THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.

P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No

1.0 Excavation & Earth Work

1.1 Item allow for claring site. Sqr 20.00 350.00 7,000.00

Excavation to form trenches for


coloum, wall and staircase foundation
1.2 depth not exceeding 3'-0" Cube 20.00 500.00 10,000.00

Hard earth filling with selected


material under floors and well
compacted in 300mm (1'-0") thikness
1.3 layers as directed by the Engineer. Cube 8.00 2,000.00 16,000.00

Total Amount of Excavation & Earth


Work 33,000.00
THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No

2.0 Concrete

Plain concrete of characteristic strength


15N/mm2 (1:3:6) with maximum 1 1/2"
aggregate.

50mm thick screed concrete under strip


2.1 (a) foundation. Sqr 5.00 3,250.00 16,250.00

(b) 2" thick concrete in floor. Sqr 9.00 3,250.00 29,250.00


Reinforced concrete of characteristic
strength 25N/mm2 with maximum
20mm aggregate.
2.2 In strip foundation Cube 0.81 24,800.00 20,088.00
In columns up to DPC from top of the
2.3 strip foundation. Cube 0.30 24,800.00 7,440.00

2.4 In staircase foundation up to DPC Cube 0.08 24,800.00 1,984.00


In plinth beams upto DPC from top of
2.5 the foundation. Cube 1.50 24,800.00 37,200.00
In columns upto slab level top of the
2.6 DPC. Cube 1.00 24,800.00 24,800.00

2.7 In beams at slab level. Cube 1.50 24,800.00 37,200.00

2.8 In staircase Cube 0.50 24,800.00 12,400.00

2.9 In column in upper floor. Cube 0.27 24,800.00 6,696.00

2.10 In Beams in upper floor. Cube 0.22 24,800.00 5,456.00

2.11 Lintol in ground floor. Cube 0.28 24,800.00 6,944.00

2.10 Lintol in upper floor. Cube 0.25 24,800.00 6,200.00

2.11 In 4 1/2" thick slab 1st floor Cube 3.00 24,800.00 74,400.00
2.12 In 4 1/2" thick water tank slab Cube 0.17 24,800.00 4,216.00

Total Amount of Concrete work 290,524.00


THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No

3.0 Form Work

All form work shall be in plywood


sheet / Timber planks ( to provide a
good finish on concrete surface) not
less than 12mm thick (if plywood) laid
a ploythene layer with suitable laps to
prevent leaking with suitable up stand
at edges.

3.1 To sides of plinth beams. Sqr 3.00 1,400.00 4,200.00

3.2 To sides of column in ground floor. Sqr 7.00 1,650.00 11,550.00

3.3 To sides of column in upper floor. Sqr 1.56 1,700.00 2,652.00

3.4 To sides and soffit of beams. Sqr 6.00 1,700.00 10,200.00

3.5 To sides of lintols Sqr 1.00 1,400.00 1,400.00

3.6 To sides and soffit of 1st floor slab. Sqr 8.00 1,500.00 12,000.00

3.7 To sides and soffit of water tank slab. Sqr 0.50 1,500.00 750.00

formwork for staircese up to 1st floor


level from ground level including
3.8 landing etc. Sqr 1.20 1,750.00 2,100.00

Total Amount of Form Work 44,852.00


THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No

4.0 Reinfrcement

Rate shall include for cutting, bending,


fabricating, placing in position,holding
and supports hangers and 16/20
binding wire, lies, spacer blocks and
chairs etc.
In base of stip foundation and cloumns
4.1 ground floor.
a) 12 mm tor steel. Nos. 100.00 75.00 7,500.00
b) 6 mm mild steel. kg 85.00 160.00 13,600.00
In staircase foundation up to DPC level
4.2 and slab level
a) 12 mm tor steel. Nos 20.00 750.00 15,000.00
b) 10 mm tor steel. Nos 10.00 580.00 5,800.00
b) 6 mm mild steel. kg 3.00 160.00 480.00

In plinth beam of foundation up to


4.3 DPC level.
a) 10 mm tor steel. Nos 40.00 580.00 23,200.00
b) 6 mm mild steel. kg 70.00 160.00 11,200.00

4.4 In beam of slab level


a) 12 mm tor steel. Nos 40.00 750.00 30,000.00
b) 6 mm mild steel. kg 70.00 160.00 11,200.00

4.5 In beam of upper floor


a) 12 mm tor steel. Nos 8.00 750.00 6,000.00
b) 6 mm mild steel. kg 12.00 160.00 1,920.00
4.6 In 1st floor slab
a) 12 mm tor steel. Nos 95.00 750.00 71,250.00
b) 10 mm tor steel. Nos 115.00 580.00 66,700.00

4.7 In water tank slab


a) 12 mm tor steel. Nos 12.00 160.00 1,920.00

Total Amount of Reinfrcement 265,770.00


THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No
5.0 Masonry work

9"x6" random rubble masonry in 1:5


cement and sand mortar up to DPC
5.1 level from top of the stip foundation. Cube 6.00 12,000.00 72,000.00
20mm thick DPC in cement and sand
1:2 finished with two coads of hat tar
5.2 and blinded with sand. Sqr 2.00 4,650.00 9,300.00

225mm thick brick work in ground


floor walls with 1:5 cement and sand
5.3 mortar. Cube 6.00 18,000.00 108,000.00

225mm thick brick work in upper floor


5.4 wall with 1:5 cement and sand mortar. Cube 10.00 18,250.00 182,500.00

Total Amount of Masonry work 371,800.00


THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No
6.0 Carpenter and Joinery

Supply and lay corrugated asbestos


sheet on class I timber formwork, rate
shall include for 5"x3" purline, 6"x2"
ride plate, 4"x3" wall plate, 4"x2" rafters
and necessary nails etc, All work
should be done as per detailed
6.1 drawing and Engineering instruction. Sqr 10.00 16,800.00 168,000.00

9"x1" thick class I timber valance and


barge board fix to rafter with necessory
6.2 screws. Lft 140.00 175.00 24,500.00

Calicut tile ridge and hip with 1:1:4


6.3 cement lime sand mortar. Lft 70.00 60.00 4,200.00

Supplying and fixing 25mm thick


peneled doors sach in special class
timber with 4"x3" frame in special c;ass
timber complete with oxidized brass or
6.4 equivalent approved quality fruniture. Sqr 1.32 48,000.00 63,360.00

Supplying and fixing 25mm thick


peneled and 3mm thick glazed
window in special class timber with
4"x3" frame in special class timber
comlete with oxidized brass or
equivalent approved quality furniture,
casement fasteners, casement stays
6.5 window ring etc. Sqr 1.42 56,000.00 79,520.00

Total Amount of Carpenter and


Joinery work 339,580.00
THE ESTIMATE FOR THE PROPOSED HOUSE MR.I.P ASHAN CHAMARA

Item
Description Unit Qty Rate Amount
No

7.0 Roof Plumber


Supply and fixing approved quality
6"x4" PVC Square type eave gutters
with brackets an 1 1/2" centres,
running heads, end caps etc. as
7.1 directed. Lft 140.00 125.00 17,500.00
Supply and fixing approved quality 3"
dia PVC down pipes with PVC clips at
3"-4" centres and all specials as
7.2 directed. Lft 100.00 135.00 13,500.00

Total Amount of Roof Plumbing


work 31,000.00
THE ESTIMATE FOR THE PROPESED HOUSE MR.I.P ASHAN
CHAMARA.

Item
Description Amount
No

1 Excavation & Earth Work 33,000.00

2 Concrete work 290,524.00

3 Form Work 44,852.00

4 Reinfrcement Work 265,770.00

5 Masonry work 371,800.00

6 Carpenter and Joinery 339,580.00

7 Roof Plumber 31,000.00

Total Amount 1,376,526.00