Spec - 2019-02 - A00 - WELDING OF METALS BASED ON ISO STANDARDS
Spec - 2019-02 - A00 - WELDING OF METALS BASED ON ISO STANDARDS
Spec - 2019-02 - A00 - WELDING OF METALS BASED ON ISO STANDARDS
DEP 30.10.60.32-Gen.
February 2019
DEM1
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, published or transmitted, in any form or by any means, without the prior
written permission of the copyright owner or Shell Global Solutions International BV.
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the standard for good design and engineering practice to be applied by Shell companies in oil and
gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help
achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these
Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of
a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned
after use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................ 5
1.1 SCOPE ....................................................................................................................... 5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 5
1.3 DEFINITIONS ............................................................................................................. 5
1.4 CROSS-REFERENCES ............................................................................................. 7
1.5 SUMMARY OF MAIN CHANGES............................................................................... 7
1.6 COMMENTS ON THIS DEP ....................................................................................... 8
1.7 DUAL UNITS............................................................................................................... 8
1.8 NON NORMATIVE TEXT (COMMENTARY) .............................................................. 8
1.9 PRECEDENCE OF DOCUMENTS............................................................................. 8
2. QUALITY PROGRAM ................................................................................................ 9
2.1 GENERAL ................................................................................................................... 9
2.2 PERSONNEL COMPETENCIES ................................................................................ 9
2.3 INSPECTION AND TEST PLAN................................................................................. 9
2.4 DEVIATIONS ............................................................................................................ 10
2.5 FINAL ACCEPTANCE .............................................................................................. 10
3. GENERAL REQUIREMENTS .................................................................................. 10
3.1 WELDING PROCESSES .......................................................................................... 10
3.2 MATERIALS.............................................................................................................. 11
4. WELDING PROCEDURE PREPARATION AND QUALIFICATION ....................... 13
4.1 GENERAL ................................................................................................................. 13
4.2 PREVIOUSLY QUALIFIED PROCEDURES ............................................................ 13
4.3 PROCEDURE DOCUMENTATION .......................................................................... 14
4.4 ESSENTIAL VARIABLES ......................................................................................... 14
4.5 WELDING PROCEDURE QUALIFICATION TESTING............................................ 14
5. WELDER QUALIFICATION ..................................................................................... 18
5.1 GENERAL ................................................................................................................. 18
5.2 WELDER IDENTIFICATION ..................................................................................... 19
5.3 WELDER PRE-QUALIFICATION ............................................................................. 19
5.4 QUALIFICATION DOCUMENTATION ..................................................................... 19
5.5 TIME LIMITATIONS .................................................................................................. 19
6. PREHEATING AND POSTWELD HEAT TREATMENT .......................................... 19
6.1 PREHEATING........................................................................................................... 19
6.2 POSTWELD HEAT TREATMENT ............................................................................ 21
7. WELD INSPECTION ................................................................................................ 27
7.1 METHODS AND EXTENT OF NONDESTRUCTIVE EXAMINATION ..................... 27
7.2 TESTING QUALIFICATIONS ................................................................................... 27
8. WELD REPAIRS ...................................................................................................... 28
8.1 DEFECT REMOVAL ................................................................................................. 28
8.2 RE-WELDING ........................................................................................................... 29
8.3 NONDESTRUCTIVE TESTING ................................................................................ 29
8.4 DEFECT AND REPAIR RATE RECORDS ............................................................... 29
9. HEALTH, SAFETY, SECURITY, AND ENVIRONMENT CONSIDERATIONS ....... 29
9.1 GENERAL ................................................................................................................. 29
9.2 WELDING EQUIPMENT ........................................................................................... 30
9.3 ALIGNMENT ............................................................................................................. 30
10. MATERIAL-SPECIFIC ADDITIONAL REQUIREMENTS ........................................ 30
10.1 GENERAL REQUIREMENTS................................................................................... 30
10.2 WPQR MONITORING .............................................................................................. 30
10.3 WPQR REQUIREMENTS ......................................................................................... 30
10.4 PARAMETER MONITORING ................................................................................... 32
10.5 CMn STEELS NOT INTENDED FOR LOW TEMPERATURE SERVICE ................ 32
APPENDICES
APPENDIX A REPORTING REQUIREMENTS FOR WELDING QUALIFICATION ............. 70
1. INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for organising and managing
quality assurance (QA) and quality control (QC) for welding of metals, based on ISO
standards.
This DEP is a counterpart to DEP 30.10.60.18-Gen., which is based on API RP 582.
This DEP is written in accordance with the latest regulations in force within the European
economic area including the European Pressure Equipment Directive (PED) 2014/68/EU
and is based on the referenced standards, which cover all aspects of the design and
fabrication of pressure equipment.
This DEP recognises and builds on the expertise and good practices developed in previous
Shell specifications.
The scope of this DEP does not include pipeline or civil structural welding.
DEP 61.40.20.30-Gen., DEP 37.81.40.31-Gen. and DEP 30.10.60.30-Gen. cover pipeline
welding, and DEP 37.81.10.34-Gen. covers civil structural welding.
This DEP contains mandatory requirements to mitigate process safety risks in accordance
with Design Engineering Manual (DEM) 1 - Application of Technical Standards.
This is a revision of the DEP of the same number dated February 2017; see (1.5) regarding
the changes.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Fabricator is the party that manufactures or fabricates the equipment and provides
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
Term Definition
CI Confidence Interval
OD Outside Diameter
Term Definition
RT Radiographic Testing
UT Ultrasonic Testing
VT Visual Testing
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section or
clause number is shown in brackets ( ). Other documents referenced by this DEP are listed
in (11).
Section/Clause Change
All Restructured and clarified requirements, enforced use of
shall/should/may for normative statements.
Feedback that has been registered in the DEP Feedback System by using one of the above
options will be reviewed by the DEP Custodian for potential improvements to the DEP.
2. QUALITY PROGRAM
2.1 GENERAL
1. Welding QA/QC of equipment and piping components shall be implemented under a
Fabricator quality management system that conforms to ISO 9001 and ISO 3834 and
certified by an IVB.
2. Fabricator shall develop and maintain its quality system for welding activities based on
ISO 3834-6.
3. A welding procedure specification (WPS) shall be considered an engineering
document and is part of the detailed design of a component.
4. The applicable requirements specified in ISO 3834-5 shall be applied.
2.4 DEVIATIONS
1. Any conflicts between the requirements of this DEP and other relevant documents
shall be referred to the Principal for resolution.
3. GENERAL REQUIREMENTS
2. Gas shielded processes (GTAW, GSFCAW, GMAW, MCAW, PAW) shall be used in
the field only if adequate weather shielding that is approved by the Principal is
provided.
3. SAW systems shall be fully mechanised (automated).
GMAW or MCAW might be allowed if the Fabricator can demonstrate to the
Principal’s satisfaction, adequate experience with the processes, ongoing control
over the process, and the continued competence of the welders.
4. The root and second pass of all single-sided welds shall be made using one of the
following methods, in order of preference:
a. GTAW (preferred);
b. Subject to review and approval by the Principal: Controlled droplet transfer
(semi)-automated Pulsed GMAW welding processes such as STT (surface
tension transfer), RMD (regulated metal deposition), ESAB QSET (optimal short
arc parameters setting), and CMT (cold metal transfer), provided that the
Contractor can demonstrate successful prior experience (e.g., previous project
listing service, material specifications and thickness ranges).
5. All GTAW machines shall be equipped with arc starting devices, e.g., high frequency
starting unit, crater-eliminating, and slope-out control.
a. If regulations do not permit arc starting devices, alternative proposals shall be
subject to the approval of the Principal.
3.2 MATERIALS
3.2.1 Grouping
1. Substrate/parent materials identified under different groupings in ISO/TR 15608 shall
be defined as dissimilar metals to be welded.
2. Similar parent material welded with other grouping weld metal shall be treated as a
dissimilar metal weld.
3.2.2 Parent materials certification
1. Materials used for qualification of WPSs shall be representative of materials to be
used in production welding.
In this context, 'representative' is determined based on the essential variables.
2. Materials used for welding procedure qualification shall be supplied to a recognised
manufacturing specification and as a minimum certified in accordance with EN10204
(ISO 10474), inspection certificate 3.1.
3.2.3 Welding consumables
3.2.3.1 General
1. Welding consumables shall be supplied by a Manufacturer/Supplier accredited in
accordance with ISO 9001 or an equivalent quality specification approved by the
Principal.
2. Welding consumables shall be approved by one of the following organisations or
another organization approved by the Principal:
a. Controlas;
b. Lloyds Register of Shipping;
c. American Bureau of Shipping;
d. Det Norske Veritas;
e. Bureau Veritas.
3. Welding consumables for new WPQRs shall be subject to the approval of Principal via
the proposed WPS prior to qualification.
4. As a minimum, all welding consumables used in production welding shall produce
welds with mechanical properties that are the same or better as those specified for the
base metal, unless otherwise specified.
5. With the following exception, all consumables shall be identified on the WPS by their
AWS or ISO classification and by their Manufacturer/Supplier’s name and designation.
a. For solid wire electrodes (ISO 636, ISO 14171 and ISO 14341), identification
solely by ISO classification may be done.
5. Wire for automatic or semi-automatic welding, remaining coil or spool that is partially
used may be reused in its original container, carefully sealed, and stored in a
controlled storage on the condition that remaining welding consumable is of adequate
quality to be reused.
6. FCAW wires shall be returned to a controlled storage area at the end of each shift.
7. Bare filler wire in coils or spools that have not been kept in sealed containers after use
or wire that has been contaminated with rust, grease or other debris, shall not be re-
used without cleaning in accordance with the wire Manufacturer/Supplier’s
specifications.
8. All wire that cannot be cleaned without damage to the surface, change in size, or other
damage that would adversely affect its use shall be discarded.
3.2.4.4 Submerged arc welding
1. SAW fluxes shall not be left in machine hoppers for extended periods when welding is
not being carried out, e.g., overnight or during non-productive shifts.
2. Recycling of flux shall only be allowed if the procedure is endorsed by the consumable
Manufacturer/Supplier and by the Principal.
3. Each batch of flux and wire shall be labelled with the information from the supply
container.
4.1 GENERAL
1. Welding procedures for all welded joints SHALL [PS] be prepared and qualified in
accordance with ISO 15614, including requirements from the design code, service and
client.
2. The documents described in (4.1, Item 1) shall be subject to review and approval by
the Mechanical, Materials & Integrity (MMI) Technical Authority of the Principal.
3. Each Fabricator shall prepare its own WPSs and qualify its own welding procedures.
a. WPSs shall contain information as specified in ISO 15609 and (Appendix A).
4. The testing results for WPQR/weld test record shall be presented in a detailed format
and with traceable document trail (Appendix A).
5. Unless otherwise specified, multi-pass fillet welds may be qualified by the qualified
procedure for groove welds in accordance with ISO 15614,
6. Separate WPSs shall be provided for groove and fillet welds.
7. Single pass fillet welds shall be separately qualified in accordance with ISO 15614.
7. When PWHT is specified, it shall be carried out in accordance with (6.2) per the
planned production sequence.
8. Multi-pass fillet welds may be qualified by groove weld performance testing.
9. Production weld testing of multi-pass fillet welds shall be performed to provide
evidence of positive penetration of the root pass only.
4.5.2 Nondestructive testing
1. The NDE shall be performed for welding procedure qualification as per Table 4.
Table 4 NDE Testing
2. Visual examination of completed welds shall be conducted by both the Fabricator and
the Principal, or its representative.
a. Cutting of a test piece for mechanical testing should not take place until it has
been visually examined and accepted by the NOBO or a recognised independent
third party.
b. If the test piece diameter be too small to allow proper examination of the weld
root, then the test piece shall be cut longitudinally to facilitate examination.
c. For new welding procedure qualifications where alternative or additional NDE
methods are proposed for production welding (e.g., time-of-flight diffraction
(TOFD)), the test piece shall also be subjected to these NDE methods.
3. When NOBO witness is required, this shall be arranged by the Fabricator.
4. When acceptance criteria are not defined in the purchase specifications, the
acceptance criteria shall be defined as “the design code requirements or ISO 5817
quality level B.”
The NDE acceptance criteria are normally covered by the selected design code for
the equipment or piping, for example PD 5500 or EN 13445.
4.5.3 Macro section examination
4.5.3.1 General
1. Macro sections shall be prepared and etched such that the whole cross section of the
weld, inclusive of HAZ, and adjacent parent material and individual weld passes are
visible.
2. Macro sections shall be examined under magnification between 3x and 8x.
3. WPQR documentation shall include original photographs or good quality digital images
of the macro sections with the following:
a. any hardness survey indentations visible on the photographs;
b. photographs marked to indicate the magnification (scale bar).
4. For weld acceptance the examination of the macro section shall not reveal any cracks,
lack of fusion (root, sidewall or inter-run) or volumetric defects (slag, porosity) that are
outside the limits set by the design code or ISO 5817 quality level B.
4.5.3.2 Hardness testing
1. Hardness surveys, as specified in ISO 15614, shall be carried out on macro sections
using Vickers hardness at 10 kg load.
2. Hardness testing shall be in accordance with ISO 6507-1.
3. The hardness requirements for base material, HAZ, and weld metal in Table 5 shall
apply:
Table 5 Hardness requirements - base material, HAZ and weld metals
ferritic metals in downstream process 250 HV10 for the entire weld and the HAZ
services, including H2 service conditions
3.5% Ni steel joint thickness > 9.5mm (3/8 in) 275 HV10 in the mid-thickness and cap
when the hardness impression is located
at least 8 mm (5/16 in) from the internal
surface
Table 6b Range of qualification for nickel alloy and nickel alloy/steel groups
5. WELDER QUALIFICATION
5.1 GENERAL
1. All welders shall be qualified in accordance with ISO 9606.
2. All welding operators shall be qualified in accordance with ISO 14732.
6.1 PREHEATING
6.1.1 Preheat temperature
1. For carbon-manganese and low alloy steels, the minimum preheat temperature shall
be as calculated in accordance with ISO/TR 17671-2 using the maximum carbon
equivalent allowed for the material to be welded and the weld metal hydrogen level
guaranteed by an approved consumable control procedure.
2. If higher preheat temperatures are necessary to meet the hardness values required by
this DEP, particularly for sour service conditions in accordance with DEP
39.01.10.12-Gen. or DEP 30.10.02.17-Gen., as applicable, the temperature margin
above the minimum required by ISO/TR 17671-2 shall be applied to all thicknesses to
be welded.
3. For reinforced branch fittings, such as olets, that are to be welded, the minimum
preheat temperature shall be 50 °C (90 °F) above that specified by ISO/TR 17671-2.
4. If preheat is not explicitly required by this DEP and ambient temperature is below 5 °C
(41 °F), or if condensation/moisture is apparent on work surfaces, then sufficient
preheat shall be applied to ensure work surfaces are dry and remain warm to the
touch.
5. For 3.5 % nickel steels, a minimum preheat temperature of 100 °C (212 °F) shall be
used for welding all thicknesses.
6.1.2 Preheat application
6.1.2.1 General
1. For materials with wall thickness up to and including 19 mm (3/4 in), preheating shall
be by gas torch or electrical resistance heaters.
a. For wall thickness above 19 mm (3/4 in), electric resistance heating mats shall be
used, unless it is agreed with Principal that access or location makes it
impractical.
2. Electrical resistance elements shall be controlled by thermocouples attached on or
adjacent to the weld preparation.
3. Thermocouple devices shall be regularly calibrated as specified in ISO 17663 and
ISO IEC 60584-1, with a maximum interval of six months.
4. Preheating with oxy/fuel gas should only be by soft flame burners designed for the
purpose.
5. Handheld oxy/fuel gas burners should only be used for welds on pipes less than
168.3 mm OD (DN150 (NPS 6)) or attachment welds less than 300 mm (12 in) long.
This only applies where preheat above 20 °C (68 °F) is required.
6. The temperature of preheat implemented by non-electrical means shall be measured
using contact pyrometers, temperature indicating crayons, or thermocouples.
a. If there is access, temperature measurement shall be taken on the surface
opposite of the one being heated.
i. Measurement shall be taken at a location that is displaced from the source
of heat by a minimum of 25 mm (1 in) in a direction parallel to the vessel,
process piping, or other equipment axis.
ii. Measurement shall be taken after removal of the heat source.
b. If there is no access to the opposite surface, temperature measurement shall be
taken 75 mm (3 in) from both weld toes/edges and delayed for a period not less
than five seconds per mm of material thickness after removal of the heat source.
7. Temperature indicating crayons shall be certified to be free (less than 1 ppm) of lead
and sulphur or any other low melting constituent.
8. Residue from crayons shall be removed from the weld surface before proceeding with
the weld.
9. Thermocouples shall be installed under resistance heater mats, unless test trials prove
the process will not expose the component to temperatures above the lower critical
transformation temperature of the base metal alloy.
6.1.2.2 Welding interruption considerations
1. Interruption of welding with loss of specified preheat temperature shall not be
permitted except for unalloyed steels (Group 1) with UTS of 450 N/mm² (65 ksi) or
lower, or for steels with UTS of 490 N/mm² (70 ksi) when welded with low hydrogen
consumables and with a welded thickness of less than 28 mm (1.1 in).
a. At least 30 % of the weld joint thickness shall have been completed prior to
interrupting welding.
b. After interruption, the joint shall be slow cooled under insulation.
3. For local PWHT the soak temperature shall be achieved and maintained in a band
2.5 times weld thickness either side of the weld centre line.
a. The width of the thermal insulation shall be 7.5 times weld thickness either side of
the weld centre line.
4. Circulation of air in the bore of the process piping or equipment work shall be
prevented.
5. The minimum number and position of thermocouples on pipe shall be as per Table 7.
Table 7 Number and position of thermocouples
6. Thermocouples shall be located on the weld centre line and be held in intimate contact
with the surface of the weld by mechanical means or by capacitance discharge
welding.
a. The attachment points of capacitance discharge welded thermocouples shall be
dressed by grinding after removal.
7. For 2G oriented welds the thermocouples shall be placed below the bottom toe of the
weld bevel.
6.2.6 Equipment calibration
1. The calibration procedures for all equipment measuring and recording temperature
shall be subject to approval by the Contractor.
2. Equipment shall be calibrated at least every three months.
6.2.7 Recording and reporting
6.2.7.1 General
1. As a minimum, the heating rate, holding time, temperature and cooling rate data shall
be recorded.
2. The temperature measured by each thermocouple should be recorded by means of a
multi-channel chart recorder.
a. Each chart should be marked with the date of the PWHT, the WPS number, the
weld or spool number(s), channel identification and signature(s) of Subcontractor
personnel.
3. A heat treatment report containing the following information shall be submitted for
review and approval by the Principal:
a. identification of the component being subjected to PWHT;
b. actual heating and soaking rates as recorded on the temperature chart;
c. actual soak and withdrawal temperatures as recorded on the temperature chart;
d. material dimensions and specification;
e. applicable WPS number;
f. project description/code;
g. a signature, from the authorised party, confirming completion of works in
accordance with design requirements.
6.2.7.2 Thermocouples
1. Thermocouple attachments shall be capacitor discharge connections, or nuts and
bolts.
2. If nuts and bolts are used, the materials should be of a composition such that they will
not be adversely affected by the PWHT process.
a. These nuts and bolts shall be treated as temporary attachments.
3. The attachment points of welded thermocouples shall be dressed by grinding after
removal.
4. All thermocouple attachments shall be insulated to prevent temperature misreading
caused by the effect of radiation.
5. The number and positions of thermocouples shall be in accordance with the design
code and the following:
a. as a minimum, three thermocouples to be directly attached on a work piece;
b. for a hollow configuration, one additional thermocouple to be on the inside.
6.2.8 Process service considerations
1. In addition to any code requirements, welds in materials for the following process
services shall be subjected to PWHT:
a. caustic and ammonia service;
b. HF service;
c. rich or lean amine service irrespective of service temperature;
d. sour service conditions as defined in DEP 30.10.02.17-Gen. (for Downstream
applications) or DEP 39.01.10.12-Gen. (for Upstream applications);
e. high pressure, high temperature hydrogen service;
f. carbonates service as defined in DEP 30.10.02.17-Gen.
2. In the services described in (6.2.8, Item 1), all carbon and low alloy steel welds of all
thicknesses shall be given PWHT and be so indicated on the applicable equipment
data sheet or piping/line designation table.
3. Holding times at designated heat-treating temperatures shall be a minimum of one
hour per 25 mm (1 in) of weld thickness.
a. When PWHT is imposed because of environmental cracking concerns,
combinations of longer-than-designated holding times at lower-than-designated
heat-treating temperatures shall not be used.
Table 7A Guidance on pre-heat and PWHT of weldments when the design is as per EN 13445 /13480
5)7) 8)
2.25Cr 1Mo all 200°(392)-250°(482) all 630°(1166)- 680°(1265) 5
6) 7)
680°(1265)- 720°(1328)
7)9)
720°(1328)- 750°(1382)
5) 7 8)
5Cr 0.5Mo 9Cr 1Mo all 200°(392)-250°(482) all 680°(1265)- 720°(1328) 5
7) 9)
720°(1328)- 760°(1400)
10)
12-17 Cr martensitic ss all 200°(392)-300°(492) all 700°(1292)- 790°(1454) 2,5
NOTES:
1. If ambient temperature is below 5°C (41 °F) pre-heating at 40 °C (104 °F) is recommended. (See also 6.1.1.)
2. Minimum holding time 1 hour.
3. Low hydrogen filler metals to be used.
4. PWHT is required for Ceq ≥ 0,45 or C ≥ 0,23.
5. For optimum high temperature creep properties in general the lower side of the temperature range to be used.
6. Temperature range in the case of service for hydrogen (H2) or general refinery services.
7. Minimum 10° below refinement temperature.
8. For the larger thickness (>25 mm (>1 in)) components De-Hydrogenation Treatment (DHT) need to be considered when Intermediate Stress Relief (ISR), according to the industry best
practices such as API 934.
9. Temperature range for maximum softening.
10. PWHT temperature selection is based on the original heat treatment temperature of the base metal used.
11. The higher temperature range is specifically for resistance to amine cracking 620° (1148) - 650° (1202) and carbonate cracking 649° (1200) - 663° (1225).
7. WELD INSPECTION
b. Radiography:
i. ASNT, CGSB or ISO 9712, Level 2.
c. Interpretation only:
i. ASNT, CGSB or ISO 9712, Level 2.
d. Ultrasonic:
i. ASNT, CGSB or ISO 9712, Level 2.
e. Supervisors responsible for overseeing and controlling NDE activities shall be
Level 3 qualified.
7.2.3 General requirements
1. Weld inspection, shall be the responsibility of the Fabricator.
2. The NDE company responsible for the final inspection of welds shall have a quality
system in compliance with ISO/IEC 17020, and be accredited by a nationally
recognised body.
3. NDE procedures shall be subject to approval by the Principal.
4. The Fabricator shall implement a system for uniquely identifying each weld, for the
control and recording of inspections (VT, MT, PT, UT and RT).
a. Isometric drawings, marked with the individual weld numbers, should be
maintained for this purpose.
5. Prior to fabrication start-up, the Fabricator shall submit its identification system for
approval by the Principal.
6. Where PWHT is required, final non-destructive testing shall not take place until final
PWHT has been completed.
7.2.4 Visual Inspection
1. Welders shall perform visual inspection on all prepared joints prior to welding, during
welding (welder self-checks) and upon completed welds before release to inspection
routine.
2. Visual inspections should include the internal surface of the weld wherever possible.
3. The visual acceptance of each weld shall be recorded by the Fabricator as part of the
NDT reporting.
8. WELD REPAIRS
1. The causes for each unacceptable defect shall be immediately investigated, with
corrective action taken to prevent further occurrence.
d. excavation shall be ground to a smooth boat shape with no sharp edges and
have sufficient slope on the sides to permit access for welding;
e. weld repair excavation depth shall be controlled by gauges to ensure the
minimum amount of material necessary is excavated to completely remove the
defect.
3. MT or PT surface inspection techniques shall be used to confirm removal of weld
defects.
8.2 RE-WELDING
1. If back purging was used on the original weld, the back purge shall be applied if the
repair excavation encroaches closer than 6 mm (1/4 in) to the inside surface of the
vessel, process piping or equipment.
9.1 GENERAL
1. Unless local regulations are more stringent, the following shall apply:
a. protective clothing for use in welding and allied processes to conform to ISO
11611;
b. equipment for oxygen and acetylene to conform ISO 14114 and ISO 5172;
c. welding equipment to conform IEC 60974-x;
d. ventilation of welding and cutting fumes to conform ANSI Z49.1/AWS Z49.1;
9.3 ALIGNMENT
1. Equipment used to hold and support process equipment, vessels, piping, shall be
capable of bearing the load whilst maintaining the stability required for working in both
the vertical and horizontal planes.
Direction of Welding A change from vertical up to vertical down or vice versa requires
requalification.
Qualification Position • For GTAW/SMAW welding, qualification in H-L045 (6G)
position can be done instead of PC (2G) + PF (5G) positions.
• Plate: The positions required to qualify are PC (2G), PF
(3Gu), PE (4G).
Single/Double Sided Single-sided welds qualify double-sided welds but not vice-versa.
Bevel/V Compound bevels qualify V-bevels but not vice versa.
Backing Addition or removal of backing strips or gas requires
qualification.
Shielding/Backing Gases Minor constituents of gases do not change by more than 10% of
their nominal value.
Arc Voltage ± 10% of the average measured for the specified weld region.
Current/Wire Feed ± 15% of the average measured for the specified weld region.
Travel Speed ± 20% of the average measured for the specified weld region.
Arc Energy or Heat Input ± 25% of the average measured for the specified weld region.
Arc Type A change in arc characteristics (e.g., dip, globular, spray)
requires requalification.
Electrode/Filler Rod Size SMAW filling & cap passes, Normal practice is one electrode
diameter change is allowed within the consumable manufacturer
recommended optimal parameters settings, max 4mm diameter
use.
PWHT Increase in total PWHT time exceeding 25% requires
requalification.
Automation • Semi-automated and automated welding processes such as
orbital GTAW, Adaptive GMAW such as STT (Surface
Tension Transfer), RMD (Regulated Metal Deposition),
ESAB QSET (optimal short arc parameters settings) and
CMT (Cold Metal Transfer), require additional quality control.
• Full parameter settings reported during qualification,
archived and fully traceable during the fabrication stage.
o One of the following:
§ Automatic weld parameter monitoring to be
used during the qualification process.
§ Automatic welding parameter monitoring
quality control during fabrication.
Cladding of corrosion • The heat input restricted in reference with the ISO 15614-7
resistant alloys by -10/ +25%.
• The electrode diameter (process 111/SMAW) can be
selected one diameter up/down from the qualified condition.
• The restriction for all changes to the “non-essential”
parameters is that the effect to the dilution of the base
material is minimal to the condition qualified.
For example, for the 111/SMAW process, the normal
recommended amperage and volt ranges are implemented
(not same amperage for lower electrode diameter).
Qualified diameter range 0.5xOD to 2xOD except that pipe diameter 168.3mm OD
for process piping (DN150/NPS 6) qualifies 0.5xOD and over, including plate
1. Typical Materials ASTM A285C, A515, A106B, A105, A234-WPB, API 5L Gr B, A516,
A216.
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), FCAW (136,114), GMAW (135), MCAW
Processes (138), SAW (121,125).
4. Consumable Restrictions SMAW electrodes: Type EXX16 or EXX18.
5. Consumable Chemistry a. Generic applications:
No additional restrictions to the standard.
b. CO2-containing corrosive service limitations:
Root and second pass limited to maximum 0.2 % Ni, 0.6 % Si,
0.5 % Mo to prevent preferential weld corrosion.
c. HF service limitations:
Cr + Cu + Ni < 0.15 % and 0.3 % Mo.
d. Matching type welding consumables:
Type Code Designation
Bare Wire AWS A5.18/A5.18M ER70S-3
ISO 636 W 42 5 W2Si
ISO 14341 G 42 2 M G2Si
Coated AWS A5.1 E7018-1 H4R
Electrode
E7016 H4R
ISO 2560-A E 46 4 B 32 H5
E 42 3 B 12 H5
1. Carbon Equivalent Production CEq max = WPQR CEq +0.03, or 0.38 whichever is
higher.
Relaxation of this variable may be permitted based upon the
Contractor demonstrating QC controls which ensure the
application of suitable preheat for higher CE values and
implementation of appropriate production hardness testing,
approved by the Principal.
2. Thickness Limits As-welded thickness limit is defined in the selected design
(other) code.
3. Bevel Angle Total production weld included angle not to be decreased by
more than 10° from the WPQR.
For weldolets, demonstration that the butt weld welding
parameters can be maintained may be accepted as
justification to waive this requirement.
4. Electrode/Filler Rod Root electrode or filler wire size requires requalification.
Size For SMAW fill and cap, one electrode diameter change may be
allowed within the consumable manufacturer recommended
optimal parameters settings, max 4 mm (5/32 in) diameter use.
5. Preheat No decrease from that qualified.
No deletion or addition except that maximum 50°C (122°F) is
allowed for condensation mitigation.
6. Interpass May be raised by 50 °C (90 °F) above WPQR maximum.
7. Interpass Limit 300 °C (572 °F) maximum.
8. Heat Input or Arc Arc energy maximum recommended is 2.5 kJ/mm (63.5 kJ/in).
Energy
9. Repair Welding Repair WPS to be issued.
Separate WPQR not required unless essential variables
change.
1. Typical Materials ASTM A537, A352, A333 Gr6, A350 LF2, A420 Gr WPL6, API
5L X##, A694 F##.
2. Approved Root GTAW (141).
Processes
3. Approved Fill and GTAW (141), SMAW (111), FCAW (136), SAW (121,125).
Cap Processes
4. Consumable SMAW electrodes: Type EXX16 or EXX18.
Restrictions
5. Consumable a. Generic applications:
Chemistry No additional restrictions to the standard.
b. Corrosive service:
For CO2 containing process service, root and second pass
limited to max 0.3% Ni, 0.6% Si, 0.5% Mo to avoid
preferential weld corrosion.
c. For HF service:
The limitation is Cr + Cu + Ni < 0.15% and 0.3% Mo.
d. Typical matching type welding consumables are as follows:
Type Code Designation
Bare Wire AWS A5.18/A5.18M ER70S-3
ISO 636 W 42 5 W2Si
ISO 14341 G 42 2 M G2Si
Coated AWS A5.1 E7018-1 H4R
Electrode
E7016 H4R
ISO 2560-A E 46 4 B 32 H5
E 42 3 B 12 H5
6. Hydrogen Control <= 5ml/100g to EN ISO 3690
1. Carbon Equivalent Production CEq max = WPQR CEq +0.03, or 0.38 whichever is
higher.
Higher CE values may be permitted subject to review by the
Principal based upon the Contractor demonstrating QC
controls which ensure the application of suitable preheat for
higher CE values and implementation of appropriate
production hardness testing, approved by the Principal.
2. Material Supply Charpy impact and hardness acceptability for normalised,
Condition TMCR, Q&T materials to be qualified or demonstrated in
accordance with low temperature qualification requirements
(4.5.3.3) and Table 5.
3. Thickness For WPQRs with T < 5 mm (0.2 in), impact tests are not
required unless the WPS is to be used on material with
thickness greater than 5mm (0.2in).
4. Thickness Limits As-welded thickness limit is defined in the selected design
(other) code.
5. Simple/Compound Change to/from compound bevel requires approval by the
Principal.
6. Bevel Angle Total included angle not to be decreased by more than 10°
from WPQR.
7. Process The welding process, combination of processes or order of
Combination welding processes not to be changed unless approved by the
Principal.
8. Consumable The consumable brand name is an essential variable.
(The Principal may agree to changes for solid wires).
9. Electrode/Filler Rod Electrode or filler wire size not to be changed at any stage of
Size welding.
10. Polarity/Current Any change in polarity or current type requires requalification.
Type
11. Preheat Decrease from qualified preheat is not permitted.
12. Interpass May be raised by 50°C (122°F) above WPQR maximum.
13. Interpass Limit 250°C (482°F) maximum.
14. Repair Welding Repair WPS to be issued.
Separate WPQR not required unless essential variables
change.
A333 Gr 3, A350 LF3, A420 WPL3 -80 (-112) (3) 27 (20) 19 (14)
NOTES 1. The acceptance criteria for sub size specimens shall be reduced to:
7.5mm x 10mm (0.3 x 0.39in) 0.83 x full size values
5mm x 10mm (0.2 x 0.39in) 0.67 x full size values
2.5mm x 10mm (0.1 x 0.39in) 0.5 x full size values
2. The application of duplex stainless steels is limited to -50 °C (-58 °F) and 40 mm (1.5 in) maximum
thickness, unless a fracture mechanics assessment is carried out to justify lower temperatures or greater
thicknesses and is approved by the Principal. (see DEP.30.10.02.31-Gen.)
3. If the design temperature is lower than -80 °C (-112 °F), the test temperature shall be the same as the
minimum design temperature.
4. The Principal might accept pre-qualified procedure that is tested at -46 °C with the same acceptance criteria
depending on actual minimum design temperature and the 1.5J per degree C transition rule.
2mm
2mm
2mm
2mm
(6) C2 = Notch at 2mm from
fusion line (and C5 = at 5mm
for heat inputs over 2kJ/mm)
2 or 5mm
NOTE:
(1), (2) and (3) - All welds
(4) - Additional for ferritic steels with wall thicknesses over 20mm.
(4), (5) and (6) - Additional for duplex stainless steels with wall thickness over 20mm.
6. Where heat inputs greater than 2 kJ/mm (51 kJ/in) have been used during WPQR an
additional set of three specimens shall be taken at the fusion line + 5 mm (0.2 in).
7. For single sided welds, the specimens shall be taken with the lower surface no more
than 2 mm (0.08 in) above the inner surface and the following apply:
a. For material thicknesses greater than 20 mm (0.8 in), a set of three specimens
are also required with their notches at the weld centre line and with their upper
surfaces within 2 mm (0.08 in) of the outer surface.
b. Each specimen to be etched prior to notching and the location of the notch
relative to the fusion or weld centre line individually marked.
c. The notch to be placed in the square face of single sided bevel welds.
d. Pre-existing welding procedure tests performed in accordance with ISO 15614-1
shall be additionally impacted tested on the root area for the materials with the
thickness greater than 19 mm and less than 50 mm according to this DEP.
8. The notch positions for double sided welds shall be agreed with the Principal.
9. Full size (10 mm x 10 mm (0.39 in x 0.39 in)) impact test specimens shall be used
wherever possible.
Where this is not possible, the larger of three quarter size (7.5 mm x 10 mm (0.3 in
x 0.39 in)) or half size (5 mm x 10 mm (0.2 in x 0.39 in)) specimens may be used.
Reduced acceptance values for reduced size samples are given in Table 8, Note 1.
10. No impact test result shall be less than the specified minimum individual value with not
more than one result less than the minimum average value specified.
a. In the event of failure, the following shall be applied
i. Three additional specimens are required to be tested.
ii. The average of the six specimens is not less than the minimum specified
average.
iii. Only two values to be below the specified minimum average value and only
one of those to be below the specified minimum individual value.
11. Fabrication of impact tested CMn piping and fittings, for process piping service (i.e.,
ASTM A333 gr6 and A350 LF2), shall be subject to PWHT based on the requirements
in the applicable design code and DEP 31.38.01.31-Gen.
1. Typical Materials ASTM A333 Gr3, A350 LF3, A420 Gr WPL3, A765 Gr III, A352
LC3, A203 D.
2. Approved Root GTAW (141)
Processes SMAW (111): Alternating current to be used for root pass
welding, to avoid magnetic arc blow problems and consequent
lack of fusion.
3. Approved Fill & Cap GTAW (141), SMAW (111), SAW (121,125).
Processes
4. Consumable Matching : GTAW : ER80S-Ni2/SMAW electrodes are
Restrictions 7016C2L, 7018C2L, 8016C2 or 8018C2.
1. Typical Materials ASTM A 387 types 0.5 Mo, 1 Cr-0.5 Mo, 1.25 Cr- 0.5 Mo, 2.25
Cr-1 Mo steels,5Cr 1Mo, 9Cr 1Mo, P91 (9Cr, 1Mo-V), AISI
4130.
2. Approved Root GTAW (141) and GMAW (1xx) for P3 to P9.
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), SAW (121,125).
Processes
4. Hydrogen Control <= 5ml/100g to EN ISO 3690.
5. PWHT Low alloy steels require post weld heat treatment.
1. Typical Materials AISI 300 Series, Grades 304L, 304, 316L, 316, 321, 347.
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), GMAW (135), SAW (121,125).
Processes FCAW (136): This can be used for design temperatures up to
150 °C (302 °F).
4. Consumable Principal alloying additions should not be made through flux
Chemistry additions.
1. Bevel Angle Total included angle not to be decreased by more than 10°
from WPQR.
For weldolets, demonstration that the butt weld welding
parameters can be maintained may be accepted as
justification to waive this requirement.
2. Process The welding process, combination of processes or order of
Combination welding processes not to be changed.
3. Electrode/Filler Rod Electrode or filler wire size not to be changed at any stage of
Size welding outside of what was qualified in WPQR.
4. Polarity/Current Any change in polarity or current type (including pulse
Type characteristics) requires requalification.
5. Interpass May be raised by 25 °C (45 °F) above WPQR maximum.
6. Interpass Limit 175 °C (347 °F) maximum.
7. Repair Welding Repair WPS to be issued. Separate WPQR not required
unless essential variables change.
1. Typical Materials UNS S31254, UNS N08367, UNS N08925, UNS N08926.
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), FCAW (136), SAW (121,125).
Processes
4. Consumable Type ERNiCrMo-3.
Restrictions
5. Consumable Principal alloying additions not to be made through flux
Chemistry additions.
6. Autogenous Welding Not permitted.
1. Typical Materials UNS S31803, UNS32205 (22% Cr) and UNS S32550, UNS
S32750, UNS S32760 (25% Cr), excluding UNS32304.
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), FCAW (136), SAW (121,125).
Processes
4. Consumable Root and 2nd pass of 22% duplex to be made with 25% duplex
Restrictions consumable unless nitrogen containing shield gas and purge
gas are used.
5. Consumable Principal alloying additions not to be made through flux
Chemistry additions.
Overmatched nickel content is required.
(Typically, 2209 type for 22% duplex and 2509 type for 25%
duplex).
9. Ferrite Test Acceptance criteria: 35% – 60% in parent and 30% – 70% in
weld/HAZ according to ISO 17781 on with measurements to
be made 1 mm from root and cap in weld, HAZ, and parent
metal.
14. Heat Input Limits a. The arc energy and interpass temperature to be controlled
to ensure a cooling rate of the weld with respect to the
thickness which avoids detrimental phases or incorrect
ferrite/austenite phase balance.
Typical arc energies are in the range 0.5 kJ/mm – 1.75
kJ/mm.
b. The second pass is normally deposited at lower arc energy
than that of the root pass to achieve satisfactory corrosion
and mechanical properties.
15. Repair Welding Separate procedure to be qualified.
1. Typical Materials UNS N08825 (Alloy 825), UNS N06625 (Alloy 625), UNS
N04400 (Alloy 400), UNS N06600 (Alloy 600), UNS N0x925
(Alloy 925), UNS N0x718 (alloy 718), UNS N10276 (Alloy
C276).
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), SAW (121,125).
Processes
4. Consumable a. The welding consumables to be agreed with Principal.
Restrictions The specific designation can be according ISO 14172, AWS
5.11 or EN 1600 for covered electrodes.
b. For wire the specific designation can be according
ISO 18274 or AWS 5.14.
5. Consumable Principal alloying additions not to be made through flux
Chemistry additions.
1. Typical Materials a. Cu/Ni alloys in the range of 90/10 and 70/30 materials
composition
Al-Brass alloys
Al-Bronze alloys
unalloyed copper
b. With reference to metallic materials DEP 30.10.02.11-Gen.
2. Approved Root GTAW (141).
Processes
3. Approved Fill & Cap GTAW (141), SMAW (111), SAW (121).
Processes
4. Consumable a. The welding consumables to be agreed with Principal.
Restrictions b. The specific designation can be according ISO 14172, AWS
5.11 or EN 1600 for covered electrodes. For wire the
specific designation can be according ISO 18274 or AWS
5.14.
5. Materials condition For the welding of copper materials, the materials’ supply
condition to be reported. (i.e., hardness/strength/deformation
grade/heat treatment, aging).
6. Consumable Principal alloying additions not to be made through flux
Chemistry additions.
7. Autogenous Welding Not permitted.
3. Maximum Hardness The maximum hardness to be the same as the base material
specification. Normally the annealed condition hardness
requirement is also applicable for the weld area.
1. Joint Type Multi-pass fillets may be qualified by butt weld fill and cap
parameters.
2. Bevel Angle Total included angle not to be decreased by more than 10°
from WPQR.
3. Process The welding process, combination of processes or order of
Combination welding processes not to be changed.
4. Electrode/Filler Rod Electrode or filler wire size not to be changed at any stage of
Size welding.
5. Polarity/Current Any change in polarity or current type (including pulse
Type characteristics).
6. Interpass May be raised by 25 °C (45 °F) above WPQR maximum.
7. Interpass Limit 175 °C (347 °F) maximum.
8. Repair Welding a. For new fabrication:
Repair WPS to be issued.
Separate WPQR not required unless essential variables
change.
b. Repair/maintenance:
The WPS/WPQR to be reviewed in relation to the process
contaminations for additional requirements in shop and field
repairs on process exposed components.
10.14 TITANIUM
1. In addition to EN ISO 15614, Tables 55 through 59 shall be applied for titanium alloys.
10.14.1 General requirements
Table 55 General requirements for titanium alloys
NOTES:
1. Locations are based on the upward direction according to EN ISO 15614-1.
2. Specimen location priority: 1st Macros, 2nd Impacts, 3rd Tensiles, 4th Corrosion Coupons, 5th Bends.
3. Additional latitude is acceptable for joints that are not in fixed 5G or 6G positions, but it is
important to ensure that two tensile specimens or two pairs of bend specimens are not adjacent to
each other
11. REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication is used, together with
any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.
SHELL STANDARDS
Wet H2S requirements for downstream process equipment and piping DEP 30.10.02.17-Gen.
AMERICAN STANDARDS
EUROPEAN STANDARDS
INTERNATIONAL STANDARDS