Coordination with Local Officials (includes signing of MOA, Jan 2022 Jun 2022
meetings on barangay boundaries, endorsement of Mayors, IEC)
Preparation of status report on the CBMS operations Aug 2022 Sep 2022
Data Processing at the PSA Provincial Offices (includes data 26 Sep 2022 07 Oct 2022
validation and field verification)
Certification pass (ID validation, completeness check and 03 Oct 2022 21 Oct 2022
machine edit) at the Provincial Offices (POs)
Submission of clean data files by PO to the Regional Statistical 24 Oct 2022 28 Oct 2022
Service Office (RSSO) including updated maps
Certification pass (ID validation, completeness check and 24 Oct 2022 04 Nov 2022
machine edit) of CBMS data files by RSSO