BOQ Kitgumhouse Focus
BOQ Kitgumhouse Focus
BOQ Kitgumhouse Focus
Pipes 23,400,000
Fittings 46,410,500
Sub-Total 113,823,500
f) Excess material; The excavated excess earthen material has to be spread in an organized manner m3 60 65,000 3,900,000
g) along the
Hiring of pipeline
equipment route, meanwhile
for lifting, has to
aligning andbeeasing
transported
layingon
ofthe
theindicated
DN400STlocation (distance
pipes and 1-
fittings Hr 24 500,000 12,000,000
5Km) the
along . The unit length.
trench cost of this cost item includes the quantity of material spread on the surrounding
h) Connection of installed pipeline
area and transport of the materilal (Both at the start and end of relocation) ; to the satisfaction and nr 2 2,000,000 4,000,000
approval of the supervising NWSC & KECC engineers. 28,218,000
9.0 Pipe Ancillary works
a) Construction of Mass Concrete, Grade C-25 Thrust Blocks for Pipe Bends, AV, WashOut and
Inter-connection points; (Volume more than 1m3 on DN400/350/200 Installed fixtures). nr 6 700,000 4,200,000
b) Provide and Install Marker posts for the installed Air Valve ;to the satisfaction and approval of nr 3 65,000 195,000
c) the supervising
Fixture NWSC
chambers, & KECC
sufficient engineers.
for all fittings and pipework necessary to complete the installation, nr 3 800,000 2,400,000
all fittings and pipework to PN 16: and of the following depths not exceeding 2.0m, Width 6,795,000
exceeding 1.5m to the satisfaction of the supervising Engineer from NWSC