F2-P1-Budowa I Stateczno Statku
F2-P1-Budowa I Stateczno Statku
F2-P1-Budowa I Stateczno Statku
1
2. B The figure presents a section of a double bottom. Select a sentence which is false: C
a) the double bottom height equals 1480 mm
b) the keel thickness equals 17 mm
c) the frame distance equals 780 mm
3. B The figure presents a section of a double bottom. Select a sentence which is false: C
a) ship has a bilge keel
b) bottom longitudinals are made of bulb flats.
c) the bottom structure is an open grate,
2
4. B The figure presents a transverse cross-section through the main deck. Stringer plate thickness equals: B
a) 18 mm
b) 24 mm
c) 36 mm
3
5. B The figure presents a transverse cross-section through the main deck. Which of the following sentences is false: B
a) deck longitudinals are made of flats
b) deck longitudinals are made of bulb flats
c) the sheer strake is 18 mm thick
4
6. B Look at the drawing. Which of the sentences is false: A
a) ship draft equals 39460 t
b) the drawing shows main dimensions of a ship
c) moulded depth equals 17.6 m
7. B The drawing presents a functional division of a container ship. FEU may be loaded on the deck in: A
a) 6 rows
b) 12 rows
c) 23 rows
23 21 19 17 15 13 11 09 07 05 03 01
5 5
90
5 5 6 6 6 6 6 6
88
5 5 6 6 6 6 6 6 6 6 5 3
86
5 5 6 6 6 6 6 6 6 6 5 3
84
5 5 6 6 6 6 6 6 6 6 5 3 82
5 5 5 5 5 5 5 5 5 06
5 5 5 5 5 5 5 5 3
04
3 5 5 5 5 5 5 3 3 02
5
8. B The figure below presents the hull in: A
a) in transverse framing,
b) in longitudinal framing,
c) in mixed framing,
10. B Shearing forces and bending moments are calculated using a loading calculator, provided that: C
a) only the forces of gravity, buoyancy and inertia are taken into account
b) the ship sails on a regular wave with a length equal to the length of the ship
c) the ship sails with no additional movements on a calm surface of water
6
Item B/D Module 2 – Ship knowledge
1. B The range and size of anchoring equipment is determined based on: B
a) block coefficient
b) equipment ratio
c) anchor cable link dimensions
2. B A swivel is a chain link in: A
a) an anchor shackle
b) an intermediate shackle
c) an anchor cable locker
3. B Lifting capacity of twin derricks equals: A
a) from 0.4 to 0.5 of a single crane load-bearing capacity
b) from 1.4 to 1.5 of a single crane load-bearing capacity
c) from 2.4 to 2.5 of a single crane load-bearing capacity
4. B Hold covers that close the cargo holds shall be compliant with the following requirements of: B
a) water tightness
b) water stream tightness
c) gas tightness
5. B In parallel operation of derrick jibs: C
a) both booms are immobile
b) one of the booms is immobile
c) booms have the same out-reach
6. B A crane handling device for holding and moving a load without a system of blocks fastened outside the C
perimeter of its own structure is a:
a) light lift derrick
b) heavy lift derrick
c) boom crane
8. B A pipe through which the cable goes from the anchor winch to the anchor cable locker is called: B
a) anchor hawsepipe
b) chain hawsepipe
c) universal hawsepipe
7
9. B The permitted load of the lifted cargo with the mass of the auxiliary gear used to lash the cargo is: C
a) a deadweight
b) a capacity
c) a lifting capacity
8
7. D The ship has a buoyancy of 10000 t, the corrected metacentric height is 0.50 m. The weight of 50 t is shifted by the C
distance of 10 m to starboard side. The angle of heel is approx.:
a) 4.3°
b) 2.6°
c) 5.7°
8. D How many tons of ballast water should be transferred from the stern tank to the forward tank for a distance of 50 m A
to correct the trim? Stern draft 4.5 m, forward draft 3.9 m, moment to alter trim 15000 Tm/m.
a) 180.0 t
b) 69.2 t
c) 15.6 t
9. D A ship displaces 7800 T. Its centre of buoyancy is located at VCG = 6.1 m above PP. The following weights C
were loaded: p1 = 450 T, VCG1 =5.30 m; p2 = 220 T, VCG2=3.54 m. The new height of the centre of gravity
equals:
a) 4.26 m
b) 4.52 m
10. B A heel
c) of 12 m
5.99 degrees in a stability criterion in terms of loading grain refers to: A
a) the maximum allowed ship heel after assumed movement of grain
b) maximum ship heeling during a voyage
c) maximum allowed ship heeling during loading
11. B Loss of stability is: C
a) capsizing of a ship
b) presence of a negative initial metacentric height
c) decrease of righting arms on the top of the wave
12. B Water tight door during a sea voyage: C
a) must be closed at all times
b) may be open for the entire duration of a voyage, provided the water tight compartment is not flooded
c) may be open, but only in special circumstances
9
15. B Which figure is not a stability criterion: B
a) heeling angle caused by circulation
b) capsizing angle
c) a heeling angle where the value of righting moment levers is the greatest
16. B To confirm whether a ship fulfils the stability requirements for departure, we use: B
a) a righting arms curve
b) a list of the allowed height of the centre of gravity
c) hydrostatic curves
17. B Blows delivered by the sea to a vessel in motion. is called: C
a) broaching
b) surf-riding
c) slamming
18. B The period of ship’s free oscillation depends on: A
a) ship’s moment of inertia
b) wave period
c) relative bearing of the ship in relation to the wave
10