UPEO (Zambia) Limited V ZCON Construction Limited (2017) ZMHC 38 (6 March 2017)
UPEO (Zambia) Limited V ZCON Construction Limited (2017) ZMHC 38 (6 March 2017)
UPEO (Zambia) Limited V ZCON Construction Limited (2017) ZMHC 38 (6 March 2017)
BETWEEN: ç J .5M8I
AND
/ 30
0
ZCON CONSTRUCTION U ITED DEFENDANT
For the Plaintiff, Mr. D M. Chakoleka, Messrs Mulenga Murzdashi Kasonde Legal Practitioners
JUDGMENT
ii I P a g e
Legislation and Other Materials referred to:
J2 I Page
prescribed the method of resolving disputes by way of an
adjudicator, and if that failed by way of arbitration.
The argument tendered to buttress the application was that the law
mandates the Court to refer a matter to arbitration and to stay
proceedings upon the request of a party, save where the contract is
incapable of being performed or is inoperative.
Reliance was also placed on the case of Heyman & another v Darmins
Limited (1942) AC 356 2, in which Lord MacMillan stated, at page 347,
the following:
"I venture to think that not enough attention has been directed to
the true nature and function of an arbitration clause in a contract.
It is quite distinct from the other clauses. The other clauses set out
the obligations which the parties undertake towards each other
but the arbitration clause does not impose on one of the parties an
obligation in favour of the other. It embodies the agreement of both
parties that, if any dispute arises with regard to the obligations
which the other party has undertaken to the other such dispute
shall be settled by a tribunal with their own constitution the
arbitration clause survives for determining the mode of their
settlement. The purposes of the contract have failed, but the
arbitration clause is not one of the purposes of the contract."
J3 I Page
for the Plaintiff had undertaken to file in their arguments on or
before Friday 10th March, 2017.
In that case, the Appellant appealed against the decision of the High
Court, staying proceedings before it and referring the matter to
arbitration, under section 10 of the Arbitration Act No. 19 of 2000.
The brief background leading up to the appeal was that on 1st April,
2003, the Appellant and Respondent entered into a Marketing
Licence Agreement. On 1st June, 2004, the Agreement was
terminated without notice by the Respondent.
The Appellant took issue with the termination of the Agreement and
commenced proceedings in the High Court. The learned High Court
Judge noted that the Agreement between the parties contained an
arbitration clause which provided that disputes arising during the
continuance of the contract would be resolved by arbitration.
Consequently, acting on the authority of the case of Leopard Ridge
Safaris Limited v Zambia Wildlife Authority, the High Court Judge
stayed the proceedings and referred the matter to arbitration,
following an application made by the Respondent.
On appeal, the Supreme considered both cases that the Defendant
herein is relying on and guided that "in determining whether a matter
is amenable to arbitration or not, it is imperative that the wording used
in the arbitration clause itself are closely studied."
The Court studied the Arbitration clause before it and noted that
the clause was couched in a manner which limited the disputes to
be referred to arbitration to disputes arising between them during
the continuance or subsistence of the Agreement. The Court then
observed that the dispute between the parties related to the manner
in which the Agreement was terminated and as such occurred after
the termination of the Agreement and not during its continuance.
Consequently, the Court set aside the order of referral by the High
Court, on the ratiocination that at the time the dispute between the
parties arose the arbitration clause had become inoperative and
incapable of being performed.
J5 j) g e
25.2 . . .Either party may refer a decision of the Adjudicator to an
Arbitrator within 28 days of the Adjudicator's written
decision. If neither party refers the dispute to arbitration
within the above 28 days, the Adjudicator's decision will be
final and binding..."
In interpreting the clause, I adopted the literal rule method that was
used by the Supreme Court in the Audrey Nyambe case. The literal
rule or plain meaning rule of interpretation requires that ordinary
words be given their ordinary meaning. In using that method, I aim
to discern the intention of the parties using the linguistic nuances
of the clause.
J6 I Papa
encompassing, a liberal or broad approach is taken. The American
case of Michele Amoruso e Figli v. Fisheries Development Corp, 499 F.
Supp. 1074, 1080 (S.D.N.Y. 1980)5 is illustrative of this proposition.
The court in that case took the position that arbitration provisions
containing phrases "arising out of or relating to this agreement"
must be treated as broad.
The ratio was echoed by the Court of Appeals for the Second Circuit
in Collins & Aikman Products Co. v. Building Systems Inc, 58 F.3d 16
(2d Cir. 1995)6 where the question whether the phrase "arising out of
or relating to" covered tortious and collateral claims. There the
Court opined that broad arbitration clauses raised the presumption
that all the asserted claims are arbitrable.
J7 I ge
decision shall be referred to the adjudicator within 14 days of the
notification of the Principal Agent's decision."
J8 I Pdge
with ease. It has always been undesirable for Counsel to swear
affidavits on behalf of a client in contentious matters as was
articulated by Doyle CJ in the case of Chikuta v Chipata Rural
District Counsel, (1974) Z.R, 2418.
In view of the above, I find that the legal proceeding before court fall
outside the scope of the arbitration clause between the parties.
Consequently, the existing arbitration clause is rendered inoperable
as regards the matter before Court. Thus, I decline to refer the
matter to arbitration and the application fails in totality.
J9 I Page
Costs are awarded to the Plaintiff, to be taxed in default of
agreement.
Justice B.G.Lungu
HIGH COURT JUDGE
J10 1