Inspection Request For Installation and Leak Test of Under Ground Drainage Pipes, As Per Attached Highlighted Drawing

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 1

WORK INSPECTION REQUEST - WIR

Construction of Townhouses & semi-detached Villas


Project Name
(412) for Phase 1B & 1C WIR Ref.No: RHP1P2-BW-TGC-4TV-00-WI-DR-00019

Contract No
Request Submission
Employer Reem Hills Sole-Proprietorship LLC 25-Jun-24
(Date & Time)
PMC Royal Development Company Inspection 26-Jun-24
PMC Royal Architect Project Management (Date & Time ) 11:00AM
Engineer AECOM Middle East LLC Rev No: 0
Main Contractor Trojan General Contracting LLC WIR Submitted By: M/s.TROJAN

MEP Contractor Royal Advance Electro Mechanical Works LLC WIR Submitted To: Consultant-AECOM

Part A: By the Contractor:


B.O.Q Ref: N/A Discipline:
B.O.Q. Description of Works to be inspected and / or tested: General MCC Works
Civil Landscaping
Storm Water Architectural
Description of Works to be inspected and /or tested: Sewer Dredging
Water Highway Bridge Works
Irrigation LRT Bridge Works
Inspection Request for Installation and leak test of Under Telephone MSE Wall
Signal Works Provisional Sum
Ground Drainage Pipes , As per Attached Highlighted Drawing
Electrical Other (state)
Street Lighting
Works Location: Villa-369 4BR (Mirror) Landscape Lighting Drainage

Works Quantity: Gas Network

Drawing attached to show the location(s) Yes No Checklist attached Yes No


Attached Test Certificates Yes No

Shop Drawing Ref: PHP1P2-BW-TGC-4TV.M-00-SD-DR-0001 Method Statement Ref: RHP1P2-BW-TGC-ZZ-XX-MS-ME-00002_00

Type of Attachment: Check list ITP Ref: ITP-01-Rev-0

Eng. Dayal Pushpakumar


(QA/QC Manager )

Date & Signature


Part B: By the Engineer:
Received by Engineer on: Date: Time: Signed by:
Engineer's Comments:

1.Inspection has been done with respect to the grid lines provided by contractor surveyor.
2.Provide adequate supports to avoid torsional stress and fully restrict the pipe dislocation
during civil works. Avoid resting the structural rebars/other loads directly on top of pipes
(pipe shall be laid load free).
3.The works at site is done in absence of approved floor tiling layout. Contractor will remain
responsible for any modification, at no extra time/cost to the project, if the piping is not
matching as per the latest approved respective tile layout drawings..
3) FD depths are reduced to 400 MM from FFL.
Above changes are to be reflected in As built drawings
Only Highlighted area offered for inspection.Remaining works inside
kitchen and outside the tie beams shall be completed later.

No Leak found.No objection for proceeding with following activities.

Name: Date & Signature


Discipline Engineer Decision:
A - Approved

B - Approved with comments 26-06-2024


C - Revise & Resubmit

D - Rejected

Sr.Resident Engineer / Resident Engineer :

Name : Suheib Aboamir 27/06/2024


Date & Signature