0% found this document useful (0 votes)
33 views5 pages

WLG 05

Uploaded by

Vongkham LVX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views5 pages

WLG 05

Uploaded by

Vongkham LVX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

Savannakhet Daily progress report

Manufacture & installation of climate change


adaptive flood forecasting and warning system in
Xe Banghieng River Basin, Lao PDR

Anajack Phatana Construction Sole Co., Ltd.

Mon 7/01/2024
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step

Work Foundation construction Name Date Mon 01/7/2024

Index

1. DAILY ACTIVITY OVERVIEW..........................................................................................2

2. HOURLY ACTIVITY DETAILS..........................................................................................2

3. ISSUES AND COOPERATION DETAILS...........................................................................2

4. PHOTOS................................................................................................................................3

5. tomorrow's plan...............................................................................................................................................4

1
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step

Work Foundation construction Name Date Mon 01/7/2024

1. Daily activity overview


- Water Level (WLG-05): Pole, Solar panel, Rain gauge Equipment Install, Cable connection and pipe of
Sensor cable.
· Name of participants: Vongkham, Tong, Kai, Kone, Serm, Bounphone, Phonexai, Soubin, An, Sone.

2. Hourly activity details

Time Activity name Activity details Issues Confirmation and


decision

08:00 - Water Level (WLG-05) - Pole, Solar panel, Rain


~ gauge Equipment Install
12:00

13:00 - Water Level (WLG-05) -Cable connection and pipe


~ of Sensor cable.
18:00

1. Issues and cooperation details


Issues Issues and cooperation details Remark

- -

2
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step

Work Foundation construction Name Date Mon 01/7/2024

2. Photos at site

- (WLG-05): Dig foundation and casting concrete for foundation - (WLG-05): Install pole

- (WLG-05): Install pole and equipment - (WLG-05): Install fence and cable connection.

3
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step

Work Foundation construction Name Date Mon 01/7/2024

3. tomorrow's plan
Date: 7 / 02 /2024
- Repair some work