Method Statement For Road and Paving Works - Work Procedure 2024-02-12 01 - 35 - 27
Method Statement For Road and Paving Works - Work Procedure 2024-02-12 01 - 35 - 27
Method Statement For Road and Paving Works - Work Procedure 2024-02-12 01 - 35 - 27
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 1 of 19
:
Scope:
This method statement describes the activities and process of
Road and paving work for School Project works include
preparation, installation and protection as per the project
requirement.
Activities:
Road and paving work will comprise the following activities
Excavation.
Subgrade.
Subbase.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 2 of 19
:
Aggregate road base.
Projection.
Purpose:
Communication:
The contents of this method statement shall be explained and
demonstrated to all involved personnel based on specific task
allocation. Site Engineer / Supervisor, subcontractors’ signatures
shall be taken on the approved method statement as a matter of
record. Daily (at the start of each shift) the Works Supervisor and
HSEO will complete a Pre-works briefing with ALL labor based on
the activities to be complete in the shift (pre-works briefing will be
signed by ALL labor to demonstrate that they have understood the
activities and associated controls. They will then complete a site
walk to ensure and verify that all the controls are in place. Both the
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 3 of 19
:
RAMS and Pre-works briefing will be located on site with the Works
Supervisor for reference and review.
Construction Methodology:
1. Sampling and Storage:
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 4 of 19
:
• The all test shall be performed as per project specification and
applicable code.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 5 of 19
:
• All material removed from an excavation shall be used in the
formation of the embankment, shoulders and at such other places
in storage yard.
3. Subgrade – Roads:
• All slopes, lines and grades shall be true, correct and accurate,
and according to latest approved shop Drawings.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 6 of 19
:
profile grade to plus or minus two (2) centimeters and, for 'top of
improved subgrade' level, plus or minus one (1) centimeter.
• Dune sand if used shall not contain more than 2% organic matter
and may contain up to 20% of stone fragments or cobbles
exceeding 20mm but not more than 63mm in size.
4. Subbase Construction:
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 7 of 19
:
• Segregation shall be avoided, and the sub-base shall be free from
pockets of coarse or fine materials.
• Along curbs, headers, walls, and all places not accessible to the
roller, compact the material with approved vibratory rollers or
compactors.
• The finished surfaces of the road sub-base shall not vary at any
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 8 of 19
:
point more than 10 mm above or below the grade.
• All aggregate road base material shall be free from dirt, shale or
other deleterious matter and shall be of such quality that it will bind
readily to form a stable aggregate road base.
• The road base aggregate course shall not be placed when the
underlying surface is muddy, or when it is raining or dusting.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 9 of 19
:
• The material shall be handled in a manner which avoids
segregation. Segregated materials shall be remixed until uniform.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 10 of 19
:
locations.
• The variations of the surface from the testing edge of the straight
edge between any two (2) contacts with the surface shall at no
point exceed ten (10mm) when placed on or parallel to the center
line or ten (10mm) when placed perpendicular to the center line of
the roadway.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 11 of 19
:
8. Preparation:
9. Prime coat:
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 12 of 19
:
vibratory rollers minimum 3 passes (in the vibratory mode) and
followed by pneumatic tire rollers until the material has been fully
compacted to achieve the required degree of compaction as per
project specification.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 13 of 19
:
• Subsequent compaction will be carried out using tandem
vibratory rollers minimum 3 passes (in the vibratory mode) and
followed by pneumatic tire rollers until the material has been fully
compacted to achieve the required degree of compaction as per
project specification.
14. Testing:
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 14 of 19
:
temperature range 139 to 163OC as per project specification.
Material delivered to site outside range will not be incorporated
within the works.
• When all the activities are completed, the area will be cleaned
thoroughly. Once the cleaning is done and approved, a "Request
for Inspection" will be raised for acceptance.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 15 of 19
:
housekeeping.
All crane lift operations shall be provided with a crane lift plan
prepared by a competent person before commencing of lift and
shall be communicated to all parties involved in the lift operation.
Generator for electricity shall be provided with drip tray to control
any spillage. Upon arrival SAB safety officer shall conduct
inspection for each equipment and document all the inspections
for records. Each equipment shall be arranged with complete file
for all certifications. After approval the equipment shall be allowed
to site for work. Following remain outlined to focus:
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 16 of 19
:
the time of execution.
• Fuel shall be provided by mobile fuel tanker on daily basis for the
equipment on site.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 17 of 19
:
11. Air Compressor - Clean the surface
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 18 of 19
:
Area should be free of any ignition sources
Conclusion:
Full article on Method Statement for Road and Paving
Works | Method Statement for Asphalt Road
Construction | Work Methodology for Road
Construction | Method Statement for Asphalt Road
Construction | Work Method Statement for Road
Construction | Method Statement for Construction of
Road | Road Construction Method Statement. Thank you for
the full reading of this article in "QA QC Civil Engineering"
platform in English. If you find this post helpful, then help
others by sharing it on social media.
https://www.qaqccivilengineering.com/2022/02/Method-Statement-for-Road-and-Paving-Works.html?m=1 2/11/24, 9 35 PM
Page 19 of 19
: