RAMS - Installation of Signboard - Rev.02
RAMS - Installation of Signboard - Rev.02
PROJECT:
MDC-BMS HQ – 17th, 18th, 19th, 20th Fitout Project- IPIC Tower- AD
1|Page
Contents
Method Statement and Risk Assessment for Installation of Signage ......................................... 2
1. Scope ................................................................................................................................ 2
2. References ........................................................................................................................ 2
3. Definitions and Abbreviations ............................................................................................ 3
4. Roles and responsibilities .................................................................................................. 3
5. Contractor Contact Details ................................................................................................ 4
6. Method of installation ........................................................................................................ 4
7. Plant & Equipment............................................................................................................. 5
8. Manpower Requirement .................................................................................................... 6
9. Material Requirement ........................................................................................................ 6
10. House keeping ................................................................................................................ 6
11. Control of Safety & Health Hazards ................................................................................. 6
12. Training ........................................................................................................................... 7
13. QA/QC Documentation .................................................................................................... 7
14. Distribution ...................................................................................................................... 7
15. Attachment ...................................................................................................................... 7
1. Scope
This Method Statement provides the Control Sequence and methodology that will be used
during the installation of Signboard and protection. The Method Statement would include a
Risk Assessment for each activity which lists out potential risks involved and risk mitigation
techniques for each activity. The method statement would help establish safety standards,
activity guidelines, and define roles and responsibilities.
2. References
Contract documents
Approved Shop drawings and Material approvals
2|Page
3. Definitions and Abbreviations
The PM will have the overall responsibility of the project for execution, Quality, Health
safety and Environment. He shall maintain the planning progress and co-ordination of
works.
3|Page
The SPE will be responsible for monitoring of the day-to-day activities on site, for
materials, drawings, testing & commissioning and allocation of resources to work areas
on site. They shall report to the Project Manager.
The SE will be responsible for monitoring of the day-to-day activities on site, for materials,
drawings, testing & commissioning and allocation of resources to work areas on site. They
shall report to the PE
Supervisor/Chargehand
Supervisor/Chargehand will be directly responsible for the day-to-day job at site, for
coordinating of work with skilled and unskilled labour or any other staff assigned in his
area
Safety Inspector
Safety Inspector shall be responsible for the Health safety and Environment aspects on
site as per approved site HSE plan Safety Inspector will be present at all times of job
execution.
Raabal El Centric
050 411 4905 [email protected]
Amin Interiors
Chady Centric
050 662 6870 [email protected]
Joubran Interiors
6. Method of installation
Preparation:
Installation of Signboard
4|Page
All materials and equipment shall be inspected by Quality Control
Department prior to shifting to work site
Project Engineer/Supervisor will orient and familiarize all the workers and
assistants involved in the installation regarding relevant approvals and
submittals
5|Page
Step ladder
Blade Cutter
Screw driver
8. Manpower Requirement
Manpower requirement like Project Engineer, Supervisor/ Foreman, Skilled operatives and
unskilled labour depends upon the approved construction program and site progress.
9. Material Requirement
Risk Controls: Risk assessment and their controls are carried out for each activity and
enclosed within the detailed section. Each Risk assessment is attached along with their
corresponding detailed method statements.
All personnel should comply with site HSE Plan.
All personnel should comply with corresponding Risk Assessments.
Adequate HSE control measures should be provided as required in the Risk Assessments.
6|Page
All personnel should attend Site Safety Induction.
Every site operative must use the required job specific PPE.
12. Training
Tradesmen performing the any activity will be experienced technicians. If deemed necessary
specific team/Individuals will undergo further training and awareness programs for this activity
by the Project/QA-QC Departments. Toolbox talks will provide general training and awareness
for each activity and also in health & safety matters and precautions
14. Distribution
Client
PM/CM
Consultant
Safety inspector
QA/QC
15. Attachment
The following document is enclosed with this method statement:
7|Page
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
L S R1 L S R2 Action By: L S R3
L S R1 L S R2 Action By: L S R3
Scaffolds: -
• Only competent scaffolders are allowed to erect
and dismantle the scaffolds.
• Scaffolds must be inspected and tagged by a
competent inspector prior to start the work.
• Inspection tags must be reviewed weekly. Visual
checks to be done daily.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
L S R1 L S R2 Action By: L S R3
L S R1 L S R2 Action By: L S R3
CONSULTANT
NAME POSITION SIGNATURE DATE
COMMENTS