Ins PPT Desntp Acs
Ins PPT Desntp Acs
Touch Pile
Secant Pile
Touch Pile
By
A.C.SHIVAKUMAR
ME(Str/PSC)
Mob 9845013493, 9110250187
[email protected]
[email protected]
DEEP EXCAVATION.
Excavations that exceed a depth of 4.5m (15ft) are considered Deep
Excavations.
22.00m
Depth
Deep Excavation for Residential Apartments
Deep Excavation for Road way
RE panels collapsed
Retrofitting by nailing
• Stabilize the embankments and levees
Soil Nailing for Tunnel
Why Deep Excavation Supporting Systems is required?
In rocky strata
25m Deep
In Hard strata
Braced Excavation method
Anchored Excavation method
Island excavation (partial excavation) methods,
Alignment of RT wall
Example for Line load and footing load
surcharge
Line load
Footing Load
Pressure diagram of Footing Load
Additional pressure for surcharge due to Footing load
Example for Strip load surcharge
Example for Strip load surcharge
If the length and depth of retaining wall is less than the length and
width of raft respectively and the retaining wall is abutting the raft
slab, then UDL surcharge can be considered.
SOIL NAILING
Soil nailing is to reinforce and
strengthen the existing ground by
installing closely spaced steel bars,
called “nails”, in to slope or
excavation as construction proceeds
from the “top down”.
Deep Excavation
Support of Hill cut for highways
Stabilize the retaining walls Federal Highway Administration
Publication No.FHWA-SA-96-069
Stabilize the embankments and levees
Nov 1996
Typical cross section of soil nailing
Permanent soil nailing
Where an extended design life is required, usually more than 50years
Permanent soil nail is hot dipped galvanised bar
The bar encapsulated with additional corrosion protection of a
corrugated polyethylene sheath which acts as a barrier for corrosion
protection.
The inner and outer annulus of the sheathing is grout filled to transfer
load and provide long term durability.
Anchorage components at the surface are usually hot dip galvanised.
Components of Permanent soil nailing
Hot dip Galvanised soil nail and Galvanised plate
Polyethylene sheath
Finished surface of Permanent soil nailing
Temporary Soil Nails
Temporary soil nails are in applications where the design
life is usually less than 2 years.
Temporary soil nails are used for temporary structures like
deep excavation in high rise buildings.
Machineries and Materials
Drilling Equipment
Grout mixer
Compressor
In-situ pile retaining walls also called column piles are rows of concrete piles either cast-in situ
Touch pile shoring is very versatile because the size of the piles and
the spacing between them can be adjusted to suite the site condition.
f. They are a much more suitable option in the area of dense urban populations or adjoining
properties. In those areas, other methods would not be possible to implement without the
g. If in the nearby areas or surrounding there are footings and underground utilities of other
building, it would be difficult with traditional retaining methods. This constraint makes a
h. These piles have much faster construction time than the secant bored piles. Cont.....
i. These walls can be constructed to provide load-bearing capacity as well
as a retaining structure where line loads can be applied to the wall.
j. Contiguous pile walls are ideal when groundwater ingress is not an issue
for the finished wall.
k. This type of retaining wall is used on a wide range of engineering
projects such as ground stabilisation, underpasses, and basement walls.
Cantilever pile wall
Cantilever pile wall represents a retaining structure performed without
additional protection. The wall is executed by digging under the level of
excavation / slide surface and stabilises the soil mass due to the resistance
of material in the front.
Performance advantages:
I. It allows undisturbed excavation in the open pit
II. It does not require an additional support
III. It is simpler construction procedure
Cantilever pile wall
Supported pile wall
Supported pile wall represents retaining structure which is executed with
additional protection when it is not possible to ensure the stability of the
structure for design loads.
Depending on design requirements, additional protection can be performed
inside (bracing system) and outside of open pit (geotechnical and self
drilling anchors etc.)
On front of side pile wall, the additional protection with steel or reinforced
concrete beams are commonly used horizontal to the pile wall.
Performance advantages:
i. possibility of deeper depth of excavation compared to the cantilever pile
wall
ii. possibility of accepting more loads (eg in existing building area)
iii. more control of horizontal displacement of pile wall
Industrial site at
Yalahanka, Bangalore
Touch Pile as foundation for retaining wall
for slope protection at collapsed portion
Slope protection to collapsed portion at Ch
87.90km on NH 275 Madikeri Mangalore road
Slope protection to collapsed portion at Ch
98.40km on NH 275 Madikeri Mangalore road
Touch pile
Touch Pile retaining wall for road work
Anchored pile wall
Pile wall for varying depth
Secant Piles
In this technique primary piles (PCC) are installed first, and then secondary piles
(RCC) constructed between primary piles when it gained some strength.
Pile overlap is typically in order of 75mm to 100mm.
The lack of waterproofness in contiguous pile walls are effectively overcome by
Secant pile system.