MODULE 1 Introduction To Quantity Surveying
MODULE 1 Introduction To Quantity Surveying
MODULE 1 Introduction To Quantity Surveying
Description:
This module introduces the course Quantity Surveying and its importance in Engineering Projects.
Learning Objective:
At the end of this module, the learner should be able to:
1. Gain knowledge on terminologies and principles of quantity surveying in Engineering Project.
2. Understand the importance in understanding specifications and plans/details in Engineering Project
3. Understand the role and task of a Quantity Surveyor in an Engineering Project
Contents:
I. QUANTITY SURVEYING
Quantity Surveying is broadly concerned with the estimation, planning and control of the cost on
construction projects. It covers a wide range of activities including cost estimation, cost planning, value
engineering, feasibility studies, cost benefit analysis, lifecycle costing and valuation.
• Cost Estimation
Cost estimation in project management is the process of forecasting the cost and other
resources needed to complete a project within a defined scope. Cost estimation accounts for each
element required for the project – from materials to labor - and calculates a total amount that
determines a project’s budget.
• Value Engineering
Value engineering is a systematic, organized approach to providing necessary functions in a
project at the lowest cost. Value engineering promotes the substitution of materials and methods
with less expensive alternatives without sacrificing functionality. It is focused solely on the functions
of various components and materials, rather than their physical attributes.
• Feasibility Study
Feasibility study is an assessment of the practicality of a proposed plan or project. A feasibility
study analyzes the viability of a project to determine whether the project or venture is likely to
succeed. The study is also designed to identify potential issues and problems that could arise while
pursuing the project.
• Cost-Benefit Analysis
Cost-benefit analysis is a way to compare the costs and benefits of an intervention, where
both are expressed in monetary units. The output of cost benefit analysis will show the net benefit
(benefit minus cost) of a project decision.
Quantity surveying plays an essential role in ensuring that the project is built efficiently while
keeping a close eye on the project’s finances and contractual relationships, making sure everything is
accurate and controlled effectively throughout the project’s timeline. As a result, it’s critical to understand
how it can affect the project and its overall costs.
Quantity Surveying puts order in the complicated procurement process. A quantity surveyor will
analyze the quantities, measurements, and cost of material altogether with the cost of labor and the
machinery required for the execution of the project.
Quantity surveyors estimate and control costs for large construction projects. They make sure
that structures meet legal and quality standards. Quantity surveyors are involved at every stage of a
project. Other names for quantity surveyor are Cost Engineer, Cost Manager, Estimator, Cost Analyst, Cost
Planner.
The main objective of a quantity surveyor is the efficient and effective utilization of resources
(materials, manpower, money). It also requires him to have an up-to-date information of market, tools
and equipment to help in planning and scheduling of construction activities and resource allocation.
Risk analysis is an area which should be thoroughly studied to become a successful quantity
surveyor. The quantity surveyor should be able to assess the risk involved and be able to decide whether
it should be retained or transferred.
Quantity surveyors plays an important role in contract procurement, tender evaluation and
dispute resolution. Good knowledge of construction technology is very much required for a quantity
surveyor.
B. Tendering Stage
1. Shortlisting of Vendors for Various work
2. Issue of Tender document for short listed Vendors
3. Conducting Pre-bid meeting with consultants on the queries raised by vendors
4. Collecting filled tender documents and making comparative statements.
5. Attending negotiation meetings and giving guidance on selecting of correct vendor to the client
The Invitation to Bid (IB) provides information that enables interested bidders to decide whether
to participate in the procurement of the particular contract at hand. (Annex II-1.1A)
Eligibility Requirements
Advertise and Post an Invitation to Appy for Eligibility and to Bid (IAEB)
- provides the information necessary for prospective bidders to prepare responsive applications for
eligibiity to bid for the contract in accordance with the requirements of the Procuring Entity
- For this particular contract to be procured, the Approved Budget for the Contract (ABC) is indicated
in the EDS. The required PCAB license for this project, based on Table 1 above, is also specified in
the EDS.
SPECIFICATIONS
- The DPWH Standard Specifications for Public Works and Highways (“Blue Book”) shall be the main
basis for the standards and codes to be met by the goods and materials to be furnished and work
performed or tested for the Contract. In particular,
a. Volume II of the Blue Book shall be used if the Contract pertains to Highways, Bridges and
Airports.
b. Volume III of the Blue Book shall be used if the Contract pertains to Buildings, Flood Control
and Drainage, or Water Supply.
- The Blue Book incorporates standards of the American Association of State Highway and
Transportation Officials (AASHTO), American Society for Testing and Materials (ASTM), and
American Concrete Institute (ACI), among others, pertaining to construction.
- The Procuring Entity shall use the Standard Pay Items in the Project and Contract Management
Application (PCMA) in drawing up the Specifications.
DRAWINGS
- list of approved Drawings for the Contract. The actual Drawings, including Site plans, shall be
attached or annexed in a separate folder
BILL OF QUANTITIES
- The Bill of Quantities (BOQ) contains the following parts:
a. BOQ for each Part of the Contract, using Form DPWH-INFR-17.
b. Summary of Bid Prices for all Parts of the Contract, using Form DPWH-INFR-18. In the ITB,
under Preparation of Bids, item 14.2 (b)
- Financial Component
This shall include all of the following documents:
(1) Bid Form using Form DPWH-INFR-09.
(2) Bill of Quantities (BOQ) indicating the bid prices, using Forms DPWH-INFR-17 and Form DPWH-
INFR-18. The bid prices may be in terms of (a) bid unit prices for different work items under the
BOQ, or (b) fixed total lump-sum price for the entire contract, based on the type and complexity
of the project.
(3) Detailed estimates, including a summary sheet indicating the unit prices of construction materials,
labor rates an equipment rentals used in coming up with the Bid.
(4) Cash flow by quarter (Use Form DPWH-INFR-19)
BIDDING FORMS
The Bidder shall use the Bidding Forms (BFs) listed below in preparing its Bid and, in case it is
awarded the contract, in preparing the documents required to perfect the contract.
VI. Competitive Bidding
Competitive or Public Bidding is a method of procurement that is open to any interested and
qualified party. A Procuring Entity should, therefore, see to it that its procurement program allows enough
time to conduct such Public Bidding.
The procurement process from the opening of bids up to the award of contract should not exceed
three (3) months, or a shorter period to be determined by the Procuring Entity concerned.
In case the deadline for each activity falls on a non-working day (i.e. Saturday and Sunday), legal
holiday, or special non-working holiday, the deadline shall be the next working day.
ESTIMATE
An estimate for any construction work may be defined as the process of calculating the quantities
and cost of various items required in connection with the work.
It is prepared by calculation the quantities from the dimensions on the drawings for the various
items required to complete the project and multiplied by unit cost of the item concerned.
To prepare an estimate, drawing consisting of the plan, elevation and the sections through
important points, along with a detailed specification giving specific description of workmanship,
properties and proportion of materials are required.
Construction estimating is the process of forecasting a project’s costs. However, true project costs
are only known once the project is completed.
Below shows an example of architectural plan consisting of floor plans, elevation and sections
Purpose of Estimate
The purpose of an estimate has different meaning to different people involved in the process. To
the owner, it provides a reasonable, accurate idea of the costs. This will help him or her decide whether
the work can be undertaken as proposed, needs to be modified, or should be abandoned. To the
contractor, it must provide the cost of materials and labor to install the project as well as make a profit.
Components of Estimate
1. Quantity
The measurement of something by stating how much of it there is. It is shown as a figure and a
unit of measurement behind it. Unit of measurement could be in terms of area (m2 or sq.m.),
length (m), volume (cu.m.) , weight (kg.), etc.
Example:
300 m
2. Rate
A fixed charge, payment or value. Rate is the cost built up of material cost, wastages, labor cost,
plant/equipment cost and profit and overhead.
3. Cost
An estimate how much money will be needed or price to be charged for something.
Types of Estimates
1. Approximate Estimate
Approximate estimate, also called preliminary estimate, abstract cost estimate, or budget
estimate, is used in the early phases of a project, usually before design documents have been completed.
This is made to find out an approximate cost in a short time and thus enable the responsible authority
concerned to consider the financial aspect of the scheme. During preparation of the approximate estimate
detailed surveying, design, drawings, etc. are not required.
Approximate Quantities
Items of Major
Estimated
= Cost Importance X
Cost Unit Rate
Measured only
a. Unit method – in this method all cost of a unit quantity such as per km for a highway, per meter
of span for a bridge, per classroom for school building, per bed for hospital, per liter for water
tank, etc. are considered first and the estimate is prepared by multiplying the cost per
corresponding unit by the number of units in the structure
Unit Method
b. Superficial or Square method is a type of approximate estimates wherein plinth area of a building
shall be determined first. Estimate of building is worked out and multiplied by the area of the
building with area rate of the locality for similar buildings constructed recently.
Superficial Method
2. Detailed Estimates
Detailed estimate involves breaking down the project scope into smaller unit prices that can be
priced individually. This includes the detailed particulars for the quantities, rates and costs of all
the items involved for satisfactory completion of project. Quantities of all items of work are
calculated from their respective dimensions on the drawings. Multiplying these quantities by their
respective rates in a separate sheet, the cost of all items are worked out individually and
summarized. All other expenses required for satisfactory completion of the work are added to
above cost.
Bill of Quantities
Estimated Measured
Cost = X Unit Rate
Quantities
3. Revised Estimate
Revised estimate is a detailed estimate for the revised quantities and rates of items of work
originally provided in the estimate without material deviations of a structural nature from the
design originally approved for the project. It is prepared and submitted for fresh technical
sanction.
4. Supplementary Estimate
While work is in progress, some changes or additional works due to material deviation of a
structural nature from the design originally approved may be thought necessary for the
development of a project.
SPECIFICATION
Specification is defined as a short or detail description of different parts of the work specifying
materials, proportions, quantities, etc. Specification specifies the nature and the class of the work,
materials to be used in the work, workmanship etc. is very important for the execution of the work. The
cost of a work depends much on specification.