Lecture 8 Evm Analysis
Lecture 8 Evm Analysis
• Activity schedule
• Data date
Information
• Budgeted Cost of Work Performed
Needed to (BCWP)
CPI = 1, on budget
CPI < 1, over budget
CPI > 1, under budget
Earned Value Reporting - Schedule
Budgeted Cost of Work Performed (BCWP)
SPI = 1, on schedule
SPI < 1, behind schedule
SPI > 1, ahead of schedule
Earned Value Reporting
(budgeted)
(earned)
(actual)
Nabil Dmaidi
9
Example 1:
% complete= (1500/2600)=
Total planned per day for 10
0.5769
days= 2600/10= 260
BCWP= 5980x0.5769
For 4 days= 4x260= 1040 sq.ft
=$3450
%planned= 1040/2600= 0.4
BCWP= 0.4x5980= $2392
Or 1500x2.3
Example 2:
•A contractor agreed to build 30 temporary sheds in 90 days at a price of Rs.
10000/unit. Twenty days later, the contractor has finished 8 sheds with an actual
total cost of Rs. 85000. What is the status of the project?
•Solution:
•-Contractor agreed to build 30 sheds in 90 days means
•1 shed completes in 3 days.
•-Price of 1 shed is Rs. 10000
•-So, 8 Sheds complete in 24 days, while contractor take only 20 days means the
project is above schedule.
•-Price of 8 shed = 8 × 10000 = 80,000,
•-while contractor has finished 8 shed with an actual cost of Rs. 85,000 means the
project is over budget.
Example 3:
ACWP or AC= $680000
BCWP or EV= 8 (units completed at 20 days) x $ 80000= $640000
BCWS or PV=
1 unit takes 3 days to complete
Units completed in 20 days= 20/3= 6.67 units
PV for 20th day= 6.6667 (units completed) x 80000= $533336
SV= BCWP-BCWS= ?
CV= BCWP-ACWP= ?
%SV= ?
%CV= ?
SPI= ?
CPI= ?
EAC= ?
ACV= ?
Example 4:
Compute Estimate At Completion (EAC) and Variance At Completion (VAC) if
both SPI and CPI influence the project work when given variables are
•Budget At Completion (BAC) = $22,000
•Earned Value (EV) = $13,000
•Planned Value (PV) = $14,000 EAC (if the both SPI and CPI
•Actual Cost (AC) = $15,000 influence the project work) = AC
+ [(BAC – EV) / (CPI x SPI)]
Solution:
These elements should be mutually exclusive to ensure that no problems will arise
when allocating costs.
This may be determined by simply allocating a proportion of the total PV for the
project to each activity or, where a Bill of Quantities document has been used to
measured the work, assigning specific bill items, or group of items, to the
construction activities.
How to Determine Planned Values
Each of the construction activities must then be allocated to a schedule that clearly
shows the start and end of each activity. From this schedule it is then possible to
calculate the budgeted cost of work scheduled (BCWS), also known as the PV for
each week/month of the project. This is normally expressed on a cumulative basis. It
is this cumulative PV that is used in the calculations and compared with the
cumulative figures for the BCWP and the ACWP to measure the performance on the
project.
EVA Calculations and Their Interpretations
Cost Variance = EV-AC
% spent = AC/BAC
CPI = %complete/%spent
Estimate at Completion
Another sought after forecasted values is the total anticipated cost of the project
when it is complete. This is called as Estimate at Completion (EAC). It is also
called the Latest Revised Estimate (LRE). For the purposes of our discussion we
will use EAC.
EAC = BAC/CPI
The BAC is the total anticipated cost of the task (or project) as determined when
the baseline budget was established.
Where
Where
Where
EAC = the estimate at completion as derived from one of the methods shown
earlier.
The ETC allows the project manager to determine what will be needed to
complete the work from a monetary or labor hours perspective. In short, what is
the cash (or labor) requirement to complete the work?
To-Complete Performance Index
The last factor used in forecasting future performance is an index that reflects the
amount of value each remaining dollar in the budget must earn to stay within the
BAC. It is called the To-Complete Performance Index (TCPI). It is based on a
ratio of the remaining work to the remaining cost and is represented by the
formula:
TCPI is essentially a ratio of the remaining work to the remaining funds. It enables a project manager to
determine the level of performance needed to achieve the cost or time objectives.
Where
The TCPI is the recommended performance from the status date going forward.
For TCPI greater than 1.00, there is more work remaining than there is budget to
pay for it.
CALCULATING TCPI USING EAC
Formula: TCPI = (BAC – EV) / (EAC – AC)
As you can see, this is basically the same math with
BAC switched out for EAC. Use this version if you want
to work out the cost performance required for
completing the project in line with the EAC.
The same interpretation of the data applies too. Where
the TCPI is calculated to be greater than 1.0, expect it
to be a challenge to complete the work to the estimated
budget with the existing resources. Where the answer is
less than 1.0, you should be OK to bring the project in
because the efficiency required should be within the
capacity of the team.
Scenario- EVA example
In this illustrative project renovations to a building require structural, electrical,
and plumbing work. The budget for the work is 1,050,000 Pounds. The work
comprises eight work packages that will be completed over a 12-month period. A
work break down structure for the construction to be undertaken is produced to
identify the budgets for each item of work. These budgets are then allocated
across the construction activities. Figure A shows the time schedule for the work
with added budget data.
The updated schedule show progress after 6 months of the project. Activity 1,
Activity 2, and Activity 3 are complete. Activity 4 is only 50% complete and will
require an extra month to complete. Activity 5 is 33% complete. Both these
activities are behind schedule. Activity 6 is 33% complete. This activity is ahead of
schedule. The ACWP at the end of this 6-month period is 430,000 Pounds. For
the overall project:
BAC = $ 150,000
BCWSc = $ 80,000
BCWPc = $ 82,000
ACWPc = $ 78,000
CV = $ 4,000
SV = $ 2,000
CPIa = 1.05
SPIa = 1.025
Here is how the given data and the previous formulas can be used:
Simple EAC = BAC/CPI= $150,000 / 1.05 = $ 142,857.00
Or EAC CPI = ACWPc + [( $150,000 - $ 82,000)/ 1.05] = $ 142,712.00
Example
Or EACcom = ACWPc + [( BAC – BCWPc) / (CPIa x SPIa)]
It is easy to see that all three numbers are reasonably close in value (
approximately 1.1 percent), especially for a forecast.
From the aforementioned data, lets apply the formulas for the ETC, VAC, and
TCPI:
VAC = BAC – EAC com = $ 150,000 - $ 141,197 = $ 8,803, shows the project will
be under budget by this amount
THANK YOU