Operation Management
Operation Management
OSCM 302
PROJECT CRASHING
PROJECT CRASHING
needrecorsec important
It is common to face the following situations:
The project is behind schedule Projecttake3yearsandyouhavetosubmited
crashed
now
The completion time has been moved forward
2
FACTORS TO CONSIDER WHEN CRASHING A
what PROJECT
mosteffective
way
We want to find the cheapest way of crashing
the project to the desired date.
3
PROJECT CRASHING AND
TIME-COST TRADE-OFF OVERVIEW
4
STEPS IN PROJECT CRASHING
5
STEPS IN PROJECT CRASHING
later
6
STEPS IN PROJECT CRASHING
7
EXAMPLE 1: PROJECT CRASHING
a) Draw the project network with Normal time. What is the project completion date? And
Cost?
b) Find the crash cost per week for each activity. crashcost whichactivityischeeper
tocrash
c) The required new due data to complete the project is 13 weeks. How much it will cost to
meet the new due date? And what is the new total cost for the project.
8
EXAMPLE 1: PROJECT CRASHING
9
EXAMPLE 1: PROJECT CRASHING
a) Draw the project network with Normal time. What is the project completion date? And
Cost?.
A C F
2 2 3
Start E H End
0 4 2 15
B D G
3 4 5
A C F
2 2 3
Start E H End
0 4 2 15
B D G
3 4 5
A C F
2 2 3
Start E H End
0 4 2 15
B D G
3 4 5
a) Draw the project network with Normal time. What is the project completion date? And
Cost?. forall
project completion date is 15 weeks, total project cost is $30,800
13
EXAMPLE 1: PROJECT CRASHING
The demand for the last seven months of Dior perfume “POISON girl”
was:
Predecessor Normal Normal Cost Crash Time Crash Crash Cost
Act Time (total) (Weeks) Cost per week
A - 2 $22,000 1 $22,750 $750
B - 3 $30,000 1 $34,000 $2000
C A 2 $26,000 1 $27,000 $1000
D A, B 4 $48,000 2 $50,000 $1000
E C 4 $56,000 2 $58,000 $1000
F C 3 $30,000 2 $30,500 $500
G D, E 5 $80,000 2 $84,500 $1500
H F, G 2 $16,000 1 $19,000 $3000
14
EXAMPLE 1: PROJECT CRASHING
A C F
Wehavetwo
criticalpath
1 2 3
Start E H End
0 4 2 14
Thereare 2things
activity
B D G 1 crashthe
common
2crashone
3 4 5
A C F
1 2 3
Start E H End
0 4 2 14
B D G
3 4 5
16
1) A-C-F-H 2) A-C-E-G-H
critical2052 5
4) B-D-G-H
Exp. Time = 1+2+3+2=8 Exp. Time = 1+2+4+5+2=14 Exp. Time = 3+4+5+2=14
3) A-D-G-H
Exp. Time = 1+4+5+2=12
16
EXAMPLE 1: PROJECT CRASHING
Predecessor
If
Normal
mn
Normal Cost
lgijfggdwddssdi0i
Crash Time Crash Crash Cost
Act Time (total) (Weeks) Cost per week
A - 2 $22,000 1 $22,750 $750
B - 3 $30,000 1 $34,000 $2000
C A 2 $26,000 1 $27,000 $1000
D A, B 4 $48,000 2 $50,000 $1000
E C 4 $56,000 2 $58,000 $1000
F C 3 $30,000 2 $30,500 $500
G D, E 5 $80,000 2 $84,500 $1500
H F, G 2 $16,000 1 $19,000 $3000
17
EXAMPLE 1: PROJECT CRASHING
A C F
1 2 3
Start E H End
0 4 2 13
B D G
3 4 4
19
EXAMPLE 2: PROJECT CRASHING
Pred.
Crash Crash Cost Normal Time Normal
Act Time (total) (Weeks) Cost
A - 4 $800 7 $500
B - 2 $350 3 $200
C A,B 4 $900 6 $500
D C 1 $500 3 $200
E B 1 $550 2 $300
a) Draw the project network with Normal time. What is the project completion
date? And cost?
b) crash cost per day for each activity.
c) Reduce the project cycle time by five weeks (Crash the network by five weeks).
And identify the new critical path.
d) Find the new cost of completing the project (after crashing).
20
EXAMPLE 2: PROJECT CRASHING
Pred. Tofindcriticalpath
Crash Crash Cost Normal Time Normal Crash cost
Act Time (total) (Weeks) Cost per day
e week
A - 4 $800 7 $500 100
B - 2 $350 3 $200 150
C A,B 4 $900 6 $500 200
D C 1 $500 3 $200 150
E B 1 $550 2 $300 250
a) Draw the project network with Normal time. What is the project completion
date? And cost? 16weeks
b) crash cost per me
day for each activity.
c) Reduce the project cycle time by 5 weeks (Crash the network by five weeks).
And identify the new critical path.
d) Find the new cost of completing the project (after crashing).
21
EXAMPLE 2: PROJECT CRASHING
criticalpath
300
2 130
ciiiijii.ee crash 2
A - 6 5 900 1,000
B - 8 6 300 400
C - 4 3 500 600
D A 5 3 900 1,200
E C 8 5 1,000 1,600
23
PRACTICE
Crash
Normal T Crash T Normal Crash
Activity Predecessor cost per
(days) (days) Cost $ Cost $
day
A - 6 5 900 1,000 100
B - 8 6 300 400 50
C - 4 3 500 600 100
D A 5 3 900 1,200 150
E C 8 5 1,000 1,600 200
24
Questions