Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 28 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)
PERIODS
PLAN ACTUAL ACTUAL PERCENT
ACTIVITY PLAN START June July August September October November December January February
DURATION START DURATION COMPLETE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
1 Document Mapping Process 1 1 1 1 100%
Page 2 of 3
API Certification Project Planner
Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 28 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)
PERIODS
PLAN ACTUAL ACTUAL PERCENT
ACTIVITY PLAN START June July August September October November December January February
DURATION START DURATION COMPLETE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
37 Training Understanding API 6D 19 1 0%
39 Internal Audit 21 3 0%
40 Management Review 24 1 0%