Appendix E - Permits

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views10 pages

Appendix E - Permits

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Appendix E - Permits

- 247 -
Part A - Permits (Owner)

Owner shall provide to Contractor the following licenses or permits required for the performance of the Work:

Permit Issuing Agency Permit Number Date of


Issuance

1. Certificate of Registration as a Board of Investments (“BOI”) BOI 2012-221 12 October


Pioneer Enterprise BOI 2012

2. Environmental Compliance Department of Environment and Natural DENR ECC 1111-020 23 April 2012
Certificate (“ECC”) Resources (“DENR”), Environmental
Management Bureau (“EMB”)

3. Special Use Agreement in Protected Areas and Wildlife Bureau (“PAWB”)


Protected Areas (“SAPA”)

4. Permit to Cut Coconut Trees Provincial Coconut Development Manager in the 31 May 2012
Philippine Coconut Authority (“PCA”) Provincial
Office or the PCA Agriculturist in the PCA (expired as
Municipal Station having responsibility over the validity is only
area where the trees are situated for five days
from date of
issuance)

5. Private Land Timber Permit Community Environment and Natural Resources CENRO 2012-001 20 April 2012
(“PLTP”) Office (“CENRO”); Provincial Environment and
Natural Resources Office, Regional Executive
Director, Undersecretary for Field Operations,
DENR Secretary (depending on the volume of
trees)

6. Certificate of Registration of CENRO, DENR CENRO 2012-001 20 April 2012

- 248 -
Permit Issuing Agency Permit Number Date of
Issuance
Tree Plantation

7. Water Rights Permit National Water Resources Board (“NWRB”) NWRB CWP 07-13-11-003 15 August 2011
Office, or deputized agent of the NWRB (i.e.,
Office of the Public Works District Engineer, the (valid up to 25
National Irrigation Authority Provincial Irrigation June 2013)
Engineer, or NPC Regional Managers, Water
Districts) in the province where the point of
diversion is situated in the case of appropriation
of waters or where the project is located in all
other cases.

8. Appointment of Pollution DENR EMB Region III


Control Officer (“PCO”)

9. Height Limitation Permit Civil Aviation Authority of the Philippines CAAP HL-010-12 29 May 2012
(“CAAP”)

10. Clearance to Develop Private Philippine Ports Authority (“PPA”)


Port Facility

11. Permit to Construct Private PPA


Port Facility

12. Certificate of Compliance Energy Regulatory Commission (“ERC”),


(“COC”) Licensing and Market Monitoring Division

13. Memorandum of Agreement DOE, Rural Electrification Administration and 20 July 2011
(“MOA”) on the Establishment Management Division
of Trust Accounts in

- 249 -
Permit Issuing Agency Permit Number Date of
Issuance
accordance with Rule 29 of the
EPIRA Law IRR the
generation company and the
Department of Energy (“DOE”)
on Benefits to Host
Communities

14. Certificate of Endorsement DOE, Electric Power Industry Management DOE COE 2011-09-01 8 August 2011
issued by the DOE Bureau

15. Registration as a WESM Philippine Electricity Marketing Corporation


Member / Market Participation (“PEMC”)
Agreement (if WESM is
already operational)

16. Grid Impact Study (“GIS”) National Grid Corporation of the Philippines February 2011
(“NGCP”)

17. Connection Agreement NGCP – Revenue and Regulatory Affairs

18. Transmission Services NGCP – Revenue and Regulatory Affairs


Agreement

19. Metering Services Agreement NGCP – Revenue and Regulatory Affairs

20. Certificate of Non-Overlap or National Commission on Indigenous People Obtaining certificate of Non-
Certification Precondition (“NCIP”) Regional Office Coverage
(Certification that the

- 250 -
Permit Issuing Agency Permit Number Date of
Issuance
consensus/approval of the
Indigenous Cultural
Communities/Indigenous
Peoples for the project has
been obtained or certification
that the project is not within an
Ancestral Domain)

21. Land Use Conversion Permit Regional Center for Land Use Policy Planning Obtaining certificate of Non-
and Implementation (if less than or equal 5 Coverage
hectares or a fraction above 5 hectares) of the
DAR Regional Office or Center for Land Use
Policy Planning and Implementation (if more than
5 hectares) of the DAR Central Office

22. Real Property Tax Declaration Provincial Assessor


over power plant after
construction

- 251 -
Part B – Contractor Permits

Contractor shall be responsible for requesting, obtaining, and paying for any other Permits required for the full and complete
performance of the Contract, including, without limitation, the following:

Permit Issuing Agency

23. Branch License of general partner (“GP”) in Securities and Exchange Commission (“SEC”)
NewCo

24. NewCo Certificate of Filing of Articles of SEC


Limited Partnership (“AOP”)

25. Bangko Sentral Registration Document Bangko Sentral ng Pilipinas (“BSP”)


(Registration of foreign investment)

26. Tax Identification Number (“TIN”) SEC

27. Certificate of Registration as a taxpayer and Bureau of Internal Revenue (“BIR”) (to be filed in
withholding agent for various taxes the Revenue District Office (“RDO”) having
jurisdiction over legal residence or place of
business)

28. Authority to Print Receipts and Invoices BIR (to be filed in the RDO having jurisdiction
over the head office)

29. Registration as employer with the Social SSS (to be filed in the branch office where the
Security System (“SSS”) place of business is located)

30. Registration of employees with the SSS SSS (to be filed in the branch office where the

- 252 -
Permit Issuing Agency
employer is registered)

31. Registration as employer with the Home Pag-IBIG (to be filed in the branch office where
Development Mutual Fund (“Pag-IBIG”) the place of business is located)

32. Registration of employees under Pag-IBIG Pag-IBIG

33. Registration as employer with the Philippine Philhealth (to be filed in the branch office where
Health Insurance Corporation (“PhilHealth”) the place of business is located)

34. Registration of employees under Philhealth Philhealth (to be filed in the branch office where
the employer is registered)

35. Registration as Employer with the DOLE (to be filed in the Regional Labor Office
Department of Labor and Employment having jurisdiction over place of work)
(“DOLE”)

36. Alien Employment Permit (“AEP”) DOLE (to be filed in the Regional Office or Field
Office having jurisdiction over the work place)

37. Pre-arranged Employment Visa (Working Bureau of Immigration (“BI”)


Visa 9(g))

38. Special Non-immigrant Visa (Working Visa Department of Justice (“DOJ”) upon
47(a)(2)) recommendation/ endorsement of the BOI for
foreign national employees of a BOI- registered
project company.

39. Barangay Clearance Barangay having jurisdiction over the place of


business of NewCo

- 253 -
Permit Issuing Agency

40. Community Tax Certificate (“CTC”) Municipality of Masinloc

41. Locational (Zoning) Clearance Municipality of Masinloc

42. Business Permit (also known as a Mayor’s Local business permits office having jurisdiction
Permit) over the place of business of NewCo

43. Sanitary Permit to Operate Local health office having jurisdiction over the
place of business of NewCo

44. Fire Safety Inspection Certificate Local fire safety office having jurisdiction over
the place of business of NewCo

45. Registration for Hazardous Wastes DENR EMB Region III


Generator’s DENR ID Number

46. Wastewater Discharge Permit DENR EMB Region III

47. Radioactive Material License Philippine Nuclear Research Institute (“PNRI”)

48. Height Clearance Permit Civil Aviation Authority of the Philippines


(“CAAP”)

49. Highway Clearance Department of Public Works and Highways


(“DPWH”) Regional Office

50. Contractor’s License Philippine Contractors Accreditation Board


(“PCAB”)

- 254 -
Permit Issuing Agency

51. Permit for electrical installation DOLE Regional Office

52. Certificate of Final Inspection DOLE Regional Office

53. Permit to install/operate internal combustion DOLE Regional Office


engine, pressure vessels and/or
boilers/pressurized water heaters/generator
set

54. Building permit and its ancillary permits (e.g., Office of the Building Official (“OBO”)/Office of
architectural permit, civil/structural permit, the City/Municipal Engineer
electrical permit, mechanical permit, sanitary
permit, plumbing permit, and electronics
permit)

55. Accessory Permits (e.g., permits for firewalls OBO/Office of the City/Municipal Engineer
separate from buildings, towers, silos,
smokestacks, chimneys etc.)

56. Certificate of Occupancy OBO

57. Certificate of Accreditation and Registration Bureau of Customs (“BOC”)


as importer

58. Permit to Operate Pollution Source and DENR EMB Region III
Control Installation

59. Permit to operate elevator, hoistway and use DOLE Regional Office
gates or doors

60. Permit to Operate Private Port Facility PPA

- 255 -
Permit Issuing Agency

61. License to Handle Controlled Precursors and Philippines Drug Enforcement Agency (“PDEA”)
Essential Chemicals

62. Permit to Purchase, Own, Use and Store Philippine National Police (“PNP”)
Controlled Chemicals

- 256 -