DESIGN CALCULATION OF RCC GIRDER STAGING

Designed by: Prodip Kumar Mondal Date 3/19/2024


This means must input This means may input

1 - General Arrangement of R.C.C. Normal Girder Bridge:


Length of girder, Lg = 24.0 m = 78.7 ft.
Width of bridge, Wb = 7.30 m = 23.9 ft.
Width of footpath, Wf = 0.65 m = 2.13 ft.
Number of girder, Ng = 3.0 nos.
Overhanging width from C/L of facia girder = 1.3 m = 4.10 ft.
Center to center spacing of girder, Sg = 7.9

CL of bearing

CL of pier
1.0 ft. 76.7 ft. span of R.C.C. girder

Integral abutment Hinged

Figure 1-1: Sectional Elevation of R.C.C. Normal Girder Bridge

23.9 ft. total width


8.0 in.

2.13 ft. 18.0 ft. roadway width 2.0 in.


8 in. deck slab 2.0 in. WC

18 in. 1.13 ft.

Figure 1-2: X - Section of R.C.C. Normal Girder Bridge

1.1 - Overhang width of deck slab:


Overhang width is less or equal to 0.5Sg = 3.9 ft.
Applied overhanging width from C/L of facia girder = 4.1 ft.
1.2 - Height of R.C.C. normal girder:
Minm height of R.C.C. - girder including deck, h g with deck = 0.07Lg-brg = 64.4 in.
Applied height of composite R.C.C. - girder, hg = 66.0 in.

94.5 in.

(c) 8.0 in.

(b) 6.0 in.


6 in.

66 in. 58 in.
(a)

18 in.
Figure 1-3: X - Section of Composite R.C.C. Normal Girder

Table 1-1 - Composite R.C.C. normal girder section properties along X-X or strong axis

Gross area, Ag y of each part from Ix of each part 3 Neutral axis, N.A (in.)
Part AY (in. )
(in.2) bottom (in.) (in.4)
Yb Yt
a 1044 29.0 292668 30276
b 36 56.0 72 2016
43.11 22.89
c 756 62.0 4030 46854
Total = 1836 296770 79146
2 - Dead Load & Live Load of Superstructure:
Number of girder, Ng = 3.0 nos.
Nos. of diaphragm, nd = 5.0 nos.
Unit weight of concrete, γc (f'c < 5 ksi) = 0.145 kcf = 0.145 kcf
Cross sectional area of non-composite girder, Ag = 1044 in.2
Both side length of girder on pier cap = 2.0 ft.
Spacing of props along the alignment (assumed) = 0.92 m = 3.00 ft.
Effective length of girder for staging, Lg-staging = 76.7 ft.
Center to center spacing of girder, Sg = 7.87 ft.
Overhanging width from C/L of facia girder = 4.10 ft.
Girder haunch/fillet width & height = 0.50 ft.
Thickness of diaphragm, td = 1.1 ft.
Depth of diaphragm, dd = 4.0 ft.
Web width of girder, bw = 18.0 in.
Slab thickness excluding wearing surface, ts = 8.0 in.

2.1 - Interior girder weight:


Girder weight, DCgirder(I) = Ag* γc = 1.05 k/ft./gir.
Deck slab weight, DCslab(I) = 0.00 k/ft./gir.
Girder & deck slab weight, DCgirder+slab = 1.05 k/ft./gir.
Total interior girder and deck slab weight = 80.7 kip

2.2 - Exterior girder weight:


Girder weight, DCgirder(E) = Ag * γc = 1.05 k/ft./gir.
Deck slab weight, DCslab(E) = 0.00 k/ft./gir.
Girder & deck slab weight, DCgirder+slab = 1.05 k/ft./gir.
Total exterior girder and deck slab weight = 161.3 kip

2.3 - Haunch weight:


Haunch weight, DChaunch = 0.00 k/ft./gir.
Total hanch weight = 0.00 kip

2.4 - Diaphragm weight:


Diaphragm weight, DCdiaphragm(I) = 0.26 k/ft./gir.
Diaphragm weight, DCdiaphragm(E) = 0.13 k/ft./gir.
Exterior & interior diaphragm weight, DCdiaphragm(E+I) = 0.39 k/ft./gir.
Total diaphragm weight = 88.7 kip

2.5 - Load on Individual Pipes:


Total load of superstructure on staging = 331 kip
= 150 ton
Formwork weight (assume 10% of dead load weight) = 15.0 ton
Construction live load (assume 5% of dead load weight) = 7.5 ton
Total load on staging = 172 ton
Number of 4-6 in. φ pipe will be used at transverse direction (assumed) = 5.0 no's
Number of 4-6 in. φ pipe will be required at longitudinal direction (single row) = 25 no's
Total number of pipe will be required = 125 no's
Average applied load on individual pipes, P = 1380 kg
3 - Driving Capacity:
Weight of hammer (standard), W = 150 kg
Free fall height of hammer, H = 5 ft. = 1524 mm
Penetration constant, C (as SI units) = 25
Average penetration on last 10 blow, S = 10 mm

3.1 - Capacity of Post:


Capacity of post, P =1/5*(W*H)/(S+C) = 1307 kg
Factor of safety, f = applied load on pipes/capacity of post = 0.95
Increase the number of pipes