1 PET Rope 33,862,821.94
1 PET Rope 33,862,821.94
No. of Working
Sr.n Month
Days
Weight
1 July 25
2 August 24
3 September 21
4 October 25
5 November 23
6 December 24
7 January 23
8 February 22
9 March 23
10 April 23
11 May 24
12 June 23
Total 280
630
945
Rope Product Mix in%
10mm 12mm 14mm Total 900
2,040 1,280 5,015
600 400 - 2,500
3.40 3.20 4.20
38 33 104
272 256
163,302 102,400 - 421,414
10,535,350
Monthly Daily
Production Production
kg kg
125,375 5,015
120,360 5,015
105,315 5,015
125,375 5,015
115,345 5,015 702,100
120,360 5,015
115,345 5,015
110,330 5,015
115,345 5,015
115,345 5,015
120,360 5,015
115,345 5,015
1,404,200
Factory Operation Stationary and Sanitary Budget Requirement for 2023/24
Qty
September October November December January February March
1 1 1 1 1 1 1
5 5
1
1 1 1 1 1 1 1
1
1 1
1
2 2
9 9 9 9 9 9 9
12 12
325 325 325 325 325 325 325
April May June Total Unit price Total Price Remark
1 1 1 12
15
2
1 1 1 12
2
1
1
3
1 4
2
2 8
9 9 9 108
0
12 48
325 325 325 3900
Material requirement plan for 2023/24
97.00%
Item description Unit July August September October November December January February March April May June
1. MF rope
PET Flakes kg 54,069 54,069 54,069 54,069 54,069 54,069 54,069 54,069 54,069 54,069 54,069 54,069
Master Batch (different color), rope kg 541 541 541 541 541 541 541 541 541 541 541 541
Screen mesh dia= 218 mm Pcs
PP bag Pcs 701 701 701 701 701 701 701 701 701 701 701 701
Total Unit Price
648,829 35
6,488 650
8,411 40
Total
1. PET ROPE PRODUCTION PLAN 2023/2024
Assumption
1 Effective working hour 20 hrs
2 Effective working day per month (Avarege) 25 days
3 Effective working days per year 280 days
Production
No of working (kg) MF Production (kg)
Month Days U.M Line Twisting Line
July 25 Kg 85,000 59,375
August 24 Kg 81,600 57,000
September 21 Kg 71,400 49,875
October 18 Kg 61,200 42,750
November 23 Kg 78,200 54,625
December 24 Kg 81,600 57,000
January 23 Kg 78,200 54,625
February 22 Kg 74,800 52,250
March 15 Kg 51,000 35,625
April 23 Kg 78,200 54,625
May 24 Kg 81,600 57,000
June 23 Kg 78,200 54,625
Total 901,000 629,375
Average Production
/Day 6,007 4,196
52 Sundays
13 Holidays
5 Maintenance
15 Forced Downtime (Power interruption,…)
85 days
uction Plan
4,563 Actual
228 Actual
Remark
Re Winding
14,302
29,187
25,750
18,391
18,618
19,442
125,689
838 Actual
41.90 Actual
3,485 Design capacity
Six Month Production Report
Twisting Re
Date Types U.M MF Line Line Winding
Plan Kg 455,600 318,250 346,122
Actual kg 151,224 136,356 125,689
effecency % 33% 43% 36%
Production loss kg 304,376 181,894 220,433
Down Time hr
Types Reason
Prepared By:-
Date
Sig
Remark