OFCI
OFCI
OFCI
I GENERAL REQUIREMENTS
1.1 Preliminaries - - - - -
Building Permit lot 1.00 50,000.00 - - - - -
Survey Plan sq.m 49.90 - - - -
Mobilization (10% og total project cost) lot 1.00 10,000.00 - - - - -
Staking and Layout lot
- -
Sub-Total I General Requirements - - - - -
Sub-Total D - - - - -
E. COMPLETE MASONRY WORKS
1.0 6" CHB (Exterior Wall) sq.m. 58.00 - - - - - - -
2.0 4" CHB (Internal Wall) sq.m. 21.44 - - - - - - -
3.0 Plastering Works (Interior & Exterior) sq.m. 153.22 - - - - - - -
- - - - - - -
Sub-Total E - - - - -
F. WATERPROOFING WORKS sq.m. 20.10
1.0 Consumables (5% of Materials Cost) - - - - - - - - -
- - - - - - -
Sub-Total F - - - - -
G ROOFING SYSTEM
1.0 Structural Steel Trusses lot - - - - - - - - -
2.0 Roofing Works lot - - - - - - - - -
Sub-Total F - - - - -
IV PAINTING WORKS - - - - - - -
V PLUMBING WORKS - -
1.0 Sanitary and Vent System lot
2.0 Storm Drainage and Sewer Line System lot
3.0 Water Distribution System lot
4.0 Installation of Plumbing Fixtures lot
5.0 Consumables(5%)
VI ELECTRICAL WORKS - - - - - - -
1.0 Power & Lighting System - - - - - - -
Conduit and supports lot
32mmØ x 3m RSC pcs
20mmØ x 3m PVC Pipe Orange pc
PVC Clamp 20mm dia pcs
Miscellenous and Consumables lot
Wires and Cables
2.0 mm2 THHN
3.5 mm2 THHN
8.0 mm2 THHN
22.0 mm2 THHN
30.0 mm2 THHN
Miscellenous and Consumables
Boxes/Pullboxes lot
Utility Box - 2"x4"
Octagonal Junction Box - 4 x 4
Miscellenous and Consumables
Installation of Wiring Devices lot
One Gang Switch pcs 2.00
Two Gang Switch pcs 3.00
Convenience Outlet pcs 7.00
Miscellenous and Consumables
Page 1 of 17
Installation of Lighting Fixtures lot
Led Pinlights pcs 6.00
Outdoor Pinlights pcs 5.00
Wall Lamp pcs 4.00
Miscellenous and Consumables
2.0 Feeder System
Conduits and Support lot
Panelboard and Circuit Breakers lot
Consumables lot
Main Breaker units 4.00
Spare Circuit units 4.00
3.0 Meter System
Metering lot
- - - - - - -
Sub-Total VI Electrical Works - - - - -
Exclusions :
1.0 Building Permits and Occupancy Permit & Charges
2.0 All general materials & consumables
3.0 All architectural & finishing works
4.0 Roofing System
5.0 Waterproofing Sytem
6.0 Electrical and Plumbing (Included roughing-ins only)
7.0 Electric & Water Consumption for Construction (by the Client)
#REF!
#REF!
`
#REF!
#REF!
#REF!
Page 2 of 17
AMOUNT
-
-
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- -
-
-
-
#REF!
#REF!
-
#REF! #REF!
-
-
-
- -
-
-
-
-
- -
-
-
-
-
-
#REF! #REF!
- -
- -
-
-
- 12,020.00
- 17,472.00
- 9,804.00
- 58,824.00
Page 3 of 17
- 29,412.00
-
- 20,304.00
- 24,600.00
- 1,430.00
-
- 6,212.00
-
- -
#REF! #REF!
###
###
140000
100000
5000
#REF!
Page 4 of 17