Consultant Letter To The Employer - Telecom Site Report Week 13
Consultant Letter To The Employer - Telecom Site Report Week 13
Dear Sir,
Below is a summary of Telecom, unboxing, Installation and Commissioning site activities at Ravi G/S,
Muzaffargarh TPS Phase-I and Sarfaraz Nagar G/S during Week 13
1. Ravi G/S:
29/03/2024 Cables:
30/03/2024 Cables:
26/03/2024 Cables:
29/03/2024 Cables:
Observed Issues:
1. It has come to our attention that at the Muzaffargarh TPS Phase-I site installation work has not
been completed yet and pending work includes, installation of 2x mini OTBs, Media converter,
VO/Analogue Telephone. Labeling for OTBs to identify the fiber links, remote end stations are
still pending. Grounding and DC cable for SMS room, Ethernet cables and Tele-protection signal
cables have not been laid yet. RTU CAT07 Cable cannot be laid due to the far distance from
Telecom Panel. The tagging of the cables is still pending.