate members only
Schedule review
• I the schedule includes progress, perhaps the most important check o all is
that key or contract dates have not moved, or, i they have, the reasons or
such movement are ully explained in the narrative.
• I required, has time risk allowance been identied against activities?
18.4.4 Scope
• Is the entire scope represented in the schedule, including latest change (up to
a suitable cut-o point)? (This should include reerences to all works by the
client, contractors and third parties.)
• Are all temporary works and other preliminaries covered? The ormer may be
on the critical path or require critical resources.
• Are intermediate milestones identied and meaningul?
• Check that all interace milestones are paired.
• Check that the key/interace milestones or the next 12 months have signed-o
milestone denition sheets and that all have SMART measures (specic,
measureable, achievable, relevant and time-bound).
• Check all activities and milestones or any constrained dates.
• Check or out-o-sequence or missing logic leading to activities on data
date.
189
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
I schedules with negative foat are presented without showing the negative
foat, they can give a alse impression that the schedule dates can be met.
Where positive foat exists in a network, it means that the work can be delayed
by the associated time and still be completed by the desired date. However, it is
worth checking that ‘excessive’ foat does not exist in the project schedule. This will
be because o missing successor logic. It is always worth checking the logic through
activity networks that seem to have proportionally more foat than seems reasonable.
Check or an excessive number o activities starting early in the programme.
Although the logic may allow this, it may not be a cost-eective approach or the
project.
190
For use by APM individual and corporate members only
Schedule review
191
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Schedules with great detail will demand more requent updates and more
management eort.
192
For use by APM individual and corporate members only
Schedule review
Calendars should be named clearly, should account or holiday periods, and
account or any other restraint on working; actory shut downs in manuacturing
or weather in construction, or example.
193
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
194
For use by APM individual and corporate members only
Schedule review
This check should be used with caution, as schedules should be pragmatic rather
than innitely precise, and some instances o this occurring will be acceptable. In
short, don’t panic i out-o-sequence activities are ound in the schedule, but be
careul.
195
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
196
For use by APM individual and corporate members only
Schedule review
target date. It is not, thereore, acceptable to have negative foat in the rst
schedule, but it may exist in subsequent schedules i progress has been unsatis-
actory. It is then a sign o a threat to the achievability o the schedule.
197
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
schedule can be the result o insucient progress or potentially poor use o hard
constraints.
The critical path should not include LOE or summary activities, leads or lags
unless justied. It should also not include activities scheduled to take place as late
as possible, even i they have zero foat by virtue o coming beore a critical activity.
198
For use by APM individual and corporate members only
19.1 Denition o BIM
BIM is a new approach to dealing with the design, procurement and installation
o an asset as well as its testing and commissioning, its handover, and its operation
and maintenance. It provides inormation to acilitate each o these lie cycle
stages and can be applied to any type o asset.
Enhancements to modelling sotware have given the ability to directly link the
project schedule to the model (3D), to visualise the construction process in real
time (4D), and also to estimate the cost prole (5D).
In essence, BIM consists o a computer aided design (CAD) model o the
asset. This may exist in 2D or 3D ormat. The model has the ability to contain
inormation to build, operate and maintain the asset. In more mature solutions,
this can extend to incorporating the project schedule and cost model. This could
mean a 3D model that can visually demonstrate the build sequence (or, indeed,
the progress o the works.) The BIM database will also contain metadata around
each individual component o the build, such as type, cost, load-bearing capacity,
supplier, etc.
The term is being used worldwide, although in the UK its adoption is mandated
on government-unded projects by the end o 2016, giving it special relevance.
BIM maturity has been dened as dierent levels, as illustrated schematically in
Figure 19.1.
Although the visualisation elements o BIM remain the most recognisable
aspect, it is the integration o scope using a common and consistent language in
order to understand the impact o change that is the key advantage o this
approach.
199
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
200
For use by APM individual and corporate members only
Building inormation modelling (BIM)
model, whereby each specialist adds the specic inormation on an iterative basis
as the design matures.
The involvement o dierent expert representatives o dierent organisations
(asset owner, investor, designers, builders, operators and maintainers) at the very
beginning o the project denition provides an opportunity o taking into account
all the requirements that will accompany the assets to be built throughout their
whole lie cycle.
All the unctions that use the data and inormation that will make the model
richer and richer as the design develops will work together in a much more
ecient manner (i.e. an integrated approach to cost and time is a natural result o
BIM).
The transition o all the records rom the construction team to the Operator
and Maintainer (O&M) will occur in an electronic manner, sometimes reerred to
as ‘digital handover’, without the need or an expensive and time-consuming
period o translation o asset data into a ormat suitable or O&M use.
201
For use by APM individual and corporate members only
For use by APM individual and corporate members only
20.1 Denition o agile
Agile is a ramework which describes a collection o tools, structure, culture and
discipline to enable a project or programme to embrace changes in requirements.
Agile methods integrate planning with execution, allowing an organisation to
‘search’ or an optimal ordering o work tasks and to adjust to changing require-
ments.
Agile is not a methodology, and does not prescribe a way o working. It seeks
to provide a ramework and a working mindset that helps a team respond
eectively to changing requirements.
203
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
20.3 Methods
There are many distinct agile processes, which are summarised in Figure 20.1.
Irrespective o which agile process a project chooses to adopt, or i they wish
to adopt more agile thinking, the ollowing principles apply:
• The project breaks a requirement into smaller pieces, which are then priorit-
ised by the team in terms o importance.
• The agile project promotes collaborative working, especially with the customer.
This involves the customer being embedded in the team, providing the team
with constant and regular eedback on deliverables and unctionality o the
end product.
• The agile project refects, learns and adjusts at regular intervals to ensure that
the customer is always satised and is provided with outcomes that result in
benets.
204
For use by APM individual and corporate members only
Sotware industry: the agile approach
(Figure 20.2). The requirements are written as ‘stories’ that are collated into a
prioritised list called the ‘backlog’. Each story in the backlog is awarded points
based on the level o denition o the requirements. Progress is monitored using
‘burn down’ charts o points; this enables the ‘velocity’ to be calculated, which
can be used to predict the out-turn duration. Points are earned either 0% or 100%,
depending on the acceptance by the client/sponsor at the end o the ‘sprint
review meeting’. The process is overseen by the ‘scrum master’, who makes sure
everyone adheres to the rules. Meetings are reerred to as ‘ceremonies’, the
most requent o which is the daily planning meeting, which identies what has
been done, what is to be done and barriers to success. Continued improvement
is embedded by holding a ‘sprint retrospective’ at the end o each sprint to access
perormance and learn rom experience.
20.3.1 Advantages
• Agile planning ocuses on delivering what is most benecial to the business
rst, identiying quick wins and earlier benets realisation.
• Agile continuously looks or process improvements as part o the ‘retrospect-
ive’ review. As the team become more ecient, they can plan to achieve more
in each sprint. Thus the velocity o delivery increases.
205
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Agile assumes that changes are normal events; thereore they are managed to
enable greater fexibility.
• Agile scheduling allows a greater level o fexibility in achieving the end result.
20.3.2 Limitations
• The organisation needs to be able to operate in an agile way and be willing
to have a ully empowered team, typically with a ull-time customer represent-
ative.
• A non-agile culture within an organisation will be a blocker on a project imple-
menting an agile ramework.
• Attendance at ‘daily scrum’ meetings is essential to keep abreast o the project
tasks.
• Agile is not appropriate or all types o projects. Where there are signicant
resource constraints, securing suitably qualied teams or the ull duration o
each time box may not be possible in the organisation.
• Agile approaches struggle on larger-scale projects due to the degree o collab-
orative working required by the approach. I team sizes become too big, then
development rates can slow.
206
For use by APM individual and corporate members only
Part Four
‘You may not control all the events that happen to you, but you can decide not to
be reduced by them.’
Maya Angelou
At the point o establishing a baseline, each activity in the schedule has a duplicate
set o dates ascribed to it. The duplicate dates are called the ‘Baseline’ dates
and are illustrated in yellow in the diagrams below. Once set, these dates are
not changed through the normal progress o the project, unless there is a
requirement to re-set the baseline. As the project progresses, the plan will be
updated and the current dates, illustrated in green in Figures 21.1–21.6, may
well vary as a result o project perormance, revised sequencing and detail devel-
opment.
The illustration shows the eect on a project schedule o a delayed start
and completion o the rst activity, which has a knock-on eect on subsequent
activities.
The same principle applies to management o resources and costs. A set o
values is recorded as the baseline, and as the work progresses and actual usage
209
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
o resource or actual costs are incurred, these are recorded or comparison with
the baseline data.
A baseline to measure against is the key requirement or any orm o project
control. Without a baseline, there is nothing to compare the working schedule
with, and thereore there is no way o measuring perormance, meaning that
projects will end up out o control.
210
For use by APM individual and corporate members only
Baseline
In order to achieve all o the above, the baseline must be robust, credible and
pragmatic, and must thereore be maintained as changes are made to the working
schedule.
The baseline will oten be reerred to as the perormance measurement
baseline, or PMB. Usually the PMB is the S-curve (or curves – early and late)
derived rom the baseline schedule. The elements o the total project that are
included in the PMB or purposes o measurement must be dened. For example,
risk and contingency may be excluded.
Following the principles below will ensure that the PMB is aligned with the
master schedule objectives and contract milestones. This PMB orms the basis
or measuring all uture progress and perormance.
211
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• The project delivery team creates controls and executes the baseline. An
appropriate level o authority, as identied in the project’s governance docu-
ment(s), approves the project baseline.
• The baselines should be established at (or beore) the commencement o each
phase.
• The baseline is only changed in accordance with a robust change control
process. Changes to the baseline must be controlled and recorded.
• In addition, the baseline is ‘maintained’ as discussed below.
• The baseline may be ‘re-planned’, as discussed below. A ‘re-plan’ should only
be considered with the relevant level o authority (e.g. client, project manager
or project sponsor, depending on circumstances).
• The baseline may be ‘re-baselined’, as discussed below. A re-baseline is only
considered with the agreement rom an appropriate level o authority (e.g.
client, project manager or project sponsor, depending on circumstances).
212
For use by APM individual and corporate members only
Baseline
• Change o planning packages into work packages (this may include the
addition o detail to the medium/long term).
• Changes in contractual conditions or work scope. Where change is identied,
it is managed through a change control process, ultimately leading to an
update o the baseline. This will take the orm o an appropriate addition,
omission or revision, and will include the eects o the change on uture
activities. Records o baseline change should be maintained to provide
traceability.
• Changes to descriptive inormation – e.g. activity or coding titles. Typically,
this may be the correction o errors. Note, however, that changes in numbering
o activity IDs should never be permitted.
213
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
214
For use by APM individual and corporate members only
Baseline
215
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
216
For use by APM individual and corporate members only
Baseline
eliminating the schedule variance, i.e. the remaining work is re-scheduled with
the current actual cost and earned value retained. The customer should be
advised prior to (and may need to approve) re-planning.
Re-planning should only be considered in two instances:
217
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
218
For use by APM individual and corporate members only
Baseline
Additional work*
Additional detail
Re-set budgets
Baseline maintenance √ √ √ ×x x× x×
Re-planning √ √ √ √ x× x×
Re-baselining √ √ √ √ √ √
219
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
220
For use by APM individual and corporate members only
22.1 Denition o perormance reporting
Perormance reporting is the measurement o progress and spending made to
date compared with the plan. It should inorm management decision making
about steps required to mitigate poor perormance or maximise better than
planned perormance. Thus, it must:
221
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
In general, the variance analysis techniques are simple to do and understand, but
they are backward-looking, oten with no way o enabling projections and
orecasts. Perormance analysis techniques are harder to set up and run, but do
have these orward-looking qualities. Most sophisticated projects will run both
orms o perormance analysis, as even these are complementary and measure
dierent things. Variance analysis techniques are used to complement and help
communicate where necessary or useul.
222
For use by APM individual and corporate members only
Perormance reporting
223
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
224
For use by APM individual and corporate members only
Perormance reporting
I a project is perectly on schedule, then the drop line remains vertical. Thus
the deviations clearly indicate which activities are ahead and which are behind.
Whilst this is a good way o looking at the detail, it is not adequate or complex
logic-linked schedules.
225
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• It is dicult to change the schedule, add data etc. Adding a new activity may
not be shown in a logical position i this is not done in scheduling sotware.
• Ultimately the schedule will not be a tool or proactively managing time, as it
will have become unrepresentative o a realistic approach to the work.
• Becomes even more unrealistic i re-sequencing takes place.
• Activity-based method that does not measure ‘work’.
• It measures time, but has no measure o cost versus value.
226
For use by APM individual and corporate members only
Perormance reporting
227
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
229
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
230
For use by APM individual and corporate members only
Perormance reporting
• May be used where environmental concerns limit usage (or example, lorry
movements in built-up areas).
231
For use by APM individual and corporate members only
Figure 22.5 Sample cost value report
233
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
234
For use by APM individual and corporate members only
Perormance reporting
235
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
236
For use by APM individual and corporate members only
Perormance reporting
237
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
22.5.2.4.4 Risk
Risk is the budget allowed or known unknowns. As noted above, there is no
practical benet in measuring risk budget, as there is not a 100% chance o it
being earned, and so it may distort perormance measurement. However, it is
sometimes required to be included or completeness. There are a number o
ways o spreading the budget or risk. One way is across the remaining project
time, but that requires adjustment at every progress update. Alternatively, it can
be held in a ‘risk pot’ at the end o the project. In any event, risk money cannot be
earned; it can only be transerred into other work packages, in line with the risk
and change process.
238
For use by APM individual and corporate members only
Perormance reporting
In either case a protocol must be agreed, but the second option is likely to be the
simpler.
239
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
240
For use by APM individual and corporate members only
Perormance reporting
Note: It will be necessary to allow or accruals in the cost collection system.
Once the actual costs have been added to the schedule, the cumulative
actual costs can be plotted as shown in Figure 22.10. In the diagram, costs are in
241
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
excess o what should be expected which would be parity with the earned
value line.
242
For use by APM individual and corporate members only
Perormance reporting
EVA measures schedule perormance in terms o value as seen, but also in terms
o time: time variance can be calculated or read o the graph as in Figure 22.13.
This is the dierence on the time axis between the quantity o work achieved to
date, or earned value, and the corresponding quantity on the planned value curve.
Measuring and expressing delay in this way may help to give an alternative
view o progress. It will also not suer rom the issue, already noted, that schedule
perormance index (SPI) and SV tend towards parity as the project nears
243
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
completion. (Although it has been stated that this is a faw in earned value
analysis, in reality we should expect project managers to be aware o approaching
completion dates!).
244
For use by APM individual and corporate members only
Perormance reporting
Cost perormance index (CPI) is the ratio o earned value over actual cost. A
gure greater than 1.0 indicates that the actual cost o the work achieved cost
less than planned.
CPI greater than 1 indicates a cost under-run
CPI equals 1 indicates on budget
CPI less than 1 indicates a cost over-run
SPI and CPI can useully be plotted against each other to create a ‘Bulls eye’
chart, as shown in Figure 22.14.
245
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The shading indicates the BRAG rating that may also be allocated to the KPIs,
where
B=Blue: Perormance over that expected (and needs investigating)
R=Red: Perormance seriously below expected (needs immediate corrective
action)
A=Amber: Perormance below expectation (needs planning or corrective action)
G=Green: perormance within expectations (no action required)
Estimate at completion (EAC): The sum o the actual costs to date plus the
estimate to complete (ETC) (‘What is the project likely to cost?’).
EAC = Actual cost + ETC
246
For use by APM individual and corporate members only
Perormance reporting
It has been shown (Webb, Alan (2003, 26) Using Earned Value, Gower) that
mathematically the ormula or EAC can, in act, be simplied to:
Again, It has been shown (Webb, Alan (2003, 26) Using Earned Value, Gower)
that mathematically the ormula or ETTC can, in act, be simplied to:
247
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
248
For use by APM individual and corporate members only
Perormance reporting
• Certainty o project position: what work has been achieved against plan; what
it has cost to reach that level o achievement.
• Whether the work achieved represents good value or money (i.e. has been
achieved eciently).
• Gives early warning o whether the project is likely to nish on time and/or on
budget.
• Improved decision making: guides attention to problem areas that need
management decisions.
• Provides the basis or inormed cost and/or time recovery actions.
• Ensures that a robust plan is established at the outset o the project.
• Management o scope creep through the change control system.
• Ensures cash-fow is measured properly and optimised.
• Provides corporate governance (when done across the organisation).
• Business benets include turnover, prot and cash being achieved on time or
as soon as practicable.
249
For use by APM individual and corporate members only
For use by APM individual and corporate members only
23.1 Denition o cost control
Cost control is the process o collecting actual costs and collating them in a
ormat to allow comparison with project budgets, identiying variances to
inorm decision making and allow action to be taken. In addition, it includes cost
orecasting.
Cost orecasting is the process o using perormance measurement, progress
inormation and risk management to estimate how the costs will be spent going
orward to the end o the project or nancial year and inorm the anticipated nal
cost (AFC).
251
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
252
For use by APM individual and corporate members only
Cost control
These changes will highlight cost variance. This is the dierence between the
assumed costs o the project or activities in the perormance measurement
baseline at the point o reporting, and the actual costs that the project is committed
to at that same point.
A recognised best practice around cost control is through the use o earned
value management where the cost perormance index (CPI) is the key indicator
o project nancial perormance. This process is described in detail insection
22.5.2. It is ideal or identiying where a project is not progressing eciently.
253
For use by APM individual and corporate members only
For use by APM individual and corporate members only
24.1 Denition o short-term planning
The duration o short-term planning may vary depending upon the duration o
the project, but is likely to consist o a 4-week look ahead and a look back at the
previous week’s progress. It would normally be issued weekly. (These durations
would obviously be inappropriate or a weekend shut-down schedule!)
255
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• the work planned over the next 3 or 4 weeks (with a strong emphasis on the
next week);
• the make ready needs or these activities (these are the start criteria or each
detailed task).
256
For use by APM individual and corporate members only
Short-term planning
257
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
258
For use by APM individual and corporate members only
25.1 Denition o change management
Change management is the ormal process through which changes to the project
are raised, assessed, approved, and introduced or rejected.
‘Changes’ are events and issues that alter the schedule, scope or objectives. In
broad terms, there are two levels o change:
• inside the project, such as risks impacting, adoption o wrong strategy, etc.,
where they will be unded rom management reserve drawdown;
• outside the project, such as a new customer requirement, where they will
require additional unding;
• a change in legislation.
259
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• change in scope;
• changes in budgets;
• changes in timing o the project;
• changes in risks that are managed as part o the project;
• changes in expenditure.
Thus, it ensures that costs are known and that the supply chain receive air
recompense or any additional work that they perorm, whilst protecting the
client rom paying or works that are not perormed.
260
For use by APM individual and corporate members only
Change management
261
For use by APM individual and corporate members only
Figure 25.1 Process overview – project change control
262
For use by APM individual and corporate members only
Change management
263
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• unique ID number;
• status o the change;
• change description;
• detailed scope o the change;
• category o change;
• created by (the change originator);
• date raised;
• impact assessment – scope/budget/schedule/risk/saety, etc.;
• authority;
• unding/budget;
• decision: (approval/deerral/rejection) and date.
264
For use by APM individual and corporate members only
Change management
more inormation is required. Once that has been supplied, then the request
re-joins the process at detailed evaluation stage.
Once a change request has got through the initial evaluation, it proceeds into
the detailed evaluation.
This evaluation is usually carried out in a regular change review meeting. The
meetings would be attended by all the relevant parties on the project, but,
importantly, they require the project sponsor or authoriser or the change
request.
There are three possible outcomes or a change request:
• rejected;
• deerred;
• approved.
This section will address rejected and deerred (approved change being dealt
with in the next section).
265
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The extra data provided then goes back into the process or detailed evaluation.
I agreement is not achieved, the schedule eects may need to be re-visited
prior to any urther action.
Again, the change log would be updated and the details o the inormation
required passed back to the requester.
266
For use by APM individual and corporate members only
Change management
267
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Once change approvals and nancial authorisations are in place, the ollowing
actions should be taken:
268
For use by APM individual and corporate members only
Change management
assess the schedule to see whether the change accurately refects the agreed
change. Checks will need to be made regarding:
269
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
270
For use by APM individual and corporate members only
Change management
NEC: New engineering contract. Now widely used in the construction industry.
EWN/EON: Early warning notices are used to contractually advise the client or
customer that there could be a potential impact on cost or time (as used within
the NEC contract).
SI: Site instruction. Used on construction projects where a small on-site change
needs to be implemented quickly.
PMI: Project manager’s instruction. The ormal notication given by the
project manager usually ollowing a more detailed review o the impact o
the change.
CO: Change order. These are used to authorise a change to the project, including
a change o scope or agreement to accept a design solution which is outside
the agreed cost and schedule parameters.
BT: Budget transers. Budget transers are made to ormalise the movement o
scope (budget and schedule) rom one part o the project to another, or,
indeed, to move scope into or out o the project.
The Projects shall maintain their own change logs as required according to Figure
25.3, and shall make these available or inspection or challenge rom the schedule
change manager at all times.
271
For use by APM individual and corporate members only
For use by APM individual and corporate members only
26.1 Denition o risk management
Risk management is the management o threats to the project (negative
impacts) and opportunities (positive impacts). It involves the identication and
management o these issues.
As part o the planning o a project, risk should be considered at all stages.
Risk management techniques will be used to help dene cost or budget
allowances, allowances or schedule risk and, indeed, any other types o risk that
a project aces. Thus, risk management is integrated with all other management
processes and is part o the planning, monitoring and control o a project.
It is worth noting that there is a clear relationship between change and risk:
change inevitably introduces more risk or greater opportunity. In addition, aside
rom identied risk and opportunity, the sheer act o changing scope will add
risk into the schedule, and the greater the amount o change, the more risk is
introduced. There is, thereore, a strong relationship between the management
o risk and change.
273
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
26.4.1 Planning
26.4.1.1 Planning or risk
Beore the commencement o a ormal risk process, a risk management plan
should be created, reviewed and accepted by all relevant parties. Regular risk
workshops and review sessions will be planned and held throughout the lie o
the project.
274
For use by APM individual and corporate members only
Figure 26.1 Risk management lie cycle
As part o the preparation or initial risk workshops, project deliverables will be
clearly identied. The documents that might be consulted may include:
• contract documents;
• tender documents;
• project schedule and associated schedules;
• project execution plan and associated documents;
• risk checklists (a list o topics and regularly encountered threats and opportun-
ities or consideration or the workshop);
• the assumptions register.
• risk workshops;
• interviews with relevant people to benet rom their knowledge and experience;
• risk review meetings;
• time issues that are known about or arise rom progress reporting;
• investigations and surveys;
• lessons learned register/inormation;
276
For use by APM individual and corporate members only
Risk management
A detailed description o each key risk is recorded within the risk log, together
with the cause, eect, and owners (Figure 26.2).
Where risks have been identied with owners or actions alling outside the
remit o those present, the relevant stakeholders will be notied.
277
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
It should also be borne in mind that risks may have a time envelope within
which they may occur, and another way o dening priority will be those risks
likely to occur in the near-term uture, whether these be threats or opportunities.
The assessments thus made may be categorised and entered in the risk log
(Figure 26.5).
It is good practice to capture the justication behind the scoring (the basis o
estimate) – it is oten challenged, particularly where the risk mitigation actions
need a cost–benet analysis.
278
For use by APM individual and corporate members only
Figure 26.5 Typical risk log (continued rom Fig 26.2), showing current impact and response planning
280
For use by APM individual and corporate members only
Risk management
• Detailed review o the most critical risks and opportunities (at least, but not
limited to, those risks deemed to be ‘red’ risks in accordance with the severity
rating score).
• Have the delegated response plans been implemented, progressed or
completed?
• Have existing item scores increased or decreased due to changes in likelihood
or impact?
• Are additional mitigation measures required?
• Can existing risks and opportunities be closed?
• Check and agree whether any draw down o management reserve is required.
• Review the need or any ocused workshops on any o the matters raised in
the review.
281
For use by APM individual and corporate members only
Figure 26.8 Tracking risk perormance over time
how this is dealt with; the ollowing are suggested ways o drawing down risk
budget.
• Where risk exposure is greater than allowance, retain the allowance in the risk
register, re-allocating to new or emerging risks i appropriate.
• Where risk allowance is greater than exposure, then a portion o risk allowance
may be released to ‘prot’.
283
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
284
For use by APM individual and corporate members only
Risk management
285
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• A robust and ully logically linked schedule where only genuine constraints
remain.
• I the project is in progress, the schedule must be updated to refect current
status.
• Identiy duration uncertainty against all activities (three-point estimate duration
or activities).
• Risks are identied, documented and their impacts assessed and allocated to
schedule activity.
• A sotware application with which to run the Monte Carlo analysis, which
produces appropriate reports.
• Terminal foat or other time contingencies should be removed rom the
schedule prior to running the QSRA.
286
For use by APM individual and corporate members only
Risk management
287
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• Values in the middle near the mean are more likely to occur than in the
triangular distribution.
• Use when there is moderate condence in three-point estimates.
288
For use by APM individual and corporate members only
Risk management
• Useul or estimates that do not appear to show any central tendency.
• Equally likely chance o occurring anywhere within a particular range.
• No ‘most likely’ value.
289
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
290
For use by APM individual and corporate members only
Risk management
• Values near the mean are more likely to occur than in the triangular or normal
distributions.
• Extremes are not as emphasised.
• Use when there is high condence in three-point estimates.
291
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The activities that have the most infuence on this outcome can be displayed in a
tornado chart, as illustrated in Figure 26.15.
It is worth analysing the tornado chart prior to proceeding with the exercise to
ensure that the results are meaningul and credible activities are identied as
having the greatest infuence on the result. The example in Figure 26.15 shows
the impact in days, but sometimes this is shown in percentage terms.
292
For use by APM individual and corporate members only
Risk management
293
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
294
For use by APM individual and corporate members only
Risk management
295
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
26.6.8 Reporting
A suggested report ormat would include:
296
For use by APM individual and corporate members only
Risk management
297
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
For the Monte Carlo simulation, a random value is selected or each risk,
based on the range o these cost estimates. The result o this is recorded, and
typically the model is run 5,000 times, each time using dierent randomly selected
values. I the risk has a 50% likelihood, then the model would run hal the iterations
as a zero cost out-turn, as it assumes that the risk is not occurring. The remaining
hal o the model would pick random values dependent upon the three-point
estimates.
Just as in the case o the QSRA, the results are plotted and condence levels
or various outcomes are calculated. These are oten reerred to as P values, e.g.
P50 or P80.
This means that, or example, i the P50 is calculated at £5 million, there is only
a 50% chance that the project will cost a total o £5 million or less. The more risk
averse the organisation is, the higher the condence value they may use.
Thereore, they may use a P80, which means that there is an 80% chance that the
project risk will cost a total o (say) £7 million or less.
298
For use by APM individual and corporate members only
Risk management
The ormat o the sensitivity data presented here is termed the ‘contribution to
variance’, and makes it easier to examine what percentage o the variance in the
target orecast is due to a particular risk.
299
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
300
For use by APM individual and corporate members only
Risk management
Example:
Risks with an ‘O’ key on the graph indicate that those particular risks appear on
the sensitivity chart mainly due to their high probability, e.g. probability o 75%.
Risks with an ‘I’ key on the graph indicate that those particular risks appear on
the sensitivity chart mainly due to their high value, e.g. £10 million, should they
occur, even i they may have a low probability o occurrence, e.g. 5% likelihood.
P0 100,637.71
P10 411,602.97
P20 502,275.44
P30 584,376.77
P40 673,217.44
P50 777,270.30
P60 915,880.23
P70 1,091,687.26
P80 1,232,564.58
P90 1,413,591.55
P100 2,702,304.39
26.7.3.3 Conclusions
Like any orecasting model, the analysis is only as good as the estimates made. It
is important to remember that it is a simulation, and basing the estimates on
current assumptions will provide greater condence in the results.
301
For use by APM individual and corporate members only
For use by APM individual and corporate members only
27.1 Denition o orensic analysis
Forensic schedule analysis reers to the study and investigation o events using
critical path methods or other recognised schedule calculation methods. In
particular, it is the study o how actual events caused delay as measured against a
dened time model.
303
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
(Continued)
304
For use by APM individual and corporate members only
Forensic analysis and delay and disruption analysis
The impacted • Good • Can be used • May only show limited • Can be used
as-planned as-planned where the cause and eect. prospectively
method schedule as-planned • Does not take account or
works by (ideally agreed schedule has o progress, resources retrospectively
inserting and or accepted at not been and changes in but . . .
linking delay or near the updated or sequence. • More suited
events into outset o the where there is • It is a theoretical or identiying
the project). limited as-built method and thereore and
as-planned • The works data available. open to criticism. quantiying
schedule. carried out • Can be used • Susceptible to potential
Any change need to closely prospectively manipulation delays rather
in the refect the logic or (unintended or than actual
completion contained retrospectively. otherwise) i only one delays.
date as a within the party’s delays are
consequence as-planned considered.
o the schedule.
(Continued)
305
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The collapsed • Good quality, • Does not • Limited prospective • Where there
as-built reliable and require an use. is no
method begins consistent as-planned • The networking o the as-planned
with the as-built data schedule. as-built schedule schedule or it
production o produced in • Based on requires a deep is o poor
a networked sucient actual as-built understanding o the quality.
as-built detail. data. schedule and its logic • Most
schedule. • Requires a • Can and normally requires appropriate
Then activities networked or demonstrate access to the project or
or parts o logic-linked cause and team. retrospective
activities as-built eect. • Expertise required to delay
representing schedule. • Can account or collapse out delays analysis.
delay events concurrency. accurately, otherwise
are removed. the collapsed schedule
may not represent the
true situation but or
the delays.
(Continued)
306
For use by APM individual and corporate members only
Forensic analysis and delay and disruption analysis
The time impact • Good as-planned • Can be carried • More suited to • Prospectively
analysis method schedule (ideally out quantiying or
provides or the agreed or accepted prospectively or potential rather retrospectively.
updating o a at or near the outset retrospectively. than actual delays. • Benecial to
networked o the project). • Deals with delays • Requires extensive carry out as a
as-planned • The as-planned at the time they records to be kept. project
schedule with schedule and its occur or in • Can be time progresses.
progress to just updates are windows intensive and slow, • Where the
beore the networked. providing clarity. and thereore contract
occurrence o a expensive to requires.
delay event. implement.
(Continued)
307
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
The delay event • Reliable and • Can account or • Can be complicated • For
is then inserted consistent progress progress, and dicult to negotiating
and linked into data in sucient resources, communicate, with purposes or in
the schedule. detail or each time changes in many charts. tribunals.
Any change in period being sequence and • Reliability reduced
the completion considered, which changes in the i schedule and
date as a should also be at critical path. record quality is
consequence o appropriate • Can identiy and poor.
the insertion o intervals. quantiy • Can produce
the delay event • All delaying events acceleration or theoretical results i
is attributed to should be identied mitigation not veried by
that delay and quantied. measures. as-built data, but i
event. • The works carried • Can disentangle carried out
Where out need to closely delays otherwise regularly takes
progress is not refect the logic considered to be account o as-built
recorded at the contained within concurrent. data.
specic date the latest • Can demonstrate • Susceptible to
just beore the as-planned cause and eect. manipulation
impact o a schedule being • More reliable in (unintended or
delay event, the considered. dispute otherwise) i only
latest schedule resolution than one party’s delays
updated or simpler methods are considered.
progress prior o delay analysis. • Accuracy can be
to occurrence • Recommended reduced i the
o the delay method o delay period between
event may still analysis by the progress update
be appropriate Society o and delay
to use. Each Construction increases.
progress Law’s Protocol. • Sensitive to the
update may • Does not require order in which
allow the a complete delays are
schedule to be as-built schedule, impacted upon the
analysed at but as-built data schedule.
discrete assists in
intervals o time veriying results.
or in ‘windows’.
308
For use by APM individual and corporate members only
Forensic analysis and delay and disruption analysis
309
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
27.3.6.4 Concurrency
Concurrency occurs when there is a delay caused by two or more events that are
o approximately equal potency. Although concurrency is oten claimed to exist,
it is actually quite rare, and delay analysis can disentangle the causative delays
and show that one cause o delay was acting beore the other or that one cause
o delay was ar more potent than the other. Where there is true concurrency,
with the customer responsible or one o the delays and the contractor respons-
ible or the other, there has been judicial guidance rom the English courts that
the contractor receives an extension o time but does not necessarily receive
associated prolongation costs unless they can be separated out.
310
For use by APM individual and corporate members only
Part Five
Record keeping
and learning
‘A learning experience is one o those things that say, “You know that thing you
just did? Don’t do that.”’
Douglas Adams
313
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
314
For use by APM individual and corporate members only
Record keeping
• Delivery records.
• Quality control records.
315
For use by APM individual and corporate members only
For use by APM individual and corporate members only
29.1 Denition o document management
Document management is the collection, storage, dissemination and archiving o
documentation in a structured manner. It is a undamental aspect o project
delivery, particularly in supporting assurance processes and the handover o a
project at completion.
Document management also encompasses the process o ‘document control’,
which involves maintaining records o document versions and an audit trail o
documents exchanged with suppliers or other stakeholders. A document control
process should control and be able to trace the fow o all inormation on the project.
The term ‘document’ applies to any ormatted inormation that passes the test
‘Is it in the interest o the schedule or project that this inormation be sae-
guarded?’.
An awareness o current legislation and corporate requirements is important,
as some project documentation, e.g. contracts, may be required to be stored or
a signicant amount o time ater the project has nished. Equally, some may be
required to be stored in a particular manner – or example in a hard copy only, or
in a sot copy only.
• all relevant parties have all the inormation they require to complete their
responsibilities;
317
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• all the inormation used in the project is up to date (i.e. latest revised inorma-
tion is in use);
• out-o-date inormation is no longer accessible or implementation purposes,
but . . .
• all data is available or record purposes.
• ensure that all document changes are recorded and documents marked appro-
priately so it is clear that a revision has taken place;
• ensure all project team members use the correct version o each document;
• maintain a tracker, e.g. an appropriate database tool, that shows the status and
revision numbers o each drawing and assurance document, i required by the
project team.
318
For use by APM individual and corporate members only
Project handover and closeout are separate processes but are oten very closely
related in time. Closeout cannot occur until the handover process is complete.
Both processes are vital to the success o the project and oten use nite
resources. The handover process is very likely a part o the critical path o the
project, whilst the closeout process is essential to the nalisation o commercial
accounts, resolution o deects/snagging and transer o the risk process. It will
also include the nal part o the lessons learned process, which is discussed in
Chapter 31. Figure 30.1 outlines the context o handover and closeout.
30.1 Handover
30.1.1 Denition o handover
The handover o a project occurs when the nal project deliverables are handed
over rom the organisation delivering the project to the user or operator o the
asset.
There are many parts to this process, including scope, training and document-
ation, all o which need to be careully planned and resourced.
319
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
that there are sucient people available, with the right skills to deliver the
handover process.
The handover process ensures that:
320
For use by APM individual and corporate members only
Handover and closeout
The nature o the project deliverables will determine how much time and
resource is allocated to handing them over. The deliverable examples below will
require dierent resources:
• all the project deliverables have been clearly dened and agreed in terms o
documentation required to accompany the physical (or virtual) product o the
project, training requirements and the like;
• the handover process has been clearly dened and agreed;
• the process or dealing with non-conormances or outstanding issues has
been agreed;
• the handover process conorms to organisation guidelines;
• all relevant customer checklists have been used;
• all the signicant stakeholders are appropriately represented at the handover
event.
• payment delays;
• increased client retentions;
321
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
• commercial settlement with the supply chain and all other parties;
• rectication o all deects noted at or since the completion o the handover
process;
• payment o all retained monies resulting rom the above.
It is also best practice to ensure that a project review takes place beore the
project team is disbanded, to ensure that appropriate lessons are learned rom
the things that went well or otherwise in the project. This is covered in the next
chapter o this guide.
322
For use by APM individual and corporate members only
Handover and closeout
323
For use by APM individual and corporate members only
For use by APM individual and corporate members only
31.1 Denition o lessons learned
The lessons learned process captures two types o inormation rom projects:
objective data (acts about perormance and outputs achieved) and subjective
data (such as good and poor practices to be repeated or avoided in the uture).
325
For use by APM individual and corporate members only
Planning, Scheduling, Monitoring and Control
Similarly, or design work, capturing the total man-hours to produce certain
types o deliverables will give useul productivity data or uture use.
• project sponsor;
• project manager;
326
For use by APM individual and corporate members only
Lessons learned
31.4.2 Considerations
• Lessons should be agreed by all project team members.
• Complete individual lessons learned as soon ater the task/activity/stage has
completed, and try to conduct within a month.
• Focus on uture improvements and re-usability.
• Categorisation o lessons learned is useul to aid uture analysis o both lessons
and actions.
• The document(s) where the lessons learned will reside and the relevant
process (i applicable) where the lessons learned are applied.
• To update the lessons learned action plan to ensure that the lessons have been
captured and the relevant documentation updated in line with the organisa-
tion’s change control process.
An action plan should be created rom the lessons learned exercise and will have
the ollowing headings to help complete the integration o the lessons back into
the organisation:
• unique ID;
• lesson learned element description;
• lesson learned owner;
• lesson learned action;
• signicance;
• relevant control document;
• change control completed.
The unctional leads are responsible or veriying that appropriate personnel are
aware o the learning points in the repository and that any recommendations
have been implemented and any actions are closed out.
327
For use by APM individual and corporate members only
For use by APM individual and corporate members only
The nal word
The plan, the real world and how the project reacts!
For use by APM individual and corporate members only
For use by APM individual and corporate members only
Glossary
Accrual A liability that has yet to be invoiced. The timing o payment and
amount o the invoice may be uncertain.
Activity-based cost The estimated time taken to complete the work activity,
multiplied by the composite hourly rate or the personnel, together with additions
or materials and equipment.
Activity weeks method A simple method o monitoring progress by
counting the number o activities in progress each week.
Actual cost Also known as actual cost o work perormed (ACWP). It is the
cost o the work that has been perormed. It may include costs rom accounting
systems with appropriate accruals.
Arrow diagram method (ADM) A method o creating a network with
activities on the ‘arrows’ rather than the ‘nodes’.
Assurance process The process by which one party – usually the customer
– makes sure that another party – oten a contractor – carries out a particular
action, e.g. compliance with standards.
Bar chart See Gantt chart.
Baseline The reerence level against which a project is monitored and
controlled.
Benet realisation review A review o the project outcomes – the analysis
o eedback rom key stakeholders and the reasons or success or ailure o the
realisation o anticipated benets. Actions and recommendations should result
rom the review.
Breakdown structure A hierarchical structure by which project elements
are broken down, or decomposed. Examples include cost breakdown structure
(CBS), organisational breakdown structure (OBS), product breakdown structure
(PBS) and work breakdown structure (WBS).
Budget at completion (BAC) The total budget or the work.
331
For use by APM individual and corporate members only
Glossary
332
For use by APM individual and corporate members only
Glossary
Delphi technique A technique based upon the principle that estimates rom
an experienced and structured panel can provide a useul judgement-based
output.
Design and build A method to deliver a project in which the design and
construction services are contracted by a single entity.
Early nish The earliest possible date by which an activity can nish within
the logical and imposed constraints o the network.
Early start The earliest possible date when an activity can start within the
logical and imposed constraints o the network.
Earned value (EV) The value o completed work expressed in terms o the
budget assigned to that work. A measure o progress, which may be expressed
in money or labour hours.
333
For use by APM individual and corporate members only
Glossary
334
For use by APM individual and corporate members only
Glossary
335
For use by APM individual and corporate members only
Glossary
336
For use by APM individual and corporate members only
Glossary
337
For use by APM individual and corporate members only
Glossary
338
For use by APM individual and corporate members only
Glossary
339
For use by APM individual and corporate members only
Glossary
340
For use by APM individual and corporate members only
Glossary
341
For use by APM individual and corporate members only
Glossary
WBS dictionary Covers the various WBS sections and denes all the deliv-
erables relating to the scope or statement o work.
Windows analysis This process is used to compare the planned schedule
with the as-built schedule during a particular period or ‘window’ o time.
Work breakdown structure (WBS) Denes the total work to be
undertaken and provides a structure or all control systems. It allows a project or
programme to be divided by level into discrete groups or programming, cost
planning and control purposes. The WBS is a tool or dening the hierarchical
breakdown o work required to deliver the products. Major categories are broken
down into smaller components. These are sub-divided until the lowest required
level o detail is established. The lowest units o the WBS are generally work
packages.
Work calendar Used to dene the amount o working and non-working time
throughout the duration o the project. They are also used to determine when
the work will be carried out, e.g. night working or weekends only.
Work package A discrete element o project scope at the lowest level o
each branch o the work breakdown structure. Collectively, the work packages
speciy all the work and products included in the project.
342
For use by APM individual and corporate members only
Acronyms
343
For use by APM individual and corporate members only
Acronyms
344
For use by APM individual and corporate members only
Index
345
For use by APM individual and corporate members only
Index
346
For use by APM individual and corporate members only
Index
denitive estimating methods 79, 80, 82 earned value management 221, 249,
delays 74, 103, 107, 225, 243, 303–6 253
deleted activities 192 earned value techniques (EVTs) 247
deliverables: and the 100% rule 61; and the ‘easy to measure’ statistics 17
baseline 211; and budgeting 84; and the ‘economic best t’ 50–1
business case 17; and closeout/handover emergency procedures 261
319, 321; and cost estimating 82; design end-user benets 17
deliverables tracker 109, 111; and the estimating: cost estimating 77–82; estimate
planning process 38, 40; as ‘product’ 57; at completion (EAC) 83, 246–7, 252;
product breakdown structure (PBS) 57; estimate to complete (ETC) 246, 252;
and the RACI matrix 68; and requirements estimated nal cost (EFC) 252, 253;
management 25, 28; and the estimated time to complete (ETCC) 247;
responsibility assignment matrix (RAM) estimating norms 40; estimation o duration
67; rolling wave planning 45–6; and 147–51; air price estimating methods 79;
scheduling 157; and scope management 21 impact o change 264; quantity o resources
Delphi technique 81 153
density o schedules 94–8 ‘events’ ocused (top-down) planning
dependencies: bar charts/Gantt charts 170; 43–4
and breakdown structures 55; coding expert opinion 150
120; and critical path networks 125, 126; external integration 160–2
dependency management 73–4; and the
planning process 38, 40; and requirements acilitated workshops 22, 44, 158
management 26, 27; and scheduling air price estimating methods 79
157–64 eeder buers 164
design and build phase 26 lters (on schedule views) 114, 184, 186,
design deliverable schedules 42 187
design deliverables tracker 109, 111 ‘nish on’ constraint 139, 197
detail density, schedule 94–9 ‘nish on or ater’ constraint 140
development/strategic schedule 101–2 ‘nish on or beore’ constraint 141
dictionaries 30, 61–2 nish to nish relationships 116, 134, 193
‘digital handover’ 201 nish to start relationships 123, 132–3, 193
discrete distributions 291 foat: and budgeting 86; and constraints
document management 317–18 137–40; and critical path networks 122,
drop line method 222, 224–6 124, 127–8, 130–1; and delay analysis 310;
dummy tasks 116, 120, 123, 136, 194 and drop line methods 225; ree foat
duration: duration uncertainty 285–6, 287, 131, 155; measurement o foat usage 222,
292, 294; estimation o duration 147–51 234–5; negative foat 131, 137, 142,
189–90, 196–7; and planning checks
early delivery 104 189–90; and quantitative schedule risk
early nish dates 126, 127 analysis 286; and scheduling 41, 50;
early/late curves 50–1, 85–6, 211 scheduling checks 196–8; shared foat 132
early start dates 126, 212 see also total foat
earned value analysis (EVA) 83, 222, 231, ‘orecast schedule’ 103
235–49 orensic schedule analysis 303–9
347
For use by APM individual and corporate members only
Index
348
For use by APM individual and corporate members only
Index
349
For use by APM individual and corporate members only
Index
product breakdown structure (PBS) 22–3, project sponsor: and the business case 11;
26–8, 56–8, 60, 157 and change management 260, 265, 266,
production curves 231, 233 268; and lessons learned 326; and
productivity data 313, 325 ‘re-planning’ 212; and requirements
‘programme’ (why book avoids use o term) 42 management 25, 29; and risk 15; and
programme manager 22, 31 scope management 22; stakeholder
progress assessments 223 management 31
progress weightings 116 project vision 48
project benets capability 151 prolongation 310 see also delays
project brie 11, 261–2, 268 PV (planned value) 49, 236, 239–40
project closeout see closeout/handover
project coding 120 QRA percentiles 298, 301–2
project controls system 40, 41, 211 qualitative lessons learned 326
project execution plan (PEP): and the quantitative cost risk analysis (QCRA)
business case 11; and change management 297–301
260, 268; and the planning process 38–9; quantitative schedule risk analysis (QSRA)
and requirements management 27, 29; 51, 93, 284–96
and risk management 276 quantity tracking 222, 223, 231–3
project amiliarisation 33–4
project lie cycle: and the baseline 211; and RACI matrix 67–9, 157
the business case 11, 13–14, 16, 19; and re-baselining 216–20
closeout/handover 320, 323; and cost record keeping 222, 313–16
estimating 77–9; and interaces 158; and recovery schedules 107
lessons learned 326; and project reviews 19; redundant activities 192
and requirements management 25; and redundant logic 194, 195
risk management 276, 280, 298; and relationship management 31–2
stakeholder management 32; and time ‘releases’ (agile planning) 47–8
contingency 51; and top-down planning repetitive schedules 99, 165, 172, 229
43–4 re-planning 216–18, 219
project management plan (PMP) 22 see also re-programming 218–20
project execution plan (PEP) requests or inormation (RFI) 257, 265
project manager 31–2, 115 see also requirements management 25–30
management issues requirements/needs-driven planning 43
project procurement proessional 18 resource breakdown structure (RBS) 23–4,
project reporting system 70 see also record 56, 70–1
keeping resource histograms 16, 154, 180, 186,
project review 19 198
project schedule: and interaces 159; and ‘resource-based estimating’ 82, 150
planning 42; and the planning process 39; resource-levelled schedules 50–1, 173, 212
project buers 164; and record keeping 314; resources: and the baseline 209–10, 211;
and requirements management 29; and budgeting 83; and the business case 14,
resource-levelled schedules 50–1; and risk 16; and calendars 118–19; and change
management 276, 285; and schedule review management 264; and closeout/handover
184; work breakdown structure (WBS) 60 320; cost estimating 77–82; ‘critical
350
For use by APM individual and corporate members only
Index
resources’ 152; denition 152; organisation scheduling: and budgeting 84–5; building the
breakdown structure (OBS) 65; and schedule 121–64; communicating the
parallel working 134; and planning 37; and schedule 167–82; ‘density’ o scheduling
the planning process 39, 40; and 94–8; orensic schedule analysis 303–9;
requirements management 28; resource high-density schedules 44–6, 94–9, 255;
buers 164; resource coding 120; resource horizontal integration 156–7; master/
monitoring 222, 230–1; resource smoothing working schedule and separate trackers 42;
154–5; resources allocation 153–6; network templates (ragnets) 99, 215; and
resources scheduling checks 198; the planning process 39, 40; planning vs
resourcing the schedule 151–5; and the scheduling 41–2, 91, 94; resourcing the
responsibility assignment matrix (RAM) schedule 151–5; and risk management 285;
67; and scheduling 41, 92; work schedule design 113–20; schedule narrative
breakdown structure (WBS) 60 43, 179–81, 268; schedule review 183–98;
responsibility assignment matrix (RAM) schedule revisions 267; scheduling checks
23–4, 56, 60, 64, 65–7 190–8; scheduling density 94–9; scheduling
risk: and the baseline 211; and the business process 92–3; and short-term planning 255;
case 15, 18; and change management 273; time-based schedules 101–7
and earned value analysis 238; health, scheduling sotware: and activities 191;
saety and environment (HSE) 75–6; activity coding 113, 116, 118; and bar
planning or risk 274–5; and the planning charts/Gantt charts 170; baseline
process 40; review o schedule risk 198; risk maintenance 213; and bottom-up planning
and opportunities register 38; risk 44; and budgeting 85; and constraint
assessment 277–8; risk draw down 281–4; dates 137; display variations 184;
risk management 273–301; risk displaying networks 147; and drop line
management plan 274; risk mitigations 40, methods 226; line o balance graphs 174;
238, 276, 278, 280, 283, 286; risk pot 281; and planning 41, 44; time chainage charts
risk register 150, 187, 268, 277, 280, 296; 174, 175; when not to use 42–3, 103, 107,
risk review 280–1; rolling wave planning 109
45–6; and schedule review 187; and the scope: and the baseline 109; and change
statement o work 30; time contingency management 266; planning checks (o
51, 164 schedule) 189; ‘scope creep’ 21; scope
risk log 277, 279, 280 development estimates 78–9; scope
rolling wave planning 45–6, 214, 226, 238 management 21–4; scope transers 267
rough order o magnitude (ROM) estimates Scrum 204
79 S-curves 51, 85–6, 211, 239–42, 298–9
sensitivity analysis 299–300
saety 75–6 shared foat 132
scenario planning (‘What is’) 107 short-term planning 255–7
schedule perormance index (SPI) 239, 243, short-term schedules 105
244 shut-downs 118, 119, 181, 224, 292
schedule risk analysis 170 single point distributions 297
schedule variance (SV) 216, 217, 218, 219, ‘single version o the truth’ reporting 104,
242–3 200
schedule visibility tasks (SVT) 116 ‘slack’ see foat
351
For use by APM individual and corporate members only
Index
352
For use by APM individual and corporate members only
Index
V model (design and development) 28 work package scope sheet see WBS
validation and verication requirements dictionary
matrix (VVRM) 29 work packages: accountability 66; and
variance analysis 222, 224–34, 242 assumptions 151; and the baseline 213;
version control 318 breaking down into 18, 30, 53; and
vertical integration 93, 157 budgeting 84; and earned value analysis
237–8; and interaces 157; product
WBS dictionary 30, 61–2 breakdown structure (PBS) 57; and
weeks, as time units 118 re-baselining 220; and requirements
‘what i’ 107, 268 management 30; and the responsibility
windows analysis 304, 309 assignment matrix (RAM) 65, 67; rolling
work breakdown structure (WBS): as wave planning 45–6; work breakdown
planning tool 53, 56, 57, 59–63; and structure (WBS) 59–60, 63
budgeting 83, 84; and interaces 157, 159, working schedule/orecast schedule 103
161; and requirements management 26, works inormation (WI) 29–30
28, 30; and the responsibility assignment
matrix (RAM) 65, 66–7; and scheduling 41; XP (eXtreme Programming) 204
scheduling checks 193; and the scope 23–4
work calendars 92 ‘zero ree foat’ constraint 138
353
For use by APM individual and corporate members only
For use by APM individual and corporate members only