03-DHI - Urban Climate Change Guidelines
03-DHI - Urban Climate Change Guidelines
03-DHI - Urban Climate Change Guidelines
CLIMATE CHANGE
GUIDELINES
JANUARY 2012
CONTENTS
1 Introduction ______________________________________________________________1
1.1 Background _________________________________________________________________ 1
1.2 Purpose ____________________________________________________________________ 2
1.3 Definition of the problem ______________________________________________________ 3
1.4 An Example – Legislation in Denmark_____________________________________________ 4
1.4.1 Sewerage plan ______________________________________________________________________ 4
1.4.2 Sewer renewal plan __________________________________________________________________ 5
1.4.3 Contingency plan ____________________________________________________________________ 5
1.4.4 Additional municipal planning, local plans, plans for water quality, etc. ________________________ 5
1.4.5 Risk assessment and analysis of extreme rain _____________________________________________ 6
1.5 The EU Flood Directive ________________________________________________________ 6
1.5.1 Preliminary flood risk assessment ______________________________________________________ 7
1.5.2 Flood hazard and flood risk maps _______________________________________________________ 7
1.5.3 Flood risk management plans __________________________________________________________ 8
1.5.4 Publication of maps, plans, etc. ________________________________________________________ 8
1.5.5 Summary __________________________________________________________________________ 8
3 Compliance with the performance requirements under the influence of climate change 20
3.1 Description of desired standard of services _______________________________________20
3.1.1 Service level and compliance with operational requirements under the influence of climate change 23
APPENDIX
The information contained in this Guideline report is for general information purposes only. The information
is provided by DHI and while we endeavor to keep the information up to date and correct, we make no
representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability,
suitability or availability with respect to the Guideline report or the information, products, services, or
related graphics contained in the Guideline report for any purpose. Any reliance you place on such
information is therefore strictly at your own risk. In no event will we be liable for any loss or damage
including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever
arising from loss of data or profits arising out of, or in connection with, the use of the Guideline report.
Through the Guideline report you are able to link to other websites which are not under the control of DHI.
We have no control over the nature, content and availability of those sites. The inclusion of any links does
not necessarily imply a recommendation or endorse the views expressed within them.
The Climate Cookbook – 2nd Edition iii Greve Forsyning, VandCenter Syd,
© DHI 2012 , PH-Consult og DHI
1 INTRODUCTION
1.1 Background
This document describes how cities around The World can respond to flooding
problems expected due to impact from climate change. These guidelines provide an
overview of information available about climate change, exemplified by using Denmark
as a case. Focus is on impacts on the urban drainage systems. The most significant
factors are the increase in extreme rainfall and rise in sea level. Examples of how floods
can be prevented and avoided describe available methods for analysing existing urban
drainage networks and evaluating the impact from various flood mitigation
augmentations.
During the recent years several cities have been affected by very long-term extreme
rainfall which showed limitations in the urban drainage in combination with the
remaining water cycle (groundwater and streams). These rainfall events emphasize the
need for municipalities to focus on flood management within urban drainage systems
and the entire water cycle. This edition of the climate cookbook is extended with
descriptions of response to flooding from the sea. The described methods are limited to
storm water systems, streams and seas.
The report is financed by DANVA and the project partners. The report is prepared by
Greve Forsyning A/S, VandCenter Syd, PH-Consult and DHI. The members of the
working group were:
The project was undertaken during the period November 2008 to June 2010.
The report provides detailed descriptions of methods for analysis of flooding from
simple "surface depression maps" or "blue spots" to the advanced hydraulic computer
This version of the guidelines (Climate Cookbook) represent a translated version of the
original Danish version under the title: "En kogebog for analyser af klimaændringers
effekter på oversvømmelser i byer".
1.2 Purpose
Design of urban drainage systems through time has been undertaken using multiple
methods such as hand calculated methods: Constant rain intensity, time-area method,
runoff diagrams, rain images or the rational method. In recent decades, these methods
have been supplemented with computer-based methods to support the dimensioning and
analysis of the urban drainage system. All over The World it is common practice to use
hydraulic models (such as MOUSE or MIKE URBAN) for analysing the function of the
urban drainage system and to calculate the effect of proposed augmentations.
Along with developments in the calculation methods, the requirements for the
dimensions of urban drainage system have evolved. For many years the common
practice was that in combined systems conduits were only allowed to reach full running
capacity every second year, and in storm water systems only once a year. National
rainfall series or some older gauged rainfall data have been used. Most of the Danish
urban drainage network is probably dimensioned from the above requirement. With the
release of Guide 27 (SVK Skrift 27) the dimension requirements were revised to a
maximum frequency of damaging flood events occurring from the systems. The urban
drainage system will now be dimensioned based on a selected return period of
damaging flood events. Additionally, it is recommended that the impact on the urban
drainage systems from even more extreme rainfall events than the urban drainage
system is designed for, are analyzed in order to minimize damage to infrastructure and
the environment.
When the rain fall exceeds the design rainfall of the systems, then there is often no
legislation or standards that describe which actions are required for the different entities
in charge of the urban drainage systems. Currently, there is no requirement for
assessments of when and where a city might be inundated caused by extreme rainfall.
Nevertheless, a real demand is present for these assessments in the light of recent years’
flood inundation events in many cities. In this report the technical procedures to
undertake the flood assessments are described. It is not considered “who you are”, but a
general urge is given to consider responsibilities so that these types of assessments are
undertaken in the future. In this way it is ensured that conscious choices are taken in
assessing flood inundation risks in cities.
Urban drainage systems are loaded directly by precipitation, and the hydraulic capacity
must be sufficient to convey water volumes to the receiving waters, otherwise when the
hydraulic capacity is met the network may discharge to the surface resulting in flooding.
The receiving waters may also be affected by climate change in terms of higher water
levels which can have significant back water effects and reduced outlet discharge
capacity in the urban drainage system. Rivers may also be affected by increased runoff
from other sources - including groundwater – which can lead to damages caused by
flooding because of the reduced hydraulic capacity. There are many contexts that should
be assessed and taken into account when looking at the function of urban drainage
systems influenced by climate change.
At this stage there is no solid knowledge about the correlation between the various key
inputs. Preliminary estimates of water levels in Køge Bay does not indicate any
correlation with extreme rainfall, but on the other hand it does not state that it is
meteorologically unlikely. In many coastal settings with low-lying built-up areas and
locations with low elevated overflow structures it is important to analyse these elements
in conjunction. If an overflow structure is not able to function as intended because of
the water level in the receiving waters, the risk of flooding increases significantly.
Similarly, if the seawater rises above quayside or dike crowns, larger areas may be
flooded with seawater and the urban drainage system may not be able to function. The
urban drainage system may in this situation have a negative effect by transporting water
to otherwise protected areas of the catchments.
Climate change is expected in some places and at certain times of the year to give rise to
increased groundwater levels which affects the urban drainage system since it can lead
to increased groundwater infiltration. The increased groundwater infiltration may lead
to reductions in the hydraulic capacity of drainage system and increasing the load to the
WWTP. Rising groundwater tables may also affect the local percolation and infiltration
systems which may lead to both local flooding and flooding due to reduce hydraulic
capacity in the urban drainage system. It is likely that extreme rainfall will occur in the
summer period, while maximum groundwater levels will occur during winter, but local
assessments should be undertaken to ensure that the effect is limited to local conditions.
It should always be assessed whether a local solution in one place may cause problems
elsewhere. The risk of this can be significant in situations where the drainage network is
operated at full capacity or is overloaded. In those cases it is recommended that the total
water cycle in the watershed is evaluated and combined with other climate-dependent
effects such as wind and seawater currents and levels. Any calculations of the urban
drainage systems should ideally be undertaken with boundary conditions that are
determined from the same expectations of climate change as rainfall. If possible, an
integrated model simulation analysis of all factors affecting runoff should be
undertaken. This integrated analysis is quite extensive and requires many details to
If the terrain and drainage system is more complex then modeling of drainage system
operation can be necessary to provide an overview of the situation. It may be an
advantage to include a runoff calculation on the surface of the watershed.
The choice of calculation level must always be adapted to the current problem and
available input and boundary conditions. It should be noted that this is the calculation of
future extreme situations based on forecasts of changes in load. There is considerable
uncertainty in all results and level of detail in the calculations, and the detail in the
model approach should be adapted to this uncertainty.
The infrastructure of the urban drainage system, connected industries etc. must be
described. In the sewerage plan, the municipality or wastewater utility must address
relevant land use planning objectives (including river basin management objectives) and
other local planning schemes. The sewerage plan must include measures to ensure that
wastewater discharges from wastewater treatment plants and storm water discharges do
not exceed water quantity and quality objectives for the receiving waters.
There is not necessarily a requirement for a full emergency plan, but only to assess the
significance of flood situations, as input to an emergency plan.
1.4.4 Additional municipal planning, local plans, plans for water quality, etc.
Climate change effects may affect other planning, particularly municipal, local plans,
plans for water quality, water levels, etc. It is important to incorporate the effects of
climate change and extreme rainfall in the work of sewerage plans. In the preparation of
sewerage and storm water plans, the municipalities are obliged to deal with the other
planning and ensure compliance. Thus, municipal plans and local plans could be
controlling the sanitation, particularly in terms of allowable imperviousness and
minimum allowable foundation elevations. Likewise, the municipality must deal with
the impact on water quality in the recipients by more extreme rainfall events.
The municipal plan represents the municipality’s plan for the area, and in this plan
guidelines should be incorporated for allocation of areas where flooded water can be
stored such as wet meadows, basins etc. Guidelines for foundation levels can be written
in the municipality plan for preventing flooding.
It should be noted that the horizon in the climate scenarios of 50 - 100 years is far
beyond time schedules in both sewerage plans and future water plans under the Water
Act directives, which operate with time horizons of 15 to 30 years.
Work on climate change will require a coordinated planning effort by the municipality.
Climate change takes place over a long time horizon. Despite this the magnitude of the
potential impacts and the consequent need for investment requires analysis of the
impacts on drainage systems now. This is required in order to prioritize, manage and
implement measures that reduce potential future damage to society as a result of climate
changes.
Since it is commonly expected that climate changes will lead to more extreme rainfall
and increased rise in sea level, it would be appropriate to assess the impact of extreme
rainfall for the drainage system - including assessment of any damage caused by
surcharged water. The methods described in Chapters 4 and 5 can be used for this work.
The Guide 27 is used by almost all Danish municipalities to design and maintain urban
drainage systems for conditions where there is no water on the ground. There are no
guidelines in Denmark for analysis and handling of the situation when there is water on
the terrain / flooding. This results in situations where important infrastructures are
flooded, e.g. as it happened in 2007 and 2010 with damages of more 1 billion dollars.
Flooding originating from the sea is covered by "Assessment and risk of flooding from
the sea, bay or other parts of the territorial sea". Ministry of Environment and the
Coastal Directorate have identified (April 2011) nine risk areas based on a preliminary
The background for the Flood Directive is the major floods that occurred in Central
Europe. The objective of the Flood Directive is to establish a framework for measures
for reducing the risk of flood damages. The Flood Directive starts with article no. 1 by
defining what type of floods is covered by the Flood Directive:
1. Flooding:
A temporary coverage with water from rivers and lakes is applied to land areas
which are normally not covered by water.
2. Flood Risk:
The combination of the probability of a flood event and the potential adverse
consequences for human health, environment, heritage and economic activity
associated with floods.
b) A description of the historic flooding that has caused extensive damage and are
likely to be repeated in the future. The description must include the extent of the
flood, flow routes and an assessment of damages.
European Member States shall complete the preliminary flood risk assessment by 22
December 2011.
a) flood level.
b) water depth or water level, whichever is applicable.
c) flow rate or the appropriate water quantities when appropriate.
European Member States shall ensure that the maps of flood hazard and flood risk are
completed by 22 December 2013.
European Member States must set "suitable targets" for the management of flood risks,
with emphasis on reducing the potential negative impacts of floods on public health,
environment, heritage and economic activity. If this is relevant emphasis should be laid
on non-structural initiatives and /or reducing the likelihood of flooding.
Flood risk management plans must include relevant aspects such as costs and benefits,
flood extent, flow paths and areas which have the potential to retain flood water.
Flood risk management plans must include all aspects of risk management with special
emphasis on prevention, protection and preparedness, including flood forecasting and
warning systems. The flood risk management plans may also include the promotion of
sustainable land use practices and improve water retention as well as the controlled
flooding of certain areas in cases where flooding is avoidable.
European Member States shall ensure that flood risk management plans are completed
and published by 22 December 2015.
1.5.5 Summary
Timeline for implementation of the directive is:
Revisions and updates of the issues mentioned in the plans listed in section 1-3 above
start in 2018 and are then updated every six years. From this date the likely climate
change impacts on the occurrence of floods must be added to the plans etc.
Flood risks from urban drainage systems may not be included in the implementation of
the Floods Directive, but it is recommended that it will be included in the calculations
of the risk of flooding, because drainage system in many cases may convey water into
the critical areas of the city from both the sea and streams. In addition, flooding due to
the capacity of the urban drainage system should be known by the local authorities in
order to produce comprehensive solutions to flooding problems and prepare
contingency plans.
It should be noted that the methods described in this report are generic, so that when
new figures for climate scenarios are available, only changes to the input values (rainfall
and sea level) are required to rerun the calculations. All methods and analysis will be
unchanged.
Denmark works currently with three climate scenarios (A2, B2, EU2C) calculated by
the Climate Center at DMI as well as climate scenario A1B which may be used for
analysis until year 2050. The reason is that the dispersion on (A2, B2, EU2C) is
insignificant until 2050 and A1B represents the average of the three scenarios. The three
scenarios (A2, B2, EU2C) is calculated based on IPCC’s reports from 2001 (IPCC,
2001) and are valid until year 2100. It has been decided by Danish officials that the
three scenarios be given equal priority, thus there is no preference for one of the
scenarios. It is therefore up to the individual water utilities or municipalities to choose
which climate scenario should be used.
B2 describes a world where the emphasis is laid on local solutions that are
economically, socially and environmentally sustainable. It is a world with a
EU2C describes a world where the international community and the individual
countries enter agreements to develop technological solutions and changes in
behavior to decrease dangerous anthropogenic influences on Earth's climate
leading to global temperature increases exceeding 2°C above pre-industrial
levels. The scenario corresponds to the EU's objective as expressed by the
European Council in 2005.
The three scenarios are shown in Figure 2.1. It should be noted that the three climate
scenarios are fairly similar within the first 30-50 years, after which the differences
between the scenarios increase.
Figure 2.1: The evolution of global climate scenarios from the IPCC in 2001 (IPCC, 2001). Climate
scenarios A2, B2 and EU2C are prioritized equally in Denmark.
Figure 2.2 represents the last calculated information from the IPCC (IPCC, 2007) on the
temporal development of the globally accepted climate change scenarios. By comparing
the climate scenario A2 - calculated by the IPCC in 2001 and 2007 - no significant
differences were found at the global level. It should be noted here that local variations in
climate scenario A2 have not yet been calculated for Denmark. It is therefore not
possible to assess the importance of the IPCC 2007 estimates for existing Danish
climate scenarios.
Table 2.1: Changes in Denmark's climate up to 2071-2100 (relative to the mean of the period 1961-
1990) for the three Danish selected scenarios.
Climate scenarios, as they are considered in the IPCC assessments, are clean climate
models with a time resolution which is in the order of days, not hours or minutes. In
connection with the runoff of rainwater, especially in cities, it is crucial that there are
time series of precipitation which represent high-intensity rainfall and precipitation
linked to well-defined repetition periods now and in the future in high temporal
resolution. Projections of future precipitation made not available, but the Wastewater
Committee in Denmark has analysed and advocated which precipitation should be
dimensioned for the future when it comes to high-intensity rainfall, see Guide 29. For
coupled rain, where the frequency of precipitation is interesting, there are no
recommendations for climate-proofing of the frequency of precipitation. In chapter 2.3
the recommendations for use of future rainfall is described.
They are evidently not dependent on either terrain or region. They appear to be random.
It is therefore chosen at the moment to recommend the same factor range for the entire
country. In Guide 29 a similar analysis of rainfall data has been undertaken and resulted
in climatic factors listed in Table 2.2 which is used for dimensioning Danish urban
drainage networks. The data analysis showed that there was a tendency for the factor to
increase with return period. The factors listed in the table are now applied in urban
drainage calculations.
The data source for predicting the changes to rainfall in the rest of the century is still
limited. Given the uncertainty in the prediction it is considered reasonable to apply a
linear increase. It should be noted that this increase may not be applied when using a
factor 1.2 to 1.4 on the depression rain-series sampled until now. It is only a factor of
extreme rainfall.
For the climate scenarios (A2, B2, EU2C) it is expected that annual precipitation in
Denmark will not change much compared to present, but that precipitation patterns will
change. It is therefore uncertain whether the current description of CDS-rain (Guide 28,
2006) can be applied for the future by simply multiplying with a factor on present CDS
rain to obtain a future extreme rainfall event. The error in this must be accounted for by
including the uncertainty in the climate factor.
Over the next 100 years it is expected that a 10 year storm event will increase by 30%.
It means that parts of the urban drainage systems, which currently meet the desired
standards of services according to Guide 27, at some point in the future will no longer
be able to meet the functional requirement because of the increased size of the 10 year
storm event.
In order to get an overview of the future performance of the urban drainage network
model simulations can be undertaken loaded with the current 10 year and 5 year storm
events adjusted for climate change. In case the predicted climate change at a given
location results in a 30% increase in the 10 year storm event, then the urban drainage
network can be simulated with the following scenarios in order to analyze the urban
drainage network’s resilience to climate change.
More specifically the mean sea level is expected to rise by 28-81 cm in Danish waters
during this century. Additionally, a wind contribution by storm surges of up to 30 cm in
maximum sea water levels is expected on the west coast of Jutland.
(http://www.klimatilpasning.dk/DA-DK/KYST/PÅVIRKNING/Sider/Forside.aspx,
December 2009).
The impact of the new extreme water levels for coastal municipalities will be calculated
as: Sea level rise plus backwater from new climate-related extreme wind fields. Output
from these oceanographic calculations will be extreme water levels for relevant return
periods including a measure of duration (i.e. day maximum or similar). This information
can be used to estimate the required pumping in a given urban drainage system and
whether inflow from the sea through rivers may occur.
DMI and Danish Coastal Authority recommend that the sensitivity of a given scenario is
examined against the projected future seawater condition and the possibility of even
higher sea water level rises associated with risk (http://www.kyst.dk/sw17746.asp).
In the future it is expected that rivers will also be affected by climatic changes. Sea level
rise will affect river and reduce the drainage capacity, and in situations of extreme water
levels the impact is increased. Since the rivers often act as boundary condition to the
urban drainage system, it is recommended that the river hydraulics are described
together with the urban drainage network.
Generally, the rivers are increasingly affected by intruding saltwater wedges, which
may alter the biological conditions in the river. Impacts from climate change on rivers
other than the hydraulic conditions are outside the scope of this study.
The expected increase in precipitation events with high intensity may have local impact
on the groundwater conditions. Especially in areas with coarse, sandy sediments a rapid
rise in groundwater table may occur under very intense rainfall with potential
infiltration into sewers, basements and other underground structures. At the same time
there may be disturbances in the dewatering plant pumping from the upper aquifers.
The projected sea level rise in coastal areas would cause a rise in groundwater
potentials. The risk of intrusion of saline water in coastal groundwater wells will
increase and the drainage of coastal catchment areas will be disturbed or altered. In
many cases the sea level rise will only have very local impact on groundwater
conditions. However, it may have significant impact on runoff conditions in coastal
rivers, where gradients are small, especially combined with the anticipated increased
intensity of rainfall. This is particularly true in rivers located in West Jutland where a
fine balance between rainfall intensity (and long periods of high rainfall) and the risk of
flooding exists.
In the winter of 2006/2007 Storåen went over its banks in the area of Holstebro because
of the high precipitation in autumn and winter months which lead to increased surface
runoff to the receiving water. Flooding from the river reoccurred in 2011 because of a
combination of frozen soil and fast snowmelt in connection with rainfall.
Finally, it is possible on the basis of local rainfall time series or the regional model to
create CDS rain representing the required return periods. The use of CDS rain is also
the only option when rain events with long return periods are required. Because of the
relatively short period of the rainfall time series, rainfall events having return periods
higher than 10 years are encumbered with high uncertainty. In this case it is
recommended to use CDS rain.
The above options can all be used when using historical data. When taking into account
the increase in precipitation due to climate change, only the latter option is directly
applicable. As described in section 2.3 it is easy to apply a climate factor to the CDS
rain and thus load the urban drainage systems with the expected increase in
precipitation.
Within a few years it will probably be possible to generate all local rainfall series
corresponding to a chosen climate projection. It will then be possible also for the future
conditions to calculate e.g. discharges to recipients and other issues that require all the
rain events to be applied. Currently, we have no experience in this country in
developing and applying such artificial rain time series in the model simulations.
There are currently no recommendations for how to take coupled rainfall into account
when applying climate adaptation.
In order to estimate local sea level rise as a result of climate-related wind fields a 2D
oceanographic model can be used. Output from these oceanographic calculations will be
extreme water levels for relevant return periods including a measure of duration (i.e.
day maximum or similar). In many cases simply using current daily sea levels (typically
an average level) or extreme water level with a specific return period (i.e. T = 10 years
estimated from a measured time series in the sea) will provide reasonable estimates. An
example of a calculation of new extreme water levels in Køge Bay is given in Appendix
D.
The water level in the stream depends on runoff intensity and volumes from urban and
rural hinterlands. When rainfall intensity increases in the future, it is expected that the
maximum flow of the rivers increases as well. The change of base flow in rivers mainly
depends on groundwater level including changes in the soil moisture capacity in the
future.
If the boundary condition of urban drainage system is a stream, it will in most cases be
necessary to include the effect of the watercourse in the calculations of the impact
because of the interdependency between streams and urban drainage systems.
In those cases where the water level in the receiving waters is currently affecting the
retention and discharge of urban drainage systems, it would also be appropriate to
include the water level of the receiving waters in future scenarios. If the overflow/outlet
is discharging to the sea, it is recommended to use future water levels in the ocean as the
The water level in the lakes will depend on the future flow in the rivers,
infiltration/recharge of groundwater and the amount of evaporation which according to
DMI will increase as a result of increased temperatures.
The water level in the groundwater zone is inversely correlated with rainfall intensity as
increased intensity will increase the surface runoff. The rain intensity during summer
increases in future rainfall scenarios which tend to reduce the groundwater potential.
The sea is the groundwater potential boundary condition. Since the sea rises in the
future a potential increase in groundwater level in coastal zones is expected. In addition,
the groundwater level in the upper soil layers will depend on temperature, evaporation
and on farmers’ anticipated changes in drainage conditions due to the expected drier
summers.
To include all of the above effects of climate change, which potentially could influence
the future drainage system, it is necessary to establish a complete hydrological model
which includes ocean, groundwater, lakes, streams and storm water system. This is
currently beyond the scope of most municipalities and it is considered sufficient to use
existing boundary condition data corrected by the IPCC recommendations (at the sea
water level).
The amount of precipitation (the further to the right the greater precipitation) is given on
the horizontal axis, and the probability of flooding is displayed on the vertical axis. The
entry on line 1) represents a normal rainfall, i.e. between 10 and 20 mm. In this situation
Along the line to the right the flood risk limit is reached for the current dimensioned
urban drainage systems. For existing urban drainage systems this situation corresponds
to a rainfall with an intensity of 8-9 mm over 10 minutes, which could previously be
expected to occur every second year (averaged over many years). In this situation the
capacity of the storm water systems will be reached, but there will be no flooding. This
is under the condition that urban drainage systems are sufficiently maintained.
If there is an increase in precipitation (higher up on the line), the risk of flooding (as
shown on the vertical axis) will increase. Within the existing network flooding can be
reduced by putting a contingency plan in operation as illustrated by 2) -> 3) in the
figure: Before the rain falls, the lakes and channels can be drained in order to have
available storage capacity, pumping water with mobile pumps, dig out additional
appropriate storage locations, cleaning grates, dam rivers, etc. In addition, if a flood
incident is forecasted in a specific area, fences can be put up to avoid accidents due to
flooding.
Point 4 in the figure illustrates the situation when flooding will occur. The rainfall is so
extreme in this situation that it will not be possible from an economic point of view to
avoid flooding.
In Figure 3.2a vision for the development of urban drainage system and implementation
of climate adaptation is given.
Based on the increasing rainfall, there is a need to revise the current dimensioning
standard so that the urban drainage systems can handle the increased amount of rainfall.
Point 3 in Figure 3.2 illustrates ....?.
The effect of Guide 27 is that the guaranteed minimum standard of services is now at
point 3 when new construction is planned. The rainfall needs to be more extreme in
order to cause flooding – which effectively means that minimum standard of service
level is raised for current rainfall but that the population will experience the same
occurrence of flooding as today when the full climate effect has been reached (approx.
year 2100).
A rainfall event corresponding to point 3) represents now the guaranteed limit against
flooding. Further along the horizontal line towards the right (increased precipitation)
there will be a risk of flooding. Contingency plans can reduce the damages illustrated by
moving from 3) to 4) in Figure 3.2.
The last item on line 4) indicates the conditions of the extreme rainfall, as seen in recent
years in many municipalities such as Greve in August 2002 with 100 mm in three hours
and in July 2007 with 250 mm within a period of three weeks (and approx. 60 mm in
one day). In these situations (4) there are no guarantees against flooding. Contingency
plans might reduce flooding and damage, but it is likely that flooding will occur.
Making a city resilient against such precipitation conditions the guaranteed minimum
service levels must be moved towards Point 4) with extensive investments as a result.
Water Utilities are responsible for fulfilling the national requirements as described by
Land Commission Guides for old systems and in the Wastewater Committee Guides in
As it is today, municipalities are not responsible for flooding in the cases where
precipitation is above point 2, and there is no legislation requiring authorities to take
into account these precipitation events.
3.1.1 Service level and compliance with operational requirements under the
influence of climate change
The changes in rainfall over Denmark as described in section 2.3 result in an altered
response in urban drainage systems in the future.
Work to reduce the negative impact from climate changes on drainage systems will
have the overall aim of reducing potential damage to community values - either by
reducing the flood level, or by reducing damage through efficient management of
potential flooding.
Danish urban drainage systems constructed after 2005, must comply with functional
requirements formulated by the Wastewater Committee in Guide 27:
These are minimum requirements, and municipalities are allowed to set higher
standards to meet additional and / or more stringent requirements. In Guide 27 it is
stated that it is the actual situation in the catchments that is decisive based on e.g. the
actual frequency of surcharges. It is pointed out that when sizing and analysing urban
drainage systems, future changes in climate must be taken into account, particularly
changes in rainfall conditions and water level in receiving waters in order to ensure that
the system meets the required functional requirements throughout the life expectancy.
Level 2. Mapping of the level of flooding as a result of the new design rainfall based on
forecasts of future climate changes. The water depth and spatial distribution of the
flooding is assessed as well as the potential damage.
When the problems are identification they are prioritized using the risk analysis
procedure described in Chapter 6.
In many cases only knowledge about whether a flood event may arise or in which areas
it may happen is required. In other cases there is a need for detailed calculations of
return periods and extent of flooding.
The types of modeling tools that are useful for different problems depend largely on the
urban drainage system dynamics and the shape of the terrain. In a simple urban drainage
system where the dynamics are less important, it is often possible to implement a
qualified calculation of flood extent based on the calculation of water balance. In urban
drainage systems that are more complicated, it is necessary to use a dynamic drainage
model.
Similarly, the terrain types are divided into simple cases, which are characterized by
gully pots / basins without dynamics and more complicated cases where the dynamics
on the surface are important.
There is often great variation in the level of detail and quality of data. For instance if
there is any calibrated dynamic model of drainage area available and if it is possible to
acquire a terrain model and GIS data of the houses and roads.
In GIS the digital terrain model, DTM is used to locate indentations in the surface and
nominate these depressions as known risk areas. An increasing number of people are
using DTM’s to assess the risk of storm water flooding in cities. In many cases, these
depressions are not necessarily risky, as there may be drainage channels draining these
gully pots, such as rivers, ditches, storm drains, etc. DTM’s are also used to assess flood
risks from the sea in the same way as for storm water flooding, however; in this case the
analysis is not necessarily complete: The depressions that appear as gully pots are only
filled if there is a system directing water to the depression.
The analytical methods can be improved by modifying the DTM so that the assessments
take into account any drainage systems directing water away from or towards the
indentation. Finally, it takes into account that the water flow has a certain duration,
which is then included in the application of numerical hydraulic models.
The technical analysis method, using the terrain model at one of the levels can be called
"technical path" see Figure 4.1.
The Landscape Architect may in some cases use the simple surface depression maps for
example to place a lake, but in other cases known water levels are required to ensure
that the lake will actually contain water! At the “climate-meter” a "multidisciplinary"
path can be added, where applications of different disciplines in technical departments
can be anchored.
4.1.4 Economy
The price for achieving the various levels of the “climate-meter” ranges from relatively
cheap to relatively expensive, from left to right: One can relatively easily work out a
"depression map" on un-quantified data, but very detailed and hard work is required to
establish an advanced hydraulic model which includes the entire water cycle.
Similarly, many other aspects of climate adaptation fit into the “climate-meter” to
support the decision where to start and where to end, e.g. who may use the different
methods: State, regions, municipalities or utilities, solution methods, environmental
conditions and economy.
1. DTM - Depression Map: GIS analysis, using the DTM is calculated depressions
in the surface. The method takes only surface runoff into account and thus not
the storage volume and hydraulics of the pipes.
2. Quality assured DTM Depression Maps: GIS analysis, using a quality assured
elevation model (DTM) to calculate depressions in the surface. The method
includes only surface runoff and does not include the hydraulics in the urban
drainage network.
3. Depression Maps combined with simple runoff models. Simple volume account
of precipitation and runoff capacities on terrain is incorporated in the
"Depression Maps" calculation. This method provides a first estimate of risk
zones.
7. Simulation of the total water cycle. In the future it will be possible to combine
models of runoff from the groundwater zone, streams, urban drainage system
and the sea. This will provide a comprehensive overview of runoff in cities.
Currently, the urban drainage system and streams can be combined with the
groundwater hydrology in the zone, but it is very computation intensive and
difficult to set up models in a detail that makes it worth executing the great
work.
In areas where there is not an existing drainage model and where the terrain mainly
consists of gully pots, the terrain model (without a hydrodynamic model) is suitable for
estimating smaller impact and for feasibility studies. The advantage of this method is
that it can provide a quick overview of the problem. On the other hand, there may be
considerable uncertainty in the method, and one should be very aware of the errors
arising from ignoring the hydrodynamics of the system.
Usually, there is a GIS registry of the largest bridges in a municipality. This can either
be directly incorporated into the terrain model or used as a template for a manual
revision of the areas. Figure 4.2 shows the changes in water levels that can be produced
by proper validation of the digital terrain model.
The analysis can be used to make an assessment of flow capacity under bridges, since
the analysis before opening the bridges gives a picture of a potential flood event where
the culverts and bridges are blocked.
Calculation of depressions
In calculating the potential flood areas, it is assumed that all surfaces are completely
impermeable. There is no option for infiltration or runoff via drains and drainage
system. The maps show potential areas of risk - namely depressions in the terrain where
there is a possibility that water can gather and cause flooding. Maps can show the
distribution of missing information about the spatial distribution and volume, and partly
a list of the depths where the depressions fill up with water. When all depressions in a
map are shown it may result in a noisy picture of the terrain model. Filtering the data
can reduce the coverage of low risk flooding areas, e.g. by showing all depressions or
depressions just above e.g. 100 or 500 m3, as shown in Figure 4.3.
Figure 4.3: Reduction in the number of depressions based on volume. The first part shows all
depressions, the second part shows depressions of 100 m3 and the third part shows
depressions over 500 m3.
When depressions have been identified depths can be calculated, see Figure 4.4.
Information about depressions can fairly easily be linked with data for the groundwater
table.
Depth
The following section describes a very simple method of how rainfall and drainage
capacity may be taken into account based on only volume considerations.
Figure 4.5: Waterways on the surface calculated without houses (left) and including houses (right).
Choice of method depends on the level of detail since a terrain model including houses
may cause some extra localized flooding, see Figure 4.6.
Catchment boundaries are defined for all depressions over 100 m3, see Figure 4.7. If
larger basin boundaries are required, then larger volume or maximum depth of
depressions can be selected.
The area and imperviousness of the catchment can be used to calculate how many
millimeters of rain are required to fill the depressions, see Figure 4.7. This may be
misleading since flooding due to a half filled large depression may be critical.
Precipitation
Catchment
As a hypothetical example Figure 4.10 shows a basin of 4 ha, where the capacity of the
outlet pipe is 80 l/s and the volume of drainage system is 43 m3. Based on observations
of water depth on the road in various heavy rain events, the imperviousness is calibrated
to 45%. Figure 4.10 shows the effect of a 76 mm rain falling in 120 minutes (equivalent
to a 100 year rainfall event). It is assumed that there is no backwater from the
downstream system. The flooded area is 0.4 hectares and it will take two to three hours
before capacity is regained in the drainage system.
Data from the terrain analysis can also be used for calculation of the return periods of
maximum water level in depressions from the surface area, imperviousness, volume
calculation and upstream contributions, see section 4.2.3 for more details. This means
that the dynamics of the drainage system and any backwater effects are disregarded.
The calculations provide a good estimate of the relationship between the contribution
from the catchment and depression volume, but they do not account for contributions
and capacity of the urban drainage system. In general, this leads to over-estimation of
flooding upstream, while flooding downstream tends to be under estimated.
Figure 4.11: Example of a pure surface runoff model made for the Road Directorate in 2009.
Figure 4.13: Example of use of Depression Map Method together with backwater effect calculations using
hydraulic drainage model. [DEFRA 2006].
VandCenter Syd and Greve Forsyning have used data from meters to calibrate and
validate models since 2004. The use of meters within Greve Forsyning is described in
Appendix F.
Digital analysis of a terrain model shows a complex system of flow patterns on the
surface. Further analysis may reveal that the description of the surface can be simplified
to be comprised of a series of depressions, channels and overflows similar to the
calculation methods implemented in dynamic 1D drainage models. Many of the
On the basis of the digital analysis a one-dimensional surface model can be generated
consisting of ponds, weirs and channels after which the surface is implemented directly
into the hydraulic drain model without coupling between different types of hydraulic
models. Figure 4.12 shows the principle diagram of the 1D-1D system.
Figure 4.14: Principle sketch of 1D-1D coupling of drainage system and surface.
Analyses of DTM data will reveal that the depressions and indentations on the surface
are rarely neat and regular closed depressions. A depression calculated by the
Depression Method as a single depression usually consists of many smaller depressions.
Figure 4.15 illustrates a hypothetical example of two depressions. Often a depression
found by the Depression Map Method consists of several hundred depressions
depending on the grid size in the DTM.
If the threshold for a given depression is less than the chosen threshold, then the
depression can be merged with the adjacent depression. The consequence of merging of
depressions versus separation is illustrated in Figure 4.16 and Figure 4.17. The selected
values for threshold depths are mainly important in cases where water is primarily
supplied to one depression and where both depressions have a relatively large volume
under the common threshold.
The most accurate and detailed model is achieved by low threshold values of
aggregation of depressions, but at a very high level of detail the complexity of 1D-1D
model and the calculation time increase significantly. If a very high level of detail on
the surface is required then it may be advantageous to use a 2D model for surface
calculations (see Section 4.2.6).
A number of sensitivity analyses of detail level and edge effects have been undertaken.
The main conclusions are that the level of detail of the result is higher or the same as the
chosen degree of detail in the model. The error caused by the level of detail is greatest
in sub-catchments situated on slopes with large storage capacity on the slope. In these
cases the capacity to retain water on the slope is ignored. In addition the velocity with
which water flows on the surface is overestimated (from nodes to reservoirs and
between reservoirs) unless overland flow canals are incorporated. By contrast, the
volume is conserved in the system corresponding to the selected drainage model and the
selected time step.
Based on GIS-generated surface depressions and results from the 1D model the flood
inundation and flood levels can be plotted in GIS, see Figure 4.18.
Depth
With 1D-1D model technique it is possible to implement flood calculations for model
areas of considerable size and with a reasonable calculation time - without using sub-
models. The model simulations of Odense and Greve have been undertaken by applying
the 1D-1D model concept. (See Annex B and E).
In Greve, the method has been used for quality assurance of the priority of climate
adaptation (as described in Chapter 6) and to generate risk maps for documentation to
EPA authority.
The advantage of a combined urban drainage model and surface model is that there is
potential for great precision of the flood extent during extreme rainfall events.
Input to MIKE FLOOD consists of elevation models, which either originate from Laser
Scans from airplanes or helicopters (also known as LIDAR - Light Detection and
Ranging) or the xyz-coordinates for a terrain model and GIS-based polygons for houses
and roads. A terrain model including roads, houses, etc. may be purchased from a local
distributor of such data, or it can be generated by putting themes together, e.g. by
raising houses four meters above the terrain level and lower roads by 20 cm. This
process is outlined in Figure 4.19.
Terrain model +
Buildings and
roads =>
Runoff Model
Figure 4.19: Surface model can be generated from terrain data, GIS theme of houses and roads.
Selected manholes from MOUSE / MIKE URBAN are coupled to the 2D terrain model.
It is important to consider which manholes should be coupled to the surface, where and
how by considering the density of pipelines and manholes and their terrain levels. In
some cases it may be advantageous to move the coupling point in the surface model to a
Physical System
There will be some uncertainty about how water is exchanged between the two models.
How quickly the water can surcharge through grates and manholes in the selected area
and how quickly it can return to the pipe network. Obviously, this can be a calibration
parameter, but as a rule of thumb it must be assumed that there is a limit to how much
pressure may be in the system before the water surcharges through all the grates and
manholes. Similarly, it is believed that the water on the surface reenters the urban
drainage system as soon as the hydraulic capacity is regained.
Calibration data for surface model may be based on observations of the extent of flood
inundation in certain areas during one or more historical rain events, but often there is
very little data available. The main tasks in a calibration are:
It is relatively simple to develop a coupled model, but calculation time is long and
requires high quality inputs. Figure 4.21 shows results from a calculation with coupled
models. An aerial photo is used as background.
Analysis of terrain data provides no information on the influence from drainage system,
so it is important to emphasize that the results must be interpreted with caution. Based
on overland flow paths and the extent of contributing areas, the analysis may
characterize an area as low-risk zone without regard to contributions from the pipes in
the urban drainage network. A GIS analysis would not have given rise to increased
preparedness at Greve Hall or Ejersmindevej in Odense since the contributing areas
have limited geographical extent.
Figure 4.23: Correlation between results of Depression Method (gray), hydraulic surface calculation (red)
and combined hydrodynamic drainage model and surface model 1D-1D (yellow) - Blue
coincide hydraulic surface calculation and combined hydrodynamic drainage model.
The traditional hydrodynamic drainage model provides a good indication of where the
water will initially surcharge to terrain, but does not describe overland flow on the
surface and the interaction between surface and drainage systems. It is therefore only
possible to reliably estimate the intensity and the volume which the urban drainage
system has the capacity to capture. When water is present on the terrain, results from the
model are unreliable.
By combining data, methods and models of the different approaches, e.g. terrain model,
Depression Method and drainage model, the required amount of information is gathered
for undertaking high-level calculations to describe the interaction between the drainage
For both model types increased detail of the surface reduces the error in the surface flow
description, but increases the calculation time. For 1D calculations, the number of
depressions in surface controls the surface flow, while 2D surface is controlled by grid
size. The results for the two surface models are comparable (Nielsen et al., 2009), but in
areas where flow time on the surface is large (long flow paths with relatively low slope),
a 2D surface description should be considered. Alternatively flow paths should be
included in the 1D description for describing the flow on the surface.
Figure 4.24: Results from models with, 1D and 2D surface descriptions respectively.
As with the analysis of flooding from storm water system, there are several methods
available to calculate flooding from the sea. These methods range from simple GIS
analysis for the use of hydraulic computer models to .......?. The methods are described
in this chapter and illustrated in Figure 5.1.
Figure 5.1: Illustration of the modeling tool and what the different modeling levels can be used for.
1. "Water Elevation Maps": GIS analysis using only a digital terrain model to
identify flooded areas. The method uses sea water levels and terrain elevations.
This method shows only where there could potentially be water on terrain if
there was a connection to the coast.
2. “Water Elevation Maps of areas in connection to the sea” (in GIS terminology
called “Cost Distance”: GIS analysis where the influence from dykes and
barriers on the flooding is taken into account. For this analysis a quality assured
DTM is required.
Terrain Models
A terrain model is a digital topographic representation of the area. This model can either
simply describe the topography in the form of contour lines (called a digital terrain
model) or it can also include structures, in the form of dykes, houses, walls, etc. known
as a height model.
When choosing which type of terrain model is the most appropriate, factors in the
model area that may affect water currents need to be evaluated. Physical structures
(dykes, houses, etc.) which significantly affect the water flow, must be included in the
terrain model. Information on houses might be generated based on GIS layers
containing information on the location of buildings. This information is often available
in the municipality. A terrain model with descriptions of houses, roads and other vital
structures can typically be purchased from a data supplier.
The flood map can be developed by calculating the local water depth as the difference
between sea level and the local terrain elevation. All areas in the terrain model, which
lie below sea level will be flooded, even those not connected to the sea. This is done in
practice by setting the signature for water level to blue until the required elevation is
visualized (e.g. 2m level). This method is obviously subject to considerable uncertainty
because the method assumes that areas which have no direct contact to the sea are
inundated. If a method in which only areas with direct contact to the sea (through the
terrain) are required, the tool "Cost-Distance" in ESRIs software can be applied.
The described method is most suitable for coastal areas with large slopes, meaning only
areas near the coast are inundated. Limitation of the method is the fact that natural
physical processes are ignored, e.g. the time it takes the water to flow on terrain. The
method yields the maximum flood image and is especially good for rapid screening of
the areas that are at risk of flooding.
Inland depression
In the following example a flood map for a maximum sea level of 2.24 m is provided.
The digital terrain model of the area has a grid size of 1.6 x 1.6 m. The calculated flood
is illustrated in Figure 5.2. The map shows flooding along the coast and in the areas
behind the coast line.
Figure 5.3: Flood maps based on elevation-map method - a pure GIS analysis.
If it is assumed that only those areas which are in direct contact with the sea are flooded
by the rising sea level, then the flooding is reduced significantly as shown in Figure 5.4.
1. Rivers are not wide enough to be described in the DTM (if e.g. the stream is 1 m
wide and the DTM resolution is 1.6x1.6m), which potentially may reduce the
flooding modeled by the model compared to reality.
2. Rivers passing through culverts under bridges may not have been opened in the
DTM (e.g. the roads and small bridges), which potentially reduces the flooding
in the model compared to reality.
3. Dikes are not represented because the DTM is prepared before a dike is
established (which leads to artificial flooding in the city by the model).
4. Bridges have been removed in the DTM, thus giving an artificial "gap" into the
city (e.g. if there is a structure under a bridge that closes at high tide which is not
represented in the DTM and results in artificial flooding of the city by the
model).
5. Storm water systems and combined sewer systems with overflow to the sea are
not described in the DTM. This is an overall situation because the DTM does not
have any information about the pipe network under the surface. This restriction
gives potentially less flooding in the model than in reality, unless non-return
valves are installed on all outlet pipes and constructions.
The dynamics of the system (energy losses in streams) and duration of high water level
are not included in this analysis and should be assessed by other criteria.
If the DTM is modified to address the limitations of the items 1-5 listed above, the Cost
Distance method is a powerful tool to show the worst case flooding of cities combined
with high water levels in the ocean.
The dynamics of the system (including energy losses in streams) and duration of high
water level is still not part of the approach, but can be assessed by analysing the
durations of storm surge and estimate the importance of this by using an average water
velocity (e.g. 0.25 m/s). If the distance from the sea to a low-lying area is short, the
duration has less significance compared to a long distance.
To ensure that "worst case" is assessed it is obvious that the DTM is quality assured. In
Figure 5.5 an example of a cost-distance calculation is shown with and without correct
description of the stream. As Figure 5.5 shows, it is necessary to ensure that all terrain
features such as rivers, dikes, bridges and culverts are represented in the DTM.
This method does not account for storm water and the ability of sanitary pipes to
transport water into the city. A rapid screening where this ability is included can be
undertaken by opening the terrain model where pipes are located in the ground. If this
analysis is carried out, then it is very important to be critical of the outcome, since the
water will only enter the network at manholes.
When the model domain is defined it must be ensured that the elevation of the inland
area is greater than the maximum expected water levels in the ocean. In addition, the
rivers, dikes, etc. must be described in the terrain model to ensure accurate descriptions
of the flow around / over / through them.
dtm_5_06feb2009.dfs2
Elevation (m)
-1.98 - -1.74
-1.73 - -1.54
-1.53 - 0.32
0.33 - 1.09
1.10 - 1.83
1.84 - 2.58
2.59 - 3.54
3.55 - 4.58
4.59 - 5.65
5.66 - 7.94
Figure 5.6: Model area when the expected maximum water level is 3.0 m.
It is possible to calculate the effect in terms of floods from time-varying water levels in
the ocean.
Figure 5.7: Illustration of a time-varying water levels in the ocean - as input to a flood calculation.
MzResultView1
6166600
6166400
6166200
6166000
6165800
6165600
6165400
711000 712000
07/02/07 16:00:00, Time step 20 of 40
Figure 5.8: Example of model results showing water depths and velocities.
Water level
Water level
Drainage pipes
Drainage pipes
Figure 5.9: Illustration of the components in a calculation with a drainage model in combination with a
model describing the flooding from sea.
Figure 5.10: Only selected areas of the drainage model (shown in red) are coupled to 2D flow model.
This optimizes the calculation time.
A time series with the variation of sea level is used as boundary condition for
calculation. In addition, the urban drainage model can be loaded with rainfall. Then the
combined effect of high tide in the ocean coinciding with a rain event can be analysed.
Results
Model results are temporal variations of water depths on terrain along with flooded
areas. In addition to this information on flow velocities can be plotted, e.g. for analysing
the impact of forces from the water as well as information on water flow and water
levels in drainage system.
A big advantage of a risk analysis is that all causes of flooding are assessed and
weighted. Hence optimizing the time and avoiding disproportionate spending of time on
some measures, while others, perhaps more important, are overlooked. As an example a
pump failure of a pumping station due to obstruction or power failure during a moderate
rain event could result in flooding comparable to the flood caused by an extreme rainfall
event. One method to find the cost related to flooding in urban areas is to collect
information on documented flood incidents by the insurance companies, as e.g. made in
Norway (König et al., 2002), Denmark (DANVA, 2005) or Brazil (Nascimento et al.,
2005). An internationally recognized technique to quantify the damage is the use of
"Flood Damage Curves", describing the extent of the damage as a function of land use
and water level, refer (Speight, 2006) and (Nascimento et al., 2005). Currently, such
"Flood Damage Curves" do not exist for any areas in Denmark.
Risk is the combination of the probability of an adverse event (e.g. failure of wastewater treatment plant /
pump station, basement flooding, releases of hazardous substances, errors in management / SCADA) and
the magnitude of the consequences (e.g. damage to facilities, personal injury, odor, traffic delays, fish kills)
and severity (is the release of 1 litre or 100 litres, is it the hospital that gets flooded, how many are injured).
Mathematically expressed as: risk = probability times consequence.
The frequency matrix consists of seven intervals named F1 to F7. F1 is an event that
statistically occurs less frequently than once every 10,000 years. F7 is an event that
statistically occurs 10-100 times a year. The frequency ranges are constructed according
to a logarithmic scale. Because of the logarithmic scale it is not important to know the
frequencies of adverse events accurately. It is important to know the magnitude of a
given event to be used. The frequency matrix is shown in Figure 6.1.
1 – 10 year F5 0.1 – 1
A logarithmic scale is used between the individual impact categories in the matrix to
make it possible to compare the impact groups. "Negligible" for instance indicates an
economic value of 10,000 to 100,000 DKK, while "Marginal" indicates a value between
100,000 and 1 million DKK.
The economic scale used in the consequence matrix is not arbitrary. Each figure is
estimated from available sources and practical guidance numbers.
The consequence matrix can describe the different impact categories ranging from
no/negligible impact to the disastrous impact described in both qualitative and
quantitative terms.
Four colors are used in the risk matrix to indicate whether the calculated risk level for a
given event is tolerable or not. A risk level above six or seven shall lead to
implementation of defined actions to reduce risk levels. According to Figure 6.3
identified mitigation measures must be implemented for the two events classified in the
non-tolerable region (indicated by circle No. 4 and No. 13 in Figure 6.3).
All items located in the yellow area should be evaluated based on a cost-benefit-analysis
that can determine what and how much is required to reduce the level of risk and
whether an investment should be made here and now, or only when the impact occurs.
An analysis provides the basis for assessing the risk level for the entire drainage system
and to assess this level relative to the acceptance threshold defined in the risk matrix.
For incidents above the acceptance threshold risk mitigation measures must be
identified and implemented. For incidents which lie in the acceptance area, an
identification of optional mitigation measures must be undertaken and assessed through
a cost-benefit-analysis.
The cost of flood damage varies depending on what is damaged, if the damaged items
have been completely or partly written off, replacement cost, etc. Moreover, the cost
depends on whether the flooding was caused by rain water and sewage, and where the
flooding occurred. It is therefore very difficult to generalize the damage costs. A general
list that accurately describes the cost of flooding of electrical cabinets, basements,
houses etc. cannot be developed. It is therefore recommended to first determine the
number of damages by type and then to cost the damage.
Streets convey rainfall water into the drains. However, when the capacity of the
drainage system is exceeded the water may surcharge to the roads. The roads are then
used to convey the excess water during the rainfall event. In these situations it is
important to know estimates of water depths, water velocities and where the water
flows. Roads are usually designed to drain storm water quickly and efficiently.
However, when there are significant amounts of water on roads, it might conflict with
the original design of the road. If an analysis shows that a road under future climate
conditions will be flooded more frequently, it should be discussed and resolved with the
road authorities. The road construction may be adapted. In connection with damage
assessments of roads it is pertinent to examine the criteria for the operation: How much
water on the road is allowed by the Authority before the road must be closed? And to
investigate the road quality, so it can be determined how much water it takes to destroy
the foundation of the road and how long the road can be flooded before damage occurs.
Valuation
The following parameters can be used for valuation of flooding:
Housing
Crèches
Kindergartens
Nursing homes and sheltered housing
Figure 6.4 shows a theme with houses inundated by various return periods. The GIS
layer of simulated floods is linked to the GIS layer of houses taking into account the
foundation level.
In Figure 6.5 the electricity cabinets are illustrated with floods exceeding 40 cm, by
which flooded electricity cabinets can be identified and counted.
Figure 6.6 and Figure 6.7 show the specific buildings plotted together with extent of the
flooding and flood depth. In this example schools, kindergartens and service stations are
shown. This type of GIS illustration shows how and where health or environmental
issues may arise.
T = 20 yr
T = 50 yr
T = 100 yr
Figure 6.4: Example of GIS theme of the houses flooded at different return periods.
Figure 6.6: Example of GIS theme showing specific buildings. Flood propagation is pictured together
with the location of schools and kindergartens and gas stations.
Figure 6.7: Example of GIS theme showing specific buildings. Flood levels are pictured together with
the location of schools, kindergartens and gas stations.
Analyses of climate adaptation can be achieved at many different levels (as described in
the introduction to Section 4). These methods can be used for different degrees of
priority: Establishing a basis for getting started, where models shall be established,
prioritizing measurement programs, prioritization of specific climate adaptation in the
form of installations, priority for emergency action, etc.
Priorities can be carried out based on assessments of risks of flooding, but can also be
implemented based on economic assessments: where do you get the greatest reduction
in flood risk or most climate change adaptation for the money?
In Greve Municipality it was decided that the entire urban drainage network must be
upgraded so that the water level in these systems only surcharge to terrain once every 10
year. Based on the experiences from the flooding in July 2007 and a flood risk map
prepared using the so-called quality-assured Depression Method, the entire municipality
is divided into 42 urban catchments, and priorities of the climate change adaptation is
planned for the next 12-15 years.
The hierarchy is based on the idea that those who have been hit hardest must be climate
change adjusted first. This plan is politically decided.
The following information was used to help guide the prioritization of upgrade works:
Experiences from the floods in July 2007, as reported directly from citizens or
landowner associations.
The digitization of the storm water system.
The digital terrain model for Greve Municipality which is used to calculate the
depth of the depressions in the surface, the "Depression Map Method".
GIS theme of buildings in the municipality and the theme of business and public
buildings.
Figure 6.8: Prioritization of urban water sheds. The numbering reflects the order of implementation
Figure 6.8 shows the prioritization of urban areas. Urban area no. 1 is the first area to
become adapted to the climate change, followed by urban area no. 2, etc.
In order to give an idea of the flood risk to commercial and public buildings, the number
of these located in the depressions is shown for each urban area. However, these
commercial and public buildings were not included in political decision on the
prioritization of climate change adaptation.
There are three types of solutions: To avoid the increased volume of water discharged to
the drainage system, increasing the discharge or the storage capacity of the drainage
system or possibly a combination of these. Reduction of inflow to the drainage system
can usually only be achieved by establishing local infiltration of water. Drainage of
storm water can be done through open channels or closed pipes to the recipient, to larger
infiltration units, or with any wastewater to treatment plants.
Storage systems can be either traditional basins like concrete boxes or pipe-basins, or it
can be lakes and ponds. Beyond the physical conditions in the catchment, treatment
plant capacity and conditions in the receiving waters, it is crucial whether the drainage
system is a combined system or a separate system. In a separate storm water system, it
is usually much easier to find diversion options for a local recipient, than it is for
overflow originating from a combined system. Figure 6.9 shows an overview of
possible ways of regulating storm water into a drainage system.
Figure 6.9: Schematic overview of possible ways of regulating runoff. Source: Parkinson & Mark 2005.
The capacity of fascines may typically be of a size equivalent to 20-30 mm of rain, but
there is no assurance that fascines are empty at the beginning of rainfall events. For this
reason it is not certain during an extreme rainfall event that flooding is reduced
significantly. However, fascines can reduce the yearly runoff volume considerably and
increase groundwater recharge.
Separating the combined system is carried out in smaller communities and new built-
outs, but rarely in the old city centers where the need is often the greatest. Therefore,
Alternatively, an additional pipeline can be added along the existing pipeline. Prior to
this augmentation the drainage system should be carefully analysed in order to only
make the necessary substitutions, and it should be considered to increase existing
dimension on some stretches, and whether there are alternative pipeline options, which
can reduce costs for expansion.
Trunk mains
The increased runoff flow from a catchment can be conveyed through larger pipes or
stored in basins. Due to lack of space it may be difficult to expand the sewage system,
and an option could be to build tunnels conveying the water from strategically well-
placed nodes in a catchment area to the recipient or main trunk line. The tunnels can
also act as extra storage capacity. The technical and economic feasibility of using such
solutions have been considerably improved in recent years. It should be noted that the
increased water flow can be critical to the rehabilitation method that can be used, and
thus the expense.
6.3.5 Overflow
In combined systems overflow or spillways are often installed to prevent the water level
in the drainage system from exceeding a certain level which protects areas from
flooding as well as ensures that only the designed volumes of water are conveyed
through the system. Overflow discharges across a weir to basin, outlet pipe or recipient.
To ensure the same hydraulic functionality at the overflow structure during higher
inflow and constant outflow, it will be required to increase the width of the weir crest or
lower the weir crest level. The latter will, however, have the unfortunate consequence
that the number of overflow increases.
To ensure the best hydraulic function of an overflow structure, i.e. ensuring that most
water flows through the structure without an increase in the backwater, the weir
structure can be equipped with movable weir, dynamically controlled crest level or a
moveable flap. This can also maximize the basin effect in the upstream drainage system.
Sizing of basins in combined systems can be made from the discharge capacity of the
basin and selected return period of overflow. There are formulas in Guide 26 to
determine the required volume of the basins, but it is recommended that updated rain
series are used and in addition the effect of climate change incorporated. A subsequent
calculation is undertaken with historical rain to verify the function of the basin.
Basins in separate storm water systems can often be engaged in recreational areas and
therefore have other functions than just smoothing the runoff. In this case the size of the
basins may be determined by the permissible water level variation, i.e. of requirements
to retention time limits. The retention time may not be too short because it gives too
little withdrawal of substance, and it must not be too long as it can cause excessive
algae growth in the basin/pond. This type of basins may also be recommended because
they are often very flexible to increased inflows partly because overflows due to the
location do not cause major damage.
It could be considered at the planning stage that newly paved areas can serve multiple
purposes, so that planned activities in this area are not harmed by water depths of
approx. 5-10 cm in the area during extreme rainfall in a short period.
Managing storm water on their own land without drainage to the combined drainage
system may therefore be recommended primarily for environmental reasons and in
order to recharge groundwater. When looking at the hydraulic balance, these
constructions are not the solution, but a complement to climate adaptation.
There are several methods that can be used by landowners if they want to reduce storm
water discharge to the public system:
Infiltration of rainwater
This refers to the diversion of rainwater into fascines on the site. Infiltration requires
adequate soil conditions. Fascines are often designed in a size equal to 20-30 mm of
rainfall, but no certainty exists that the complete capacity is available when the rainfall
starts.
Rainwater barrels
By collecting rainwater in rain barrels a reduction in the discharge to the drainage
system is obtained and water consumption is reduced in cases where the water replaces
the standard drinking water supply used e.g. for garden watering. The volume that can
be collected is often very limited, 200-500 l is often seen, and this is only a modest
proportion of the volume of extreme rain on a roof. Rainwater barrels can be full at the
start of the rainfall and therefore not reduce runoff at all.
Reuse of rainwater
Use of rainwater in homes as a substitute for water supply has only been implemented
in a few places, but has the same advantages as rain barrels and the further advantage
that consumption - as opposed to irrigation - is more evenly distributed over time. A
major drawback is also here that the storage capacity is limited and therefore there is no
guarantee that systems can store water during critical situations.
In Rørcentrets guidance "Use of rainwater" the use of a tank of 3 m3 for such plants is
recommended, and it is estimated that a tank like this will be able to store a large part of
the annual precipitation to be used in the dwelling for toilet flushing and washing
machines. In connection with extreme rainfall an overflow is required to divert water,
since a 5 year storm event alone requires at least 7.5 m3 for a single-family house. Re-
use of rainwater should be in regulatory guidelines (see EPA guidelines and Rørcenteret
guidelines).
Green roofs
Techniques have been developed for using the so-called green roofs, where a grid of
growth layers in which plants can grow, are laid out on the roofs of buildings. The aim
is to store the water fallen on the roof in the growing layer where it is absorbed by
plants. However, the storage ability of the growth layer is limited, only 6-10 mm, so the
storage effect during extreme rainfall is limited. However, on an annual basis a quite
good effect can be achieved in terms of reduced inflow to drainage systems.
Green roofs can therefore only be recommended for reasons of aesthetics and have very
limited effect on the hydraulic system in the event of rain.
It is estimated that water in the urban environment will help to increase the recreational
value. Water storage in the urban environment will often require a landscape design that
involves green areas and thereby achieve positive side effects such as cooler urban areas
in summer and greater recreational value.
Projects in Odense and Copenhagen have shown that a solution based solely on local
infiltration is probably not sufficient, both because of increases in the groundwater table
and required space for creation. It will need additional measures such as storage of
rainwater in the terrain for which modeling is required. In Odense a contingency plan
has been established for handling rainwater at Sports Park.
Figure 6.10: Relief channel to reduce flooding at Sports Park in Odense, established in 2008.
Preparedness involves a wide range of activities and assessments that can protect assets
and people from damage caused by water. The contingency plans should of course
contain important phone numbers and other important administrative information, but in
this report only the hydraulic aspects of preparedness will be discussed.
Preparedness can be divided into before, during and after because the state of
emergency must be investigated and planned before it occurs, actions may be required
during the emergency situation and there will be an evaluation after the event where the
experience will be evaluated and possibly incorporated into new updated contingency
plans.
Contingency plans are plans which are used by municipalities to respond to overloads to
urban drainage system and water surcharges to terrain, and they include:
Once contingency plans have been established for a large area, e.g. a municipality or a
region, priorities for all catchment areas in the region should be set. This must be done
before a critical situation occurs, because there might not be sufficient personnel and
equipment available to implement the effort in all catchments at once. A prioritized
contingency plan would be a good decision support tool for incident management team.
The hierarchy of plans can be implemented using the same principles as the
prioritization of climate change adaptation.
The embankment at Godsparken is not expensive in construction and ensures not only
against extreme long term rainfall, but also against extreme water levels in the ocean.
Figure 6.13: Sample proposals for mobile emergency response in combination with online measurement.
Figure 6.14: Mobile Pump used at Greve Gymnasium during extreme rainfall in Greve on 5th July 2010.
Warning
It is essential that the municipality and wastewater utility is warned about possible
adverse events that should be acted upon. Meanwhile, it is also appropriate that citizens
are warned that flooding is expected and adviced to secure personal belongings. .
A number of meteorological institutes forecast heavy rainfall events today, but the risk
of subsequent floods in cities are often based on experience. This is inadequate because
local conditions in the urban drainage systems determine if flooding occurs or not.
Alerts are currently used in selected locations abroad to reduce costs associated with
flooding. Can the urban drainage system for instance be partially emptied until rain
Some floods are acceptable if people are informed in a timely and appropriate manner
about how to behave. However, this requires that the municipality is in possession of an
appropriate action and contingency plan that can be executed when an extreme rainfall
is warned. If an analysis shows that there will be flooding in an area under future
climate change conditions which are not acceptable, then it will take some time from the
analysis is performed until new infrastructure is built. In this period a warning is useful.
When the warning comes into force, it is important that the wastewater utility has a
communication channel set up through which information to the citizens about the
measures affecting them can be communicated. Before the emergency situation occurs,
citizens must be aware of how to seek information: Website, radio or similar.
Existing storage basins, canals, streams, rivers and lakes that can be drained
before the emergency situation arises, ensuring an optimum volume available in
the systems.
How soon operational staff can be warned so they are ready to implement
contingency plans
Existing grates, outlets, non-return valves, etc. are reviewed to ensure that they
are fully operational before the rainfall occurs.
A control strategy could be developed when a sufficient understanding of how the urban
drainage system functions are available. The coupled models described in Chapter 4
may be useful to provide an overview of where it is appropriate to control the water, e.g.
by implementing gates or pumps. The analysis may have identified a critical area where
it may be useful to store water upstream by flooding less critical areas. By applying on-
line meters at strategic locations in the urban drainage system, gates or pumps can be
controlled by set points and be in operation at the right time. Additional storage can be
created by emptying existing ponds, canals, rivers and lakes before the situation arises.
After a flood event very detailed knowledge of what exactly happened during the
incident is required.
Control
The control is implemented before the incident as outlined in the plans.
Operating experience
It is valuable to compare experiences with expectations and conclude if flooding is
caused by operational problems or lack of capacity in the urban drainage systems.
The Climate Cookbook is an update of the previous edition from 2007 and contains the
status of knowledge on climate change that has been reported from the Danish state and
recommended for use when calculating the risk of flooding from the sea in the cities. In
regard to calculations of the effects of changes in precipitation, it is recommended to
use the recommendations in the Guidelines published by the Wastewater Committee of
the Danish Engineering Association.
Methods for analysis of flooding and flood risks in cities from both the rainfall as well
as the sea is described in the report. The methods are differentiated from the very simple
GIS method to the most advanced hydraulic model that includes several elements in the
hydraulics of the drainage system.
The calculation methods are used in many contexts to assess interventions against
flooding due to climate change. It includes examples from Greve and Odense.
The methods described in this report are generic and can thus be used when the existing
climate scenarios is updated with new estimates of precipitation and variation in sea
level.
Providing the level of desired standard of service on runoff from cities is very important
when deciding whether to analyse climate change and especially when making very
costly decisions about specific adaptation of drainage systems. The Climate Cookbook
contains a description of service on rainwater and water conditions and a proposal for
how this can be disseminated.
The methods described in the Climate Cookbook can be used as the basis for the
preparation of risk assessments and maps, providing decision support on many different
levels and to prioritize climate adaptation efforts. It includes a description of how to
implement a detailed risk analysis of floods, how to prioritize, and finally it provides
examples of what type of solutions can be deployed at the specific climate adaptation.
In recent years, floods in cities all over The World show that there is a very real need of
having a good contingency plan of rainwater when rainfalls exceed what the systems
can handle. The Climate Cookbook is a comprehensive approach to precipitation
emergency described and given examples of contingency operations "before, during and
after" extreme precipitation events.
Thus, the Climate Cookbook is a guide for both technicians to conduct the tests and the
basic hydraulic work that planners must establish to inform decision makers on climate
adaptation and work with the effort against flooding in cities.
DANVA (2005)
Funktionspraksis for afløbssystemer under regn – Baggrundsrapport for Skrift 27
Domingo, N.D.S., Paludan, B., Madsen, H., Hansen, F., Sunyer, M., Mark, O. 2010.
Climate Change and Storm Surges: Assessing Impacts on Your Coastal City Though
MIKE FLOOD Modeling. 2010 MIKE by DHI Conference, Copenhagen, Denmark, 6-8
September 2010. DHI ref. 41/10
Domingo, N.D.S., Paludan, B., Hansen, F., Madsen, H., Sunyer, M., Mark,
O.”MODELING OF SEA LEVEL RISE AND SUBSEQUENT URBAN FLOODING
DUE TO CLIMATE CHANGES”. SimHydro 2010:Hydraulic modeling and
uncertainty, 2-4 June 2010, Sophia Antipolis
Domingo, N.D.S., Refsgaard, A., Mark, O., Paludan, B. “Flood analysis in mixed-urban
areas reflecting interactions with the complete water cycle through coupled hydrologic-
hydraulic modeling. IWA Publishing 2010, Water Science & Technology—WST | 62.6
| 2010.
Grum, M., Jørgensen A.T., Johansen, R.M. and Linde, J.J. (2005)
The Effect of Climate Change on Urban Drainage: An Evaluation Based on Regional
Climate Model Simulations
10th International Conference on Urban Drainage, Copenhagen, Denmark, August 2005
Kystdirektoratet, (2008)
Mark, O., Weesakul, S., Apirumanekul, C., Boonya-Aroonnet, S., Djordjević. S. (2004)
Potential and limitations of 1-D modelling of urban flooding
Journal of Hydrology
Paludan, B., Brink-Kjær, A., Nielsen, N.H., Linde, J. J., Jensen, L.N., Mark, O.
“Climate change management in drainage systems – A “Climate Cookbook” for
adapting to climate changes. Novatech, France 2010
PH-Consult (2003)
Hydrauliske undersøgelser af opland F7 i Odense
PH-Consult for Odense Vandselskab
Regeringen (2008)
Strategi for tilpasning til klimaændringer i Danmark
ISBN: 978-87-7844-720-3
Sonnenborg, T.O., Christensen, B.S.B., van Roosmalen, L., H.J. Henriksen (2006).
Klimaændringers betydning for vandkredsløbet i Danmark.
GEUS rapport.
Spildevandskomiteen (1995)
Skrift 25 - Nedsivning af regnvand - dimensionering
Spildevandskomiteen (1999)
Skrift 26 - Regional variation af ekstremregn i Danmark
Spildevandskomiteen (2006)
Skrift 28 – Regional variation af ekstremregn i Danmark – ny bearbejdning (1979-
2005)
Spildevandskomiteen (2008)
Skrift 29 – Forventede ændringer i ekstremregn som følge af klimaændringer
© DHI 2012
C.1 Appendix C. Odense – Sports Stadium
C.1.1 Terrain regulation at Odense Stadium
The new sports centre of approx. 1,400m2 at Odense Stadium has been flooded three
times since its completion in 2005, most recently on 30-06-2007. Photos from one of
the flooding events are shown in Figure C.1.
In the following a 2-D model is applied for simulation of surface run-off resulting from
water held back in the sewage system. Calculations are made on the flooding events
on 13th and 18th August 2006 together with a 100 years’ CDS rainfall, and calculations
with suggested solutions based on terrain adjustment are made.
If the rainfall event on 13th August is compared to the historical rainfall series (standard
national rain series) it is found that the rainfall event is T = 5-7 years for high
intensities, up to a variation of approx. 15 minutes. In this connection it should be
mentioned that precipitation in August 2006 was record-breaking. From 1st August to
13th August precipitation was 78.2 mm, of which 42 mm fell on 11th August. On 13th
August the drainage system in the Sports Stadium has obviously still been draining off
water from the event on 11th August. The water level in the Bolbro trench has probably
also been higher than normal, also due to a high groundwater level.
On 17th August 17.8 mm rain fell in 28 minutes. Highest intensity was 30 µm/s. The
rain was a 4-year rainfall event for 5-minute intensities, but a 2-year rainfall event for
10-minute intensities, i.e. a less intense rainfall than the one on 13th August, however, it
did result in damages in the form of flooding.
Drawing material of the drainage of the Sports Stadium has been received from
Odense Vandcenter and it shows the following, see figure c.2:
© DHI 2012
Drainage to the rain water system:
The whole area around the sports hall drains surface water to the rain water pipe.
The new athletic facility probably also drains to the ø1000 rain water pipe.
Ice stadium and skating hall discharge surface water to the ø1000 rain water pipe.
The cabin house in the biking stadium also discharges to the ø1000 rain water pipe
via a ø300 pipe under Møllemarksvej
According to municipal information four drainage pipes are connected to the rain
water pipe in the Sports Stadium. There are probably also a number of connections
upstream. Presumed drainage volume to the rain water pipe is 20-30 ha.
© DHI 2012
Figure C.3 shows the sewer system around the Sports Stadium. The blue line is a
ø1000 rainwater pipeline discharging to the Bolbro trench. The pipe starts in Ole
Worms Gade and receives overflow water from the combined system in the wells
marked with a red circle (wells J50O025 and J51F16X).
Figure C.4 shows a MOUSE model and surface (elevation conditions) for the area
around the Sports Stadium.
Odense
Idrætspark
© DHI 2012
C.1.2 Design assumptions
The calculation tool MIKE FLOOD is used as a link module between the programs
MOUSE (sewer system), MIKE21 (surface 2D) and MIKE11 (streams etc.). The last-
mentioned can be left out and is not applied in the following. Configuration of these
programs is made individually. MOUSE and MIKE21 are executed simultaneously from
the link module MIKE FLOOD. A time interval of 2 seconds is applied, resulting in a
running velocity of the models, cf. surface extract figure C.4, of approx. 5-6 hours per
real hour (2.6 GHz Pentium).
Inlet hydrographs and the sewer system is calculated in MOUSE. The model applied
has been supplemented with drain pipes and other pipes in the area around the Sports
Stadium, among others drainage systems have been established under the football
stadium (Fionia Park) and the athletic field. This information stem from sewage plans
received.
For calculation of existing conditions precipitation data from SVK rain gauge 28181,
Bolbro Waterworks, have been applied due to its geographical location relative to the
Sports Stadium.
The terrain model is supplied in DVR90, and therefore all levels in the MOUSE model
has been converted from DNN to DVR90, cf. section 1.2.2.
Data basis for calculating surface flows is a so-called digital terrain model (DTM).
Contrary to DTH (digital height model) DTM does not include roads, houses, etc. The
DTM applied is based on a 5 m grid where the height uncertainty is 35 cm. The
reference system is System34/DVR90. Appendix A is an extract from the DTM model
in the Sports Stadium area. The figure shows the density of ground levels which form
the basis for the MIKE21 calculations.
The interpolation between height levels results in the terrain being levelled out, e.g. on
the soccer and athletic fields. Therefore, the terrain levels have been manually
adjusted to match the actual conditions.
The MIKE21 model is set up in a j,k-system with a chosen grid size of 4 metres rotated
50.650 relative to the MOUSE model, in order that among others relevant roads
(Møllemarksvej and Højstrupvej) are placed approximately parallel between the axis of
the j,k-system. This is the most appropriate method since the flux between the grid
points can only take place parallel to the j or the k axis. The surface covers an area of
1.448 m x 1.140 metres corresponding to 362 j-points and 285 k-points. The grid size
of 4 metres is chosen partly due to the solution of the digital terrain model, partly in
consideration of the calculation velocity.
Roads, houses and other sealed areas appear as shape files (ArcGIS). The shape files
are converted and exported to the terrain model in MIKE21. Roads and sealed areas
are digitised separately in ArcMap prior to export, since the items do not appear as
closed polygons (areas). Roads and other sealed areas are imported into the terrain
model deducting 20 cm, and houses are raised by 3 metres compared to the terrain
model.
© DHI 2012
Figure C.5 Surface of the area surrounding Odense Sports Stadium. The map is turned as the extract in
figure C.4
On 13th August 40.6 mm precipitation within 4 hours and 50 minutes was registered by
rain gauge 28181 at Bolbro waterworks. 30-40 cm water was observed in the new
gymnasium, 10 cm water in the club rooms of the ice skating stadium, and 30-40 cm
water in the locker and storage room of the athletic field.
Figure C.6 shows a snapshot at 16:16 (GMT), where the water depth in front of the
entrance to the gymnasium is calculated to 35-40 cm (yellow colour). This is the max.
water depth in front of the gymnasium, and it corresponds more or less to the
observation mentioned above. The rainfall started at 11.11 (GMT), i.e. the max. water
level is found approx. 5 hours later.
It should be noted that the new sports hall (gymnasium) established in 2005 is not
included in the aerial photo, however, it has been added to the surface.
© DHI 2012
Figure C.6 13/8 2006. Status calculation with data from rain gauge 28181 Bolbro waterworks. Water
depths at 16:16 GMT are shown.
On 17th August 17.8 mm precipitation within 28 minutes was registered by rain gauge
28181 at Bolbro waterworks. The rainfall started at 12:23 (GMT). The result was
basically the same as on 13th August, however, the max. water depths were a little bit
smaller. Figure C.7 shows the situation at 13:03.
Figure C.7 17/8 2006. Status calculation with data from rain gauge 28181 Bolbro waterworks. Water
depths on 17th August at 13:03 GMT are shown.
© DHI 2012
A calculation with a 100 years’ CDS (Chicago Design Storm) rainfall with a duration of
2 hours has been made. This results in a max. intensity of 61.4 m/sec (3.7 mm/min)
and a rainfall depth of 48.9 mm, cf. figure c.8.
RAINFALL [my-m/s] CDS100år
60.0
55.0
50.0
45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0
The rainfall results in water depths in the area in front of the sports stadium of up to 70
cm and water depths at the athletic field of approx. 50 cm.
Figure C.9 100 years’ CDS rainfall. Water depths 1 hour and 35 minutes after the rainfall started are
shown.
© DHI 2012
C.1.4 Suggested solution
The height difference between the floor level and the athletic field grass is approx. 2
metres. This could be used to establish a trench or a canal with an average gradient of
6.4 per mille and with outlet in a yet to be determined place in the area surrounding the
athletic field which is the lowest point in the area (level 6.85 DVR90). The distance from
the front side of the sports stadium to the athletic field grass is approx. 300 metres. In
this way the athletic field is used as storage capacity. After this the area is trained to
the Bolbro trench. Dikes must be established in some places to keep water away from
the buildings, among others the ramps at the ice skating stadium, the facilities at the
athletic field and other facilities where water may enter.
The proposal of the municipality increases the recurrence interval for flooding of the
sports hall floor from approx. 1-2 years to less frequent than every 5 years. The
proposal can be optimised by choosing a surface with less resistance (concrete
slapping), a more steep gradient at the start before the profile narrows at the corner
around the sports hall, and a wider profile along the wall of the sports hall towards
north-west. The final canal is shown in figure C.11. The canal has been in use twice
and has prevented flooding of the sports hall.
© DHI 2012
Figure C.11 Photos from the area after terrain regulation.
© DHI 2012
APPENDIX B
Climate Cookbook for DANVA – Appendix B D.1 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
D.1 Appendix D. Climate Analysis for Greve Midt and Karlslunde
D.1.1 Introduction
On 1st August 2002 Greve centre received a rainfall event of 100 mm in three hours.
The incident caused damaging flooding at the city hall and high school. The rainfall
event is estimated to be an event that statistically occurs less than every 500 years.
On 3rd August 2002 the same area received another rainfall of 30 mm, which became
detrimental because all storage capacities and volumes within the municipality were
filled from the previous rainfall.
Since this incident Greve Municipality has focused on optimizing the operation of the
storm water systems and ensuring that the desired standard of services is met and
staying on top of problems before they occur despite the fact that it is beyond what is
required through the desired standard of services.
Greve Municipality has chosen to use many resources to improve the operation of the
storm water system when it became clear that it is not a question of whether there will
be extreme rainfall events, but rather when they will occur. It is indifferent to Greve Mu-
nicipality whether the more frequent extreme rainfall events are due to climate change
or not.
In August 2002, the centre of Greve was hit hard as the centre of the rainfall event was
just above Greve centre where the city hall and gymnasium are located.
At that time it was not clearly stated who was responsible for doing what, i.e. who
would be responsible for pumping when and where. In the hindsight it would have been
helpful to have identified who should do what in such an extreme rainfall event. The
centre of Greve is therefore used in this case, as it illustrates how the overloading of
drainage systems can be analysed.
The drainage system in the centre of Greve has a separate sewer system. All storm
water drains to a main storm water channel called Streget, which drains into the Bay of
Køge via a gravity outlet with invert level in Streget in elevation 0m DNN. Additionally to
this there is a combined sewer outlet and a pump which in 2005 was upgraded to pro-
vide 1 m3/s and is controlled by the water level in the Streget. In this case the focus is
solely on the separate storm water system.
The Greve Utility works currently on upgrading the storm water system in the centre of
Greve, so it fully meets the new desired standards of services for newly built drainage
systems. This case describes the solutions being applied to achieve functional re-
quirement and focuses on describing the damage that can be expected if no action is
taken on the system and what actions can alleviate some of the problems occurring
during extreme rainfall events.
During the period 2003 to 2007 Greve Municipality worked on getting a good under-
standing of the physical conditions in the drainage systems through the use of continu-
ous measuring systems, where water level, velocity and rainfall data were measured
simultaneously in different catchments. The measurements were used for calibration of
hydraulic models, analysis of the operational situation and to some extent to alert risks
of flooding. In this case, possible warning systems for Greve will be described.
Climate Cookbook for DANVA – Appendix B D.2 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
The model used in this case is covering the storm water system upstream the high
school and has been calibrated using the water level, velocity and rainfall gauges. In
the case study urban climate cook book concept is applied.
At DTU's Department of Environment & Resources they have in some projects calcu-
lated the increase which climate models predict for extreme rain events (repetition pe-
riods of 5 and 10 years). For climate scenario A2 it is found that for these repetition pe-
riods increases in rainfall depth of approx. 20-50% can be expected. However, the
modelling does not show that a different intensity distribution of precipitation is fore-
seen. It is therefore believed that the increase in precipitation is best recognized by a
factor (climate factor) of rain as the ones used today. Due to the uncertainty about cli-
mate change it has been decided in Greve to use a climate factor of 1.2. In addition,
the MOUSE model for Greve is partially calibrated, and this is why a model uncertainty
of 20% is chose, i.e. the total factor on future CDS rain is 1.44. A current and a climate
projected 10-year CDS rain (including model uncertainty) for Greve seen in Figure D.1.
Climate Cookbook for DANVA – Appendix B D.3 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
60
50
Regnintensitet (my meter/s)
40
20
10
0
0 50 100 150 200 250 300 350 400
Tid (minutter)
Figure D.1 Present design and climate projected 10-year CDS rainfall for Greve. Time step = 1 minute.
Climate factor = 1.2. The climate projected rainfall is based on scenario A2.
Climate Cookbook for DANVA – Appendix B D.4 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
D.1.4 Development in meeting functional requirements in Greve
Greve municipality is interested in analysing the development of how the sewage sys-
tem meets the present functional requirements under the influence of climate changes.
In order to prioritise initiatives made on the sewage system, the time-related develop-
ment in climate changes is simulated by linear extrapolation of a 10-year CDS rain and
the water level in Køge Bay for climate scenario A2. This results in the following simu-
lations:
This means that problem identification is made first by running ordinary MOUSE pipe
calculations and identifying flooded places. Since the terrain is not described in the
most common MOUSE models, the indicated flooding depth is only indicative. The re-
sult of the four simulations is shown in Figures D.2 to D.5.
130600.0
130500.0
130400.0
130300.0
130200.0
130100.0
130000.0
129900.0
129800.0
129700.0
129600.0
129500.0
129400.0
129300.0
129200.0
129100.0
129000.0
128900.0
128800.0
128700.0
128600.0
128500.0
128400.0
128300.0
128200.0
128100.0
128000.0
127900.0
127800.0
127700.0
127600.0
-92500.0 -92000.0 -91500.0 -91000.0 -90500.0 -90000.0 -89500.0 -89000.0 -88500.0 -88000.0
[m]
Figure D.2 Indication of flooding depths i.e. places where the drainage system will run into problems to-
day for a 10-year rain. Input 10-year CDS rainfall.
Climate Cookbook for DANVA – Appendix B D.5 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
[m] FLOOD Meter - Maximum 10y6h_10%.PRF
130700.0
130600.0
130500.0
130400.0
130300.0
130200.0
130100.0
130000.0
129900.0
129800.0
129700.0
129600.0
129500.0
129400.0
129300.0
129200.0
129100.0
129000.0
128900.0
128800.0
128700.0
128600.0
128500.0
128400.0
128300.0
128200.0
128100.0
128000.0
127900.0
127800.0
127700.0
127600.0
-92500.0 -92000.0 -91500.0 -91000.0 -90500.0 -90000.0 -89500.0 -89000.0 -88500.0 -88000.0
[m]
Figure D.3 Indication of flooding depths, i.e. places where the sewage system in 10 years will have
problems for an extrapolated 10-year rainfall. Input: 10-year CDS rainfall and water level in
Køge Bay extrapolated for climate scenario A2.
[m] FLOOD Meter - Maximum 10y6h_25%.PRF
130700.0
130600.0
130500.0
130400.0
130300.0
130200.0
130100.0
130000.0
129900.0
129800.0
129700.0
129600.0
129500.0
129400.0
129300.0
129200.0
129100.0
129000.0
128900.0
128800.0
128700.0
128600.0
128500.0
128400.0
128300.0
128200.0
128100.0
128000.0
127900.0
127800.0
127700.0
127600.0
-92500.0 -92000.0 -91500.0 -91000.0 -90500.0 -90000.0 -89500.0 -89000.0 -88500.0 -88000.0
[m]
Figure D.4 Indication of flooding depths, i.e. places where the sewage system in 25 years will have
problems for an extrapolated 10-year rainfall. Input: 10-year CDS rainfall and water level in
Køge Bay extrapolated for climate scenario A2.
Climate Cookbook for DANVA – Appendix B D.6 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
[m] FLOOD Meter - Maximum 10y6h_100%.PRF
130700.0
130600.0
130500.0
130400.0
130300.0
130200.0
130100.0
130000.0
129900.0
129800.0
129700.0
129600.0
129500.0
129400.0
129300.0
129200.0
129100.0
129000.0
128900.0
128800.0
128700.0
128600.0
128500.0
128400.0
128300.0
128200.0
128100.0
128000.0
127900.0
127800.0
127700.0
127600.0
-92500.0 -92000.0 -91500.0 -91000.0 -90500.0 -90000.0 -89500.0 -89000.0 -88500.0 -88000.0
[m]
Figure D.5 Indication of flooding depths, i.e. places where the sewage system in 10 years will have
problems for an extrapolated 10-year rainfall. Input: 10-year CDS rainfall and water level in
Køge Bay extrapolated for climate scenario A2.
After having made a problem identification, the extent of the flooding must be quantified
and damages assessed. For quantification of flooding a digital terrain model is set up to
be used as surface model for MOUSE/MIKE URBAN. To illustrate the method it has
been chosen to focus on the area at Greve High School and Greve Town Hall, i.e. the
two areas which were struck by flooding in 2002. As it appears from Figure D.2 a great
deal of flooding is expected in this area for a 10-year CDS rainfall today. The combined
MOUSE and hydrodynamic surface model (MIKE FLOOD) are used to calculate the
flooding in detail. Figure D.6 shows that flooding (of up to 33 cm at the high school) can
be expected in 10 years, if climate changes follow climate scenario A2. Please note the
uncertainty factor of 20%. Figure D.7 shows the calculated flooding depths for climate
scenario A2 in 100 years. It is seen that climate changes are now expected to cause
flooding of up to 83 cm at the high school. A comparison of the calculated distribution
of flooding for a 10-year rainfall at Greve High School in 10 years and 100 years re-
spectively is shown in Figures D.8 and D.9. It is seen that the development in a 10-year
rainfall and in sea water levels gives rise to more extensive flooding, which is expected
to further increase over time.
In the present situation (today’s 10-year rainfall) no safety factor is applied in the area,
since the model is calibrated for the present situation. For the future situation with cli-
mate changes and e.g. extension, a safety factor of 1.2 is applied.
Climate Cookbook for DANVA – Appendix B D.7 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
Thus, the above calculation reflects the function of the sewage system in two fields:
1) Development in fulfilment of the functional requirement, and 2) Conditions under ex-
treme events where the design precipitation and water level in Køge Bay has been ex-
ceeded. It will be 2) which will form the basis of a decision-making as to how to react in
case of very extreme events where the sewage system cannot and is not expected to
be able to handle the rain water. A solution could be warning systems utilizing the ex-
isting systems more efficiently in order to minimize damages and lead the water to
places where it is less damaging, e.g. green areas.
Figure D.6 Max. flooding depths calculated for a 10-year CDS rainfall extrapolated by 10 years. Input:
10-year CDS rainfall and water level in Køge Bay extrapolated for climate scenario A2.
Today, Greve municipality has quite a lot of digitalised information on the infrastructure.
This information is among others found in the GIS system of the municipality, making it
possible to easily estimate the extent of damages under the designed conditions. Im-
portant information on infrastructure in relation to flooding could be: Supply boxes
(boxes placed at all cadastres); fiber point (junction box with optical fibres); stations
connecting supply boxes; buildings with basements; public buildings and environmen-
tally heavy industrial companies. Examples of comparisons of the municipal GIS data
with designed flooding are shown in Figure D.8. Among other things it is seen that the
flooding in the area around the town hall is expected to develop from a scenario with
quite a lot of water in the streets to a scenario with flooding of a child care centre. At
the same time it is seen that the service station will be flooded already in 10 years, and
therefore the consequences of a flooding like this should be taken into account.
Climate Cookbook for DANVA – Appendix B D.8 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
F
Figure D.7 Max. Flooding depths calculated for a 10-year CDS rainfall, extrapolated by 100 years. In-
put: 10-year CDS rainfall and water level in Køge Bay extrapolated for climate scenario A2.
Figure D.8 Yellow/brown colour indicates flooding calculated for a 10-year CDS rainfall, extrapolated by
10 years. Rosy/pink colours show flooding calculated for a 10-year CDS rainfall, extrapolat-
ed by 100 years. Input: 10-year CDS rainfall and water level in Køge Bay extrapolated for
climate scenario A2.
Climate Cookbook for DANVA – Appendix B D.9 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
D.1.5 Alternative solutions to reduce damages from flooding in Greve
Immediately behind the town hall and the high school there is a football field belonging
to the high school. During the flooding in 2002 this area was not flooded, because it is
at a higher level than the high school and town hall. Figure D.9 shows the football field.
Figure D.9 Football field behind Greve High School which could be used for storage of rain water during
extreme rainfall.
Since a mound has already been established around the football field, it was investi-
gated whether it is possible to close the mound completely and then use the football
field as rain water basin during extreme rainfall. If so, water from the sewage system
will be pumped to the football field. Two pumps were added to the sewage system
model, each with a capacity of 0.5 m3/s. Furthermore, in the terrain model 1.2 metres
have been digged from the whole surface of the football field in order to obtain extra
basin volume during extreme rainfall.
The result of the calculation shows that the extent and depths of the flooding is heavily
reduced. Figure D.10 shows that the max. water depth in the terrain outside the high
school has been reduced from approx. 83 cm to 17 cm. Furthermore, the extension of
flooding in the area has been heavily reduced, cf. Figure D.9. In this figure it is also
seen that the utilisation of the football field for storage of water has the additional effect
that the tank station and child care centre are no longer flooded in the climate scenario.
It should be noted, however, that the quality of the football field after a possible excava-
tion of 1.2 metres of soil has not been tested in the project. In order to secure the high
school in a situation as mentioned above, the curb in front of the school entrance must
be increased by approx. 20 cm.
Climate Cookbook for DANVA – Appendix B D.10 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
3
Figure D.10 Blue/purple colour indicates flooding after installation of two 0.5 m /s pumps and utilisation
of the football field as rain water basin. The red colour shows the extent of flooding before
installation of the two pumps. Input: 10-year CDS rainfall and water level in Køge Bay ex-
trapolated for climate scenario A2.
Climate Cookbook for DANVA – Appendix B D.11 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
3
Figure D.11 Max. water levels after installation of two 0.5 m /s pumps and utilisation of the football field
as rain water basin. Reference calculation is shown in Figure D.6. Input: 10-year CDS rain-
fall and water level in Køge Bay extrapolated for climate scenario A2.
A relatively quick analysis of the ”direct effect” of increased sea water level on a coastal
municipality like e.g. Greve can be made with advantage. “Direct effect” means the
possibility of backwater from the sea to urban areas in the event of extreme high wa-
ters.
In Greve municipality a GIS analysis has been performed, where the terrain level at all
cadastres in the city have been compared to the existing extreme water level and the
future level (estimated to be 0.5 metres higher, which is probably a little lower than
what can be expected, since changed wind patterns will lead to increased storm surg-
es). Figure D.12 shows the recurrence intervals for the water level at Drogden Light-
house, which has turned out to be representative for Mosede Habour in Greve. It is
seen that a 10-year event corresponds to a water level of approx. 1.3 metres.
Climate Cookbook for DANVA – Appendix B D.12 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
Figure D.12 Recurrence interval for max. water level at Drogden lighthouse, data from 1992-2002.
In the existing situation the GIS analysis shows that 165 cadastres are situated below
this water level and thus potentially threatened in the event of extreme high waters. If
the level is increased to 1.8 metres (1.3 + 0.5 metres) the number of potentially threat-
ened cadastres is increased to 1,179, cf. figure D.9. This analysis can be extended to
include also cadastres including houses with basements, levels to ground floor, etc.
Climate Cookbook for DANVA – Appendix B D.13 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012
Figure D.13 Number of cadastres lying below sea level today and under future climate changes due to
increase in extreme water level in Køge Bay.
Whether in the future there will be a convergence between extreme water level and ex-
treme rainfall cannot be predicted at present. However, in order to clarify conditions in
the sewage system it is a very relevant analysis which should be performed. Under the
existing conditions there is no convergence between extreme rainfall and extreme wa-
ter level in Køge Bay.
D.1.7 Summary
This example shows how you can extrapolate climate rainfall and analyse the sewage
system as to where problems may arise, and how you can quantify the extent of the
flooding and potential damages.
Climate Cookbook for DANVA – Appendix B D.14 Greve Forsyning, VandCenter Syd, PH-Consult and DHI
© DHI 2012