NTPC 240MW Pending Points-17.11.2023
NTPC 240MW Pending Points-17.11.2023
NTPC 240MW Pending Points-17.11.2023
Arunkumar 4 4 0
Kingston 1 0 1
Chenthil 1 1 0
Ganesh 7 7 0
Marimuthu 4 1 3
Rama Krishnan 1 0 0 1
Ramachandran 18 16 0 2
Subbiah 6 3 0 3
Grand Total 42 32 4 6
Orange colour font indicates Update
Date : 17-11-2023
S. No. Issue Responsibility Target Date Status Remarks
Adjustment/amendment of
3 recovery for payment pertaining Marimuthu Open Action has to be taken from NTPC
to land PO
4 Supply of RFID reader along with all accessories as per contract agreement Ramachandran Closed
5 Submission of VGF Documents as per observation fron SECI Chenthil Closed Issued detailed report thru mail dated 22.09.2023 Annexure -III 23.09.2023
9 Removal of debris & excess unwanted soil Ramachandran Closed Annexure XI 28.09.2023
Slope protection in the blocks where it is required and plantation of grass in Closed
10 Arunkumar
the slope for protecting soil erosion
Ground clearance from Module bottom level to FGL asper drawing and Closed Annexure X 01.10.2023
11 Ramachandran
excess earth to be removed still pending
Submission of documents pertaining to approval from local
Issued NTPC approval details thru Annexure -1V
12 authority/administration for road constructed from main road to project Arunkumar Closed Annecure -IV 23.09.2023
dated 23.09.2023
boundary
Submitted O&M manuals on 21.09.2023 and thru
14 Submission of OEM manuals Subbiah Closed Annexure -V 23.09.2023
Annexure -V dated 23.09.2023
Submission of documents pertaining to approval from local
18 authority/administration pertaining to the block to CMCS cable laying area Arunkumar Closed
and providing boundary,cable root marker etc.
Pending approvals from Engg etc pertaining to rectification works in SCB Closed Annexure -XVII
19 Subbiah
cablings
20 Submission of punch point clearance certificate from PGCIL Arunkumar Closed
Submission of special tools and tackles and other instruments as per contract Submitted tools & tackles report with NTPC and
29 (G-1, Page -11,8j). One set of required Special tools per RMU shall be in the Ramachandran Closed acknowledged and the same sent thru Annexure - Annexure -VI 23.09.2023
scope of supply to NGEL O&M. V1 dated 23.09.2023
Sound issue completion mail sent to NTPC on
Root cause analysis to be submitted for abnormal sound issue in 220KV Solar Closed 22.09.2023 and thru Annexure - V11 dated Annexure -VII 23.09.2023
30 Ramachandran
plant end Switchyard line CT BAY No- 205 Y & B Phase. 22.09.2023
Complete Root cause analyses of frequent failure of hardware /software & Closed Annexure XX
32 Ramachandran
Stabilization of Module Cleaning 5/31/2023
Complete root cause analysis of failure & modification/replacement of Closed Annexure XIV
33 Ramachandran
contractors for inverters
5/31/2023
Scada work completed and sent mail to NTPC on
Completion of Web CLIENT SCADA work Closed 21.08.2023 and thru Annexure - V111 dated Annexure -VIII 23.09.2023
34 Ramachandran
23.09.2023
MS Office CD and license numbers, Printer driver need to be handed over to Closed Annexure XIX
35 Ramachandran
NGEL O&M.
36 Zig-Zag painting on back side of the electrical panel in switch gear room. Ramachandran Closed Annexure XIII 9/2/2023
LA and earthing checking data not available, A separate register to be opened Closed
37 Ramachandran
with checklist, and it should be monitored on regular basis(Monthly)
HIRA (Hazard Identification and Risk Assessment) & JSA (Job safety Closed
39 Ganesh
analysis) to be work specific.
Incidents register to be maintained and all Near Miss, Reportable, Non- Closed Annexure XXI
40 Ganesh
Reportable, Fire are to be recorded Judiciously
PTW is to be review and cancelled by and checked by column to be added in
41 the PTW Ganesh Closed Annexure XXI
format(M/S Hild Energy).
Rubber Mat not Provided. Area- Switch Gear Panel Room back as informed Closed Annexure XII 8/19/2023
42 Ramachandran
and agreed during RE CC Safety audit