BASF Operating Handbook Rev June 2008
BASF Operating Handbook Rev June 2008
BASF Operating Handbook Rev June 2008
®
aMDEA
Process
Operation of aMDEA Plants
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
Handbook of the
®
aMDEA
Process
CONFIDENTIAL page 1 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
1 Cleaning procedure
1.2 Pre-cleaning
The pre-cleaning of the unit is done by air or steam blasting and by water flushing using fire
hoses. Thereby, coarse grime which may have been introduced during construction is
removed. The vortex breaking packing should not yet have been installed at this stage of the
cleaning procedure.
• open manholes and bottom drains of the columns and tanks
• remove orifice meters in the liquid lines and, in advance, close the taps in the
impulse pressure line connections
• plate and frame heat exchangers should be disconnected or bypassed during the
initial cleaning steps until the plant is sufficiently clean. Otherwise, they could get
plugged rapidly.
• flush the equipment with water using fire hoses
• clean lines in sections in the same manner
It is recommended to remove the grease and oil from the vortex breaking packing outside the
columns. The reason for this recommendation is that during the caustic flushing step, sludge
and debris usually gathers in the bottoms of the columns, which can only be removed when
the vortex breaking packing is not yet installed. On the other hand the oil from this packing
needs to be removed, which can be done effectively by using a caustic or potash solution. In
general the same chemicals, temperatures, procedures, etc. as for the cleaning of the plant can
be applied. The cleaning can eventually be carried out in a pit or in a container, which can be
CONFIDENTIAL page 2 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
heated up using live steam. The cleaning can then be done by submerging big bags with the
packing in the solution and leaving them there for some time. Afterwards, the caustic solution
shall be flushed away. Appropriate safety measures are required.
The vortex breaking packing should not be installed before the first condensate/demin water
flush to allow for easy removal of solids and sludge.
CONFIDENTIAL page 3 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
• Circulate the solution through the system for about 8 hours at a temperature of 50
to 70°C (122 to 158°F) at full flow rate. For this purpose the solvent circulation
pumps have to be taken in operation according to the vendor's instructions. As
soon as steady conditions are achieved, check the circulation rate by means of the
FIC valve positions. Simultaneously, the level indicators should be checked.
• Full flow rate means 100 % of design flow rate. Pumps and spare pumps should be
taken into service and cleaned one after the other. Do not operate all pumps
simultaneously in order to avoid an extremely high flow rate, which could exceed
the hydraulic limits of the plant.
• Empty the entire system. Take liquid samples.
• If the potash solution after flushing is extremely dirty, the caustic flushing step
will have to be repeated, eventually several times. This applies especially to plants
which are very dirty or rusty, e.g. new plants in hot and humid climate zones,
plants operated formerly with amine solution containing arsenic for corrosion
protection, hot pot units with severe arsenic or vanadium deposits inside the
vessels and lines, etc. In other cases two caustic flushing steps should be enough.
• According to BASF's experience, it is extremely difficult to remove arsenic or
vanadium residues totally from the vessel walls and column internals in plants
operated formerly with amine solution containing arsenic or in revamped Hot
Potassium Carbonate systems. Even after several flushing steps the flushing water
might still contain arsenic or vanadium in the range of 100 ppm (wt.). It is
recommended to remove these contaminants with reasonable effort as far as
possible in order to keep the aMDEA solution clean. However, there are no
detrimental effects on the performance of the system known, which are caused by
traces of arsenic or vanadium.
• Remove and clean strainers in the pump suction lines.
• Re-install the suction side strainers of the pumps.
In case the waste water has to be neutralized prior to disposal, the neutralization must be
carried out outside the CO2 removal unit.
CONFIDENTIAL page 4 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
• Full flow rate means 100 % of design flow rate. Pumps and spare pumps should be
taken into service and cleaned one after the other. Do not operate all pumps
simultaneously in order to avoid an extremely high flow rate, which could exceed
the hydraulic limits of the plant.
• Take a liquid sample from the water used for flushing and add about the same
volume of MDEA or aMDEA to the sample so that the specified amine
concentration is approximately met. Check this diluted amine solution for foaming
activity (see separate manual: "Analysis Manual for the BASF aMDEA Process").
The foaming tendency is considered low when the foam volume is not higher than
300 ml and the collapse time 20 s or less. However, a somewhat higher foaming
tendency during operation can be compensated by an increased antifoam dosage
rate.
• Compare the result of the foam test with a foam test carried out with a mixture of
aMDEA and demineralized water. This blind test gives you the baseline for the
foam tests carried out with samples from the system.
• Check the pH value of the solution. The pH value should be ≤ 9. A higher pH
value indicates too high a potassium carbonate content.
• Drain the water and check the suction strainers for dirt.
• If the flushing water is clean, the foaming tendency is low (foam volume ≤ 300 ml
and collapse time ≤ 20 s) and the pH value is not too high, the second
condensate/demineralized water flush can be omitted.
CONFIDENTIAL page 5 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
• If the flush water is clean, the foaming tendency is low (foam volume ≤ 300 ml
and collapse time ≤ 20 s) and the pH value is not too high, the aMDEA can be
charged. Otherwise, flushing with 3 %(w/w) potash solution and/or the
demineralized water flush has to be repeated. A foam volume not higher than 300
ml and a collapse time of 20 s or less are required for a low foaming tendency.
However, these figures still have to be compared with the results of a blind test
(foam test with a mixture of pure aMDEA and demineralized water), which
defines the baseline for the foaming tendency. Better values than in the blind test
can usually not be achieved. An exception might be revamped systems, where
traces of the antifoam agent formerly used might be present in the wash water. A
somewhat higher foaming tendency than recommended during operation can be
compensated by an increased antifoam dosage rate.
After the final water flush, the content of particles in the wash water should be small. As a
rule of thumb, the solid content can be judged as follows:
<10 ppm (wt.) solids: excellent
<50 ppm (wt.) solids: good
<100 ppm (wt.) solids: acceptable
A higher content of solids usually leads to an excessive foaming tendency. In this case, a
further flushing step is required.
CONFIDENTIAL page 6 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
MDEAH+ + HCO3-
CO2 SLOW
MDEA + H2O
According to the formulas shown, water is not just a diluent but also a reactant. Hence, a too
dilute solution as well as a too concentrated solution leads to a deterioration of absorption
performance.
H2S reacts with both, MDEA and activators in a fast reaction of an acid with a base as
follows:
H2S + MDEA ↔ MDEAH+ + HS-
CONFIDENTIAL page 7 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CONFIDENTIAL page 8 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
The electrical conductivity at 25°C (77°F) should be less than 10 µS/cm (25.4 ⋅ 10-6Ω-1inch-1).
For chloride see also section 2.5. The amount of suspended solids should be limited due to the
increased foaming propensity encountered with high particle levels. The other specifications
are given as a precaution in order to keep the solution clean and free of contaminants. Hence,
deviations from the recommendations above are still possible, depending on the water quality
available on site. Please contact BASF's aMDEA group in case of doubt. There is no
detrimental effect on the performance of the amine system known, which could be caused by
the compounds listed above.
CONFIDENTIAL page 9 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
The storage tank used for storing the aMDEA solution has to be blanketed with nitrogen at all
times. In some specific cases other gases may be used for blanketing, too. Contact BASF in
case no nitrogen is available for tank blanketing.
The nitrogen blanketing is particularly important in hydrogen plants where residual hydrogen
or other flammable gases can be released from the solvent when the solvent is transferred from
CONFIDENTIAL page 10 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
the system to the storage tank. There is a high risk that these flammable gases form an
explosive mixture in the tank if it is not blanketed with nitrogen. There have been several
documented cases of tank explosions due to gas that has been released or flown back from the
absorber into the storage tank.
Although the aMDEA Premix can be stored at temperatures as low as -20 °C (-4 °F) the
liquid will become viscous as its temperature is lowered. For example, the aMDEA Premix is
flowable, but has a viscosity similar to honey at -20 °C (-4 °F).
CONFIDENTIAL page 11 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
3 Start-up procedure
CONFIDENTIAL page 12 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
The aMDEA premix is very viscous at low temperature. When ambient temperature is low it
might have to be preheated before charging it to the system. Make sure to empty the
containers or drums completely, i.e. without leaving any possibly-precipitated activators
behind.
CONFIDENTIAL page 13 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
• If the gas used for pressurizing the absorber contains CO2, it will be absorbed by
the solvent and the pressure in the absorber will drop. Once the CO2 is removed
from the absorber the gas released as acid off gas contains pure hydrocarbons in
case natural gas is used for pressurizing the absorber or pure syngas (CO/H2), if
syngas is used for pressurizing the absorber. That means the acid off gas will have
a very high heating value and will even be flammable/explosive.
• Bring the solution to its operating temperatures by feeding steam to the reboiler
and operating the lean solution coolers.
• Add the initial charge of antifoam agent according to section 3.1.
• Start feeding gas at < 30 % rate.
• Establish the operating pressures and temperatures in the system.
• Start-up the reflux pumps after a condensate level has been established.
• Slowly increase the plant capacity by 5 % to 10 % steps (both gas and liquid
streams).
• During start-up the liquid flow rate should always be 20 % higher than the amount
required for the current feed gas rate.
• Check for foam activity.
• Afterwards, antifoam agent should be added as necessary or according to the
recommendation in section 4.4. The initial charge of antifoam is usually sufficient
for the first couple of days.
• Check the solvent strength.
CONFIDENTIAL page 14 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
4 Operating instructions
CONFIDENTIAL page 15 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CO2 slip. The effect is shown in Figure 3. Up to a certain degree a lack of activators can be
balanced by a slightly increased solvent circulation rate. Finally, make-up of the activator
system is required, see section 2.6 of this Handbook.
CO2 breakthrough
kinetic limitation
1400
1200
CO2 conc. [ppm (v/v)]
1000
800
0
0 2 4 6 8 10 12
Figure 3: Increased CO2 slip due to kinetic limitation of the system (example)
In section 5 of this Handbook the effect of a variation of the numerous operating parameters
on the performance of the system is discussed. The adjustment of the solution flow rate,
which is one of the major operating parameters, is described in section 4.2.
CONFIDENTIAL page 16 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CONFIDENTIAL page 17 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
stopped, the antifoam agent contained in the solution might precipitate. To avoid foaming
problems after starting up again, about one third of the initial amount of antifoam should be
added.
A detrimental effect on the performance of the system caused by excessive dosage of
antifoam agent has not yet been experienced. This applies to Amerel™ 1500, Pluronic and
SAG. Also laboratory tests could not reliably prove that an overdose of antifoam would result
in foaming problems as believed earlier. Reports claiming a relationship between excessive
antifoam still exist, but they might refer to specific types of antifoam agents other than the
ones used in aMDEA plants. Nevertheless, continuous high overdosage of antifoam over a
longer period of time should be avoided since it might lead to rapid plugging of the side
stream filter. Instead, the real reason for the high antifoam requirement should be traced in
order to look for a way to avoid the problem.
CONFIDENTIAL page 18 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
GE recommends to add the antifoam continuously to the discharge side of the solution pump,
in order to avoid shear forces, which could lead to a smaller and less efficient droplet size.
However, according to BASF's experience the agent is also effective when charged to the
suction side of the solution pump.
Typical dosage rate of the undiluted antifoam Pluronic or SAG is as follows:
• Natural gas: 1000 ml/day for a plant capacity of 100,000 Nm3/h
Note that the figure mentioned above is only a rough estimate. The actual demand of antifoam
might be higher or lower. During foaming problems an increased antifoam dosage rate might
be required. In such a case it is better to dose the antifoam in smaller quantities several times
a day rather than dosing a large quantity in one shot. In any case the antifoam dosage to the
unit has to be optimized individually for each plant.
For the initial start-up an antifoam content in the solution of about 50 ppm (wt.) is
recommended. Hence, the amount to be added initially depends on the solution inventory.
CONFIDENTIAL page 19 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CO2 in the absorber and a poor regeneration in the stripper are possible consequences. A
liquid load less than 10 m3/m2/h can lead to maldistribution in the packing with the same
effect of poor plant performance. Considering a possible reduced plant operation a design
with a liquid load below 20 m3/m2/h should be avoided. In case of doubt please contact
BASF's aMDEA group.
CONFIDENTIAL page 20 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CONFIDENTIAL page 21 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
In applications where the feed gas is saturated with water, the water input with the feed gas
might increase significantly with higher temperature. In such a case the amount of make-up
water has to be adjusted. It might even be required to drain condensate from the regenerator
reflux drum to fulfil water balance of the unit, it the feed gas temperature is too high.
CONFIDENTIAL page 22 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CONFIDENTIAL page 23 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CONFIDENTIAL page 24 / 29
BASF SE aMDEA Handbook
CZA/ML - E 100 Part III
67056 Ludwigshafen, Germany Revision 3.0, June 2008
CO2 and H2S vent line. The use of a nitrogen purge on the stripper at this time
should be considered.
• Drain the aMDEA solvent to the storage tank.
• Wait as long as possible to insure that most of the aMDEA® solution has trickled
off the column internals. Rushing this step will result in higher aMDEA® losses,
so it must be balanced with the time available for the shutdown. Typically, this
can take up to 24 hours to insure low solvent losses. The required time depends on
the type of column internals.
• Before opening the absorber and HP-flash column, flushing with nitrogen is
required to replace flammable gases. This can be accomplished efficiently by
pressurizing the columns 3 times with nitrogen to 3 to 5 bar g (50 psig) and
releasing the pressure afterwards to the flare or to a safe location. The LP-flash
and stripper column do not require flushing with nitrogen, if the solvent circulation
without feed gas during the acid gas degassing of the solvent and cooling down of
the equipment were carried out under nitrogen pressure in the absorber.
• Open the manholes for ventilation and install an air blower for blowing air through
the columns.
• Check for liquid in the vessel sump. If present, drain the bottom section again.
• Make sure that the O2 content inside the vessels is high enough to enter without
breathing apparatus.
• Check for toxic gases such as CO or H2S, where applicable, before entering the
columns.
• In case the treating gas contains H2S, see chapter 6.2 for special precautions
before entering the columns.
• Entry into a confined space must be performed following the plants confined space
entry procedures. The inspection of the equipment can be done following normal
personnel protection measures. Follow the guidelines in the MSDS for exposure to
aMDEA®.
• aMDEA solution is not flammable. Therefore, with regard to the aMDEA solvent,
no special precautions have to be taken for hot work, i.e. welding inside the
columns.
• Obey the safety rules, guidelines and regulations issued for the specific plant.
• In case there will be no opening of equipment or no de-inventorying of the vessels
and no inspecting of the unit, then the shutdown procedure can be reduced to the
required extend.
1. Gas release into storage tank
Make sure that no gas is released into the tank, where it could potentially cause
hazards. It is recommended to flush the columns with nitrogen and to release the
pressure to the flare or a safe location before draining the system. The absorber should
be isolated with block valves, in order to avoid a backflow of solution or gas while the
absorber is under feed gas pressure. This is particularly important when the storage
tank is – contrary to BASF's recommendation - not blanketed with nitrogen. There
have been a number of documented cases of tank explosions due to the back flow of
process gases into a storage tank.
2. Not opening or not de-inventorying the vessels or not inspecting the unit:
The shutdown procedure can be reduced to the required extend.
CONFIDENTIAL page 25 / 29